How to start a construction company as a contractor
1. E- Faculty development program
Estimation and Billing process in Construction Industry
By
Suguru Anusha
2. CONTENTS
Initial steps required for starting construction business as a contractor
A Case Study on civil finishing work.
Billing process
Payment process
3. Over view of the construction company
Stage
1
Registration of
the company
Applying for GST
number
Estimation of
tender work
Stage 2 Quoting rate Work Order
Tender
Documents
Stage 3 Requirement of
Materials
Requirement of
Manpower
Requirement of
Equipments
Requirement of
Initial amount
Stage 4 Negotiation with
material supplier
Negotiation with
labour supplier
Negotiation with
equipment
supplier
Stage 5 Preparing project
planning
Hiring the skilled
employees
4. The building consists of 63 floors
No. of flats per floor = 32 flats.
Scope of work: Block work for 32 flats.
No. of floors to do work = 4floors.
Case Study
6. Stage 1
Estimation of tender work:
Client will provide drawings and BOQ.
Calculating quantity of work.
Comparing rates i.e., client/ contractor.
7. Stage 2
Work Order:
Agreement between the client and the contractor stating that they have
permission to start the work in the assigned area.
Scope of work
Contract value
Retention money
Variation in quantity
Quality Assurance/ Quality control/ Tests Performed
Payment terms
Safety codes
Termination of contract
Labour hutment
8. Stage 3
Requirement of material tender work:
Listing out types of materials required i.e., AAC Blocks, Adhesive Chemical,
Shuttering, Steel, Cement, Coarse aggregate, Water.
Calculating the quantity required for each material.
Requirement of Man power:
Calculating how many labour and mason (skilled labour) required to do work.
Requirement of equipments:
Listing out the equipments required i.e., Excavator, Concrete mixer, Adhesive mixer
etc.
9. Stage 4 - Negotiation with the material suppliers
Check the quality before giving order
Follow the terms and conditions given by the client
Always maintain 20% margin in the purchase order.
No payments in advance
F.O.R = Freight on Road
(The term FREIGHT is used for the goods that are transported
in bulk from one place to another place)
10. Stage 4 - Negotiation with the labour contractors
Always keep 30% to 40% margin
Number of labours that contractor can provide?
Rates of the contractor i. e., Labour, mason, per sft and lift charge.
The base rate for block work per sft – Rs. 18/-
The base rate for lift charge for ground floor is 18/- and adding 3% for every floor.
Discuss mode of payments : It is of two types – Weekly payment and Monthly
payment
Weekly payment – Rs. 1000/ labour/ week
Monthly payment – Submitted bill
12. Stage 4 - Negotiation with the equipment supplier
Chemical mixer – MRP 2000 - 5000
13. Stage 4 – Initial amount required
Materials:
Material suppliers will supply materials by accepting 45days PD Cheque.
In very rare cases, keep 25% of amount aside from estimated material expenses.
Labour:
Weekly wages Rs.1000/labour/ week.
Equipments:
Buying adhesive chemical mixer
14. Project planning
Calculate quantity of materials required before starting the project.
List out the steps & procedure of your assigned work. i.e., blocks below/ after beam,
beam casting.
Prepare work break down structure before starting the project
Equipment requirements
Man power requirements
Material requirements
No delay in providing equipments or requirements from our side.
Maintain material in-site in advance i.e., 10days
Prepare a timetable to the labour contractors.
15. Tracking the work done
Keep weekly update records through email and maintaining file.
Always be ready for one stop solution.
Visit to the site at every three days.
17. Responsibilities
Contractor
Ability to tackle different mindsets.
Able to prepare project planning.
Should have knowledge to check client/ sub - contractor Bills, BOQ, Tender documents.
Always maintain enough bank balance.
Should not postpone sub – contractors bills.
18. Responsibilities
Billing Engineer
Estimating amount of work to be done and calculating quantities of material required.
Quoting rates according to the tender work to the client.
Register vendor listing in the client office.
Preparing & Submitting RA (Running Account) bills to the client.
Checking and Verifying sub- contractors submitted bills.
Maintaining taxation files.
Maintaining up – to - date financial records
19. Responsibilities
Site Manager
Ability to take on spot decisions/ solutions. i.e., site accidents.
Maintaining good relationships with client officer’s.
Should be punctual.
Preparing daily/ weekly plans or target.
Maintaining site financial records/ material records.
Maintaining terms and conditions of client in quality of work.
To get certified and verified of work submitted in monthly bill by Engineer – in – charge.
20. Responsibilities
Site Engineer
Shifting material from office store to place of work
Taking adequate steps for safety of labours
Ensuring quality of work
Ensuring work has been done in systematic manner and by step by step process.
Fulfilling needs and requirements of labours.
21. Billing process
Sub - Contractor to Contractor:
Preparing
Measurement book
Preparing cost
abstract
23. Payment process
Client to Contractor:
Prepare RA (Running account) between 28th – 30th of every month
Submit on 1st of every month along with the measurement sheets
Client billing department will check the submitted bill
Client certifies with “ Certificate of Payment.”
After approval by the client, payment will be done according to the payment terms and
conditions
24. Payment process
Contractor to Sub - Contractors:
All the Sub - Contractors submit their RA (Running account) bills between 28th – 30th of
every month along with the measurement sheets
Submitted bill should be checked & verified by Billing engineer.
After being approved by the contractor, payment will be done according to the payment
terms and conditions
25. Tips
Try to maintain same employees from project starting to ending.
Pay taxes in time, else GST number will be blocked, no material supplier will supply
goods for you.
Always maintain good relationship with clients.
Always maintain quality.
Conduct weekly meetings with the site employees (motivate them).