The document discusses payment of water use charges and net hydel profit to Azad Jammu & Kashmir (AJ&K). Key points include:
- AJ&K argues it should receive the same treatment as provinces in terms of hydel proceeds and electricity rates. Currently it receives Rs. 0.15/kWh while provinces receive Rs. 1.10/kWh.
- The federal government has proposed declaring AJK's electricity department a distribution company (DISCO) and allowing the national regulator NEPRA to determine electricity tariffs for AJ&K consistent with other DISCOs.
- This would eliminate outstanding receivables of over Rs. 80 billion owed by AJ&K to DISCO
The document discusses water usage charges and net hydel profits owed to provinces based on electricity generated from hydroelectric dams. It notes that Khyber Pakhtunkhwa and Punjab provinces are owed billions in unpaid net hydel profits according to the constitution and agreements. The government of Pakistan and provinces have signed agreements to uncapped net hydel profit rates and settle arrears owed to the provinces over several years.
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
The document summarizes the regulatory regime for renewable energy projects in Andhra Pradesh. It outlines the state commission's role in promoting renewable generation under the Electricity Act of 2003. Key points include a renewable purchase obligation of 5% for distribution licensees from 2005-2008, with 0.5% reserved for wind. Tariffs were determined in 2004 and incentives were provided, like banking privileges for mini-hydel and wind projects. The order rationalized tariffs for various renewable technologies.
This document provides an overview of the availability based tariff (ABT) mechanism and deviation settlement mechanism (DSM) in India. It discusses the constituents of the power grid in India and the evolution of the regional grids into a unified national grid. It then explains the constituents of ABT, including generators, transmission lines, load dispatch centers, and regulatory authorities. The key aspects of ABT are described, such as scheduling of generation and load, deviation charges for over-injection and under-injection to incentivize grid discipline. Finally, the document outlines the changes introduced in Maharashtra through the DSM regulations of 2019, bringing the state mechanism in line with the central electricity regulatory commission guidelines.
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
The document discusses various policy developments and regulatory orders related to wind and renewable energy in India:
1) State electricity regulators in Andhra Pradesh and Karnataka announced increased retail tariffs for FY2012-13 which will make third party sale of wind power and open access more attractive.
2) The Ministry of Power is examining legislative and policy changes to accelerate renewable energy development including long term renewable purchase obligations.
3) Electricity regulators issued orders determining pooled power purchase costs, transmission charges, and renewable energy tariffs for FY2012-13.
4) Regulators also announced renewable purchase obligations for utilities, open access consumers, and captive power producers aimed at promoting renewable energy.
This document outlines a proposed power purchase agreement between Power One Ltd. and Gujarat Urja Vikas Nigam Limited for a solar PV project. Key points include:
- The PPA defines the commercial terms for sale of electricity from the solar project to GUVNL over 25 years.
- Power One will be responsible for project construction and commissioning by the scheduled date. Liquidated damages apply for delays.
- GUVNL will pay a fixed tariff of Rs. 15/unit for the first 12 years and Rs. 5/unit for years 13-25 for solar energy delivered.
- Billing and payment terms require Power One to submit monthly invoices and GUVNL
This document outlines the general terms and conditions of electricity tariffs applicable to both high tension (HT) and low tension (LT) supply in Karnataka, India. Some key points include:
1. Electricity supply is subject to execution of agreement, payment of deposits, and compliance with supply conditions and regulations.
2. Tariffs apply to single point supply unless approved otherwise. Minimum charges are payable irrespective of installation usage.
3. Tariffs apply within the licensee's area of operation. Taxes and surcharges are extra as decided by the state government.
4. Provisions for unauthorized resale, delayed bill payment penalties, load limit exemptions, and incentive for timely/advance
The document discusses water usage charges and net hydel profits owed to provinces based on electricity generated from hydroelectric dams. It notes that Khyber Pakhtunkhwa and Punjab provinces are owed billions in unpaid net hydel profits according to the constitution and agreements. The government of Pakistan and provinces have signed agreements to uncapped net hydel profit rates and settle arrears owed to the provinces over several years.
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
The document summarizes the regulatory regime for renewable energy projects in Andhra Pradesh. It outlines the state commission's role in promoting renewable generation under the Electricity Act of 2003. Key points include a renewable purchase obligation of 5% for distribution licensees from 2005-2008, with 0.5% reserved for wind. Tariffs were determined in 2004 and incentives were provided, like banking privileges for mini-hydel and wind projects. The order rationalized tariffs for various renewable technologies.
