SlideShare a Scribd company logo
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
1
KARNATAKA ELECTRICITY REGULATORY COMMISSION
Date: 16th November, 2015
“Discussion paper for determination of tariff for Grid-Interactive Rooftop and Small
kilowatt scale solar photovoltaic plants in Karnataka’’
1. Preamble:
The Karnataka Electricity Regulatory Commission had issued an Order dated
10th October, 2013 on “Determination of Tariff for grid connected solar
photovoltaic, solar thermal and rooftop solar photovoltaic and other small solar
power plants”. The tariff determined in this Order is valid for projects entering
into Power Purchase Agreement (PPA) on or after 1st April, 2013 and upto 31st
March, 2018 but excluding those projects for which the tariff is discovered
through bidding process.
Further, the Commission in its Order dated 30th July, 2015, has revised the tariff
for grid connected megawatt scale solar photovoltaic and solar thermal
power plants duly factoring the decline in capital cost. This has resulted in
reduction in tariff from Rs.8.40/unit to Rs.6.51/unit for solar PV plants and from
Rs.10.92/unit to Rs. 10.85/unit in respect of solar thermal plants effective from 1st
September, 2015.
The Government of India (GoI), vide Resolution dated 1st July, 2015, has revised
the National Solar Mission targets from 20,000 MW to 1, 00,000 MW to be
achieved by the year 2021-22. This targeted capacity is proposed to be
achieved through deployment of 40,000 MW of Rooftop solar projects and
60,000 MW of large and medium-scale solar projects. This proposed capacity
addition of rooftop solar power is envisaged under the following categories:
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
2
 Institutional sector (hospitals and educational institutions etc.);
 Industrial sector;
 Commercial sector;
 Housing sector;
The year-wise revised targets of rooftop-solar power plants proposed to be
achieved under the National Solar Mission to accomplish the scaled-up target
of 40,000MW is as under:
Category
Year-wise target (MW)
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 Total
Roof-top
Solar
200 4,800 5,000 6,000 7,000 8,000 9,000 40,000
The targeted capacity of rooftop-solar power plants proposed to be achieved
by Karnataka under the National Solar Mission is as under:
Category
Year-wise target (MW)
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 Total
Roof-top
Solar
10 275 290 344 403 460 518 2300
Further, the Government of Karnataka (GoK) has notified the Karnataka Solar
Policy 2014-2021 on 22nd May, 2014 which envisages achieving a minimum of
400 MW of grid connected solar rooftop plants and 1600 MW of grid
connected utility scale solar projects in the State by 2018.
Minimum program targets (MW):
Year 2014-15 2015-16 2016-17 2017-18
Roof-top (grid connected
and off-grid)
100 100 100 100
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
3
The Ministry of New and Renewable Energy (MNRE) in its guidelines dated 26th
June, 2014 on grid connected Rooftop and small Solar Power Plants, has
focussed on capacity addition of solar power ranging from 1KWp to 500KWp
rooftop and small solar power plants. The guidelines suggest net metering and
tariff determination by regulators such that the tariffs are attractive to investors
and also do not put too much burden on ESCOMs. The MNRE would provide
incentives which includes 15% subsidy for selected categories, accelerated
depreciation benefits for industrial and commercial buildings, bank loans at
interest rate of housing loan from public sector Banks, Customs Duty
concessions and Excise Duty exemptions etc.
2. Need for Mid-course revision:
The Commission in its Order dated 10th October, 2013, has approved the
following tariff for rooftop solar PV plants:
Type of rooftop project Tariff (Rs./unit)
Rooftop project without subsidy 9.56
Rooftop project with 30% capital subsidy 7.20
The Commission has already made midcourse revision of the tariff of megawatt
scale solar PV and solar thermal plants. The revision was prompted by
consistent reduction in the capital cost which is one of the main factors for
determination of tariff. Reduction of capital cost is due to reduction in the price
of solar modules that forms the single most major component of solar tariff. Tariff
in respect of rooftop and small solar PV plants also needs to similarly reflect their
present capital cost. The Commission therefore considers that there is a case for
review of the tariff determined for solar rooftop and small kilowatt scale solar PV
power plants along with review of the features of net metering approach
adopted by the Commission and also a relook of other issues of relevance as
discussed in this paper. Hence, this discussion paper is issued to elicit the views
of all the stakeholders before taking further decision in the matter.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
4
3. Revision of Tariff for kilowatt scale Solar PV rooftop and small Solar power
plants:
The Commission proposes the following parameters for revision of tariff of
kilowatt scale rooftop and small Solar PV power plants:
i) Life of the Plant:
It is proposed to continue with the currently fixed life of plant which is 25 years
for the purpose of determination of tariff.
ii) Term and Tariff design:
Since the life of the plant is being considered as 25 years, in order to ensure
certainty of revenue streams to the investors, the Commission proposes to
continue with current provision of levelized tariff for a period of 25 years as
discussed in the subsequent paras of this discussion paper.
iii) Capacity Utilisation factor:
The Commission in its Tariff Order dated 10th October, 2013 had considered CUF
of 19% for solar photovoltaic plants and it proposes to continue with the same
levels of CUF for kilowatt scale rooftop and small Solar PV power plants.
iv)Capital Cost:
The Commission in its Tariff Order dated 10th October, 2013 had considered
capital cost of Rs.90,000 per KW for kilowatt scale rooftop and small Solar PV
power plants. MNRE in its website has indicated a benchmark capital cost of
Rs.80000 per KW rooftop solar plants.
The Solar Corporation of India (SECI) in its notification of successful of bidders
for allocation of rooftop PV projects under Part-A of Phase IV dated 23rd
September, 2014 has allocated 2 MW of rooftop PV projects in Karnataka at
module price of Rs.67/Wp. Further, SECI in its notification of successful of bidders
for allocation of rooftop PV projects under Part-B of Phase IV dated 3rd
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
5
November, 2014 has allocated 2 MW of rooftop PV projects in Karnataka at
levelized tariff of Rs.5.97/kWh.
The Commission in its Order dated 30th July, 2015 has considered the solar
module cost at Rs.31.20 / Wp and total capital cost of Rs.600 lakhs / MW.
Excluding the land cost of Rs.25 lakhs / MW, the capital cost would be Rs.575
lakhs / MW. This works out to Rs.57, 500 / KW.
The Commission notes that though the cost of solar modules used in rooftop
and small solar plants would be on par with that used in megawatt scale
plants, the cost of power conditioning units and balance of system may not be
comparable with megawatt scale plants. Hence, the Commission is of the
view that capital cost of Rs.57,500 / KW is not feasible for such plants. The
Commission takes note of the recent phenomenon of several players entering
into the field of solar rooftop power generation and the competition therein,
which is likely to result in significant reduction in capital cost. The revised capital
cost should take into account the current cost and also the likely reduction in
the days to come.
Considering the above available references of price bids for solar rooftop PV
and benchmark cost of MNRE, as discussed in the above paragraphs, the
Commission proposes to adopt a capital cost of Rs.75,000 /KW for tariff
determination.
v) Debt-Equity Ratio
The Commission proposes to consider a debt equity ratio of 70:30 as currently
fixed for the purpose of factoring loan and equity.
vi)Operation & Maintenance Cost:
The operation and maintenance cost consists of employee cost, administrative
and general expenses and Repairs & Maintenance expenses. The Commission
in its order dated 10th October, 2013 has considered O & M expenses of Rs.1500
/ KW (2% of the capital cost) with an annual escalation of 5.72%.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
6
The Commission is of the view that it would be appropriate to consider a
percentage of the capital cost as O & M expenses duly providing annual
escalation to meet the inflationary costs.
vii) Interest and Tenure of Debt:
Considering the normative tenure of long term debts, the Commission proposes
to consider the tenure of debts as 12 years. The Commission in its Order dated
30th July, 2015 on megawatt scale solar PV plants has considered interest on
debt at 12.30%. The MNRE has advised Banks to include capital cost of solar
rooftop PV plant as part of the home loan. Many Banks have already initiated
action and as such loans are available at lower interest rates. The Commission
proposes to review the interest allowable on debt based on the prevailing
interest rates applicable for solar power projects.
viii) Working Capital:
The Commission in its present tariff order on megawatt scale PV plants has
