Project Kick- Off Presentation
for
Construction of State Sports Academy Cum
International Standard Modern Cricket Stadium
Project at Rajgir, Nalanda, Bihar
08th October, 2018
CONTENTS
1
• PROJECT BRIEF
2
• COMMERCIAL TERMS & CONDITIONS
3
• SITE LOCATION, MASTER PLAN
4
• MAJOR QUANTITIES
PROJECT BRIEF
1
PROJECT BRIEF
 Name of the Project: Construction of State Sports Academy cum International
Standard Modern Cricket Stadium
 Location of the Project: Rajgir, Nalanda, Bihar (near Nalanda University campus)
 Client: Building Construction Division, Bihar.
 Architect / PMC : Arcop Associates Private Limited, New Delhi.
 Type of Contract: Percentage Rate for Scheduled Items and Item Rate for
Non-Scheduled items
 Contract Value: Rs. 740.82 Cr. (Client estimated value – 656.36 cr.)
 Project Duration: 24 months
 Defect Liability Period: 36 months
LOA
BUILT UP AREA
Sl No Name of Structure Building
Details
Individual
BUA in Sqft
BUA in Sqft
(Subtotal)
1 Sports Halls
a Sports Hall - 1 G+1 69,810.88
b Sports Hall - 2 G+1 68,670.32
b Sports Hall - 3 G+1 69,810.88
d Sports Hall - 4 G+1 63,397.92
e Sports Hall - 5 G+1 68,670.32
f Sports Hall - 6 G+1 68,196.88
TOTAL of 6sports halls 4,08,557.20
2 Academic block G+2 72,565.44 72,565.44
3 Hostels Blocks
a Transit hostel block i/c commercial G+4 48,667.48
b Boy's hostel G+4 60,335.73
c Girl's hostel G+4 35,520.27
d Dinning hall G 14,257.00
TOTAL of hostel blocks 1,58,780.48
BUILT UP AREA
4 Residential Blocks
a Coaches Suites G+7 42,053.31
b Staff quarter type - III G+3 15,866.59
c Staff quarter type - IV G+6 45,202.76
d Assistant Director's bungalow G+1 7,074.70
e Deputy director's bungalow G 3,507.76
f Director's bungalow G 2,428.53
g Menial quarter G 1,291.20
Total of Residential blocks 1,17,424.85
5 Cricket Stadium ( 38900 capacity)
a Pavilion G+5 1,53,814.20
b Reverse pavilion G+3 1,18,177.08
c General stands - East & West G+4 2,90,950.40
Total of Cricket stadium 5,62,941.68
6 Building for Footbal & hockey
field and Athletic Track
G 18,270.48 18,270.48
Total BUA 13,38,540.13
PROJECT BRIEF
Sl No Subheads
1 All Civil & Structural Work including piling
2 Steel Structural & Roof sheeting work
3 Tensile fabric work including special structural steel work
4 Internal & External PHE
5 Internal & External Electrical
6 Stadium Lighting
7 HVAC
8 Fire Fighting
9 BMS
10 Signage
11 Furnitures & Interiors
12 Stadium & sports Hall chairs
13 Landscaping
14 Preparation of cricket field, foodball field, athletic track
15 Indoor sports flooring
Major subhead of works
Note - TOTAL PLOT AREA – 90 ACRE
COMMERCIAL TERMS &
CONDITIONS
2
Sl. No. Features Detail
1 Earnest Money Deposit Rs. 6.66 Cr in the form of Demand Draft / FDR / Bank Guarantee.
2 Mobilisation Advance 10 % of contract value against BG of 100% in two or more
instalments. Interest @ 10% per annum. 2nd and subsequent
instalments shall be released only after furnishing of proof of
satisfactory utilization of earlier instalment. Recovery shall be start
after achieving gross work done of 10% of CV and recovery along
with interest shall be done in such a rate so that the whole
recovery may be completed within completion of 80% of CV.
3 Secured Advance @ 75% of assessed value of non perishable material. On perishable
material secured advance may by granted as per the opinion of
Superintending Engineer.
4 Performance Guarantee 2% of contract value valid up DLP + 28 days. PBG shall be submitted
within 15 days from the date of LOA.
5 Security / Retention Money A sum of 8% shall be deducted from each R/A bills. 50% shall be
