SlideShare a Scribd company logo
1 of 27
ESTIMATING
SEMINAR 2
Aishath Hussain 0320429
Andrew Mah KoonYan 0318798
Ervinna Endela 0327508
MaybelleWang Sze Kher 0327553
WendyTeo SiewYen 0328242
Question‽
You are working for a house builder at Kuala Lumpur. Your company has recently received
an invitation to tender a low cost apartment in Kajang, Selangor. You are required to
make a recommendation whether to accept or decline the tender invitation. What are the
5 main factors you will consider before making the recommendation? Explain how these
factors influence your decision.
COMPANY’S BACKGROUND
■ Date of Establishment: June 2008
■ Completed Projects : Low to medium cost residential buildings/shoplots
■ In-house Employees : Quantity Surveyors, Engineers, Project Manager etc.
■ Capital / Assets : RM250,000 in bank
■ No. of SiteWorkers : 20
■ MachineriesOwned : 2 excavators
TYPE OF PROJECT
TYPE OF PROJECT
Site location and accessibility :-
■ Low cost apartment is suitable to be constructed around Kajang
■ Existing road to provide safe access and egress
■ 35km away from our office
Past experience with similar projects ;-
■ Projects undertaken include low to medium range residential buildings
TYPE OF PROJECT
Is the project within the company boundaries?
■ Yes, capable of delivering the project due to past experiences.
Method of construction?
■ Adopt traditional construction method. (eg.Timber formwork)
TYPE OF PROJECT
Is the project complexity beyond the capability of the company?
■ No, it involves simple and typical designs only
The risk involved considering the nature of the work?
■ Accidents and injuries might occur at site due to traditional method of construction
■ Exterior work such as concreting and painting depends on weather condition
PROJECT SIZE
ANDVALUE
PROJECT SIZEANDVALUE
Project Size :-
■ 4 units x 5 storeys x 4 blocks
ProjectValue :-
■ RM 100,000 per unit x 4 units x 5 storeys x 4 blocks = RM8 million
PROJECT SIZEANDVALUE
Projected cash flow required during execution :-
■ Standard S Curve onGraph – past cost information and details of completed.
■ Critical Path Method (CPM) – technique for project planning made up of a
number of individual activities.
PROJECT SIZEANDVALUE
Is the project size beyond the capability of the firm?
■ Yes. It is within our boundaries as it is a medium scaled project.
Equipment, Labour and Plants :-
■ Equipment(s)– owns 2 excavators.
■ Labour(s) – 20-30 workers available.
PROJECT SIZEANDVALUE
Risks of project :-
■ Force majeure (construction risk)
■ Late changes / additional work
■ Site access
■ Labour productivity (performance risk)
■ Defective work – latent defects
■ Vandalism (security)
■ Intrusion
■ Delays
■ Liquidated ascertained damages (LAD)
PROJECT SIZEANDVALUE
Conditions of contract :-
■ Date of possession, deferment of possession, progress, delays, completion date
■ Liquidated ascertained damages
■ Partial possession
■ Quality of works
■ Testing and defects (Defects Liability Period)
TYPE OF CLIENT
TYPE OF CLIENT
Public Sector or Private Sector
■ Private Sector – Kelly Jeners
Financial capability of the client :-
■ Financially strong, reliable and has good financial records.
TYPE OF CLIENT
Reputation of the client :-
■ Well known among the peers in the industry.
■ Kelly Jeners delivers on its promises to the customers and is worthy of respect and
trust.
Relationship with the client :-
■ Has an existing and positive relationship with the client.
TYPE OF CLIENT
Expectations of the client :-
■ Client expects contractor to focus on their requirements, all of their needs and how to
solve their problems.
Form of contract :-
■ PAM Contract 2006 (With Quantities)
CURRENT AND
PROJECTEDWORKLOAD
OFTHE COMPANY
CURRENTAND PROJECTED
WORKLOAD OFTHE COMPANY
The need for work :-
■ The need for work is present since the company is only dealing with a medium range
cost residential project at the moment.
Other projects currently out for tender :-
■ Currently bidding for 2 projects and one of them is the Kajang low-cost apartment
project.
CURRENTAND PROJECTED
WORKLOAD OFTHE COMPANY
Forecast for upcoming projects :-
■ To be able to secure at least 5 projects in the next 2 years.
Availability of in-house staff :-
■ Yes. Quantity Surveyors, Engineers, Project Managers, etc.
CURRENTAND PROJECTED
WORKLOAD OFTHE COMPANY
Labour force availability :-
■ 20 workers.
Availability of equipment owned by the contractor :-
■ 2 excavators.
REGIONAL MARKET
CONDITIONS
REGIONAL MARKET CONDITIONS
Economical situation overall and the construction industry :-
■ Have to look into the economic factors of the country, such as GDP growth rate, or
GDP for construction (July 2016 – RM11899 million)
• How many projects are currently available in the market?
• How many competitors are expected to tender?
• How competitive are they and what is the experience of estimators?
• What are the status of the competitors?
REGIONAL MARKET CONDITIONS
Amount of work currently available in the industry :-
■ The lesser the work, the more likely contractors are forced to bid for works which may
be partly out of their competence and therefore more risky in terms of successful
implementation.
Availability of skilled workers and equipment needed :-
■ Not always available due to high demand at peak periods (January – April)
REGIONAL MARKET CONDITIONS
Rate of price escalation in labour/materials price :-
■ Different price between tender period and obtaining actual material period.
Unforeseeable circumstances which affects the final costs.
Codes and standards applicable in the region :-
■ Different area, different standards and procedures. Eg: Noise level cannot exceed
certain decibels in residential areas.
Reliability of subcontractors :-
■ Finding a good subcontractor would be a tough job without connection.
CONCLUSION
5 factors to consider:
■ Type Of Project
■ Project Size AndValue
■ Type of Client
■ Current and ProjectWorkload
■ Regional Market Conditions
FinalVerdict : OUR COMPANY IS RECOMMENDEDTO
ACCEPTTHETENDER FORTHE
PROJECT.
THE END