considered two months receivables as working capital. The Commission
proposes to fix an appropriate working capital for smaller solar power projects
based on the suggestions / comments it receives.
ix) Interest on Working Capital:
The Commission in its recent Order on megawatt scale PV plants has
considered interest on working capital at 12.50%. Considering the prevailing
base rates and interest rates on short term loans, the Commission proposes to
decide suitably, the allowable interest on working capital.
x) Depreciation:
Since the Commission has proposed 70% of the capital cost to be financed by
debt component and the tenure of debt at 12 years, the Commission proposes
to adopt annual depreciation at 5.83% for the first 12 years to provide
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
7
adequate depreciation to meet the loan repayment and an annual
depreciation at 1.54% for the balance period of 13 years.
xi) Return on Equity:
The Commission in its present Tariff Order on megawatt scale PV plants has
allowed RoE of 16% and the actual tax component as a pass through. The
Commission proposes to continue with the same.
xii) Discount Rate:
Since the financing of capital cost is based on 70% debt and 30% equity, the
Commission is of the opinion that it would be appropriate to consider weighted
average cost of capital (WACC) as the discount factor.
Summary of the parameters adopted by KERC and some of the other States for
determination of tariff is indicated in Annexure.
4. Other issues of importance:
i) Sanctioned load Vs installed capacity of solar rooftop PV plant:
The Commission notes that many consumers are intending to install rooftop
and other small solar power plants far in excess of their sanctioned load. For
example, as per the data furnished by BESCOM vide its letter dated 1st August,
2015, an installation with 100 KW sanctioned load and consuming only 637
units/month on an average, is proposing to install 500 KW rooftop/small solar
plant and would be exporting 59,363 units / month on net metering basis.
Similarly, a consumer with sanctioned load of 1 KW intends to install SRTPV of
100 KW which would result in pumping large quantity of net metered energy
into the grid. This disparity between the sanctioned and the installed capacity
is resulting in disproportionately large surplus energy being pumped into the
grid under the net metering arrangement by consumers installing rooftop solar
power plants.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
8
The Commission is of the view that rooftop and small solar power plants are
intended to encourage utilising the energy at the point of generation. Rooftop
solar generation will also reduce transmission and distribution losses besides
savings on creation of transmission and distribution infrastructure.
The Commission is of the view that this trend of consumers installing solar
rooftop power plants of capacities far in excess of their sanctioned load should
not be encouraged as it is not in the larger interest of the distribution licensees
and also the general consumers. There is a need to fix a cap on the generation
capacity vis-a-vis the sanctioned load. Even in States where net metering
facility is extended to consumers installing rooftop / small solar power plants,
there is a cap on the generation capacity of such plants as detailed below:
Name of State Reference Allowable Installed Capacity of
Solar Rooftop Plant
Tamilnadu Guidelines for Net-metering
issued by TEDA
Not more than
Sanctioned/Contracted load
Telangana TSSPDCL Less than or equal to
Sanctioned/Contracted load
Maharashtra Draft Net-metering
regulations 2015
Not more than contract
demand or connected load.
Rajasthan Net-metering Regulations
issued by Rajasthan ERC
dated
Not more than 80% of the
sanctioned connected load or
contract demand.
Punjab Policy on net-metering for
grid interactive Roof-top Solar
Photo Voltaic Power Plants
dated 05.11.2014 issued by
Government of Punjab
Not more than 80% of the
sanctioned connected load or
contract demand.
Haryana HERC Rooftop solar grid
interactive system based on
net-metering Regulations
2014 dated 25.11.2014
Not more than
Sanctioned/Contracted load
Gujarat Gujarat Solar Policy-2015
dated 13.08.2015
Upto a maximum of 50% of the
Consumer’s sanctioned load
It could be seen from the above table, the allowable installed capacity is not
more than the Sanctioned/Contract load in all the above States. Hence,
keeping in view the issues of grid stability and the financial health of distribution
licensees, the Commission proposes to limit the allowable capacity of SRTPV
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
9
and small solar PV plants to the sanctioned load as indicated in the
subsequent paras of this paper.
ii) Small Solar Plants mounted on Ground:
The Commission in its Order dated 10th October, 2013 had determined tariff for
kilowatt scale small Solar PV plants and Rooftop solar PV plants. The
Commission had decided that for solar PV plants of installed capacity of
beyond 1MW, the tariff as determined for megawatt scale plants will be
applicable. Doubts have been expressed as to whether tariff determined and
net metering facility extended to rooftop solar PV plants is also available to
small solar PV plants mounted on ground. The MNRE guidelines issued on 26th
June, 2014 identifies rooftop and small scale solar power plants with maximum
capacity of 500KWp and a minimum of 1KWp.
The Commission is of the view that solar power generation in a consumers
premises needs to be encouraged irrespective of whether it is on rooftop or
ground mounted. The Commission therefore proposes to allow rooftop and
small ground mounted solar power plants with installed capacities ranging from
1KW to maximum of 500 KW in a premises based on net-metering concept. In
case the installed capacity of a solar plant exceeds 500KW, then the tariff
determined for the megawatt scale will be applicable to such plants.
iii) Net-metering & Gross metering:
The Commission in its Order dated 10th October, 2013 had allowed power
purchase by the distribution licensees from rooftop solar plants including small
solar power plants by introducing the concept of net metering
arrangement/scheme. In net metering the consumer is paid for the net energy
i.e., the difference of energy generated from solar rooftop plant and energy
consumed in his/her installation. This concept allows only surplus energy to be
injected into the grid by the consumer. The Commission proposes to continue
with net-metering concept for all consumers other than domestic consumers.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
10
In case of domestic consumers, the Commission proposes to adopt gross
metering concept wherein the entire energy generated by the solar rooftop
plant including small solar power plants is allowed to be injected into the grid
without reckoning the consumption by the domestic consumer’s installation.
This would allow sale of entire energy generated at the tariff to be fixed by the
Commission.
iv) Grid Connectivity:
The Commission in its Order dated 10th October, 2013 had decided that, the
evacuation from 1 kW upto 5 kW installed capacity of solar rooftop PV shall be
at single phase 230 volts, the evacuation from 5 kW upto 50 kW installed
capacity shall be at 3 phase 415 volts level. Further, it was decided that the
solar rooftop PV systems with installed capacity of 50 kW and above shall be
connected at 11 kV distribution systems. The maximum installed capacity of
solar rooftop PV plant at any single location was limited upto 1 MW, for the
purpose of applying the solar rooftop PV tariff.
The grid connectivity shall have to be arranged by the distribution licensee in
accordance with the prevailing CEA (Technical Standards for Connectivity to
the Grid) Regulations, 2007 and CEA (Technical Standards for Connectivity to
the Grid) Amendment Regulations, 2013 and KERC Grid Code as amended
from time to time.
The Commission proposes to adopt following grid connectivity in compliance
with the above said Regulations / Code:
Installed Capacity of solar installation Voltage Level
From 1 KWp and upto 5 KWp 240 volts
Above 5 KWp and upto 50 KWp 415 volts
Above 50 KWp and upto 500 KWp 11 KV HT / 415 volts LT
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
11
v) Metering:
As per the current Order in force, metering shall be in compliance with the
CEA (Installation and Operation of Meters) Regulations 2006 as amended from
time to time.
In the case of solar rooftop PV systems including small solar power plants
connected to LT grid of a distribution company, the concept of gross or net
metering will be adopted and the energy pumped into the grid will be billed
accordingly. However, if site specific issues are observed by ESCOMs, the
ESCOMs should adopt such metering arrangement wherein the solar injection
and consumer’s self-consumption are metered separately and gross or net
metered component is computed and billed as per the Commission’s Orders
in force.
5. Tariff for the Small Kilowatt scale and Rooftop Solar PV Plants:
The Commission had considered fixing a separate feed-in-tariff for rooftop and
small solar power plants and extending net metering facility for measuring the