This document provides an overview of the availability based tariff (ABT) mechanism and deviation settlement mechanism (DSM) in India. It discusses the constituents of the power grid in India and the evolution of the regional grids into a unified national grid. It then explains the constituents of ABT, including generators, transmission lines, load dispatch centers, and regulatory authorities. The key aspects of ABT are described, such as scheduling of generation and load, deviation charges for over-injection and under-injection to incentivize grid discipline. Finally, the document outlines the changes introduced in Maharashtra through the DSM regulations of 2019, bringing the state mechanism in line with the central electricity regulatory commission guidelines.
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
The document discusses various policy developments and regulatory orders related to wind and renewable energy in India:
1) State electricity regulators in Andhra Pradesh and Karnataka announced increased retail tariffs for FY2012-13 which will make third party sale of wind power and open access more attractive.
2) The Ministry of Power is examining legislative and policy changes to accelerate renewable energy development including long term renewable purchase obligations.
3) Electricity regulators issued orders determining pooled power purchase costs, transmission charges, and renewable energy tariffs for FY2012-13.
4) Regulators also announced renewable purchase obligations for utilities, open access consumers, and captive power producers aimed at promoting renewable energy.
This document outlines a proposed power purchase agreement between Power One Ltd. and Gujarat Urja Vikas Nigam Limited for a solar PV project. Key points include:
- The PPA defines the commercial terms for sale of electricity from the solar project to GUVNL over 25 years.
- Power One will be responsible for project construction and commissioning by the scheduled date. Liquidated damages apply for delays.
- GUVNL will pay a fixed tariff of Rs. 15/unit for the first 12 years and Rs. 5/unit for years 13-25 for solar energy delivered.
- Billing and payment terms require Power One to submit monthly invoices and GUVNL
This document outlines the general terms and conditions of electricity tariffs applicable to both high tension (HT) and low tension (LT) supply in Karnataka, India. Some key points include:
1. Electricity supply is subject to execution of agreement, payment of deposits, and compliance with supply conditions and regulations.
2. Tariffs apply to single point supply unless approved otherwise. Minimum charges are payable irrespective of installation usage.
3. Tariffs apply within the licensee's area of operation. Taxes and surcharges are extra as decided by the state government.
4. Provisions for unauthorized resale, delayed bill payment penalties, load limit exemptions, and incentive for timely/advance
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
The document provides a summary of recent developments in India's wind and renewable energy sectors. Key points include:
- The Tamil Nadu and Rajasthan electricity regulators have extended existing wind power tariffs.
- TNEB has proposed increasing electricity tariffs for industrial consumers in Tamil Nadu.
- TANGEDCO submitted a proposal to overcome power shortages in Tamil Nadu, including utilizing more wind power and establishing new transmission infrastructure.
- Upcoming events include the Wind IPP Summit in January and the publication of CERC's draft tariff regulations for 2012-17, which aim to promote renewable energy projects.
This document summarizes Gujarat's new Wind Power Policy for 2013-2016. The key points are:
- It aims to promote wind power generation in Gujarat by providing various incentives over a 25 year period.
- It sets renewable purchase obligations for distribution licensees to purchase a portion of energy from wind and other renewable sources.
- It allows private companies and individuals to set up wind turbines either for captive use or third party sale, and lays out terms for wheeling power, banking surplus energy, and selling excess to distribution utilities.
This document summarizes the key issues facing Pakistan's economy and energy security, specifically in the power sector. It identifies three main causes of the ongoing problems: (1) an unwillingness by many to pay the true price for electricity due to subsidies and lack of enforcement, (2) political pressure to maintain subsidies across all consumers rather than targeting the poor, and (3) high transmission losses from theft and poor infrastructure that amount to $1.7 billion annually. The document evaluates some proposed solutions in Pakistan's new National Power Policy to address tariffs, losses, and competition, but questions who will be responsible to implement and oversee the reforms across different agencies.
