SlideShare a Scribd company logo
1 of 31
Financial Analysis of Sale/Purchase of Electricity
vis-a-vis
Water Usage Charges/Net Hydel Profit
1
2
Water Use Charges (WUC)
• In line with the decision of CCI KP and Punjab provinces are
being paid NHP @ Rs.1.10/KWh
• Under Mangla Dam Raising Agreement 2003, WUC are being
paid to GoAJ&K @ Rs. 0.15/KWh
• Income of MHP from WUC@ Rs. 0.15/KWh for FY 15-16 is
Rs. 1.076 billion (For FY 16-17 estimated Income is Rs. 1.2 billion)
• Potential Income of MHP from WUC @ Rs 1.10/KWh for
FY 15-16 is Rs. 7.888 billion (7171MKWh)
• Annual loss from MHP to GoAJ&K is Rs 6.812 billion
3
Water Use Charges (WUC)
• Income of NJHEP (5150 MKWh) from WUC @ Rs 0.425/KWh
would be almost Rs. 2.189 billion
• Income of NJHEP from WUC @ Rs. 1.10/KWh would be almost
Rs. 5.665 billion (Rs. 3.476 billion excess)
• Total annual Income from WUC @ 0.15/KWh and 0.425 /KWh
against Mangla HPP and NJHEP is Rs. 3.265 billion
• Total annual Income from WUC @ Rs 1.10/KWh against
Mangla HPP and NJHEP would be almost Rs. 13.553 billion
• Net raising in annual Income from MHP and NJHP is
Rs. 10.288 billion
• On the basis of Arbitration Award 2006 claim of WUC against
Mangla HPP since 1990 would almost be Rs. 356.068 billion
4
Sale of Electricity From Jagran-1 HPP
• Power Purchase Agreement (PPA) of Jagran-1 HPP not being
signed on the pretext of GoAJ&K being defaulter and beneficiary
of low tariff
• Annual loss of approximately Rs. 700 million due to non signing
of PPA
• Due to delay in signing of PPA of 30.4 MW Jagran-I HPP
outstanding amount on account of energy charges since Aug. 2010
is Rs. 3.178 billion
5
Sale & Purchase of Electricity
• According to the clause 5.2 (b) of the Mangle Dam Raising
Agreement , power tariff beyond September, 2003 was fixed by GoP
on the recommendation of Standing Sub-Committee notified by
Ministry of KANA and SAFRON
• Accordingly, power tariff for AJK was decided on the basis of
following guidelines issued in the meeting of Sub-Committee held on
11-09-2003
i. The power tariff for AJ&K from 1st Oct 2003 shall be Rs. 2.59 per
unit. The basis of the decision was that WAPDA charger Rs. 2.58
per unit for domestic consumers upto 100 units. The AJ&K
Government agreed to reduce losses from 37.5% to 27%.
Accordingly, the rate per unit should be Rs. 2.60. The committee
agreed to take the average of these tow rates at Rs. 2.59 per unit
6
Sale & Purchase of Electricity
ii. Since the AJ&K Government don't have provision in their
current year’s budget to pick up additional liability of
Rs. 0.27 per unit, the sub-committee recommended that the
finances required in this regard would be provided by the
Federal Government
iii. The reduction in losses will be reviewed on monthly basis
and any financial gains from reduced losses would be
adjusted to reduce the Government subsidy
• On 08-12-2015 the sub-committee recommended revised tariff
for AJ&K@ Rs. 5.79 per unit
• Losses reported against purchase and sale of electricity for the
last 18 years are almost 39%
• Outstanding liabilities against electricity charges claimed by
WAPDA are almost Rs. 76.463 billion
7
Sr. Description
Amount
(Rs. in billion)
B.E for FY 2015-16 from sale of Electricity 11.000
Position at Purchase Rate of Rs. 2.59/KWh
1. Income from Sale of Electricity during FY 2015-16 8.661
2.
Expenditures by Electricity Department
i. Purchase of Electricity from WAPDA @ Rs. 2.59/KWh = Rs. 4.300 b
ii. Other administrative expenditures = Rs. 1.660 b
5.960**
3. Net income from sale of Electricity (as reported by Finance Department) 2.701
Scenario at the Purchase Rate of Rs. 5.79/KWh
1. Income from sale of Electricity 8.661
2.
Expenditure
i. Purchase of Electricity from WAPDA @ Rs. 5.79/KWh = Rs. 8.963 b
ii. Other administrative expenditures = Rs. 1.660 b
10.623**
3. Net expected loss -1.962
* Power Tariff for consumers of AJ&K is same as for rest of Pakistan
**Excluding Rs. 0.660 billion released to Electricity department from Development budget.
Sale and Purchase of Electricity*
8
Recommendation
• The GoAJ&K may ask the GoP for the same treatment
as is given to provinces/DISCOs in terms of :-
i. Sharing of benefits from Hydel Proceeds
ii. Sale and Purchase of electricity
9
THANKS
10
• Article 161 (2) of Constitution of Islamic Republic of Pakistan guarantees the
payment of Net Hydel Profit (NHP) to the relevant Province. Following is the
text:
“The net profits earned by the Federal Government or any undertaking
established or administered by the Federal Government for the bulk generation
of power at a hydro electric station shall be paid to the province in which the
hydro electric station is situated”.
Explanation:
For the purpose of this clause it is further explained in the Article that:
“Net Profit” shall be computed by deducting from the revenues accruing from the
bulk supply of power from the bus-bars of a hydro electric station at a rate to be
determined by the Council of Common Interests (CCI), the operating expenses of
the station which shall include any sums payable as taxes, duties, interest or return
on investment and depreciations and element of obsolescence, and overheads and
provision for reserves”.
Extract of Article 161 of the Constitution
Next
Back
11
Detail of Power Generation by Mangla Power Station
Units No Commissioning
1 03-07-1967
2 14-07-1967
3 07-03-1968
4 17-06-1969
5 29-12-1973
6 11-03-1974
7 25-05-1981
8 22-07-1981
9 24-09-1993
10 06-07-1994
Next
Back
12
UNIT
NO DATE UNIT
NO. DATE
1 30.04.1977 8 03.12.1982
2 27.05.1977 9 05.02.1985
3 18.06.1977 10 29.04.1985
4 11.07.1977 11 14.02.1993
5 03.08.1982 12 23.11.1992
6 05.10.1982 13 20.07.1992
7 27.10.1982 14 09.05.1992
Detail of Power Generation by Tarbela Power Station
Next
Back
13
Chronology of Events
• The matter of calculation of NHP remained unattended un-till 1978. The
issue was then brought in the notice of the Chief Martial Law Administrator,
during his visit of the Peshawar in March 1978 by the GoKP.
• Of late, the matter was brought in the Notice of the National Finance
Commission (NFC) in its meeting held on 22nd November, 1986.
• A Committee was constituted on 24th November, 1986 under the
Chairmanship of Mr. A. G. N. Kazi Deputy Chairman Planning Division
along with Secretary Finance Division, Additional Secretary W&P and
Finance Secretaries KP and Punjab
• The Committee, after series of meeting evolved a methodology and also
calculated NHP for hydro power plants located in KP for the year 1986-87.
Next
Back
14
Chronology of Events
• Report of the Committee was considered in the NFC meeting held on 14th
February, 1988. As a result of unanimous decision, the same was endorsed in its
entirety to the Council of Common Interests (CCI). The CCI approved the
methodology in its meeting held on 12th January, 1991.