surplus energy injected to distribution licensee’s grid, in order to harness the
large potential for generating power using solar energy with plants being
installed on un-utilised rooftops and vacant lands around buildings by grid
connected consumers. This was to facilitate the consumers to get their return
on their investments in a shorter period and encourage more consumers to
invest in such solar power plants, which would be in the larger interest of the
State. The surplus generation capacity was envisaged to be within reasonable
limits.
The tariff of solar power is declining year on year. This is mainly due to reduction
in module price, market competition and economies of scale over a period of
time. In the recent reverse bidding held in Madhya Pradesh, developers have
offered to install solar rooftop PV plants and supply power generated at a rate
of Rs.5.00 per unit. The latest tariffs discovered on 4th November, 2015 in the
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
12
NTPC Tender for setting up of 500MW Solar plant in Andhra Pradesh is as low as
Rs.4.63 per unit. This indicates that the cost of generation from solar power
plants is on the decline. The tariff allowed in other States on net metering basis
is indicated in the Annexure for reference.
The Commission proposes to determine tariff duly considering all components
of expenditure like capital cost, interest on loan, depreciation, interest on
working capital and return on equity which have been discussed in the above
paragraphs.
6. Implementation of scheme of SRTPV Plants:
Based on the above discussions, considering the present retail tariff for different
categories of consumers in the State, the Commission proposes the following
approach for implementation of the scheme of SRTPV and small Solar Plants:
Category of Consumers Allowable Installed
Capacity of rooftop and
small solar PV plants
Billing
NET-METERING
(Applicable to Industrial, Commercial and all categories of consumers other
than Domestic category)
HT Consumers
(other than Residential)
Equivalent to Contract
Demand/Sanctioned
Load subject to a
maximum of 500KW (HT
Power supply beyond
50KW).
50% of energy
generated has to be
consumed by the
consumer. Balance 50%
energy is to be billed at
tariff determined by the
Commission.
In case the self-
consumption is less than
50%, such shortfall in
energy consumption
shall be billed at
Average Pooled Power
Purchase cost notified
by the Commission from
time to time.
LT Consumers
(other than Domestic)
Equivalent to Sanctioned
Load subject to a
maximum of 5KW on
single phase supply and
for above 5KW upto 50KW
on three phase supply.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
13
In case of installed
capacity in excess of
allowable capacity, the
energy injected in
excess of the allowable
installed capacity shall
be billed at Average
Pooled Power Purchase
cost notified by the
Commission from time
to time.
GROSS METERING
(Applicable to only Domestic Consumers)
Domestic Consumers
HT Residential Consumers
(HT-4):
Equivalent to Contract
Demand/Sanctioned
Load subject to a
maximum of 500KW (HT
Power supply beyond
50KW).
LT Domestic Consumers
(LT2(a)):
Equivalent to Sanctioned
Load subject to a
maximum of 5KW on
single phase supply and
for above 5KW upto
50KW on three phase
supply.
Gross energy generated
by the Solar Rooftop
plant will be allowed to
be injected into the grid
payable at the tariff to
be fixed by the
Commission based on
the parameters
discussed in this paper.
The Consumer shall
continue to pay his
energy bills for the
energy consumed at the
prevailing applicable
retail supply tariff.
In case of installed
capacity in excess of
allowable capacity, the
energy injected in
excess of the allowable
installed capacity shall
be billed at Average
Pooled Power Purchase
cost notified by the
Commission from time to
time.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
14
7. Applicability of the revised tariff:
The revised tariff to be determined is proposed to be made applicable to all
the new rooftop solar and small solar PV plants of stipulated capacity entering
into power purchase agreement from 1st January, 2016 onwards and on or
before 31st March, 2018.
8. Suggestions/Comments/Views:
As per the above discussions, the Commission proposes to determine tariff for
rooftop and kilowatt scale small solar power plants.
The Commission requests all stakeholders and the general public to furnish their
views/suggestions/comments before 16th December, 2015. The stakeholders
are requested to furnish any documents or material as may be available in
support of their proposals / views so as to enable determination of tariff in a
reasonable manner.
*******
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
15
Annexure
Summary of tariff parameters considered in some of the other SERCs in
comparison with KERC
State Haryana Gujarat KERC
Date of issue 13.08.2014 17.08.2015 10.10.2013 As
proposed in
this
discussion
paper
Draft/Final Final Order Final Order Final Order Draft Oder
Applicability Plants to be
commissioned
between FY 2014-
15 and FY 2015-16
Plants to be
commissioned during
1st July, 2015 to 31st
March, 2018
Plants to be
commissione
d between
FY 14 and
FY18
Plants to be
commission
ed during
1st
January,201
6 and upto
31st March,
FY18
Capital cost Rs.6.80 Crores/MW Rs. 80,000/kW Rs. 90,000/kW Rs.
75000/kW
CUF 19% 19% 19% 19%
Operation and
maintenance
expenses
Rs.1124 /kW with an
annual escalation
of 5.72%
Rs, 1090/kW with an
escalation of 5.72%
2% of Capital
cost i.e
Rs.1800/kW
with an
annual
escalation of
5.72%
Rs.1500 /
KW (2% of
the capital
cost) with
an annual
escalation
of 5.72%
Life of plant
and
machinery
25 years 25 years 25 years 25 years
Term of Loan 10 years 10 years 10 years 12 years
Interest on
loan
13.75% 12.70% 12.50% 12.30%
Working
Capital
components
a)O&M for one
month;
(b) Receivables
equivalent to 2
months of energy
charges for sale of
electricity
calculated on the
normative CUF;
(c) Maintenance
spare @ 15% of
operation and
maintenance
expenses.
a)O&M expense for
one month;
(b) One month
energy charge at
normative CUF;
2 months
receivables
2 months
receivables
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
16
Interest on
working
capital
14.00% 11.85% 13% 12.50%
Return on
equity
16% on normative
equity
(MAT / Corporate
Tax shall be
separately allowed
in the tariff)
14% 16% 16%
Debt-equity
ratio
70 : 30 70:30 70:30 70:30
Depreciation
rate
7% for first 10 years
up to maximum of
90%
6% for first 10 years
then 2% for the next
15 years
Depreciation
rate for the
first 10
years=7%
and the next
15
years=1.33%
Depreciatio
n rate for
the first 12
years=5.83%
and the
next 13
years=1.54%
Discount
factor
14.42% 10.647% 13.41% WACC
Tariff
(Without
Accelerated
Depreciation)
7.19/kWh Rs.8.42/Unit during 1st
July,2015 to 31st
March, 2016
Rs.7.83/Unit during 1st
April, 2016 to 31st
March, 2017
Rs.7.28/Unit during 1st
April,2017 to 31st
March, 2018
9.56/kWh
without
subsidy
7.20/kWh
with subsidy
To be
determined
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
17
The tariff allowed in other States on net metering basis for SRTPV
Name of State Reference Allowable tariff for Solar
Rooftop Plant
Tamil Nadu TEDA Guidelines for
implementation of LT
connectivity/Net-
Metering
Injection upto 90% of the
consumption annually
will be adjusted at
applicable retail supply
tariff. Excess beyond 90%
will go as lapsed.
Andhra Pradesh Andhra Pradesh Solar
Power Policy-2015 dated
12.02.2015
Net-metering OR Gross
metering allowed at
tariff equal to the
average cost to serve
determined by APERC
every year. For FY14, it is
Rs.5.25/Unit.
Telangana Telangana Solar Policy
2015
Net-metering OR Gross
metering is allowed.
Under gross metering the
power would be sold at
average cost of service
of the DISCOM. The tariff
applicable for units
under net metering
would be at average
pooled power purchase
cost.
Maharashtra Net-metering
Regulations 2015
Net energy at the end of
each Financial year shall
be purchased by the
DISCOM at approved
Average Cost of Power
Purchase for that year.
Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants
18
Rajasthan Net-metering
Regulations issued by
Rajasthan ERC dated
26.02.2015 & RERC Solar
Tariff Order dated
19.06.2015.
Excess energy of 50units
or more in month is paid
at RERC determined
tariff. In case it is less
than 50 units in a month,
the same is carried
forward till the
cumulative excess
reaches 50 Units. At
present RERC tariff is
Rs.6.74/Unit.
Punjab Policy on net-metering
for grid interactive Roof-
top Solar Photo Voltaic
Power Plants dated
05.11.2014 issued by
Government of Punjab
Injection upto 90% of the
consumption annually
will be adjusted at
applicable retail supply
tariff. Excess beyond 90%
will go as lapsed.
Haryana HERC Rooftop solar grid
interactive system based
on net-metering
Regulations 2014 dated
25.11.2014
Injection upto 90% of the
consumption annually
will be adjusted at
applicable retail supply
tariff. Excess beyond 90%
will go as lapsed.
Delhi DERC Guidelines on Net-
metering Regulations-
2014
Excess generation is paid
at Average Pooled
Power Purchase Cost to
be settled at the end of
the year
Gujarat Gujarat Solar Policy-2015
dated 13.08.2015
Surplus energy will be
paid at Average Pooled
Power Purchase rate of
the year in which the
plant is commissioned.