More Related Content

What's hot

construction quality improvement- Presentation
construction quality improvement- Presentationconstruction quality improvement- Presentation
construction quality improvement- PresentationManjunatha L.R
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...aarenneoone
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Nekumi Kida
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibsUTHM
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Supervisor de obras
Supervisor de obrasSupervisor de obras
Supervisor de obrasJohnx Tang
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignmentwendyteosy
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
BNMurthy-Updated CV- QC Inspector
BNMurthy-Updated CV- QC InspectorBNMurthy-Updated CV- QC Inspector
BNMurthy-Updated CV- QC Inspectornarasimha murthy
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof coveringEst
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Lecture 2 registration of estate agents
Lecture 2   registration of estate agentsLecture 2   registration of estate agents
Lecture 2 registration of estate agentsMohamad Isa Abdullah
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II ReportBolin Loong
 

What's hot (20)

construction quality improvement- Presentation
construction quality improvement- Presentationconstruction quality improvement- Presentation
construction quality improvement- Presentation
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...Building Construction 1 : Experience construction; a building construction re...
Building Construction 1 : Experience construction; a building construction re...
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Boq sample
Boq sampleBoq sample
Boq sample
 
Supervisor de obras
Supervisor de obrasSupervisor de obras
Supervisor de obras
 
Pp group assignment
Pp group assignmentPp group assignment
Pp group assignment
 
Cesmm
CesmmCesmm
Cesmm
 
Cv precast concrete
Cv   precast concreteCv   precast concrete
Cv precast concrete
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
074 Modern Methods of Construction
074 Modern Methods of Construction074 Modern Methods of Construction
074 Modern Methods of Construction
 
BNMurthy-Updated CV- QC Inspector
BNMurthy-Updated CV- QC InspectorBNMurthy-Updated CV- QC Inspector
BNMurthy-Updated CV- QC Inspector
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof covering
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
 
Lecture 2 registration of estate agents
Lecture 2   registration of estate agentsLecture 2   registration of estate agents
Lecture 2 registration of estate agents
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 

Viewers also liked

M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sumEst
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESwendyteosy
 