• The President further strengthened the decision of the CCI vide his order of 1991
called “The Distribution of Electricity Profits from Hydro-Electric Station to
provinces, Order 1991.
• An amount of Rs. 6.3 billion was estimated as NHP for financial year 1991-92.
• WAPDA started to pay a capped amount of Rs. 6 billion from financial year 1991-
92 to KP Government.
• On the basis of approved formula, the NHP was required to be increased with the
tariff of electricity. Despite the fact that the tariff of electricity was increased
manifold by WAPDA, the amount of the NHP was remained capped.
Next
Back
15
Chronology of Events
• The Provincial Government raised the issue of increasing NHP repeatedly
before the Federal Government / WAPDA. Different Committees were
constituted but the issue remained unresolved.
• The issue was once again raised before the 6th NFC wherein it was decided
that the matter may be resolved through arbitration.
• For that purpose, an Arbitral Tribunal was constituted on 31st October 2005.
• The Arbitral Tribunal announced its Award on 9th October 2006, according to
which an amount of Rs. 110 billion was payable to the Government of NWFP
in five installments. First installment (of Rs. 22 billion) was to be paid within
three months of the announcement of the Award along with Rs. 2.7 billion
as mark-up payable for 3 months. Rest of the installments will be payable on
31st December of each Calendar year along with 10% mark-up on the
balance amount.
• A meeting was held on 14th March 2013 under the Chairmanship of Finance
Minister regarding uncapping the rate of the NHP.
Next
Back
16
Chronology of Events
• It was decided that:
Rate of NHP shall be Rs.1.10 Per KWH to be approved w.e.f next financial
year. This rate shall however index @ 5.5% per annum with a review on
indexation every five years.
• In another meeting Chaired by Minister Water & Power, WAPDA was advised
to incorporate NHP / WUC @ Rs.1.10 /KWh for all hydel power stations
payable to respective Provinces/AJK.
• Accordingly, a petition was filed by the WAPDA for approval of NEPRA for
financial year 2015-16 based upon estimated net electrical output of all hydel
power stations operated by WAPDA.
• The NEPRA did not agree the view point of WAPDA and observed that:
“With regard to equating Water Use Charges (WUC) with Net Hydel Profit,
the Authority is of the opinion that WUC is distinct from NHP and should
not be confused with each other. The WUC is a charge for water usage, and
has its origin in the power policy of 2002. While NHP owes its existence to
the Constitution of 1973”. Next
Back
17
Chronology of Events
• NEPRA further approved that:
“While taking a projected generation of 17,004 gWh on
account of hydel power stations situated in KPK, NHP @
Rs.1.10/KWh for Fy 2016 works out to be Rs.18,704 million
against Rs.6000 million previously allowed and therefore, the
Authority is including Rs.18,704 million in the Revenue
Requirement of WAPDA as payment obligation of WAPDA in
respect of payment of net hydel profit to the KPK province, as
in interim arrangements”.
Next
Back
18
MOU between Federal Govt. and GoKP
• An MOU had been signed between the Federal Minister for Water &
Power and Chief Minister KP on this issue with following contents:
• Net Hydel Profit (NHP)
a. the uncapped NHP as determined and transmitted from NEPRA,
would be notified immediately by Ministry of Water & Power;
b. A total amount of Rs.70 billion has been agreed upon on account of
arrears of uncapped NHP after reconciliation of mutual claims in the
power sector between the two Governments as full and final
settlement; and
c. WAPDA, after seeking concurrence of CCI through the Ministry of
Water & Power, would file a tariff petition for recovery of the arrears
in four installments as follows (i) Rs.25 billion in current fiscal year
and (ii) Rs.15 billion each in the next 3 years”.
Next
Back
19
Approval of CCI
• The CCI gave its concurrence to the MoU signed between Government of
Pakistan and Government of Khyber Pakhtunkhwa on 25th February 2016
specially directing WAPDA to file a Tariff Petition as agreed in the MoU.
• In pursuance of CCI decision, Ministry of Water & Power on 7th March 2016,
notified the decision of NEPRA dated 8th January 2016 wherein NHP for KP
has been uncapped @ Rs.1.10 per kWh on the generation of power plants
located in KP.
• WAPDA filed supplementary tariff petition for the recovery of agreed NHP
arrears as per the directives of CCI in NEPRA on 20th April 2016 and NEPRA
gave its decision on 25th May 2016 allowing the recovery of NHP and arrears
as per the MoU which was notified by Ministry of Water & Power on 24th
June 2016.
Next
Back
20
Approval of CCI
• CCI has approved payment of payment of Rs 83 billion NHP to
Punjab for Gazi Brotha Hydel power Station in its meeting held
on 16-12-2016 on the same analogy and manner on which
settlement reached earlier this year with the KP Government in
case of Tarbela Dam Hydro Power Station.
• The CCI in its decision # (iii) Case No.CCI.1/1/2016 during the
meeting dated 29th February 2016 referred above also decided
that:
"The Government of Punjab will submit their claim to Ministry of
Water and Power for consideration in the light of said MOU, "(i.e.
MOU with GoKP dated 25-02- 2016)
Next
Back
21
Claim of Govt. of Punjab
• In the light of above decision, Punjab Govt. submitted to Ministry
of Water and Power, its claim of NHP arrear on the analogy of
settlement between GoP and GoKP. A high level meeting at
Ministry of Water & Power was held on 13thOctober 2016 followed
by another meeting on 7th November 2016 in the Prime Minister
House, Islamabad in which claims of Government of Punjab
regarding NHP were agreed in the Minutes of meeting. It was
decided to present the agreed position to CCI for its approval. For
this purpose Ministry of Water & Power submitted a summary
dated 28thNovember 2016 to CCI for approval and CCI in its
decision on Case No.CCI.7/3/2016 during its meeting held on
16thDecember 2016 (Annex-III) approved the proposal contained
in Para-3 of the summary as below:
a. The claim of Government of Punjab for Rs. 82.71 billion as arrears
of NHP, duly endorsed by WAPDA will be the full and final
settlement of GoP claim as on June, 2016.
Next
Back
22
Claim of Govt. of Punjab
b. To settle Rs. 38.12 billion, WAPDA would issue irrevocable promissory
note of one year duration to GoP by December 31, 2016. The issuance of
this promissory note will not be contingent upon tariff.
c. The balance Rs.44.59 billion will be paid in three equal installments after
tariff determination by CCl/NEPRA as follows:
Rs 14.86 billion in FY 2017-18
Rs 14.86 billion in FY 2018-19
Rs 14.86 billion in FY 2019-20
d. WAPDA would file a Tariff petition for recovery of the above arrears.