More Related Content

What's hot

Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Gensol Engineering Limited
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
Bhargav Parmar
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Gensol Engineering Limited
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermal
Tapasya123
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Gensol Engineering Limited
 
Bhiwandi electricity distribution
Bhiwandi electricity distributionBhiwandi electricity distribution
Bhiwandi electricity distribution
Thapar Institute of Engineering and Technology.
 
Uttar pradesh solar rooftop policy 2014
Uttar pradesh solar rooftop policy 2014Uttar pradesh solar rooftop policy 2014
Uttar pradesh solar rooftop policy 2014
Headway Solar
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
Headway Solar
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
Gensol Engineering Limited
 
Day 2 Try NEGAWATT Power Plants
Day 2 Try NEGAWATT Power Plants Day 2 Try NEGAWATT Power Plants
Day 2 Try NEGAWATT Power Plants
RCREEE
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
Binit Das
 
Design analysis for solar photovoltaic with and without nem
Design analysis for solar  photovoltaic with and without nemDesign analysis for solar  photovoltaic with and without nem
Design analysis for solar photovoltaic with and without nem
yhckelvin
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionSanman Rajput
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
Harish Sharma
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Gensol Engineering Limited
 
Final Report Biomass
Final Report BiomassFinal Report Biomass
Final Report BiomassNeel Patel
 
Abt meter
Abt meterAbt meter
Abt meter
Jay Ranvir
 

What's hot (20)

Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
 
Wind Force Newsletter Dec, Edition, 2011
Wind Force Newsletter   Dec, Edition, 2011Wind Force Newsletter   Dec, Edition, 2011
Wind Force Newsletter Dec, Edition, 2011
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Cost appraisal of chhabra thermal
Cost appraisal of chhabra thermalCost appraisal of chhabra thermal
Cost appraisal of chhabra thermal
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Bhiwandi electricity distribution
Bhiwandi electricity distributionBhiwandi electricity distribution
Bhiwandi electricity distribution
 
Uttar pradesh solar rooftop policy 2014
Uttar pradesh solar rooftop policy 2014Uttar pradesh solar rooftop policy 2014
Uttar pradesh solar rooftop policy 2014
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Day 2 Try NEGAWATT Power Plants
Day 2 Try NEGAWATT Power Plants Day 2 Try NEGAWATT Power Plants
Day 2 Try NEGAWATT Power Plants
 
Overview of solar power generation in india
Overview of solar power generation in indiaOverview of solar power generation in india
Overview of solar power generation in india
 
Design analysis for solar photovoltaic with and without nem
Design analysis for solar  photovoltaic with and without nemDesign analysis for solar  photovoltaic with and without nem
Design analysis for solar photovoltaic with and without nem
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-edition
 
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
States Policies and SERCs Regulatory/ Tariff Order for rooftop solar power pr...
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Final Report Biomass
Final Report BiomassFinal Report Biomass
Final Report Biomass
 
Abt meter
Abt meterAbt meter
Abt meter
 

Viewers also liked

Softexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
Softexpert GRC Kurumsal Yönetişim Risk ve UyumlulukSoftexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
Softexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
Hydron Consulting Grup
 
Empathy map 3 pages
Empathy map   3 pagesEmpathy map   3 pages
Empathy map 3 pages
tramanh_huynh
 
Certificates of conformity
Certificates of conformityCertificates of conformity
Certificates of conformity
Jana Perackova
 
Social Sharing for Pharma
Social Sharing for Pharma Social Sharing for Pharma
Social Sharing for Pharma
Wendy Blackburn
 
Type Chart Boltdepot
Type Chart BoltdepotType Chart Boltdepot
Type Chart BoltdepotEvan Fan
 
IBM Proventia IPS
IBM Proventia IPSIBM Proventia IPS
IBM Proventia IPS
Петр Королев
 
Izlases veidosanas un funkcionesanas sistemas modeli
Izlases veidosanas un funkcionesanas sistemas modeliIzlases veidosanas un funkcionesanas sistemas modeli
Izlases veidosanas un funkcionesanas sistemas modeli
Edgars Bernans
 
Company Information
Company InformationCompany Information
Ornamental Iron Catalog-Hebei Founder
Ornamental Iron Catalog-Hebei FounderOrnamental Iron Catalog-Hebei Founder
Ornamental Iron Catalog-Hebei FounderEvan Fan
 
Ontologies presentation
Ontologies presentationOntologies presentation
Ontologies presentation
zoerose
 
Softexpert HDM Çalışan Gelişim Yönetimi
Softexpert HDM Çalışan Gelişim YönetimiSoftexpert HDM Çalışan Gelişim Yönetimi
Softexpert HDM Çalışan Gelişim Yönetimi
Hydron Consulting Grup
 