ASIS CPP Study Flash Cards and Quiz
ASIS CPP Study Flash Cards and QuizASIS CPP Study Flash Cards and Quiz
ASIS CPP Study Flash Cards and QuizBrandon Gregg, CPP
 
Advanced Planning & Scheduling
Advanced Planning &  SchedulingAdvanced Planning &  Scheduling
Advanced Planning & Schedulinguapippo
 
Advance Planning & Scheduling
Advance Planning & SchedulingAdvance Planning & Scheduling
Advance Planning & SchedulingAnand Subramaniam
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Tender processing
Tender processingTender processing
Tender processingdnyandev_d
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 

Viewers also liked (20)

Depreciation
DepreciationDepreciation
Depreciation
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
New jeevan anand
New jeevan anandNew jeevan anand
New jeevan anand
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDES
 
ASIS CPP Study Flash Cards and Quiz
ASIS CPP Study Flash Cards and QuizASIS CPP Study Flash Cards and Quiz
ASIS CPP Study Flash Cards and Quiz
 
Advanced Planning & Scheduling
Advanced Planning &  SchedulingAdvanced Planning &  Scheduling
Advanced Planning & Scheduling
 
Advance Planning & Scheduling
Advance Planning & SchedulingAdvance Planning & Scheduling
Advance Planning & Scheduling
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Tender processing
Tender processingTender processing
Tender processing
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Tender
TenderTender
Tender
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 

Similar to Estimating seminar

BS Enterprise Bathinda CONSTRUCTION COMPANY
BS Enterprise Bathinda CONSTRUCTION COMPANYBS Enterprise Bathinda CONSTRUCTION COMPANY
BS Enterprise Bathinda CONSTRUCTION COMPANYimaanbakshi
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016Sanjeewa Mahawedage
 
BS Enterprise Bathinda
BS Enterprise BathindaBS Enterprise Bathinda
BS Enterprise Bathindaimaanbakshi
 
Profile -Gaurav Pant
Profile  -Gaurav PantProfile  -Gaurav Pant
Profile -Gaurav PantGaurav Pant
 
English Gemininew Catalogue
English Gemininew CatalogueEnglish Gemininew Catalogue
English Gemininew Cataloguegemini2012
 
English Gemininew Catalogue
English Gemininew CatalogueEnglish Gemininew Catalogue
English Gemininew Cataloguegemini2012
 
CRM -Construction Industry and Construction Projects.pptx
CRM -Construction Industry and Construction Projects.pptxCRM -Construction Industry and Construction Projects.pptx
CRM -Construction Industry and Construction Projects.pptxPrasadKadam82
 
Resume Update-15-01-2015
Resume Update-15-01-2015Resume Update-15-01-2015
Resume Update-15-01-2015Engineer Haque
 
Najir mechanical engg. (HVAC)
Najir mechanical engg. (HVAC)Najir mechanical engg. (HVAC)
Najir mechanical engg. (HVAC)NAJIRHUSEN
 
Prjm project management
Prjm project managementPrjm project management
Prjm project managementRakesh Kumar
 
ASMAA ATIA-Wuzzuf-CV
ASMAA ATIA-Wuzzuf-CVASMAA ATIA-Wuzzuf-CV
ASMAA ATIA-Wuzzuf-CVAsmaa Gouda
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Amir Mohammed
 

Similar to Estimating seminar (20)

BS Enterprise Bathinda CONSTRUCTION COMPANY
BS Enterprise Bathinda CONSTRUCTION COMPANYBS Enterprise Bathinda CONSTRUCTION COMPANY
BS Enterprise Bathinda CONSTRUCTION COMPANY
 
Sanjeewa_CV updated on 23.02.2016
Sanjeewa_CV  updated on 23.02.2016Sanjeewa_CV  updated on 23.02.2016
Sanjeewa_CV updated on 23.02.2016
 
BS Enterprise Bathinda
BS Enterprise BathindaBS Enterprise Bathinda
BS Enterprise Bathinda
 
Profile -Gaurav Pant
Profile  -Gaurav PantProfile  -Gaurav Pant
Profile -Gaurav Pant
 
English Gemininew Catalogue
English Gemininew CatalogueEnglish Gemininew Catalogue
English Gemininew Catalogue
 