e. Payment of NHP to Government of Punjab @ 1.10 per unit on the analogy
of Government of KPK, generated from Hydel Power Stations located in
Punjab for the FY 2016-17 and onwards.
Next
Back
23
Detail of Action Taken
• As per the CCI decision, WAPDA on 10th January 2017 has already
issued the Promissory Note in the favor of Government of Punjab
which is backed by GoP guarantee under ECC decision dated 11th
January, 2017.
• NHP payable to Government of Punjab has been included in the
petition file for tariff 2017-2018.
• GoAJK is being paid Net Hydel Profit/Water Use Charges (Royalty)
from Mangla Power Station @ Rs.0.15/KWh under signed agreement
between WAPDA and GoAJ&K.
• The rate of NHP being paid to AJ&K for Mangla Power Station is not
as same as to KP and Punjab.
Next
Back
24
Demand of GoAJ&K
• During his visit to Muzaffarabad on 29th December 2016, the
Prime Minister Islamic Republic of Pakistan has made
following decision / direction on the issue of payment of Water
Use Charges (WUC) / Net Hydel Profit (NHP) (serial No. 29
of the record note issued by the Secretary to the Prime
Minister) presented by the GoAJ&K:
“PM directed to Finance Minister to review this matter.
• A position Paper was submitted to the office of the Prime
Minister of Pakistan vide letter No. CS/KH/45-50 dated 26-1-
2017.
Back
25
Analysis of Energy Purchased, Energy Sold (MKWH), and
Losses (%AGE)
Back
Year
Energy
Purchased
(MKWh)
Energy
Sold
(MKWh)
Energy
Losses
(MKWh)
Per Unit
Price (Rs.)
Total Purchase
Price (MRs.)
Losses %age
1998-99 734.648 445.978 288.67 1.69 786.5 39.29
1999-00 805.482 473.182 332.3 1.82 912.205 41.25
2000-01 862.623 525.355 337.268 2.12 1964.573 39.1
2001-02 897.207 558.975 338.232 2.32 1284.573 37.7
2002-03 913.67 575.415 338.255 2.32 2117 37.02
2003-04 1026.144 632.668 393.476 2.32 2426 38.35
2004-05 1114.28 704.874 409.406 2.32 2599.632 38.4
2005-06 1132.924 658.432 474.492 2.59 2431.217 41.88
2006-07 1345.815 792.038 553.777 2.59 3346.774 41.15
2007-08 1321.978 800.877 521.101 2.59 3395.824 39.42
2008-09 1165.075 776.774 388.301 2.59 3179.338 37.82
2009-10 1277.371 790.324 487.047 2.59 4646.144 38.13
2010-11 1378.331 825.223 553.108 2.59 3310.579 40.13
2011-12 1389.469 841.194 548.275 2.59 3722.979 39.46
2012-13 1432.509 861.915 570.594 2.59 3833.919 39.83
2013-14 1507.4 900.517 606.883 2.59 4208.895 40.26
2014-15 1418.174 878.325 539.849 2.59 3863.084 38.07
2015-16 1547.615 940.928 606.687 2.59 4096.19 39.2
26
Details of Arrears for Electricity
(Ending March 2017)
Sr# Region Amount (Rs in million)
1 North 30286.103
2 South 46176.669
Total 76462.772
Back
27
Year-wise Calculation of NHP (1991-92 TO 2016-17)
Year
Net Hydel Profit
(MRs)*
Amount
Paid
Indexation
(10% P.A)**
Amount
Payable
Balance
Amount
1990-1991 3,595.00 - 0.00 3595.00 3,595.00
1991-1992 3,595.00 - 359.50 3954.50 3,954.50
1992-1993 3,954.50 - 395.45 4349.95 4,349.95
1993-1994 4,349.95 - 435.00 4784.95 4,784.95
1994-1995 4,784.95 - 478.49 5263.44 5,263.44
1995-1996 5,263.44 - 526.34 5789.78 5,789.78
1996-1997 5,789.78 - 578.98 6368.76 6,368.76
1997-1998 6,368.76 - 636.88 7005.64 7,005.64
1998-1999 7,005.64 - 700.56 7706.20 7,706.20
1999-2000 7,706.20 - 770.62 8476.82 8,476.82
2000-2001 8,476.82 - 847.68 9324.50 9,324.50
2001-2002 9,324.50 - 932.45 10256.95 10,256.95
2002-2003 10,256.95 - 1025.70 11282.65 11,282.65
2003-2004 11,282.65 707.99 1128.27 12410.92 11,702.93
2004-2005 12,410.92 601.80 1241.09 13652.01 13,050.21
Rs in million
Next
* Amount referred in Arbitration Award 2006 with reference to Chairman WAPDA's
letter addressed to Secretary Water & Power dated 22.04.1991
** Indexation allowed in case of KP for calculation of Net Hydel Profit
28
Year-wise Calculation of NHP (1991-92 TO 2016-17)
Year
Net Hydel
Profit (MRs)*
Amount
Paid
Indexation
(10% P.A)**
Amount
Payable
Balance
Amount
2005-2006 13,652.01 796.13 1365.20 15017.21 14,221.08
2006-2007 15,017.21 891.38 1501.72 16518.93 15,627.55
2007-2008 16,518.93 685.27 1651.89 18170.82 17,485.55
2008-2009 18,170.82 352.92 1817.08 19987.90 19,634.98
2009-2010 19,987.90 654.57 1998.79 21986.69 21,332.13
2010-2011 21,986.69 1,279.05 2198.67 24185.36 22,906.32
2011-2012 24,185.36 699.88 2418.54 26603.90 25,904.02
2012-2013 26,603.90 686.48 2660.39 29264.29 28,577.81
2013-2014 29,264.29 858.82 2926.43 32190.72 31,331.90
2014-2015 32,190.72 741.64 3219.07 35409.79 34,668.15
2015-2016 6,591.00 1,075.75 0.00 6591.00 5,515.25
2016-2017 6,591.00 640.36 0.00 6591.00 5,950.64
Total 356,067.66
* Amount referred in Arbitration Award 2006 with reference to Chairman WAPDA's
letter addressed to Secretary Water & Power dated 22.04.1991
** Indexation allowed in case of KP for calculation of Net Hydel Profit
Back
Rs in million
COMPOSITION OF SUB COMMITTEE
DATED 06-JUNE-2003
29
1) Secretary, Water and Power Chairman
2) Chairman, WAPDA Member
3) Chief Secretary, AJ&K Government Member
4) Joint Secretary (PF) Finance Division Member
5) Joint Secretary, KANA & SAFRON Member
TORs:
• Consumption pattern of AJ&K
• Acceptable line losses in AJ&K
• Mangla Dam Agreement of 1967
• Any other relevant point.
Back
30
30.4 MW Jagran-I HPP
• 30.4 MW Jagran-I HPP was commissioned in 2000 with National Grid at MZD
• Initially PEPCO (WAPDA) made adjustment on mutually agreed tariff to AJ&K
PDO on account of energy dispatched from Jagran-I Power Station through
Electricity Department till July 2010 for Rs. 1.587 billion
• From August 2010 PEPCO (WAPDA) stopped the adjustment of energy
dispatched from Jagran-I power station due to non availability of Power Purchase
Agreement
• This issue was also discussed in the meeting of 08-12-2015 held under the
chairmanship of Secretary Water & Power and it was decided that “Power
Purchase Agreement for Jagran-I HPP will be sign with the CPPA and tariff
approval from NEPRA will be obtained”
• The matter is still pending with Central Power Purchase Agency
• Due to delay in signing of Power Purchase Agreement, outstanding/pending
payment on account of energy dispatched from 30.4 MW Jagran-I hydro power
station from August 2010 to the date is Rs 3.178 billion
Back
31
Annual Revenue from 30.4 MW Jagran-I HPP
Sr. Year
Annual
Generation
(MKWh)
Tarrif as per indexation
based on WPI Rs./KWh
Annual Revenue
(Rs in million)
1 2000-01 61.992 1.700 105.386
2 2001-02 110.159 1.700 187.270
3 2002-03 97.22 1.700 165.274
4 2003-04 107.008 1.700 181.914
5 2004-05 83.059 1.700 141.200
6 2005-06 103.607 1.815 188.026
7 2006-07 96.386 1.998 192.589
8 2007-08 130.812 2.137 279.545
9 2008-09 126.605 2.487 314.917
10 2009-10 143.563 2.939 422.018
11 2010-11 18.469 3.958 73.100
12 2011-12 90.601 4.545 411.782
13 2012-13 137.004 5.252 719.545
14 2013-14 126.101 5.344 673.884
15 2014-15 117.576 6.030 708.982
Total 4765.433
Payment 1587.383
Balance 3178.050
Back