Boxtoppers
BoxtoppersBoxtoppers
Boxtoppers
A'deas Printing
 
על עיצוב ובניית למידה רספונסיבית ורב מכשירית
 על עיצוב ובניית למידה רספונסיבית ורב מכשירית על עיצוב ובניית למידה רספונסיבית ורב מכשירית
על עיצוב ובניית למידה רספונסיבית ורב מכשיריתKineo Israel
 

Viewers also liked (20)

Softexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
Softexpert GRC Kurumsal Yönetişim Risk ve UyumlulukSoftexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
Softexpert GRC Kurumsal Yönetişim Risk ve Uyumluluk
 
Empathy map 3 pages
Empathy map   3 pagesEmpathy map   3 pages
Empathy map 3 pages
 
La catedral de santiago
La catedral de santiagoLa catedral de santiago
La catedral de santiago
 
Certificates of conformity
Certificates of conformityCertificates of conformity
Certificates of conformity
 
Social Sharing for Pharma
Social Sharing for Pharma Social Sharing for Pharma
Social Sharing for Pharma
 
Winter
Winter Winter
Winter
 
Type Chart Boltdepot
Type Chart BoltdepotType Chart Boltdepot
Type Chart Boltdepot
 
IBM Proventia IPS
IBM Proventia IPSIBM Proventia IPS
IBM Proventia IPS
 
Prezentare
PrezentarePrezentare
Prezentare
 
Izlases veidosanas un funkcionesanas sistemas modeli
Izlases veidosanas un funkcionesanas sistemas modeliIzlases veidosanas un funkcionesanas sistemas modeli
Izlases veidosanas un funkcionesanas sistemas modeli
 
Company Information
Company InformationCompany Information
Company Information
 
Ornamental Iron Catalog-Hebei Founder
Ornamental Iron Catalog-Hebei FounderOrnamental Iron Catalog-Hebei Founder
Ornamental Iron Catalog-Hebei Founder
 
Ontologies presentation
Ontologies presentationOntologies presentation
Ontologies presentation
 
Bill Gates
Bill GatesBill Gates
Bill Gates
 
Bill Gates
Bill GatesBill Gates
Bill Gates
 
Softexpert HDM Çalışan Gelişim Yönetimi
Softexpert HDM Çalışan Gelişim YönetimiSoftexpert HDM Çalışan Gelişim Yönetimi
Softexpert HDM Çalışan Gelişim Yönetimi
 
Boxtoppers
BoxtoppersBoxtoppers
Boxtoppers
 
Tata Bbye
Tata   BbyeTata   Bbye
Tata Bbye
 
על עיצוב ובניית למידה רספונסיבית ורב מכשירית
 על עיצוב ובניית למידה רספונסיבית ורב מכשירית על עיצוב ובניית למידה רספונסיבית ורב מכשירית
על עיצוב ובניית למידה רספונסיבית ורב מכשירית
 
Nieuwjaar 2011
Nieuwjaar 2011Nieuwjaar 2011
Nieuwjaar 2011
 

Similar to Discussion paper 16.11.2015

Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
Chirag Jain
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
professionalpanorama
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsSanman Rajput
 
Solar power plant Opportunity and Costing
Solar power plant Opportunity and CostingSolar power plant Opportunity and Costing
Solar power plant Opportunity and Costing
Viraj Bhosale M.S. (Renewables) B.E.(Elect)
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012rupeshsingh_1
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Solar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy CrisisSolar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy Crisis
solarindia
 
National Solar Mission Status (July'17)
National Solar Mission Status (July'17)National Solar Mission Status (July'17)
National Solar Mission Status (July'17)
Gensol Engineering Limited
 
J&K Solar policy 2010
J&K Solar policy 2010J&K Solar policy 2010
J&K Solar policy 2010
Headway Solar
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
smsksolar
 
Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015
Abhay Ocean India ltd.
 
Floating Solar
Floating SolarFloating Solar
Floating Solar
plzsorry
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
SHOBHIT NARAIN PANDEY
 
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
AHRP Law Firm
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
AbhishekMallick29
 
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
Headway Solar
 

Similar to Discussion paper 16.11.2015 (20)

Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)Cost Appraisal of Chhabra Thermal Power Station(250 mw)
Cost Appraisal of Chhabra Thermal Power Station(250 mw)
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
 
Solar power plant Opportunity and Costing
Solar power plant Opportunity and CostingSolar power plant Opportunity and Costing
Solar power plant Opportunity and Costing
 
Wind Force Newsletter September, Edition, 2012
Wind Force Newsletter   September, Edition, 2012Wind Force Newsletter   September, Edition, 2012
Wind Force Newsletter September, Edition, 2012
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
Solar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy CrisisSolar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy Crisis
 
National Solar Mission Status (July'17)
National Solar Mission Status (July'17)National Solar Mission Status (July'17)
National Solar Mission Status (July'17)
 
J&K Solar policy 2010
J&K Solar policy 2010J&K Solar policy 2010
J&K Solar policy 2010
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015Aoil floating solar power plant ppt 2015
Aoil floating solar power plant ppt 2015
 
Floating Solar
Floating SolarFloating Solar
Floating Solar
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
Issuance of Ministry of Energy and Mineral Resources Regulation No. 2 of 2024...
 
Renewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
 
Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
 

Recently uploaded

Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
CECOS University Peshawar, Pakistan
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
chaitaliambole
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
Piermenotti Mauro
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
zm9ajxup
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
yadavakashagra
 

Recently uploaded (20)

Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
growbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdfgrowbilliontrees.com-Trees for Granddaughter (1).pdf
growbilliontrees.com-Trees for Granddaughter (1).pdf
 