This document summarizes the key issues facing Pakistan's economy and energy security, specifically in the power sector. It identifies three main causes of the ongoing problems: (1) an unwillingness by many to pay the actual costs of electricity due to subsidies; (2) political pressure to maintain subsidies across all consumers; and (3) high transmission losses and theft due in part to weak accountability. The document reviews various proposals in Pakistan's new National Power Policy to address these issues through tariff reforms, curbing losses, and increasing competition in generation. Overall it argues comprehensive reforms are needed across regulatory bodies, state-owned companies, and the civil service to resolve the systemic problems plaguing the power sector.
The document provides information about pumped storage hydropower projects. Some key points:
- Pumped storage projects store excess energy by pumping water to an upper reservoir, and generate power by releasing the water when demand is high.
- There are three types of projects based on reservoir locations: on-stream, off-stream open loop, and off-stream closed loop.
- The Government of India has issued guidelines to promote pumped storage, including providing clearances, waiving transmission costs, and budgetary support for infrastructure.
- States are encouraged to allocate projects to public sector units and conduct competitive bidding. Tariffs will be set to incentivize peak power supply.
This document discusses rationales for capping fixed charges for coal mine/block projects under DBFOO bidding. It provides:
1) Tables showing recent bid tariffs with average fixed charges ranging from Rs. 2.28-4.47/kWh.
2) Calculations of fixed charges from Rs. 2.26-3.3/kWh based on project costs of Rs. 9,000-14,000 crores per CERC regulations.
3) Arguments that actual costs are higher than CERC norms due to additional railway infrastructure, mine development costs, risk premiums, and assumptions around station heat rate, auxiliary power, and availability penalties in DBFOO documents.
The newsletter provides a summary of developments in the renewable energy sector in India for the month of October 2012. Key points include:
- REC prices remained at the floor price due to a large oversupply of RECs, with over 13 lakh RECs remaining unsold.
- The CERC provided an order on eligibility of UP co-gen plants for RECs, clarifying that plants consuming 51% or more of power for self-use are not eligible if they avail electricity duty waivers.
- Tamil Nadu announced a new solar policy targeting 3000 MW of solar capacity by 2015 through various programs.
- In REC trading for the month, demand was lower than supply, keeping prices at
The document provides an overview of availability based tariff (ABT) in India. Some key points:
- ABT was introduced to address issues with the previous single and two-part tariff systems and encourage grid discipline.
- Under ABT, generators declare their expected output capacity daily and regional load dispatch centers schedule generation and issue dispatch instructions. Beneficiaries pay capacity charges based on entitlements and energy charges based on scheduled generation.
- Deviations from schedules are settled at 15-minute intervals using frequency-linked UI charges, with penalties for overdrawals at lower frequencies.
- Fixed costs recovered through capacity charges include return on equity, interest, depreciation and O&M. Variable
Wind Force Newsletter Nov, Edition, 2011rupeshsingh_1
The document discusses several developments related to wind power in India:
1. Jami Hossain of WinDForce was elected Treasurer of the World Wind Energy Association.
2. Key topics covered in a government publication include the potential and trends of wind technology.
3. Electricity regulators in Karnataka announced increased tariffs and amended agreements for wheeling and banking of wind power. Time-of-day tariffs and wheeling charges were also adjusted.
Petition of MSEDCL for seeking approval for deviation in bidding document from MoP
guidelines for long term procurement of Solar Power under “Mukhyamantri Saour Krishi
Vahini Yojana” with 2 to 10 MW capacity projects connected to distribution network with
total quantum of 1000 MW through competitive bidding (E- reverse auction); under
Section 19 of MERC (RPO, Its Compliance and Implementation of REC Framework)
Regulations, 2016 Order 131 of 2018-12062018
Electricity Act (Amendment) Bill 2022.pptxmsounak95
Electricity Amendment Bill, 2022 presents a landmark opportunity in overhauling the electricity sector. It introduces free and fair competition in distribution business as well as updated arbitration procedures.
The document summarizes key proposed amendments in the Electricity (Amendment) Bill, 2020. Some of the major changes proposed include establishing a National Renewable Energy Policy, introducing a payment security mechanism before scheduling electricity dispatch, allowing cross border electricity trade through rules prescribed by the central government, constituting a selection committee for regulatory commissions and authorities, establishing an Electricity Contract Enforcement Authority to settle contract disputes, reducing surcharges and cross subsidies progressively, and requiring state governments to pay in advance any electricity subsidies through a direct benefit transfer mechanism.