More Related Content

Similar to PDO BOD Agenda Item 13-06-2017.pptx

Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaBhargav Parmar
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxKheljitSingh
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case studyWaseem Hashmat
 
Energy generation 10_11
Energy generation 10_11Energy generation 10_11
Energy generation 10_11rameshgoudru
 
CESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptCESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptMdSazibMollik
 
QLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjQLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjbitseeeRandD
 
Re connect newsletter xxvi
Re connect newsletter xxviRe connect newsletter xxvi
Re connect newsletter xxviVibhav Nuwal
 
Indian power sector
Indian power sectorIndian power sector
Indian power sectorVivek Mohan
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanIBRAR AHMAD
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Spark Network
 
Implementation of Electricity Tariff Methodology in Sri Lanka
Implementation of Electricity Tariff Methodology in Sri LankaImplementation of Electricity Tariff Methodology in Sri Lanka
Implementation of Electricity Tariff Methodology in Sri LankaJLanka Technologies (Pvt) Limited
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
 
Renewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismRenewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismKranav Sharma
 
Lag 05 mgl k-electric 13-03-2019
Lag 05 mgl k-electric 13-03-2019Lag 05 mgl k-electric 13-03-2019
Lag 05 mgl k-electric 13-03-2019abdul basit
 
Eskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationEskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationMatthew Le Cordeur
 

Similar to PDO BOD Agenda Item 13-06-2017.pptx (20)

Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptx
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
Discussion paper 16.11.2015
Discussion paper 16.11.2015Discussion paper 16.11.2015
Discussion paper 16.11.2015
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case study
 
Energy generation 10_11
Energy generation 10_11Energy generation 10_11
Energy generation 10_11
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
Tariff
TariffTariff
Tariff
 
CESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.pptCESU_07-08_Staff_Presentation_during_hearing.ppt
CESU_07-08_Staff_Presentation_during_hearing.ppt
 
Rotating.ppt
Rotating.pptRotating.ppt
Rotating.ppt
 
QLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjQLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjj
 
Re connect newsletter xxvi
Re connect newsletter xxviRe connect newsletter xxvi
Re connect newsletter xxvi
 
Indian power sector
Indian power sectorIndian power sector
Indian power sector
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
 
Implementation of Electricity Tariff Methodology in Sri Lanka
Implementation of Electricity Tariff Methodology in Sri LankaImplementation of Electricity Tariff Methodology in Sri Lanka
Implementation of Electricity Tariff Methodology in Sri Lanka
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012
 
Renewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) MechanismRenewable Energy Certificate (REC) Mechanism
Renewable Energy Certificate (REC) Mechanism
 
Lag 05 mgl k-electric 13-03-2019
Lag 05 mgl k-electric 13-03-2019Lag 05 mgl k-electric 13-03-2019
Lag 05 mgl k-electric 13-03-2019
 
Eskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentationEskom MYPD 3Selective Reopener presentation
Eskom MYPD 3Selective Reopener presentation
 

Recently uploaded

Rising temperatures also mean that more plant pests are appearing earlier and...
Rising temperatures also mean that more plant pests are appearing earlier and...Rising temperatures also mean that more plant pests are appearing earlier and...
Rising temperatures also mean that more plant pests are appearing earlier and...Christina Parmionova
 
Production, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollenProduction, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollenSangram Sahoo
 
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...CIFOR-ICRAF
 
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...Travis Hills MN
 
Peat land Restoration Project in HLG Londerang
Peat land Restoration Project in HLG LonderangPeat land Restoration Project in HLG Londerang
Peat land Restoration Project in HLG LonderangCIFOR-ICRAF
 
2024-05-16 Composting at Home 101 without link to voucher
2024-05-16 Composting at Home 101 without link to voucher2024-05-16 Composting at Home 101 without link to voucher
2024-05-16 Composting at Home 101 without link to voucherEllen Book
 
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...CIFOR-ICRAF
 
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...In vitro evaluation of antibacterial activity of chloroform extract Andrograp...
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...Open Access Research Paper
 
Cooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and PerspectivesCooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and PerspectivesCIFOR-ICRAF
 