released after 06 months of completion and rest shall be released
after DLP.
COMMERCIAL TERMS & CONDITIONS
Sl. No. Features Detail
6 Interim Payment The amount admissible shall be paid by 10th working day after the day
of presentation of the bill by the contractor to the Engineer-in-Charge
or his Assistant Engineer. Minimum monthly bill value is 5 cr.
7 Final Bill Payment The final bill shall be submitted by the contractor within three months
of physical completion of the work or within one month of the date of
the final certificate of completion furnished by the Engineer-in-Charge
whichever is earlier. Payment will be made within 4 months from the
date of receipt of the Bill.
8 Taxes & Duties All tendered rates shall be inclusive of all taxes and levies payable
under respective statutes. However, pursuant to the constitution (46th
amendment) act 1982, if any further tax or levy is imposed by statute
after the last stipulated date for the receipt of tender including
extensions if any and the contractor thereupon necessarily and
properly pays such taxes / levies the contractor shall be reimbursed
the amount so paid, provided such payments, if any, is not, in
the opinion of the Chief Engineer (whose decision shall be
final and binding on the contractor) attributable or delay in
execution of work within the control of the contractor.
9 Liquidated Damages 2% of CV per month delay maximum up to 10% of CV. 1% of the
tendered value of work will be with hold for failure of each Mile stone.
COMMERCIAL TERMS & CONDITIONS
Sl. No. Features Detail
10 Site Infrastructure The contractor shall be provided adequate area for construction of
storage/ office space for his use. The space has to be maintained/
constructed by the contractor as per his usage requirements.
11 Land for Labour Hutment The contractor to submit the Project Management Plan
showing the material storing yard, Batching Plant , facilities
for labour ( Accommodation, toilets etc.),approach roads,
site office of owner, PMC and Contractor, location for
preservation of top soil, staging and spill prevention
measures, erosion and sedimentation control measures
etc. The plan should be such that area of disturbance
should be minimum and get the same approved by
Engineer-In-charge prior to start of work at site.
12 Construction Water Contractor’s responsibility.
COMMERCIAL TERMS & CONDITIONS
13 Construction Power Contractor’s responsibility.
14 Quantity Variation As per PWD Code clause 182A,292XII,293XVII & 294XVI
Sl. No. Features Detail
15 Client Facility Client office of 2300 Sqft including all furniture, computers office
equipment, drinking water, electricity, 2 nos. car including
maintenance shall be provided.
16 Extra Items On the basis of the cost to the Contractor at Site of Works plus 15%
to cover all overheads and profit.
17 Arbitration As per the Arbitration and Conciliation act 1996. Single Arbitrator
shall be appointed by Engineer-in-chief. If any fees shall be paid to
the Arbitrator, the same shall be paid by both the parties equally.
18 Defect Liability Period 36 months from date of completion.
19 Bonus 1% of the CV per month computed on per day basis subject to a
maximum limit of 5% of CV.
20 Base Rate Not Applicable
21 Escalation Applicable as per clause 10CC.
22 EPF & ESI The contractor shall be responsible for all statutory
provisions and deductions towards ESI, PF or any other, as
the case may be or any other levies and taxes shall be
borne by the contractor. No claim in this regard shall be
entertained.
COMMERCIAL TERMS & CONDITIONS
SITE LOCATION & MASTER
PLAN
3
SITE LOCATION