The document provides an overview of the Indian power sector, including its structure, operations, and transactions. It discusses how the Indian power system is divided into five regional grids and the interconnections between them. It also summarizes the installed generation capacity by source and region as of 2007. Finally, it introduces availability-based tariff (ABT), which was implemented in the Southern Region in 2003. ABT uses a three-part tariff structure including capacity charges, energy charges, and UI charges to incentivize grid discipline among generators, transmitters, and beneficiaries.
This document provides guidelines for implementing the Pradhan Mantri Kisan Urja Suraksha evem Utthan Mahabhiyan (PM KUSUM) Scheme in India. The scheme has three components: 1) Setting up decentralized ground or stilt-mounted solar power plants up to 2 MW capacity, 2) Installing 17.5 lakh standalone solar pumps for agriculture, and 3) Solarizing 10 lakh existing grid-connected agriculture pumps. It aims to add 25,750 MW of solar capacity by 2022 with Rs. 34,422 crore in central funding. Distribution companies will notify available surplus capacity at substations and invite applications from farmers, cooperatives, or developers to set up renewable plants
The document is a determination by the National Electric Power Regulatory Authority (NEPRA) of Pakistan regarding a proposed modification to the generation license of K-Electric Limited (KEL).
NEPRA approved adding re-gasified liquefied natural gas (RLNG) as an alternate fuel for KEL's generation facilities. This was proposed by KEL due to declining natural gas supply from the Sui Southern Gas Company and to ensure optimal use of existing generation assets. Some stakeholders expressed concerns about the potential tariff impact and need for evaluation of plant efficiencies using RLNG. NEPRA will enforce performance standards and protect consumer interests related to increased costs from using the more expensive RLNG fuel.
The summary provides an overview of India's solar policies and the Jawaharlal Nehru National Solar Mission (JNNSM). Key points include:
- The JNNSM aims to achieve 20,000 MW of grid-connected solar power by 2022 through a phased approach from 2010-2022. Phase 1 targets 500 MW by 2013.
- It also targets 1,000 MW of off-grid solar power by 2017 and 2,000 MW by 2022 through programs like solar home lighting and microgrids.
- Policies include capital subsidies, soft loans, generation-based incentives and renewable purchase obligations set by states to encourage solar development.
- For grid projects,
The document discusses Russia's investment guarantee mechanism (MGI) for constructing new power plants. The MGI aims to attract private investment for needed new generating capacity when projects are currently uneconomical. It outlines regulations and processes for MGI projects, including regional authorities petitioning for plants, approval of options, competitive bidding process selected by system operators, investor construction and operation, payments guaranteeing investor returns. The MGI is intended to ensure electricity supply reliability without large tariff increases for consumers while also providing revenue guarantees and opportunities for investors.
webinar on " Economics Behind the Solutions to Optimize KVAh Billing”Ganesh Kondikire
We at SAS Powertech were involved in auditing 100 consumers of MSEDCL and bringing out relevant findings which initiated this change. We are here now to presented an unbiased and realistic webinar
NEPRA has revised new tariff rate. Fesco bill will be calculated according to the new slab rate. Fesco bill will also be generated as per new rates. New rates are applied form 25/07/2022
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
Wind Force Newsletter Dec, Edition, 2011rupeshsingh_1
The document provides a summary of recent developments in India's wind and renewable energy sectors. Key points include:
- The Tamil Nadu and Rajasthan electricity regulators have extended existing wind power tariffs.
- TNEB has proposed increasing electricity tariffs for industrial consumers in Tamil Nadu.
- TANGEDCO submitted a proposal to overcome power shortages in Tamil Nadu, including utilizing more wind power and establishing new transmission infrastructure.
- Upcoming events include the Wind IPP Summit in January and the publication of CERC's draft tariff regulations for 2012-17, which aim to promote renewable energy projects.
This document summarizes Gujarat's new Wind Power Policy for 2013-2016. The key points are:
- It aims to promote wind power generation in Gujarat by providing various incentives over a 25 year period.
- It sets renewable purchase obligations for distribution licensees to purchase a portion of energy from wind and other renewable sources.
- It allows private companies and individuals to set up wind turbines either for captive use or third party sale, and lays out terms for wheeling power, banking surplus energy, and selling excess to distribution utilities.