Carbon Stock Assessment in Banten Province and Demak, Central Java, Indonesia
Carbon Stock Assessment in Banten Province and Demak, Central Java, IndonesiaCarbon Stock Assessment in Banten Province and Demak, Central Java, Indonesia
Carbon Stock Assessment in Banten Province and Demak, Central Java, IndonesiaCIFOR-ICRAF
 
Presentation on GLOBALISATION IN MBA sem
Presentation on GLOBALISATION IN MBA semPresentation on GLOBALISATION IN MBA sem
Presentation on GLOBALISATION IN MBA semAnikaSingh30
 
Impacts of agriculture on the environment.
Impacts of agriculture on the environment.Impacts of agriculture on the environment.
Impacts of agriculture on the environment.AyushKumar76331
 
Up to 40% of food crops are lost to plant pests and diseases annually.
Up to 40% of food crops are lost to plant pests and diseases annually.Up to 40% of food crops are lost to plant pests and diseases annually.
Up to 40% of food crops are lost to plant pests and diseases annually.Christina Parmionova
 
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...Amil baba
 
Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...Sangram Sahoo
 
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...Amil Baba Dawood bangali
 
slidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reuseslidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reusedhanalakshmi88488
 
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...Aggregage
 
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...Amil Baba Dawood bangali
 
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRY
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRYEFFLUENT TREATMENT PLANT For PHARMA INDUSTRY
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRYSyed Atif Naseem
 

Recently uploaded (20)

Rising temperatures also mean that more plant pests are appearing earlier and...
Rising temperatures also mean that more plant pests are appearing earlier and...Rising temperatures also mean that more plant pests are appearing earlier and...
Rising temperatures also mean that more plant pests are appearing earlier and...
 
Production, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollenProduction, dispersal, sedimentation and taphonomy of spores/pollen
Production, dispersal, sedimentation and taphonomy of spores/pollen
 
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...
Sungsang Mangrove Restoration and Ecotourism (SMART): A participatory action ...
 
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...
Travis Hills of Minnesota: Making Livestock Water and Energy the Best in Buil...
 
Peat land Restoration Project in HLG Londerang
Peat land Restoration Project in HLG LonderangPeat land Restoration Project in HLG Londerang
Peat land Restoration Project in HLG Londerang
 
2024-05-16 Composting at Home 101 without link to voucher
2024-05-16 Composting at Home 101 without link to voucher2024-05-16 Composting at Home 101 without link to voucher
2024-05-16 Composting at Home 101 without link to voucher
 
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...
Coastal and mangrove vulnerability assessment In the Northern Coast of Java, ...
 
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...In vitro evaluation of antibacterial activity of chloroform extract Andrograp...
In vitro evaluation of antibacterial activity of chloroform extract Andrograp...
 
Cooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and PerspectivesCooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and Perspectives
 
Carbon Stock Assessment in Banten Province and Demak, Central Java, Indonesia
Carbon Stock Assessment in Banten Province and Demak, Central Java, IndonesiaCarbon Stock Assessment in Banten Province and Demak, Central Java, Indonesia
Carbon Stock Assessment in Banten Province and Demak, Central Java, Indonesia
 
Presentation on GLOBALISATION IN MBA sem
Presentation on GLOBALISATION IN MBA semPresentation on GLOBALISATION IN MBA sem
Presentation on GLOBALISATION IN MBA sem
 
Impacts of agriculture on the environment.
Impacts of agriculture on the environment.Impacts of agriculture on the environment.
Impacts of agriculture on the environment.
 
Up to 40% of food crops are lost to plant pests and diseases annually.
Up to 40% of food crops are lost to plant pests and diseases annually.Up to 40% of food crops are lost to plant pests and diseases annually.
Up to 40% of food crops are lost to plant pests and diseases annually.
 
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...
NO1 Best Amil Baba In Pakistan Authentic Amil In pakistan Best Amil In Pakist...
 
Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...
 
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
NO1 Pakistan Black magic In Pakistan Kala Ilam Expert Specialist In UK Kala I...
 
slidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reuseslidesgo-maximizing-sustainability-the-case-for-plastic-reuse
slidesgo-maximizing-sustainability-the-case-for-plastic-reuse
 
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
The Key to Sustainable Energy Optimization: A Data-Driven Approach for Manufa...
 
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
 
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRY
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRYEFFLUENT TREATMENT PLANT For PHARMA INDUSTRY
EFFLUENT TREATMENT PLANT For PHARMA INDUSTRY
 

