3. MENARA SENTRAL VISTA
PROJECT TITLE
Cadangan Pembangunan 1 blok Pejabat 20 Tingkat Termasuk
4 Tingkat Car Park Podium
LOCATION
Jalan Tun Sambanthan 4, KL
CLIENT
Yayasan Wilayah Persekutuan
6. GROSS FLOOR AREA TO BE MEASURED
Ground Floor - Commercial Floor
1st-4th Floor - Carpark
5th Floor - Commercial, Food Court, Management Office
6th-18th Floor - Office Tower
19th Floor - Lift Motor Room, Roof Top
7. G R O U N D F L O O R A R E A
Usable Area
Circulation Area
Ancillary Area
Usable Area : 900.52 m2
Circulation Area : 300.72 m2
Ancillary Area : 146.37 m2
Internal Division : 52.05
Total GFA : 1399.66 m2
8.
9. 1 S T F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 94.74 m2
Circulation Area : 1515.74 m2
Ancillary Area : 218.51 m2
Internal Division : 113.90 m2
Total GFA : 1942.89 m2
10.
11. 2 N D F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 0 m2
Circulation Area : 1872.81 m2
Ancillary Area : 22.05 m2
Internal Division : 48.03
Total GFA : 1942.89 m2
12.
13. 3 R D F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 14.56 m2
Circulation Area : 1785.49 m2
Ancillary Area : 53.01 m2
Internal Division : 89.88 m2
Total GFA : 1942.89 m2
14.
15. 3 A F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 0 m2
Circulation Area : 1852.18 m2
Ancillary Area : 46.89 m2
Internal Division : 43.82 m2
Total GFA : 1942.89 m2
16.
17. 5 T H F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 427.72 m2
Circulation Area : 238.75 m2
Ancillary Area : 625.05 m2
Internal Division : 59.72 m2
Total GFA : 1351.24 m2
18.
19. 6 - 9 T H , 11 - 12 T H F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 1125.46 m2
Circulation Area : 161.77 m2
Ancillary Area : 22.05 m2
Internal Division : 47.03 m2
Total GFA : 1356.31 m2
20.
21. 1 0 T H F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 1125.46 m2
Circulation Area : 161.77 m2
Ancillary Area : 22.05 m2
Internal Division : 47.03 m2
Total GFA : 1356.31 m2
22.
23. 1 6 T H F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 1117.90 m2
Circulation Area : 161.77 m2
Ancillary Area : 22.05 m2
Internal Division : 30.27 m2
Total GFA : 1331.99 m2
24.
25. 1 8 T H F L O O R
Usable Area
Circulation Area
Ancillary Area
Usable Area : 1158.30 m2
Circulation Area : 133.04 m2
Ancillary Area : 4.45 m2
Internal Division : 60.52 m2
Total GFA : 1356.31 m2
26.
27. 19 TH FLOOR
Circulation Area
Ancillary Area
Circulation Area : 73.28 m2
Ancillary Area : 550.82 m2
Internal Division : 35.62m2
Total GFA : 659.72 m2
28.