SITE LOCATION AS PER GOOGLE MAP
MASTER PLAN
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
SITE PHOTOGRAPHS
MAJOR QUANTITIES
4
MAJOR QUANTITIES (APPROXIMATE)
Sl No Item Description Unit Quantity
1 Excavation Cum 1,21,891
2 Earth filling Cum 5,74,900
3 500mm dia piling ( approx 20m long) Rm 1,46,246
4 Concrete excluding piling Cum 1,43,406
5 Form work Sqm 4,29,545
6 Reinforcement work MT 22,500
7 Brick work Cum 26,238
8 Half brick work Sqm 48,260
9 Plastering Work Sqm 2,61,642
10 Putty & Painting Sqm 4,66,201
11 Structural steel work MT 3,772
12 Total tile, granite work Sqm 2,21,015
13 False ceiling Sqm 36,619
14 Semi unitized glazing system Sqm 7,475
QUANTITY OF MAJOR CIVIL ITEMS
MAJOR QUANTITIES (APPROXIMATE) – contd.
15 ACP cladding Sqm 9,718
16 Road work Sqm 64,641
17 Double skin insulated roofing system (Galvalume) Sqm 21,308
18 GFRC jali Sqm 18,020
19 100mm thick Kota & Cuddaph cobble stone Sqm 7,764
20 Vinyl flooring Sqm 5,322
21 Sports flooring Sqm 3,415
22 Cricket ground Sqm 19,000
23 Football ground Sqm 13,472
24 Astro turf for Hocky ground Sqm 6,388
25 Athletictrac Sqm 4,232
26 Rubber flooring Sqm 2,764
27 Tensile fabricwork incluidng supporting structure Sqm 16,050
28 Out door chair Nos 38900
29 Indoor chair Nos 10,100
MAJOR QUANTITIES (APPROXIMATE) – contd.
Service Equipment Description Capacity Qty
Transformer 33 KV/11 KV transformer 4.0/5.0 MVA 3 Nos
11 KV/0.415 KV transformer 1.6MVA 6 nos
HT Panel Five Panel Board 33KV 1 Set
Eleven Panel Board 11 kv 1 set
PACKAGE SUB-STATION-For
Residential
11KV / 0.433 KV COMPACT
SUB-STATION
800 KVA 2 nos.
PACKAGE SUB-STATION (For
HVAC Plant)
11KV / 0.433 KV COMPACT
SUB-STATION
1600 KVA 2 nos.
LT Panel Main Panel 415 V 3 Sets
DG 11 KV Silent TYPE 1500KVA/1010KVA 1 nos/2nos
Cricket Stadium Sports
Lighting
400 nos fixture in each High
masts (55 Mtr H)
1500W 4 nos tower
Indoor Sports LED lighting LED Sports Floodlight Fixture 900W 110 Nos
TRACK & FOOTBALL 144 nos fixture in each High
masts (40 Mtr H)
1500W 4 nos tower
Score boards & timing system for indoor sports halls 14nos
Centrifugal Chiller 415 V LT Chiller 565 TR 4 nos.
Cooling Tower Induced Draft 680TR 4 nos.
AHU/CHU Total 110 Nos
QUANTITY OF MAJOR MEP ITEMS
HVAC
Electrical
MAJOR QUANTITIES (APPROXIMATE) – contd.
Main Electric Motor Driven
Pump
2280 LPM, 90 M Head 2 nos.
Engine Driven Pump 2280 LPM, 90 M Head 2 nos.
Jockey Pump 180 LPM, 90 M Head 2 nos.
Electric Driven Pump-Water
Curtain
2050 LPM, 55 M Head 1 No
Electric Driven Pump-Terrace 900 LPM, 35 M Head 11 nos.
Piping MSPipe 25mm to 200 mm
dia
29KM
WTP 25200 LPH 1 set
STP 260KLD 1 set
External piping External Drainage piping-RCC
Pipe-np2/Np3
150mm to
1800mm
14 KM
RACING POOL 50 M (L), 25 M (W)
and 2.0 M Depth
4 nos
Elevator Passenger Lift Lift Verious type 17 nos
PHE
Fire
Fighting
LIST OF EQUIPMENT CONSIDERED
Sl No Name of Equipment Capacity Nos.
A Concrete
1 Batching Plant 30cum / hr 2
2 Transit Mixer 6cum 7
3 Backhoe loader 1
4 Concrete pump 3
5 Concrete Placer Boom 1
6 High frequency vibrator 6
7 Curing pump 10
B Reinforcement
1 Bar bending Machine 8
2 Bar Shearing machine 8
3 Trailor 1
4 Hydra 1
MAJOR EQUIPMENTS CONSIDERED
LIST OF EQUIPMENT CONSIDERED
C Overall
1 Hydra 1
2 Tower Crane 4
3 Builder Hoist 10
4 Crawler Crane 150 MT 1
5 Weigh Bridge 1
6 Tractor / Dumper / Mini dumper 7
7 Car 4
8 Bus 2
9 DG 125 KVA 7
10 DG 62.5 KVA 2
11 DG for labour camp 40 KVA 1
D Structural Steel work
1 Crawler crane 75 MT 2
2 Hydra / pick & carry crane 10 MT 5
3 Trailor 2
E Tensile Fabric with supporting structure
In specilized vendors scope
THANK YOU