This document summarizes the key issues facing Pakistan's economy and energy security, specifically in the power sector. It identifies three main causes of the ongoing problems: (1) an unwillingness by many to pay the true price for electricity due to subsidies and lack of enforcement, (2) political pressure to maintain subsidies across all consumers rather than targeting the poor, and (3) high transmission losses from theft and poor infrastructure that amount to $1.7 billion annually. The document evaluates some proposed solutions in Pakistan's new National Power Policy to address tariffs, losses, and competition, but questions who will be responsible to implement and oversee the reforms across different agencies.
This document summarizes the key issues facing Pakistan's economy and energy security, specifically in the power sector. It identifies three main causes of the ongoing problems: (1) an unwillingness by many to pay the actual costs of electricity due to subsidies; (2) political pressure to maintain subsidies across all consumers; and (3) high transmission losses and theft due in part to weak accountability. The document reviews various proposals in Pakistan's new National Power Policy to address these issues through tariff reforms, curbing losses, and increasing competition in generation. Overall it argues comprehensive reforms are needed across regulatory bodies, state-owned companies, and the civil service to resolve the systemic problems plaguing the power sector.
The document provides information about pumped storage hydropower projects. Some key points:
- Pumped storage projects store excess energy by pumping water to an upper reservoir, and generate power by releasing the water when demand is high.
- There are three types of projects based on reservoir locations: on-stream, off-stream open loop, and off-stream closed loop.
- The Government of India has issued guidelines to promote pumped storage, including providing clearances, waiving transmission costs, and budgetary support for infrastructure.
- States are encouraged to allocate projects to public sector units and conduct competitive bidding. Tariffs will be set to incentivize peak power supply.
This document discusses rationales for capping fixed charges for coal mine/block projects under DBFOO bidding. It provides:
1) Tables showing recent bid tariffs with average fixed charges ranging from Rs. 2.28-4.47/kWh.
2) Calculations of fixed charges from Rs. 2.26-3.3/kWh based on project costs of Rs. 9,000-14,000 crores per CERC regulations.
3) Arguments that actual costs are higher than CERC norms due to additional railway infrastructure, mine development costs, risk premiums, and assumptions around station heat rate, auxiliary power, and availability penalties in DBFOO documents.
The newsletter provides a summary of developments in the renewable energy sector in India for the month of October 2012. Key points include:
- REC prices remained at the floor price due to a large oversupply of RECs, with over 13 lakh RECs remaining unsold.
- The CERC provided an order on eligibility of UP co-gen plants for RECs, clarifying that plants consuming 51% or more of power for self-use are not eligible if they avail electricity duty waivers.
- Tamil Nadu announced a new solar policy targeting 3000 MW of solar capacity by 2015 through various programs.
- In REC trading for the month, demand was lower than supply, keeping prices at
The document provides an overview of availability based tariff (ABT) in India. Some key points:
- ABT was introduced to address issues with the previous single and two-part tariff systems and encourage grid discipline.
- Under ABT, generators declare their expected output capacity daily and regional load dispatch centers schedule generation and issue dispatch instructions. Beneficiaries pay capacity charges based on entitlements and energy charges based on scheduled generation.
- Deviations from schedules are settled at 15-minute intervals using frequency-linked UI charges, with penalties for overdrawals at lower frequencies.
- Fixed costs recovered through capacity charges include return on equity, interest, depreciation and O&M. Variable
Wind Force Newsletter Nov, Edition, 2011rupeshsingh_1
The document discusses several developments related to wind power in India:
1. Jami Hossain of WinDForce was elected Treasurer of the World Wind Energy Association.
2. Key topics covered in a government publication include the potential and trends of wind technology.
3. Electricity regulators in Karnataka announced increased tariffs and amended agreements for wheeling and banking of wind power. Time-of-day tariffs and wheeling charges were also adjusted.
Petition of MSEDCL for seeking approval for deviation in bidding document from MoP
guidelines for long term procurement of Solar Power under “Mukhyamantri Saour Krishi
Vahini Yojana” with 2 to 10 MW capacity projects connected to distribution network with
total quantum of 1000 MW through competitive bidding (E- reverse auction); under
Section 19 of MERC (RPO, Its Compliance and Implementation of REC Framework)
Regulations, 2016 Order 131 of 2018-12062018
Electricity Act (Amendment) Bill 2022.pptxmsounak95
Electricity Amendment Bill, 2022 presents a landmark opportunity in overhauling the electricity sector. It introduces free and fair competition in distribution business as well as updated arbitration procedures.