English Gemininew Catalogue
English Gemininew CatalogueEnglish Gemininew Catalogue
English Gemininew Catalogue
 
Eng. Ahmed Yhia
Eng.  Ahmed YhiaEng.  Ahmed Yhia
Eng. Ahmed Yhia
 
CRM -Construction Industry and Construction Projects.pptx
CRM -Construction Industry and Construction Projects.pptxCRM -Construction Industry and Construction Projects.pptx
CRM -Construction Industry and Construction Projects.pptx
 
Resume Update-15-01-2015
Resume Update-15-01-2015Resume Update-15-01-2015
Resume Update-15-01-2015
 
MAA CV 2015
MAA CV 2015MAA CV 2015
MAA CV 2015
 
Quantity Surveyor CV
Quantity Surveyor CVQuantity Surveyor CV
Quantity Surveyor CV
 
Ajay Latest CV 20 Mar
Ajay Latest CV 20 MarAjay Latest CV 20 Mar
Ajay Latest CV 20 Mar
 
CV june-2016
CV june-2016CV june-2016
CV june-2016
 
Najir mechanical engg. (HVAC)
Najir mechanical engg. (HVAC)Najir mechanical engg. (HVAC)
Najir mechanical engg. (HVAC)
 
Abdullah Hamed Rashid Al-madailwi
Abdullah Hamed Rashid Al-madailwiAbdullah Hamed Rashid Al-madailwi
Abdullah Hamed Rashid Al-madailwi
 
07-CV - Andresa Lyra - Civil Engineer - 2016
07-CV - Andresa Lyra - Civil Engineer - 201607-CV - Andresa Lyra - Civil Engineer - 2016
07-CV - Andresa Lyra - Civil Engineer - 2016
 
Prjm project management
Prjm project managementPrjm project management
Prjm project management
 
ASMAA ATIA-Wuzzuf-CV
ASMAA ATIA-Wuzzuf-CVASMAA ATIA-Wuzzuf-CV
ASMAA ATIA-Wuzzuf-CV
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
 
Muhamad Ismail_Resume-Linkedin
Muhamad Ismail_Resume-LinkedinMuhamad Ismail_Resume-Linkedin
Muhamad Ismail_Resume-Linkedin
 

Recently uploaded

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 

Recently uploaded (20)