PDO BOD Agenda Item 13-06-2017.pptx

  • 1. Financial Analysis of Sale/Purchase of Electricity vis-a-vis Water Usage Charges/Net Hydel Profit 1
  • 2. 2 Water Use Charges (WUC) • In line with the decision of CCI KP and Punjab provinces are being paid NHP @ Rs.1.10/KWh • Under Mangla Dam Raising Agreement 2003, WUC are being paid to GoAJ&K @ Rs. 0.15/KWh • Income of MHP from WUC@ Rs. 0.15/KWh for FY 15-16 is Rs. 1.076 billion (For FY 16-17 estimated Income is Rs. 1.2 billion) • Potential Income of MHP from WUC @ Rs 1.10/KWh for FY 15-16 is Rs. 7.888 billion (7171MKWh) • Annual loss from MHP to GoAJ&K is Rs 6.812 billion
  • 3. 3 Water Use Charges (WUC) • Income of NJHEP (5150 MKWh) from WUC @ Rs 0.425/KWh would be almost Rs. 2.189 billion • Income of NJHEP from WUC @ Rs. 1.10/KWh would be almost Rs. 5.665 billion (Rs. 3.476 billion excess) • Total annual Income from WUC @ 0.15/KWh and 0.425 /KWh against Mangla HPP and NJHEP is Rs. 3.265 billion • Total annual Income from WUC @ Rs 1.10/KWh against Mangla HPP and NJHEP would be almost Rs. 13.553 billion • Net raising in annual Income from MHP and NJHP is Rs. 10.288 billion • On the basis of Arbitration Award 2006 claim of WUC against Mangla HPP since 1990 would almost be Rs. 356.068 billion
  • 4. 4 Sale of Electricity From Jagran-1 HPP • Power Purchase Agreement (PPA) of Jagran-1 HPP not being signed on the pretext of GoAJ&K being defaulter and beneficiary of low tariff • Annual loss of approximately Rs. 700 million due to non signing of PPA • Due to delay in signing of PPA of 30.4 MW Jagran-I HPP outstanding amount on account of energy charges since Aug. 2010 is Rs. 3.178 billion
  • 5. 5 Sale & Purchase of Electricity • According to the clause 5.2 (b) of the Mangle Dam Raising Agreement , power tariff beyond September, 2003 was fixed by GoP on the recommendation of Standing Sub-Committee notified by Ministry of KANA and SAFRON • Accordingly, power tariff for AJK was decided on the basis of following guidelines issued in the meeting of Sub-Committee held on 11-09-2003 i. The power tariff for AJ&K from 1st Oct 2003 shall be Rs. 2.59 per unit. The basis of the decision was that WAPDA charger Rs. 2.58 per unit for domestic consumers upto 100 units. The AJ&K Government agreed to reduce losses from 37.5% to 27%. Accordingly, the rate per unit should be Rs. 2.60. The committee agreed to take the average of these tow rates at Rs. 2.59 per unit
  • 6. 6 Sale & Purchase of Electricity ii. Since the AJ&K Government don't have provision in their current year’s budget to pick up additional liability of Rs. 0.27 per unit, the sub-committee recommended that the finances required in this regard would be provided by the Federal Government iii. The reduction in losses will be reviewed on monthly basis and any financial gains from reduced losses would be adjusted to reduce the Government subsidy • On 08-12-2015 the sub-committee recommended revised tariff for AJ&K@ Rs. 5.79 per unit • Losses reported against purchase and sale of electricity for the last 18 years are almost 39% • Outstanding liabilities against electricity charges claimed by WAPDA are almost Rs. 76.463 billion
  • 7. 7 Sr. Description Amount (Rs. in billion) B.E for FY 2015-16 from sale of Electricity 11.000 Position at Purchase Rate of Rs. 2.59/KWh 1. Income from Sale of Electricity during FY 2015-16 8.661 2. Expenditures by Electricity Department i. Purchase of Electricity from WAPDA @ Rs. 2.59/KWh = Rs. 4.300 b ii. Other administrative expenditures = Rs. 1.660 b 5.960** 3. Net income from sale of Electricity (as reported by Finance Department) 2.701 Scenario at the Purchase Rate of Rs. 5.79/KWh 1. Income from sale of Electricity 8.661 2. Expenditure i. Purchase of Electricity from WAPDA @ Rs. 5.79/KWh = Rs. 8.963 b ii. Other administrative expenditures = Rs. 1.660 b 10.623** 3. Net expected loss -1.962 * Power Tariff for consumers of AJ&K is same as for rest of Pakistan **Excluding Rs. 0.660 billion released to Electricity department from Development budget. Sale and Purchase of Electricity*
  • 8. 8 Recommendation • The GoAJ&K may ask the GoP for the same treatment as is given to provinces/DISCOs in terms of :- i. Sharing of benefits from Hydel Proceeds ii. Sale and Purchase of electricity
  • 10. 10 • Article 161 (2) of Constitution of Islamic Republic of Pakistan guarantees the payment of Net Hydel Profit (NHP) to the relevant Province. Following is the text: “The net profits earned by the Federal Government or any undertaking established or administered by the Federal Government for the bulk generation of power at a hydro electric station shall be paid to the province in which the hydro electric station is situated”. Explanation: For the purpose of this clause it is further explained in the Article that: “Net Profit” shall be computed by deducting from the revenues accruing from the bulk supply of power from the bus-bars of a hydro electric station at a rate to be determined by the Council of Common Interests (CCI), the operating expenses of the station which shall include any sums payable as taxes, duties, interest or return on investment and depreciations and element of obsolescence, and overheads and provision for reserves”. Extract of Article 161 of the Constitution Next Back
  • 11. 11 Detail of Power Generation by Mangla Power Station Units No Commissioning 1 03-07-1967 2 14-07-1967 3 07-03-1968 4 17-06-1969 5 29-12-1973 6 11-03-1974 7 25-05-1981 8 22-07-1981 9 24-09-1993 10 06-07-1994 Next Back
  • 12. 12 UNIT NO DATE UNIT NO. DATE 1 30.04.1977 8 03.12.1982 2 27.05.1977 9 05.02.1985 3 18.06.1977 10 29.04.1985 4 11.07.1977 11 14.02.1993 5 03.08.1982 12 23.11.1992 6 05.10.1982 13 20.07.1992 7 27.10.1982 14 09.05.1992 Detail of Power Generation by Tarbela Power Station Next Back
  • 13. 13 Chronology of Events • The matter of calculation of NHP remained unattended un-till 1978. The issue was then brought in the notice of the Chief Martial Law Administrator, during his visit of the Peshawar in March 1978 by the GoKP. • Of late, the matter was brought in the Notice of the National Finance Commission (NFC) in its meeting held on 22nd November, 1986. • A Committee was constituted on 24th November, 1986 under the Chairmanship of Mr. A. G. N. Kazi Deputy Chairman Planning Division along with Secretary Finance Division, Additional Secretary W&P and Finance Secretaries KP and Punjab • The Committee, after series of meeting evolved a methodology and also calculated NHP for hydro power plants located in KP for the year 1986-87. Next Back