More Related Content

Similar to Rajgir Sports Complex_Project Kick Off Presentation.pptx

Measurement iv
Measurement ivMeasurement iv
Measurement ivtfkc1212
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95MaximaSheffield592
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final accountahmong4
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2tfkc1212
 
contract difference for 12 sod modified 28_1_14
contract difference for 12 sod modified 28_1_14contract difference for 12 sod modified 28_1_14
contract difference for 12 sod modified 28_1_14David King
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignmentashleyyeap
 
Infopack pavilion court royale 31.01.14
Infopack pavilion court royale 31.01.14Infopack pavilion court royale 31.01.14
Infopack pavilion court royale 31.01.14Dakssh
 
Presentation. jkr lawatan IBS kilang HC Precast System
Presentation.   jkr lawatan IBS kilang HC Precast SystemPresentation.   jkr lawatan IBS kilang HC Precast System
Presentation. jkr lawatan IBS kilang HC Precast SystemTeow Beng Hur
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSTeow Beng Hur
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogdenahcitycouncil
 
Elan Sector-80,service apartments
Elan Sector-80,service apartmentsElan Sector-80,service apartments
Elan Sector-80,service apartmentsrealagentck
 

Similar to Rajgir Sports Complex_Project Kick Off Presentation.pptx (20)

LGC PP-ABC Int
LGC PP-ABC IntLGC PP-ABC Int
LGC PP-ABC Int
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Measurement iv
Measurement ivMeasurement iv
Measurement iv
 
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95CE 444 Contracts and SpecificationsAssignment 7 -  Conduct a 95
CE 444 Contracts and SpecificationsAssignment 7 - Conduct a 95
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
total report
total reporttotal report
total report
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Building ssr 2013-14
Building ssr 2013-14Building ssr 2013-14
Building ssr 2013-14
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2
 
contract difference for 12 sod modified 28_1_14
contract difference for 12 sod modified 28_1_14contract difference for 12 sod modified 28_1_14
contract difference for 12 sod modified 28_1_14
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
 
Infopack pavilion court royale 31.01.14
Infopack pavilion court royale 31.01.14Infopack pavilion court royale 31.01.14
Infopack pavilion court royale 31.01.14
 
Presentation. jkr lawatan IBS kilang HC Precast System
Presentation.   jkr lawatan IBS kilang HC Precast SystemPresentation.   jkr lawatan IBS kilang HC Precast System
Presentation. jkr lawatan IBS kilang HC Precast System
 
Presentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPSPresentation. _ JKR Lawatan kilang HCPS
Presentation. _ JKR Lawatan kilang HCPS
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogden
 
Draft vol. ii
Draft vol. iiDraft vol. ii
Draft vol. ii
 
Elan Sector-80,service apartments
Elan Sector-80,service apartmentsElan Sector-80,service apartments
Elan Sector-80,service apartments
 

Recently uploaded

Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxgeorgebrinton95
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 

Recently uploaded (20)

Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 

Rajgir Sports Complex_Project Kick Off Presentation.pptx

  • 1. Project Kick- Off Presentation for Construction of State Sports Academy Cum International Standard Modern Cricket Stadium Project at Rajgir, Nalanda, Bihar 08th October, 2018
  • 2. CONTENTS 1 • PROJECT BRIEF 2 • COMMERCIAL TERMS & CONDITIONS 3 • SITE LOCATION, MASTER PLAN 4 • MAJOR QUANTITIES
  • 4. PROJECT BRIEF  Name of the Project: Construction of State Sports Academy cum International Standard Modern Cricket Stadium  Location of the Project: Rajgir, Nalanda, Bihar (near Nalanda University campus)  Client: Building Construction Division, Bihar.  Architect / PMC : Arcop Associates Private Limited, New Delhi.  Type of Contract: Percentage Rate for Scheduled Items and Item Rate for Non-Scheduled items  Contract Value: Rs. 740.82 Cr. (Client estimated value – 656.36 cr.)  Project Duration: 24 months  Defect Liability Period: 36 months
  • 5. LOA
  • 6. BUILT UP AREA Sl No Name of Structure Building Details Individual BUA in Sqft BUA in Sqft (Subtotal) 1 Sports Halls a Sports Hall - 1 G+1 69,810.88 b Sports Hall - 2 G+1 68,670.32 b Sports Hall - 3 G+1 69,810.88 d Sports Hall - 4 G+1 63,397.92 e Sports Hall - 5 G+1 68,670.32 f Sports Hall - 6 G+1 68,196.88 TOTAL of 6sports halls 4,08,557.20 2 Academic block G+2 72,565.44 72,565.44 3 Hostels Blocks a Transit hostel block i/c commercial G+4 48,667.48 b Boy's hostel G+4 60,335.73 c Girl's hostel G+4 35,520.27 d Dinning hall G 14,257.00 TOTAL of hostel blocks 1,58,780.48
  • 7. BUILT UP AREA 4 Residential Blocks a Coaches Suites G+7 42,053.31 b Staff quarter type - III G+3 15,866.59 c Staff quarter type - IV G+6 45,202.76 d Assistant Director's bungalow G+1 7,074.70 e Deputy director's bungalow G 3,507.76 f Director's bungalow G 2,428.53 g Menial quarter G 1,291.20 Total of Residential blocks 1,17,424.85 5 Cricket Stadium ( 38900 capacity) a Pavilion G+5 1,53,814.20 b Reverse pavilion G+3 1,18,177.08 c General stands - East & West G+4 2,90,950.40 Total of Cricket stadium 5,62,941.68 6 Building for Footbal & hockey field and Athletic Track G 18,270.48 18,270.48 Total BUA 13,38,540.13
  • 8. PROJECT BRIEF Sl No Subheads 1 All Civil & Structural Work including piling 2 Steel Structural & Roof sheeting work 3 Tensile fabric work including special structural steel work 4 Internal & External PHE 5 Internal & External Electrical 6 Stadium Lighting 7 HVAC 8 Fire Fighting 9 BMS 10 Signage 11 Furnitures & Interiors 12 Stadium & sports Hall chairs 13 Landscaping 14 Preparation of cricket field, foodball field, athletic track 15 Indoor sports flooring Major subhead of works Note - TOTAL PLOT AREA – 90 ACRE
  • 10. Sl. No. Features Detail 1 Earnest Money Deposit Rs. 6.66 Cr in the form of Demand Draft / FDR / Bank Guarantee. 2 Mobilisation Advance 10 % of contract value against BG of 100% in two or more instalments. Interest @ 10% per annum. 2nd and subsequent instalments shall be released only after furnishing of proof of satisfactory utilization of earlier instalment. Recovery shall be start after achieving gross work done of 10% of CV and recovery along with interest shall be done in such a rate so that the whole recovery may be completed within completion of 80% of CV. 3 Secured Advance @ 75% of assessed value of non perishable material. On perishable material secured advance may by granted as per the opinion of Superintending Engineer. 4 Performance Guarantee 2% of contract value valid up DLP + 28 days. PBG shall be submitted within 15 days from the date of LOA. 5 Security / Retention Money A sum of 8% shall be deducted from each R/A bills. 50% shall be released after 06 months of completion and rest shall be released after DLP. COMMERCIAL TERMS & CONDITIONS