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 

Estimating seminar

  • 1. ESTIMATING SEMINAR 2 Aishath Hussain 0320429 Andrew Mah KoonYan 0318798 Ervinna Endela 0327508 MaybelleWang Sze Kher 0327553 WendyTeo SiewYen 0328242
  • 2. Question‽ You are working for a house builder at Kuala Lumpur. Your company has recently received an invitation to tender a low cost apartment in Kajang, Selangor. You are required to make a recommendation whether to accept or decline the tender invitation. What are the 5 main factors you will consider before making the recommendation? Explain how these factors influence your decision.
  • 3. COMPANY’S BACKGROUND ■ Date of Establishment: June 2008 ■ Completed Projects : Low to medium cost residential buildings/shoplots ■ In-house Employees : Quantity Surveyors, Engineers, Project Manager etc. ■ Capital / Assets : RM250,000 in bank ■ No. of SiteWorkers : 20 ■ MachineriesOwned : 2 excavators
  • 5. TYPE OF PROJECT Site location and accessibility :- ■ Low cost apartment is suitable to be constructed around Kajang ■ Existing road to provide safe access and egress ■ 35km away from our office Past experience with similar projects ;- ■ Projects undertaken include low to medium range residential buildings
  • 6. TYPE OF PROJECT Is the project within the company boundaries? ■ Yes, capable of delivering the project due to past experiences. Method of construction? ■ Adopt traditional construction method. (eg.Timber formwork)
  • 7. TYPE OF PROJECT Is the project complexity beyond the capability of the company? ■ No, it involves simple and typical designs only The risk involved considering the nature of the work? ■ Accidents and injuries might occur at site due to traditional method of construction ■ Exterior work such as concreting and painting depends on weather condition
  • 9. PROJECT SIZEANDVALUE Project Size :- ■ 4 units x 5 storeys x 4 blocks ProjectValue :- ■ RM 100,000 per unit x 4 units x 5 storeys x 4 blocks = RM8 million
  • 10. PROJECT SIZEANDVALUE Projected cash flow required during execution :- ■ Standard S Curve onGraph – past cost information and details of completed. ■ Critical Path Method (CPM) – technique for project planning made up of a number of individual activities.
  • 11. PROJECT SIZEANDVALUE Is the project size beyond the capability of the firm? ■ Yes. It is within our boundaries as it is a medium scaled project. Equipment, Labour and Plants :- ■ Equipment(s)– owns 2 excavators. ■ Labour(s) – 20-30 workers available.
  • 12. PROJECT SIZEANDVALUE Risks of project :- ■ Force majeure (construction risk) ■ Late changes / additional work ■ Site access ■ Labour productivity (performance risk) ■ Defective work – latent defects ■ Vandalism (security) ■ Intrusion ■ Delays ■ Liquidated ascertained damages (LAD)
  • 13. PROJECT SIZEANDVALUE Conditions of contract :- ■ Date of possession, deferment of possession, progress, delays, completion date ■ Liquidated ascertained damages ■ Partial possession ■ Quality of works ■ Testing and defects (Defects Liability Period)
  • 15. TYPE OF CLIENT Public Sector or Private Sector ■ Private Sector – Kelly Jeners Financial capability of the client :- ■ Financially strong, reliable and has good financial records.
  • 16. TYPE OF CLIENT Reputation of the client :- ■ Well known among the peers in the industry. ■ Kelly Jeners delivers on its promises to the customers and is worthy of respect and trust. Relationship with the client :- ■ Has an existing and positive relationship with the client.
  • 17. TYPE OF CLIENT Expectations of the client :- ■ Client expects contractor to focus on their requirements, all of their needs and how to solve their problems. Form of contract :- ■ PAM Contract 2006 (With Quantities)
  • 19. CURRENTAND PROJECTED WORKLOAD OFTHE COMPANY The need for work :- ■ The need for work is present since the company is only dealing with a medium range cost residential project at the moment. Other projects currently out for tender :- ■ Currently bidding for 2 projects and one of them is the Kajang low-cost apartment project.
  • 20. CURRENTAND PROJECTED WORKLOAD OFTHE COMPANY Forecast for upcoming projects :- ■ To be able to secure at least 5 projects in the next 2 years. Availability of in-house staff :- ■ Yes. Quantity Surveyors, Engineers, Project Managers, etc.
  • 21. CURRENTAND PROJECTED WORKLOAD OFTHE COMPANY Labour force availability :- ■ 20 workers. Availability of equipment owned by the contractor :- ■ 2 excavators.
  • 23. REGIONAL MARKET CONDITIONS Economical situation overall and the construction industry :- ■ Have to look into the economic factors of the country, such as GDP growth rate, or GDP for construction (July 2016 – RM11899 million) • How many projects are currently available in the market? • How many competitors are expected to tender? • How competitive are they and what is the experience of estimators? • What are the status of the competitors?
  • 24. REGIONAL MARKET CONDITIONS Amount of work currently available in the industry :- ■ The lesser the work, the more likely contractors are forced to bid for works which may be partly out of their competence and therefore more risky in terms of successful implementation. Availability of skilled workers and equipment needed :- ■ Not always available due to high demand at peak periods (January – April)
  • 25. REGIONAL MARKET CONDITIONS Rate of price escalation in labour/materials price :- ■ Different price between tender period and obtaining actual material period. Unforeseeable circumstances which affects the final costs. Codes and standards applicable in the region :- ■ Different area, different standards and procedures. Eg: Noise level cannot exceed certain decibels in residential areas. Reliability of subcontractors :- ■ Finding a good subcontractor would be a tough job without connection.
  • 26. CONCLUSION 5 factors to consider: ■ Type Of Project ■ Project Size AndValue ■ Type of Client ■ Current and ProjectWorkload ■ Regional Market Conditions FinalVerdict : OUR COMPANY IS RECOMMENDEDTO ACCEPTTHETENDER FORTHE PROJECT.