The document summarizes key proposed amendments in the Electricity (Amendment) Bill, 2020. Some of the major changes proposed include establishing a National Renewable Energy Policy, introducing a payment security mechanism before scheduling electricity dispatch, allowing cross border electricity trade through rules prescribed by the central government, constituting a selection committee for regulatory commissions and authorities, establishing an Electricity Contract Enforcement Authority to settle contract disputes, reducing surcharges and cross subsidies progressively, and requiring state governments to pay in advance any electricity subsidies through a direct benefit transfer mechanism.
The document provides an overview of the Indian power sector, including its structure, operations, and transactions. It discusses how the Indian power system is divided into five regional grids and the interconnections between them. It also summarizes the installed generation capacity by source and region as of 2007. Finally, it introduces availability-based tariff (ABT), which was implemented in the Southern Region in 2003. ABT uses a three-part tariff structure including capacity charges, energy charges, and UI charges to incentivize grid discipline among generators, transmitters, and beneficiaries.
This document provides guidelines for implementing the Pradhan Mantri Kisan Urja Suraksha evem Utthan Mahabhiyan (PM KUSUM) Scheme in India. The scheme has three components: 1) Setting up decentralized ground or stilt-mounted solar power plants up to 2 MW capacity, 2) Installing 17.5 lakh standalone solar pumps for agriculture, and 3) Solarizing 10 lakh existing grid-connected agriculture pumps. It aims to add 25,750 MW of solar capacity by 2022 with Rs. 34,422 crore in central funding. Distribution companies will notify available surplus capacity at substations and invite applications from farmers, cooperatives, or developers to set up renewable plants
The document is a determination by the National Electric Power Regulatory Authority (NEPRA) of Pakistan regarding a proposed modification to the generation license of K-Electric Limited (KEL).
NEPRA approved adding re-gasified liquefied natural gas (RLNG) as an alternate fuel for KEL's generation facilities. This was proposed by KEL due to declining natural gas supply from the Sui Southern Gas Company and to ensure optimal use of existing generation assets. Some stakeholders expressed concerns about the potential tariff impact and need for evaluation of plant efficiencies using RLNG. NEPRA will enforce performance standards and protect consumer interests related to increased costs from using the more expensive RLNG fuel.
The summary provides an overview of India's solar policies and the Jawaharlal Nehru National Solar Mission (JNNSM). Key points include:
- The JNNSM aims to achieve 20,000 MW of grid-connected solar power by 2022 through a phased approach from 2010-2022. Phase 1 targets 500 MW by 2013.
- It also targets 1,000 MW of off-grid solar power by 2017 and 2,000 MW by 2022 through programs like solar home lighting and microgrids.
- Policies include capital subsidies, soft loans, generation-based incentives and renewable purchase obligations set by states to encourage solar development.
- For grid projects,
The document discusses Russia's investment guarantee mechanism (MGI) for constructing new power plants. The MGI aims to attract private investment for needed new generating capacity when projects are currently uneconomical. It outlines regulations and processes for MGI projects, including regional authorities petitioning for plants, approval of options, competitive bidding process selected by system operators, investor construction and operation, payments guaranteeing investor returns. The MGI is intended to ensure electricity supply reliability without large tariff increases for consumers while also providing revenue guarantees and opportunities for investors.
webinar on " Economics Behind the Solutions to Optimize KVAh Billing”Ganesh Kondikire
We at SAS Powertech were involved in auditing 100 consumers of MSEDCL and bringing out relevant findings which initiated this change. We are here now to presented an unbiased and realistic webinar
NEPRA has revised new tariff rate. Fesco bill will be calculated according to the new slab rate. Fesco bill will also be generated as per new rates. New rates are applied form 25/07/2022
Similar to (WUC P&DD) Presentation for Cabinet 08-11-2017 on Net Hydel.pptx (20)
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
Epcon is One of the World's leading Manufacturing Companies.EpconLP
Epcon is One of the World's leading Manufacturing Companies. With over 4000 installations worldwide, EPCON has been pioneering new techniques since 1977 that have become industry standards now. Founded in 1977, Epcon has grown from a one-man operation to a global leader in developing and manufacturing innovative air pollution control technology and industrial heating equipment.