  • 11. Sl. No. Features Detail 6 Interim Payment The amount admissible shall be paid by 10th working day after the day of presentation of the bill by the contractor to the Engineer-in-Charge or his Assistant Engineer. Minimum monthly bill value is 5 cr. 7 Final Bill Payment The final bill shall be submitted by the contractor within three months of physical completion of the work or within one month of the date of the final certificate of completion furnished by the Engineer-in-Charge whichever is earlier. Payment will be made within 4 months from the date of receipt of the Bill. 8 Taxes & Duties All tendered rates shall be inclusive of all taxes and levies payable under respective statutes. However, pursuant to the constitution (46th amendment) act 1982, if any further tax or levy is imposed by statute after the last stipulated date for the receipt of tender including extensions if any and the contractor thereupon necessarily and properly pays such taxes / levies the contractor shall be reimbursed the amount so paid, provided such payments, if any, is not, in the opinion of the Chief Engineer (whose decision shall be final and binding on the contractor) attributable or delay in execution of work within the control of the contractor. 9 Liquidated Damages 2% of CV per month delay maximum up to 10% of CV. 1% of the tendered value of work will be with hold for failure of each Mile stone. COMMERCIAL TERMS & CONDITIONS
  • 12. Sl. No. Features Detail 10 Site Infrastructure The contractor shall be provided adequate area for construction of storage/ office space for his use. The space has to be maintained/ constructed by the contractor as per his usage requirements. 11 Land for Labour Hutment The contractor to submit the Project Management Plan showing the material storing yard, Batching Plant , facilities for labour ( Accommodation, toilets etc.),approach roads, site office of owner, PMC and Contractor, location for preservation of top soil, staging and spill prevention measures, erosion and sedimentation control measures etc. The plan should be such that area of disturbance should be minimum and get the same approved by Engineer-In-charge prior to start of work at site. 12 Construction Water Contractor’s responsibility. COMMERCIAL TERMS & CONDITIONS 13 Construction Power Contractor’s responsibility. 14 Quantity Variation As per PWD Code clause 182A,292XII,293XVII & 294XVI
  • 13. Sl. No. Features Detail 15 Client Facility Client office of 2300 Sqft including all furniture, computers office equipment, drinking water, electricity, 2 nos. car including maintenance shall be provided. 16 Extra Items On the basis of the cost to the Contractor at Site of Works plus 15% to cover all overheads and profit. 17 Arbitration As per the Arbitration and Conciliation act 1996. Single Arbitrator shall be appointed by Engineer-in-chief. If any fees shall be paid to the Arbitrator, the same shall be paid by both the parties equally. 18 Defect Liability Period 36 months from date of completion. 19 Bonus 1% of the CV per month computed on per day basis subject to a maximum limit of 5% of CV. 20 Base Rate Not Applicable 21 Escalation Applicable as per clause 10CC. 22 EPF & ESI The contractor shall be responsible for all statutory provisions and deductions towards ESI, PF or any other, as the case may be or any other levies and taxes shall be borne by the contractor. No claim in this regard shall be entertained. COMMERCIAL TERMS & CONDITIONS