Discussion paper 16.11.2015

  • 1. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 1 KARNATAKA ELECTRICITY REGULATORY COMMISSION Date: 16th November, 2015 “Discussion paper for determination of tariff for Grid-Interactive Rooftop and Small kilowatt scale solar photovoltaic plants in Karnataka’’ 1. Preamble: The Karnataka Electricity Regulatory Commission had issued an Order dated 10th October, 2013 on “Determination of Tariff for grid connected solar photovoltaic, solar thermal and rooftop solar photovoltaic and other small solar power plants”. The tariff determined in this Order is valid for projects entering into Power Purchase Agreement (PPA) on or after 1st April, 2013 and upto 31st March, 2018 but excluding those projects for which the tariff is discovered through bidding process. Further, the Commission in its Order dated 30th July, 2015, has revised the tariff for grid connected megawatt scale solar photovoltaic and solar thermal power plants duly factoring the decline in capital cost. This has resulted in reduction in tariff from Rs.8.40/unit to Rs.6.51/unit for solar PV plants and from Rs.10.92/unit to Rs. 10.85/unit in respect of solar thermal plants effective from 1st September, 2015. The Government of India (GoI), vide Resolution dated 1st July, 2015, has revised the National Solar Mission targets from 20,000 MW to 1, 00,000 MW to be achieved by the year 2021-22. This targeted capacity is proposed to be achieved through deployment of 40,000 MW of Rooftop solar projects and 60,000 MW of large and medium-scale solar projects. This proposed capacity addition of rooftop solar power is envisaged under the following categories:
  • 2. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 2  Institutional sector (hospitals and educational institutions etc.);  Industrial sector;  Commercial sector;  Housing sector; The year-wise revised targets of rooftop-solar power plants proposed to be achieved under the National Solar Mission to accomplish the scaled-up target of 40,000MW is as under: Category Year-wise target (MW) 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 Total Roof-top Solar 200 4,800 5,000 6,000 7,000 8,000 9,000 40,000 The targeted capacity of rooftop-solar power plants proposed to be achieved by Karnataka under the National Solar Mission is as under: Category Year-wise target (MW) 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 Total Roof-top Solar 10 275 290 344 403 460 518 2300 Further, the Government of Karnataka (GoK) has notified the Karnataka Solar Policy 2014-2021 on 22nd May, 2014 which envisages achieving a minimum of 400 MW of grid connected solar rooftop plants and 1600 MW of grid connected utility scale solar projects in the State by 2018. Minimum program targets (MW): Year 2014-15 2015-16 2016-17 2017-18 Roof-top (grid connected and off-grid) 100 100 100 100
  • 3. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 3 The Ministry of New and Renewable Energy (MNRE) in its guidelines dated 26th June, 2014 on grid connected Rooftop and small Solar Power Plants, has focussed on capacity addition of solar power ranging from 1KWp to 500KWp rooftop and small solar power plants. The guidelines suggest net metering and tariff determination by regulators such that the tariffs are attractive to investors and also do not put too much burden on ESCOMs. The MNRE would provide incentives which includes 15% subsidy for selected categories, accelerated depreciation benefits for industrial and commercial buildings, bank loans at interest rate of housing loan from public sector Banks, Customs Duty concessions and Excise Duty exemptions etc. 2. Need for Mid-course revision: The Commission in its Order dated 10th October, 2013, has approved the following tariff for rooftop solar PV plants: Type of rooftop project Tariff (Rs./unit) Rooftop project without subsidy 9.56 Rooftop project with 30% capital subsidy 7.20 The Commission has already made midcourse revision of the tariff of megawatt scale solar PV and solar thermal plants. The revision was prompted by consistent reduction in the capital cost which is one of the main factors for determination of tariff. Reduction of capital cost is due to reduction in the price of solar modules that forms the single most major component of solar tariff. Tariff in respect of rooftop and small solar PV plants also needs to similarly reflect their present capital cost. The Commission therefore considers that there is a case for review of the tariff determined for solar rooftop and small kilowatt scale solar PV power plants along with review of the features of net metering approach adopted by the Commission and also a relook of other issues of relevance as discussed in this paper. Hence, this discussion paper is issued to elicit the views of all the stakeholders before taking further decision in the matter.
  • 4. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 4 3. Revision of Tariff for kilowatt scale Solar PV rooftop and small Solar power plants: The Commission proposes the following parameters for revision of tariff of kilowatt scale rooftop and small Solar PV power plants: i) Life of the Plant: It is proposed to continue with the currently fixed life of plant which is 25 years for the purpose of determination of tariff. ii) Term and Tariff design: Since the life of the plant is being considered as 25 years, in order to ensure certainty of revenue streams to the investors, the Commission proposes to continue with current provision of levelized tariff for a period of 25 years as discussed in the subsequent paras of this discussion paper. iii) Capacity Utilisation factor: The Commission in its Tariff Order dated 10th October, 2013 had considered CUF of 19% for solar photovoltaic plants and it proposes to continue with the same levels of CUF for kilowatt scale rooftop and small Solar PV power plants. iv)Capital Cost: The Commission in its Tariff Order dated 10th October, 2013 had considered capital cost of Rs.90,000 per KW for kilowatt scale rooftop and small Solar PV power plants. MNRE in its website has indicated a benchmark capital cost of Rs.80000 per KW rooftop solar plants. The Solar Corporation of India (SECI) in its notification of successful of bidders for allocation of rooftop PV projects under Part-A of Phase IV dated 23rd September, 2014 has allocated 2 MW of rooftop PV projects in Karnataka at module price of Rs.67/Wp. Further, SECI in its notification of successful of bidders for allocation of rooftop PV projects under Part-B of Phase IV dated 3rd
  • 5. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 5 November, 2014 has allocated 2 MW of rooftop PV projects in Karnataka at levelized tariff of Rs.5.97/kWh. The Commission in its Order dated 30th July, 2015 has considered the solar module cost at Rs.31.20 / Wp and total capital cost of Rs.600 lakhs / MW. Excluding the land cost of Rs.25 lakhs / MW, the capital cost would be Rs.575 lakhs / MW. This works out to Rs.57, 500 / KW. The Commission notes that though the cost of solar modules used in rooftop and small solar plants would be on par with that used in megawatt scale plants, the cost of power conditioning units and balance of system may not be comparable with megawatt scale plants. Hence, the Commission is of the view that capital cost of Rs.57,500 / KW is not feasible for such plants. The Commission takes note of the recent phenomenon of several players entering into the field of solar rooftop power generation and the competition therein, which is likely to result in significant reduction in capital cost. The revised capital cost should take into account the current cost and also the likely reduction in the days to come. Considering the above available references of price bids for solar rooftop PV and benchmark cost of MNRE, as discussed in the above paragraphs, the Commission proposes to adopt a capital cost of Rs.75,000 /KW for tariff determination. v) Debt-Equity Ratio The Commission proposes to consider a debt equity ratio of 70:30 as currently fixed for the purpose of factoring loan and equity. vi)Operation & Maintenance Cost: The operation and maintenance cost consists of employee cost, administrative and general expenses and Repairs & Maintenance expenses. The Commission in its order dated 10th October, 2013 has considered O & M expenses of Rs.1500 / KW (2% of the capital cost) with an annual escalation of 5.72%.
  • 6. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 6 The Commission is of the view that it would be appropriate to consider a percentage of the capital cost as O & M expenses duly providing annual escalation to meet the inflationary costs. vii) Interest and Tenure of Debt: Considering the normative tenure of long term debts, the Commission proposes to consider the tenure of debts as 12 years. The Commission in its Order dated 30th July, 2015 on megawatt scale solar PV plants has considered interest on debt at 12.30%. The MNRE has advised Banks to include capital cost of solar rooftop PV plant as part of the home loan. Many Banks have already initiated action and as such loans are available at lower interest rates. The Commission proposes to review the interest allowable on debt based on the prevailing interest rates applicable for solar power projects. viii) Working Capital: The Commission in its present tariff order on megawatt scale PV plants has considered two months receivables as working capital. The Commission proposes to fix an appropriate working capital for smaller solar power projects based on the suggestions / comments it receives. ix) Interest on Working Capital: The Commission in its recent Order on megawatt scale PV plants has considered interest on working capital at 12.50%. Considering the prevailing base rates and interest rates on short term loans, the Commission proposes to decide suitably, the allowable interest on working capital. x) Depreciation: Since the Commission has proposed 70% of the capital cost to be financed by debt component and the tenure of debt at 12 years, the Commission proposes to adopt annual depreciation at 5.83% for the first 12 years to provide