  • 14. 14 Chronology of Events • Report of the Committee was considered in the NFC meeting held on 14th February, 1988. As a result of unanimous decision, the same was endorsed in its entirety to the Council of Common Interests (CCI). The CCI approved the methodology in its meeting held on 12th January, 1991. • The President further strengthened the decision of the CCI vide his order of 1991 called “The Distribution of Electricity Profits from Hydro-Electric Station to provinces, Order 1991. • An amount of Rs. 6.3 billion was estimated as NHP for financial year 1991-92. • WAPDA started to pay a capped amount of Rs. 6 billion from financial year 1991- 92 to KP Government. • On the basis of approved formula, the NHP was required to be increased with the tariff of electricity. Despite the fact that the tariff of electricity was increased manifold by WAPDA, the amount of the NHP was remained capped. Next Back
  • 15. 15 Chronology of Events • The Provincial Government raised the issue of increasing NHP repeatedly before the Federal Government / WAPDA. Different Committees were constituted but the issue remained unresolved. • The issue was once again raised before the 6th NFC wherein it was decided that the matter may be resolved through arbitration. • For that purpose, an Arbitral Tribunal was constituted on 31st October 2005. • The Arbitral Tribunal announced its Award on 9th October 2006, according to which an amount of Rs. 110 billion was payable to the Government of NWFP in five installments. First installment (of Rs. 22 billion) was to be paid within three months of the announcement of the Award along with Rs. 2.7 billion as mark-up payable for 3 months. Rest of the installments will be payable on 31st December of each Calendar year along with 10% mark-up on the balance amount. • A meeting was held on 14th March 2013 under the Chairmanship of Finance Minister regarding uncapping the rate of the NHP. Next Back
  • 16. 16 Chronology of Events • It was decided that: Rate of NHP shall be Rs.1.10 Per KWH to be approved w.e.f next financial year. This rate shall however index @ 5.5% per annum with a review on indexation every five years. • In another meeting Chaired by Minister Water & Power, WAPDA was advised to incorporate NHP / WUC @ Rs.1.10 /KWh for all hydel power stations payable to respective Provinces/AJK. • Accordingly, a petition was filed by the WAPDA for approval of NEPRA for financial year 2015-16 based upon estimated net electrical output of all hydel power stations operated by WAPDA. • The NEPRA did not agree the view point of WAPDA and observed that: “With regard to equating Water Use Charges (WUC) with Net Hydel Profit, the Authority is of the opinion that WUC is distinct from NHP and should not be confused with each other. The WUC is a charge for water usage, and has its origin in the power policy of 2002. While NHP owes its existence to the Constitution of 1973”. Next Back
  • 17. 17 Chronology of Events • NEPRA further approved that: “While taking a projected generation of 17,004 gWh on account of hydel power stations situated in KPK, NHP @ Rs.1.10/KWh for Fy 2016 works out to be Rs.18,704 million against Rs.6000 million previously allowed and therefore, the Authority is including Rs.18,704 million in the Revenue Requirement of WAPDA as payment obligation of WAPDA in respect of payment of net hydel profit to the KPK province, as in interim arrangements”. Next Back
  • 18. 18 MOU between Federal Govt. and GoKP • An MOU had been signed between the Federal Minister for Water & Power and Chief Minister KP on this issue with following contents: • Net Hydel Profit (NHP) a. the uncapped NHP as determined and transmitted from NEPRA, would be notified immediately by Ministry of Water & Power; b. A total amount of Rs.70 billion has been agreed upon on account of arrears of uncapped NHP after reconciliation of mutual claims in the power sector between the two Governments as full and final settlement; and c. WAPDA, after seeking concurrence of CCI through the Ministry of Water & Power, would file a tariff petition for recovery of the arrears in four installments as follows (i) Rs.25 billion in current fiscal year and (ii) Rs.15 billion each in the next 3 years”. Next Back
  • 19. 19 Approval of CCI • The CCI gave its concurrence to the MoU signed between Government of Pakistan and Government of Khyber Pakhtunkhwa on 25th February 2016 specially directing WAPDA to file a Tariff Petition as agreed in the MoU. • In pursuance of CCI decision, Ministry of Water & Power on 7th March 2016, notified the decision of NEPRA dated 8th January 2016 wherein NHP for KP has been uncapped @ Rs.1.10 per kWh on the generation of power plants located in KP. • WAPDA filed supplementary tariff petition for the recovery of agreed NHP arrears as per the directives of CCI in NEPRA on 20th April 2016 and NEPRA gave its decision on 25th May 2016 allowing the recovery of NHP and arrears as per the MoU which was notified by Ministry of Water & Power on 24th June 2016. Next Back
  • 20. 20 Approval of CCI • CCI has approved payment of payment of Rs 83 billion NHP to Punjab for Gazi Brotha Hydel power Station in its meeting held on 16-12-2016 on the same analogy and manner on which settlement reached earlier this year with the KP Government in case of Tarbela Dam Hydro Power Station. • The CCI in its decision # (iii) Case No.CCI.1/1/2016 during the meeting dated 29th February 2016 referred above also decided that: "The Government of Punjab will submit their claim to Ministry of Water and Power for consideration in the light of said MOU, "(i.e. MOU with GoKP dated 25-02- 2016) Next Back
  • 21. 21 Claim of Govt. of Punjab • In the light of above decision, Punjab Govt. submitted to Ministry of Water and Power, its claim of NHP arrear on the analogy of settlement between GoP and GoKP. A high level meeting at Ministry of Water & Power was held on 13thOctober 2016 followed by another meeting on 7th November 2016 in the Prime Minister House, Islamabad in which claims of Government of Punjab regarding NHP were agreed in the Minutes of meeting. It was decided to present the agreed position to CCI for its approval. For this purpose Ministry of Water & Power submitted a summary dated 28thNovember 2016 to CCI for approval and CCI in its decision on Case No.CCI.7/3/2016 during its meeting held on 16thDecember 2016 (Annex-III) approved the proposal contained in Para-3 of the summary as below: a. The claim of Government of Punjab for Rs. 82.71 billion as arrears of NHP, duly endorsed by WAPDA will be the full and final settlement of GoP claim as on June, 2016. Next Back
  • 22. 22 Claim of Govt. of Punjab b. To settle Rs. 38.12 billion, WAPDA would issue irrevocable promissory note of one year duration to GoP by December 31, 2016. The issuance of this promissory note will not be contingent upon tariff. c. The balance Rs.44.59 billion will be paid in three equal installments after tariff determination by CCl/NEPRA as follows: Rs 14.86 billion in FY 2017-18 Rs 14.86 billion in FY 2018-19 Rs 14.86 billion in FY 2019-20 d. WAPDA would file a Tariff petition for recovery of the above arrears. e. Payment of NHP to Government of Punjab @ 1.10 per unit on the analogy of Government of KPK, generated from Hydel Power Stations located in Punjab for the FY 2016-17 and onwards. Next Back