  • 14. SITE LOCATION & MASTER PLAN 3
  • 16. SITE LOCATION AS PER GOOGLE MAP
  • 24. MAJOR QUANTITIES (APPROXIMATE) Sl No Item Description Unit Quantity 1 Excavation Cum 1,21,891 2 Earth filling Cum 5,74,900 3 500mm dia piling ( approx 20m long) Rm 1,46,246 4 Concrete excluding piling Cum 1,43,406 5 Form work Sqm 4,29,545 6 Reinforcement work MT 22,500 7 Brick work Cum 26,238 8 Half brick work Sqm 48,260 9 Plastering Work Sqm 2,61,642 10 Putty & Painting Sqm 4,66,201 11 Structural steel work MT 3,772 12 Total tile, granite work Sqm 2,21,015 13 False ceiling Sqm 36,619 14 Semi unitized glazing system Sqm 7,475 QUANTITY OF MAJOR CIVIL ITEMS
  • 25. MAJOR QUANTITIES (APPROXIMATE) – contd. 15 ACP cladding Sqm 9,718 16 Road work Sqm 64,641 17 Double skin insulated roofing system (Galvalume) Sqm 21,308 18 GFRC jali Sqm 18,020 19 100mm thick Kota & Cuddaph cobble stone Sqm 7,764 20 Vinyl flooring Sqm 5,322 21 Sports flooring Sqm 3,415 22 Cricket ground Sqm 19,000 23 Football ground Sqm 13,472 24 Astro turf for Hocky ground Sqm 6,388 25 Athletictrac Sqm 4,232 26 Rubber flooring Sqm 2,764 27 Tensile fabricwork incluidng supporting structure Sqm 16,050 28 Out door chair Nos 38900 29 Indoor chair Nos 10,100
  • 26. MAJOR QUANTITIES (APPROXIMATE) – contd. Service Equipment Description Capacity Qty Transformer 33 KV/11 KV transformer 4.0/5.0 MVA 3 Nos 11 KV/0.415 KV transformer 1.6MVA 6 nos HT Panel Five Panel Board 33KV 1 Set Eleven Panel Board 11 kv 1 set PACKAGE SUB-STATION-For Residential 11KV / 0.433 KV COMPACT SUB-STATION 800 KVA 2 nos. PACKAGE SUB-STATION (For HVAC Plant) 11KV / 0.433 KV COMPACT SUB-STATION 1600 KVA 2 nos. LT Panel Main Panel 415 V 3 Sets DG 11 KV Silent TYPE 1500KVA/1010KVA 1 nos/2nos Cricket Stadium Sports Lighting 400 nos fixture in each High masts (55 Mtr H) 1500W 4 nos tower Indoor Sports LED lighting LED Sports Floodlight Fixture 900W 110 Nos TRACK & FOOTBALL 144 nos fixture in each High masts (40 Mtr H) 1500W 4 nos tower Score boards & timing system for indoor sports halls 14nos Centrifugal Chiller 415 V LT Chiller 565 TR 4 nos. Cooling Tower Induced Draft 680TR 4 nos. AHU/CHU Total 110 Nos QUANTITY OF MAJOR MEP ITEMS HVAC Electrical
  • 27. MAJOR QUANTITIES (APPROXIMATE) – contd. Main Electric Motor Driven Pump 2280 LPM, 90 M Head 2 nos. Engine Driven Pump 2280 LPM, 90 M Head 2 nos. Jockey Pump 180 LPM, 90 M Head 2 nos. Electric Driven Pump-Water Curtain 2050 LPM, 55 M Head 1 No Electric Driven Pump-Terrace 900 LPM, 35 M Head 11 nos. Piping MSPipe 25mm to 200 mm dia 29KM WTP 25200 LPH 1 set STP 260KLD 1 set External piping External Drainage piping-RCC Pipe-np2/Np3 150mm to 1800mm 14 KM RACING POOL 50 M (L), 25 M (W) and 2.0 M Depth 4 nos Elevator Passenger Lift Lift Verious type 17 nos PHE Fire Fighting
  • 28. LIST OF EQUIPMENT CONSIDERED Sl No Name of Equipment Capacity Nos. A Concrete 1 Batching Plant 30cum / hr 2 2 Transit Mixer 6cum 7 3 Backhoe loader 1 4 Concrete pump 3 5 Concrete Placer Boom 1 6 High frequency vibrator 6 7 Curing pump 10 B Reinforcement 1 Bar bending Machine 8 2 Bar Shearing machine 8 3 Trailor 1 4 Hydra 1 MAJOR EQUIPMENTS CONSIDERED
  • 29. LIST OF EQUIPMENT CONSIDERED C Overall 1 Hydra 1 2 Tower Crane 4 3 Builder Hoist 10 4 Crawler Crane 150 MT 1 5 Weigh Bridge 1 6 Tractor / Dumper / Mini dumper 7 7 Car 4 8 Bus 2 9 DG 125 KVA 7 10 DG 62.5 KVA 2 11 DG for labour camp 40 KVA 1 D Structural Steel work 1 Crawler crane 75 MT 2 2 Hydra / pick & carry crane 10 MT 5 3 Trailor 2 E Tensile Fabric with supporting structure In specilized vendors scope