29. SUMMARY OF GROSS FLOOR AREA (GFA)
GF 1399.66
1F-5F 1942.89
6F-9F,11F-12F,18F 1356.31
10F,13F-17F 1331.99
19F 659.72
TOTAL GROSS FLOOR AREA: 28692.61
43. Work below lowest floor finish
Total cost of element (RM)=519,073.68
Cost per m2 GFA (RM)=18.09
Element Unit Quantity=1,399.62
Element Unit Rate (RM)=370.87
Element Unit per ratio GFA =0.049
Reinforced concrete (m3)= 380
Reinforcement (KG) =54,428
Formwork (m2)=2,535
46. Frame
Total cost of element (RM)=11,806,404.01
Cost per m2 GFA (RM)=411.47
Element Unit Quantity=28,693
Element Unit Rate (RM)=411.47
Element Unit per ratio GFA =1.00
Reinforced concrete (m3)= 5,502
Reinforcement (KG) =323,045
Formwork (m2)=39,847
50. Upper floor
Total cost of element (RM)=4,429,733.54
Cost per m2 GFA (RM)=154.38
Element Unit Quantity=27,293.00
Element Unit Rate (RM)=162.30
Element Unit per ratio GFA =0.951
Reinforced concrete (m3)=4,430
Reinforcement (KG) =279,083
Formwork (m2)=22,341
55. Roof
Total cost of element (RM)=2,514,644.39
Cost per m2 GFA (RM)=87.64
Element Unit Quantity=1,576.49
Element Unit Rate (RM)=1,595.09
Element Unit per ratio GFA =0.055
Reinforced concrete (m3)=129
Reinforcement (KG) =9,414
Formwork (m2)=826
56. Structural Steelwork
Roof
Cost of Element = Total of structural steelwork + total roof finishes + roof slab + handrailing to terrace
62. Staircase
Total cost of element (RM)=659,951.69
Cost per m2 GFA (RM)=23.00
Reinforced concrete (m3)=593
Reinforcement (KG) =28,709
Formwork (m2)=1,700
63. Staircase Structure
Cost of element = Total of staircase structure + Total of staircase finishes + Total of handrailing
66. External wall
Total cost of element (RM)=10,871,459.38
Cost per m2 GFA (RM)=378.89
Element Unit Quantity=4,646.20
Element Unit Rate (RM)=2,339.86
Element Unit per ratio GFA =0.162
Reinforced concrete (m3)= N/A
Reinforcement (KG) = N/A
Formwork (m2)= N/A
67. External Wall
Cost of element = Total of external wall + Aluminium work and glazing work
71. Internal wall
Total cost of element (RM)=2,957,834.00
Cost per m2 GFA (RM)=103.09
Element Unit Quantity=29,823.57
Element Unit Rate (RM)=99.18
Element Unit per ratio GFA =1.039
Reinforced concrete (m3)= 202
Reinforcement (KG) = 54,248
Formwork (m2)= 1,173
72. Internal Wall & Partition
Cost of element = Total of internal wall and partition
74. Window and External doors
Total cost of element (RM)=855,535.64
Cost per m2 GFA (RM)=29.82
Element Unit Quantity=1,529.66
Element Unit Rate (RM)=559.30
Element Unit per ratio GFA =0.053
Reinforced concrete (m3)= N/A
Reinforcement (KG) = N/A
Formwork (m2)= N/A
75. Internal doors
Total cost of element (RM)=945,597.23
Cost per m2 GFA (RM)=32.96
Element Unit Quantity=2,453.72
Element Unit Rate (RM)=385.37
Element Unit per ratio GFA =0.086
Reinforced concrete (m3)= N/A
Reinforcement (KG) = N/A
Formwork (m2)= N/A
77. Internal wall finishes
Total cost of element (RM)=2,384,602.00
Cost per m2 GFA (RM)=83.11
Element Unit Quantity=115,918.00
Element Unit Rate (RM)=20.57
Element Unit per ratio GFA =4.04
Reinforced concrete (m3)= N/A
Reinforcement (KG) = N/A
Formwork (m2)= N/A
80. Internal floor finishes
Total cost of element (RM)=1,426,958.44
Cost per m2 GFA (RM)=49.73
Element Unit Quantity=28,087.00
Element Unit Rate (RM)=50.80
Element Unit per ratio GFA =0.979
87. Internal ceiling finishes
Total cost of element (RM)=1,031,829.12
Cost per m2 GFA (RM)=35.96
Element Unit Quantity=27,384.00
Element Unit Rate (RM)=37.68
Element Unit per ratio GFA =0.954
91. External Finishes
Cost of element = Total of external wall finishes + Total of external floor finishes + Total of external ceiling finishes
External wall finishes
102. Services
Sanitary Appliances
Cost of element = Total cost of Sanitary - Cost of stainless steel frame mirror
RM596,112.00 - RM178,040.00 = RM418,272.00
112. Drainage
Total cost = total cost of surface water drains + total cost of sewerage reticulation
Surface water drains Sewerage reticulation
RM236,843.20 + RM144,000.00 = RM380,843.20