  • 23. 23 Detail of Action Taken • As per the CCI decision, WAPDA on 10th January 2017 has already issued the Promissory Note in the favor of Government of Punjab which is backed by GoP guarantee under ECC decision dated 11th January, 2017. • NHP payable to Government of Punjab has been included in the petition file for tariff 2017-2018. • GoAJK is being paid Net Hydel Profit/Water Use Charges (Royalty) from Mangla Power Station @ Rs.0.15/KWh under signed agreement between WAPDA and GoAJ&K. • The rate of NHP being paid to AJ&K for Mangla Power Station is not as same as to KP and Punjab. Next Back
  • 24. 24 Demand of GoAJ&K • During his visit to Muzaffarabad on 29th December 2016, the Prime Minister Islamic Republic of Pakistan has made following decision / direction on the issue of payment of Water Use Charges (WUC) / Net Hydel Profit (NHP) (serial No. 29 of the record note issued by the Secretary to the Prime Minister) presented by the GoAJ&K: “PM directed to Finance Minister to review this matter. • A position Paper was submitted to the office of the Prime Minister of Pakistan vide letter No. CS/KH/45-50 dated 26-1- 2017. Back
  • 25. 25 Analysis of Energy Purchased, Energy Sold (MKWH), and Losses (%AGE) Back Year Energy Purchased (MKWh) Energy Sold (MKWh) Energy Losses (MKWh) Per Unit Price (Rs.) Total Purchase Price (MRs.) Losses %age 1998-99 734.648 445.978 288.67 1.69 786.5 39.29 1999-00 805.482 473.182 332.3 1.82 912.205 41.25 2000-01 862.623 525.355 337.268 2.12 1964.573 39.1 2001-02 897.207 558.975 338.232 2.32 1284.573 37.7 2002-03 913.67 575.415 338.255 2.32 2117 37.02 2003-04 1026.144 632.668 393.476 2.32 2426 38.35 2004-05 1114.28 704.874 409.406 2.32 2599.632 38.4 2005-06 1132.924 658.432 474.492 2.59 2431.217 41.88 2006-07 1345.815 792.038 553.777 2.59 3346.774 41.15 2007-08 1321.978 800.877 521.101 2.59 3395.824 39.42 2008-09 1165.075 776.774 388.301 2.59 3179.338 37.82 2009-10 1277.371 790.324 487.047 2.59 4646.144 38.13 2010-11 1378.331 825.223 553.108 2.59 3310.579 40.13 2011-12 1389.469 841.194 548.275 2.59 3722.979 39.46 2012-13 1432.509 861.915 570.594 2.59 3833.919 39.83 2013-14 1507.4 900.517 606.883 2.59 4208.895 40.26 2014-15 1418.174 878.325 539.849 2.59 3863.084 38.07 2015-16 1547.615 940.928 606.687 2.59 4096.19 39.2
  • 26. 26 Details of Arrears for Electricity (Ending March 2017) Sr# Region Amount (Rs in million) 1 North 30286.103 2 South 46176.669 Total 76462.772 Back
  • 27. 27 Year-wise Calculation of NHP (1991-92 TO 2016-17) Year Net Hydel Profit (MRs)* Amount Paid Indexation (10% P.A)** Amount Payable Balance Amount 1990-1991 3,595.00 - 0.00 3595.00 3,595.00 1991-1992 3,595.00 - 359.50 3954.50 3,954.50 1992-1993 3,954.50 - 395.45 4349.95 4,349.95 1993-1994 4,349.95 - 435.00 4784.95 4,784.95 1994-1995 4,784.95 - 478.49 5263.44 5,263.44 1995-1996 5,263.44 - 526.34 5789.78 5,789.78 1996-1997 5,789.78 - 578.98 6368.76 6,368.76 1997-1998 6,368.76 - 636.88 7005.64 7,005.64 1998-1999 7,005.64 - 700.56 7706.20 7,706.20 1999-2000 7,706.20 - 770.62 8476.82 8,476.82 2000-2001 8,476.82 - 847.68 9324.50 9,324.50 2001-2002 9,324.50 - 932.45 10256.95 10,256.95 2002-2003 10,256.95 - 1025.70 11282.65 11,282.65 2003-2004 11,282.65 707.99 1128.27 12410.92 11,702.93 2004-2005 12,410.92 601.80 1241.09 13652.01 13,050.21 Rs in million Next * Amount referred in Arbitration Award 2006 with reference to Chairman WAPDA's letter addressed to Secretary Water & Power dated 22.04.1991 ** Indexation allowed in case of KP for calculation of Net Hydel Profit
  • 28. 28 Year-wise Calculation of NHP (1991-92 TO 2016-17) Year Net Hydel Profit (MRs)* Amount Paid Indexation (10% P.A)** Amount Payable Balance Amount 2005-2006 13,652.01 796.13 1365.20 15017.21 14,221.08 2006-2007 15,017.21 891.38 1501.72 16518.93 15,627.55 2007-2008 16,518.93 685.27 1651.89 18170.82 17,485.55 2008-2009 18,170.82 352.92 1817.08 19987.90 19,634.98 2009-2010 19,987.90 654.57 1998.79 21986.69 21,332.13 2010-2011 21,986.69 1,279.05 2198.67 24185.36 22,906.32 2011-2012 24,185.36 699.88 2418.54 26603.90 25,904.02 2012-2013 26,603.90 686.48 2660.39 29264.29 28,577.81 2013-2014 29,264.29 858.82 2926.43 32190.72 31,331.90 2014-2015 32,190.72 741.64 3219.07 35409.79 34,668.15 2015-2016 6,591.00 1,075.75 0.00 6591.00 5,515.25 2016-2017 6,591.00 640.36 0.00 6591.00 5,950.64 Total 356,067.66 * Amount referred in Arbitration Award 2006 with reference to Chairman WAPDA's letter addressed to Secretary Water & Power dated 22.04.1991 ** Indexation allowed in case of KP for calculation of Net Hydel Profit Back Rs in million
  • 29. COMPOSITION OF SUB COMMITTEE DATED 06-JUNE-2003 29 1) Secretary, Water and Power Chairman 2) Chairman, WAPDA Member 3) Chief Secretary, AJ&K Government Member 4) Joint Secretary (PF) Finance Division Member 5) Joint Secretary, KANA & SAFRON Member TORs: • Consumption pattern of AJ&K • Acceptable line losses in AJ&K • Mangla Dam Agreement of 1967 • Any other relevant point. Back
  • 30. 30 30.4 MW Jagran-I HPP • 30.4 MW Jagran-I HPP was commissioned in 2000 with National Grid at MZD • Initially PEPCO (WAPDA) made adjustment on mutually agreed tariff to AJ&K PDO on account of energy dispatched from Jagran-I Power Station through Electricity Department till July 2010 for Rs. 1.587 billion • From August 2010 PEPCO (WAPDA) stopped the adjustment of energy dispatched from Jagran-I power station due to non availability of Power Purchase Agreement • This issue was also discussed in the meeting of 08-12-2015 held under the chairmanship of Secretary Water & Power and it was decided that “Power Purchase Agreement for Jagran-I HPP will be sign with the CPPA and tariff approval from NEPRA will be obtained” • The matter is still pending with Central Power Purchase Agency • Due to delay in signing of Power Purchase Agreement, outstanding/pending payment on account of energy dispatched from 30.4 MW Jagran-I hydro power station from August 2010 to the date is Rs 3.178 billion Back
  • 31. 31 Annual Revenue from 30.4 MW Jagran-I HPP Sr. Year Annual Generation (MKWh) Tarrif as per indexation based on WPI Rs./KWh Annual Revenue (Rs in million) 1 2000-01 61.992 1.700 105.386 2 2001-02 110.159 1.700 187.270 3 2002-03 97.22 1.700 165.274 4 2003-04 107.008 1.700 181.914 5 2004-05 83.059 1.700 141.200 6 2005-06 103.607 1.815 188.026 7 2006-07 96.386 1.998 192.589 8 2007-08 130.812 2.137 279.545 9 2008-09 126.605 2.487 314.917 10 2009-10 143.563 2.939 422.018 11 2010-11 18.469 3.958 73.100 12 2011-12 90.601 4.545 411.782 13 2012-13 137.004 5.252 719.545 14 2013-14 126.101 5.344 673.884 15 2014-15 117.576 6.030 708.982 Total 4765.433 Payment 1587.383 Balance 3178.050 Back