1. PROJECT FOR
PREPARED BY
Tan Shen Sin 0324602
Teow Kah Yan 0327201
Thasia 0329015
Yap Choe Hoong 0323161
Yap Foong Mei 0324867
Yeo Gin Faye 0330001
Wong Tian Yi 0326891
DOUBLE STORY SEMI-DETACHED
Life Quantity
Surveyor Sdn Bhd
Life Quantity Surveyor Sdn Bhd
No. 10, Jalan Taylor's,
47500 Subang Jaya, Selangor Darul Ehsan.
Tel : + 603 – 7725 1122
Fax : + 603 – 7725 3344
E-mail : admin@fecco.com.my
2. CADANGAN MEMBINA SATU RUMAH BERKEMBAR DI ATAS LOT 17 MUKIM
KAJANG, DAERAH HULU LANGAT, SELANGOR DARUL EHSAN
ARCHITECT
TULC ACES HOMES
Sdn Bhd
NO. 19, Jalan
BK5/10B, Bandar
Kancil, Selayang.
M&E ENGINEER
M/s Wisma In M&E Sdn
Bhd
No.77, Block D,
Tingkat 8, Jalan Gajah
Petaling Jaya
C&S ENGINEER
Legacy Engineering
Consultancy Sdn Bhd
No. 89 , Jalan Hilton 2,
Taman Jaya, Kuala
Lumpur
DEVELOPER
M/s Intelligent Homes
Sdn Bhd
Block D4, No. 19,
Jalan Tempua, Subang
Jaya
DETAILS OF MANAGEMENT
11. DECLARATION OF
NON-COLLUSION
This is a form for the tenderer to fill in and sign
Aim : To declare that they are not under any
agreement with any other tenderers or parties to
submit any pre-determined tender amount.
12. CONDITION OF CONTRACT
PAM CONTRACT 2006 (WITH QUANTITIES)
With this contract, a contractual relationship between the Employer and the contractor are formed .
Why PAM CONTRACT 2006?
Architects will be the contract administrator and thus will act fairly between the contracting company.
Extension time issue will be granted in a judicious manner as understanding of work programmes and delay
analysis would be beneficial to the Architect.
13. FORM OF TENDER
Tenderer insert his tender amount and proposed
completion time & agreement to validity period
By attesting its signature or company seal to make
this form a legal offer to the Employer
14. INSTRUCTIONS TO
TENDERERS
Inform tenderer on the rules & procedures that they need to comply within the entire tendering process.
Failure to comply may be deemed to be disqualified
1. Tender deposit / tender documentation fees shall be RM 800.00 in the form of cash or Banker’s draft
2. Tender bond/ earnest money shall be submitted together with an amount of RM12,000.00 in a form
of Bank Guarantee or Banker’s draft.
3. Submission of tender shall to be the Employer’s office not later than 12.00 noon
15. CONDITION OF
TENDERING
States the conditions that need to be complied with
by the tenderer in submission of tender.
1. Tender validity period : 60 days
2. Form of contract: PAM Contract 2006
16. GENERAL SUMMARY
OF TENDER
Collection of all the priced bills for all sections of
the project
The tenderer will then sum up the amount from the
Bill and to come up with a total amount to be filled
into the form of tender.
18. PREAMBLES
Contain clauses that serve to introduce & explain
the provisions in the “Specification” & “Bills of
Quantities” sections & the scope of coverage of the
rates in the BQ. It also stating the workmanship
and the materials to be used.
19. PRELIMINARIES
Employer’s requirements & the Contractor’s
obligations in carrying out the works
- Name of parties
- Description of the works
- Form & type of contract
- Facilities to be provided by the Contractor
- Application for necessary permits & license
- Schedule for inspections, records submission
etc.
1.Contractor’s All Risk Insurance Policy
- Act as a form of protection
2. All temporary work shall be removed
upon completion.
- This is to ensure that the cost to
removed will be on the contractor
instead to the employer.
20. BILLS OF QUANTITIES
- Piling work
- Work Below Lowest Floor Level
- Frame
- Upper Floors
- Roof Construction and Finishes
- Stairs and Staircase finishes
- External Walls
- Internal Walls and Partitions
- Windows
- Doors
- Internal Wall Finishes
- Internal Floor Finishes
- Internal Ceiling Finishes
- External Finishes
- External Work Within Lot Boundary
21. Bill No.3- Prime Cost and Provisional Sum
Prime Cost Sum
Allowance for works/materials
from nominated sub-contractor
Provisional Cost Sum
For works that cannot be
determined precisely at the time of
preparing BQ
31. SCHEDULE OF
DAYWORK RATES
For tenderer to fill in daywork rates for “labour” &
“machineries”
Form the basis of payment for daywork ordered by
the Architect
Avoid protracted argument on the reasonable
rates to be used
33. FORM OF BANK
GUARANTEE FOR
EARNEST MONEY
Standard form with pre-determined wordings for
the tenderer’s sourcing of a Bank Guarantee for
Earnest Money in the event of a successful tender
To prevent tenderers from fails to submit or fails to
enter into the contract after being selected
34. FORM OF BANK
GUARANTEE FOR
PERFORMANCE BOND
Standard form with pre-determined wordings for
the tenderer’s sourcing of a Bank Guarantee for
Performance Bond in the event of a successful
tender
Bank Guarantee, that the contractor will fulfill his
obligation