  • 7. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 7 adequate depreciation to meet the loan repayment and an annual depreciation at 1.54% for the balance period of 13 years. xi) Return on Equity: The Commission in its present Tariff Order on megawatt scale PV plants has allowed RoE of 16% and the actual tax component as a pass through. The Commission proposes to continue with the same. xii) Discount Rate: Since the financing of capital cost is based on 70% debt and 30% equity, the Commission is of the opinion that it would be appropriate to consider weighted average cost of capital (WACC) as the discount factor. Summary of the parameters adopted by KERC and some of the other States for determination of tariff is indicated in Annexure. 4. Other issues of importance: i) Sanctioned load Vs installed capacity of solar rooftop PV plant: The Commission notes that many consumers are intending to install rooftop and other small solar power plants far in excess of their sanctioned load. For example, as per the data furnished by BESCOM vide its letter dated 1st August, 2015, an installation with 100 KW sanctioned load and consuming only 637 units/month on an average, is proposing to install 500 KW rooftop/small solar plant and would be exporting 59,363 units / month on net metering basis. Similarly, a consumer with sanctioned load of 1 KW intends to install SRTPV of 100 KW which would result in pumping large quantity of net metered energy into the grid. This disparity between the sanctioned and the installed capacity is resulting in disproportionately large surplus energy being pumped into the grid under the net metering arrangement by consumers installing rooftop solar power plants.
  • 8. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 8 The Commission is of the view that rooftop and small solar power plants are intended to encourage utilising the energy at the point of generation. Rooftop solar generation will also reduce transmission and distribution losses besides savings on creation of transmission and distribution infrastructure. The Commission is of the view that this trend of consumers installing solar rooftop power plants of capacities far in excess of their sanctioned load should not be encouraged as it is not in the larger interest of the distribution licensees and also the general consumers. There is a need to fix a cap on the generation capacity vis-a-vis the sanctioned load. Even in States where net metering facility is extended to consumers installing rooftop / small solar power plants, there is a cap on the generation capacity of such plants as detailed below: Name of State Reference Allowable Installed Capacity of Solar Rooftop Plant Tamilnadu Guidelines for Net-metering issued by TEDA Not more than Sanctioned/Contracted load Telangana TSSPDCL Less than or equal to Sanctioned/Contracted load Maharashtra Draft Net-metering regulations 2015 Not more than contract demand or connected load. Rajasthan Net-metering Regulations issued by Rajasthan ERC dated Not more than 80% of the sanctioned connected load or contract demand. Punjab Policy on net-metering for grid interactive Roof-top Solar Photo Voltaic Power Plants dated 05.11.2014 issued by Government of Punjab Not more than 80% of the sanctioned connected load or contract demand. Haryana HERC Rooftop solar grid interactive system based on net-metering Regulations 2014 dated 25.11.2014 Not more than Sanctioned/Contracted load Gujarat Gujarat Solar Policy-2015 dated 13.08.2015 Upto a maximum of 50% of the Consumer’s sanctioned load It could be seen from the above table, the allowable installed capacity is not more than the Sanctioned/Contract load in all the above States. Hence, keeping in view the issues of grid stability and the financial health of distribution licensees, the Commission proposes to limit the allowable capacity of SRTPV
  • 9. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 9 and small solar PV plants to the sanctioned load as indicated in the subsequent paras of this paper. ii) Small Solar Plants mounted on Ground: The Commission in its Order dated 10th October, 2013 had determined tariff for kilowatt scale small Solar PV plants and Rooftop solar PV plants. The Commission had decided that for solar PV plants of installed capacity of beyond 1MW, the tariff as determined for megawatt scale plants will be applicable. Doubts have been expressed as to whether tariff determined and net metering facility extended to rooftop solar PV plants is also available to small solar PV plants mounted on ground. The MNRE guidelines issued on 26th June, 2014 identifies rooftop and small scale solar power plants with maximum capacity of 500KWp and a minimum of 1KWp. The Commission is of the view that solar power generation in a consumers premises needs to be encouraged irrespective of whether it is on rooftop or ground mounted. The Commission therefore proposes to allow rooftop and small ground mounted solar power plants with installed capacities ranging from 1KW to maximum of 500 KW in a premises based on net-metering concept. In case the installed capacity of a solar plant exceeds 500KW, then the tariff determined for the megawatt scale will be applicable to such plants. iii) Net-metering & Gross metering: The Commission in its Order dated 10th October, 2013 had allowed power purchase by the distribution licensees from rooftop solar plants including small solar power plants by introducing the concept of net metering arrangement/scheme. In net metering the consumer is paid for the net energy i.e., the difference of energy generated from solar rooftop plant and energy consumed in his/her installation. This concept allows only surplus energy to be injected into the grid by the consumer. The Commission proposes to continue with net-metering concept for all consumers other than domestic consumers.
  • 10. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 10 In case of domestic consumers, the Commission proposes to adopt gross metering concept wherein the entire energy generated by the solar rooftop plant including small solar power plants is allowed to be injected into the grid without reckoning the consumption by the domestic consumer’s installation. This would allow sale of entire energy generated at the tariff to be fixed by the Commission. iv) Grid Connectivity: The Commission in its Order dated 10th October, 2013 had decided that, the evacuation from 1 kW upto 5 kW installed capacity of solar rooftop PV shall be at single phase 230 volts, the evacuation from 5 kW upto 50 kW installed capacity shall be at 3 phase 415 volts level. Further, it was decided that the solar rooftop PV systems with installed capacity of 50 kW and above shall be connected at 11 kV distribution systems. The maximum installed capacity of solar rooftop PV plant at any single location was limited upto 1 MW, for the purpose of applying the solar rooftop PV tariff. The grid connectivity shall have to be arranged by the distribution licensee in accordance with the prevailing CEA (Technical Standards for Connectivity to the Grid) Regulations, 2007 and CEA (Technical Standards for Connectivity to the Grid) Amendment Regulations, 2013 and KERC Grid Code as amended from time to time. The Commission proposes to adopt following grid connectivity in compliance with the above said Regulations / Code: Installed Capacity of solar installation Voltage Level From 1 KWp and upto 5 KWp 240 volts Above 5 KWp and upto 50 KWp 415 volts Above 50 KWp and upto 500 KWp 11 KV HT / 415 volts LT
  • 11. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 11 v) Metering: As per the current Order in force, metering shall be in compliance with the CEA (Installation and Operation of Meters) Regulations 2006 as amended from time to time. In the case of solar rooftop PV systems including small solar power plants connected to LT grid of a distribution company, the concept of gross or net metering will be adopted and the energy pumped into the grid will be billed accordingly. However, if site specific issues are observed by ESCOMs, the ESCOMs should adopt such metering arrangement wherein the solar injection and consumer’s self-consumption are metered separately and gross or net metered component is computed and billed as per the Commission’s Orders in force. 5. Tariff for the Small Kilowatt scale and Rooftop Solar PV Plants: The Commission had considered fixing a separate feed-in-tariff for rooftop and small solar power plants and extending net metering facility for measuring the surplus energy injected to distribution licensee’s grid, in order to harness the large potential for generating power using solar energy with plants being installed on un-utilised rooftops and vacant lands around buildings by grid connected consumers. This was to facilitate the consumers to get their return on their investments in a shorter period and encourage more consumers to invest in such solar power plants, which would be in the larger interest of the State. The surplus generation capacity was envisaged to be within reasonable limits. The tariff of solar power is declining year on year. This is mainly due to reduction in module price, market competition and economies of scale over a period of time. In the recent reverse bidding held in Madhya Pradesh, developers have offered to install solar rooftop PV plants and supply power generated at a rate of Rs.5.00 per unit. The latest tariffs discovered on 4th November, 2015 in the
  • 12. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 12 NTPC Tender for setting up of 500MW Solar plant in Andhra Pradesh is as low as Rs.4.63 per unit. This indicates that the cost of generation from solar power plants is on the decline. The tariff allowed in other States on net metering basis is indicated in the Annexure for reference. The Commission proposes to determine tariff duly considering all components of expenditure like capital cost, interest on loan, depreciation, interest on working capital and return on equity which have been discussed in the above paragraphs. 6. Implementation of scheme of SRTPV Plants: Based on the above discussions, considering the present retail tariff for different categories of consumers in the State, the Commission proposes the following approach for implementation of the scheme of SRTPV and small Solar Plants: Category of Consumers Allowable Installed Capacity of rooftop and small solar PV plants Billing NET-METERING (Applicable to Industrial, Commercial and all categories of consumers other than Domestic category) HT Consumers (other than Residential) Equivalent to Contract Demand/Sanctioned Load subject to a maximum of 500KW (HT Power supply beyond 50KW). 50% of energy generated has to be consumed by the consumer. Balance 50% energy is to be billed at tariff determined by the Commission. In case the self- consumption is less than 50%, such shortfall in energy consumption shall be billed at Average Pooled Power Purchase cost notified by the Commission from time to time. LT Consumers (other than Domestic) Equivalent to Sanctioned Load subject to a maximum of 5KW on single phase supply and for above 5KW upto 50KW on three phase supply.
  • 13. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 13 In case of installed capacity in excess of allowable capacity, the energy injected in excess of the allowable installed capacity shall be billed at Average Pooled Power Purchase cost notified by the Commission from time to time. GROSS METERING (Applicable to only Domestic Consumers) Domestic Consumers HT Residential Consumers (HT-4): Equivalent to Contract Demand/Sanctioned Load subject to a maximum of 500KW (HT Power supply beyond 50KW). LT Domestic Consumers (LT2(a)): Equivalent to Sanctioned Load subject to a maximum of 5KW on single phase supply and for above 5KW upto 50KW on three phase supply. Gross energy generated by the Solar Rooftop plant will be allowed to be injected into the grid payable at the tariff to be fixed by the Commission based on the parameters discussed in this paper. The Consumer shall continue to pay his energy bills for the energy consumed at the prevailing applicable retail supply tariff. In case of installed capacity in excess of allowable capacity, the energy injected in excess of the allowable installed capacity shall be billed at Average Pooled Power Purchase cost notified by the Commission from time to time.
  • 14. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 14 7. Applicability of the revised tariff: The revised tariff to be determined is proposed to be made applicable to all the new rooftop solar and small solar PV plants of stipulated capacity entering into power purchase agreement from 1st January, 2016 onwards and on or before 31st March, 2018. 8. Suggestions/Comments/Views: As per the above discussions, the Commission proposes to determine tariff for rooftop and kilowatt scale small solar power plants. The Commission requests all stakeholders and the general public to furnish their views/suggestions/comments before 16th December, 2015. The stakeholders are requested to furnish any documents or material as may be available in support of their proposals / views so as to enable determination of tariff in a reasonable manner. *******
  • 15. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 15 Annexure Summary of tariff parameters considered in some of the other SERCs in comparison with KERC State Haryana Gujarat KERC Date of issue 13.08.2014 17.08.2015 10.10.2013 As proposed in this discussion paper Draft/Final Final Order Final Order Final Order Draft Oder Applicability Plants to be commissioned between FY 2014- 15 and FY 2015-16 Plants to be commissioned during 1st July, 2015 to 31st March, 2018 Plants to be commissione d between FY 14 and FY18 Plants to be commission ed during 1st January,201 6 and upto 31st March, FY18 Capital cost Rs.6.80 Crores/MW Rs. 80,000/kW Rs. 90,000/kW Rs. 75000/kW CUF 19% 19% 19% 19% Operation and maintenance expenses Rs.1124 /kW with an annual escalation of 5.72% Rs, 1090/kW with an escalation of 5.72% 2% of Capital cost i.e Rs.1800/kW with an annual escalation of 5.72% Rs.1500 / KW (2% of the capital cost) with an annual escalation of 5.72% Life of plant and machinery 25 years 25 years 25 years 25 years Term of Loan 10 years 10 years 10 years 12 years Interest on loan 13.75% 12.70% 12.50% 12.30% Working Capital components a)O&M for one month; (b) Receivables equivalent to 2 months of energy charges for sale of electricity calculated on the normative CUF; (c) Maintenance spare @ 15% of operation and maintenance expenses. a)O&M expense for one month; (b) One month energy charge at normative CUF; 2 months receivables 2 months receivables
  • 16. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 16 Interest on working capital 14.00% 11.85% 13% 12.50% Return on equity 16% on normative equity (MAT / Corporate Tax shall be separately allowed in the tariff) 14% 16% 16% Debt-equity ratio 70 : 30 70:30 70:30 70:30 Depreciation rate 7% for first 10 years up to maximum of 90% 6% for first 10 years then 2% for the next 15 years Depreciation rate for the first 10 years=7% and the next 15 years=1.33% Depreciatio n rate for the first 12 years=5.83% and the next 13 years=1.54% Discount factor 14.42% 10.647% 13.41% WACC Tariff (Without Accelerated Depreciation) 7.19/kWh Rs.8.42/Unit during 1st July,2015 to 31st March, 2016 Rs.7.83/Unit during 1st April, 2016 to 31st March, 2017 Rs.7.28/Unit during 1st April,2017 to 31st March, 2018 9.56/kWh without subsidy 7.20/kWh with subsidy To be determined
  • 17. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 17 The tariff allowed in other States on net metering basis for SRTPV Name of State Reference Allowable tariff for Solar Rooftop Plant Tamil Nadu TEDA Guidelines for implementation of LT connectivity/Net- Metering Injection upto 90% of the consumption annually will be adjusted at applicable retail supply tariff. Excess beyond 90% will go as lapsed. Andhra Pradesh Andhra Pradesh Solar Power Policy-2015 dated 12.02.2015 Net-metering OR Gross metering allowed at tariff equal to the average cost to serve determined by APERC every year. For FY14, it is Rs.5.25/Unit. Telangana Telangana Solar Policy 2015 Net-metering OR Gross metering is allowed. Under gross metering the power would be sold at average cost of service of the DISCOM. The tariff applicable for units under net metering would be at average pooled power purchase cost. Maharashtra Net-metering Regulations 2015 Net energy at the end of each Financial year shall be purchased by the DISCOM at approved Average Cost of Power Purchase for that year.
  • 18. Discussion paper for determination of tariff for Rooftop and Small kilowatt scale solar PV plants 18 Rajasthan Net-metering Regulations issued by Rajasthan ERC dated 26.02.2015 & RERC Solar Tariff Order dated 19.06.2015. Excess energy of 50units or more in month is paid at RERC determined tariff. In case it is less than 50 units in a month, the same is carried forward till the cumulative excess reaches 50 Units. At present RERC tariff is Rs.6.74/Unit. Punjab Policy on net-metering for grid interactive Roof- top Solar Photo Voltaic Power Plants dated 05.11.2014 issued by Government of Punjab Injection upto 90% of the consumption annually will be adjusted at applicable retail supply tariff. Excess beyond 90% will go as lapsed. Haryana HERC Rooftop solar grid interactive system based on net-metering Regulations 2014 dated 25.11.2014 Injection upto 90% of the consumption annually will be adjusted at applicable retail supply tariff. Excess beyond 90% will go as lapsed. Delhi DERC Guidelines on Net- metering Regulations- 2014 Excess generation is paid at Average Pooled Power Purchase Cost to be settled at the end of the year Gujarat Gujarat Solar Policy-2015 dated 13.08.2015 Surplus energy will be paid at Average Pooled Power Purchase rate of the year in which the plant is commissioned.