Recycling and Disposal on SWM Raymond Einyu pptxRayLetai1
Increasing urbanization, rural–urban migration, rising standards of living, and rapid development associated with population growth have resulted in increased solid waste generation by industrial, domestic and other activities in Nairobi City. It has been noted in other contexts too that increasing population, changing consumption patterns, economic development, changing income, urbanization and industrialization all contribute to the increased generation of waste.
With the increasing urban population in Kenya, which is estimated to be growing at a rate higher than that of the country’s general population, waste generation and management is already a major challenge. The industrialization and urbanization process in the country, dominated by one major city – Nairobi, which has around four times the population of the next largest urban centre (Mombasa) – has witnessed an exponential increase in the generation of solid waste. It is projected that by 2030, about 50 per cent of the Kenyan population will be urban.
Aim:
A healthy, safe, secure and sustainable solid waste management system fit for a world – class city.
Improve and protect the public health of Nairobi residents and visitors.
Ecological health, diversity and productivity and maximize resource recovery through the participatory approach.
Goals:
Build awareness and capacity for source separation as essential components of sustainable waste management.
Build new environmentally sound infrastructure and systems for safe disposal of residual waste and replacing current dumpsites which should be commissioned.
Current solid waste management situation:
The status.
Solid waste generation rate is at 2240 tones / day
collection efficiently is at about 50%.
Actors i.e. city authorities, CBO’s , private firms and self-disposal
Current SWM Situation in Nairobi City:
Solid waste generation – collection – dumping
Good Practices:
• Separation – recycling – marketing.
• Open dumpsite dandora dump site through public education on source separation of waste, of which the situation can be reversed.
• Nairobi is one of the C40 cities in this respect , various actors in the solid waste management space have adopted a variety of technologies to reduce short lived climate pollutants including source separation , recycling , marketing of the recycled products.
• Through the network, it should expect to benefit from expertise of the different actors in the network in terms of applicable technologies and practices in reducing the short-lived climate pollutants.
Good practices:
Despite the dismal collection of solid waste in Nairobi city, there are practices and activities of informal actors (CBOs, CBO-SACCOs and yard shop operators) and other formal industrial actors on solid waste collection, recycling and waste reduction.
Practices and activities of these actor groups are viewed as innovations with the potential to change the way solid waste is handled.
CHALLENGES:
• Resource Allocation.
Microbial characterisation and identification, and potability of River Kuywa ...Open Access Research Paper
Water contamination is one of the major causes of water borne diseases worldwide. In Kenya, approximately 43% of people lack access to potable water due to human contamination. River Kuywa water is currently experiencing contamination due to human activities. Its water is widely used for domestic, agricultural, industrial and recreational purposes. This study aimed at characterizing bacteria and fungi in river Kuywa water. Water samples were randomly collected from four sites of the river: site A (Matisi), site B (Ngwelo), site C (Nzoia water pump) and site D (Chalicha), during the dry season (January-March 2018) and wet season (April-July 2018) and were transported to Maseno University Microbiology and plant pathology laboratory for analysis. The characterization and identification of bacteria and fungi were carried out using standard microbiological techniques. Nine bacterial genera and three fungi were identified from Kuywa river water. Clostridium spp., Staphylococcus spp., Enterobacter spp., Streptococcus spp., E. coli, Klebsiella spp., Shigella spp., Proteus spp. and Salmonella spp. Fungi were Fusarium oxysporum, Aspergillus flavus complex and Penicillium species. Wet season recorded highest bacterial and fungal counts (6.61-7.66 and 3.83-6.75cfu/ml) respectively. The results indicated that the river Kuywa water is polluted and therefore unsafe for human consumption before treatment. It is therefore recommended that the communities to ensure that they boil water especially for drinking.
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Open Access Research Paper
Water polluted by dyestuffs compounds is a global threat to health and the environment; accordingly, we prepared a green novel sorbent chemical and Physical system from an algae, chitosan and chitosan nanoparticle and impregnated with algae with chitosan nanocomposite for the sorption of Malachite green dye from water. The algae with chitosan nanocomposite by a simple method and used as a recyclable and effective adsorbent for the removal of malachite green dye from aqueous solutions. Algae, chitosan, chitosan nanoparticle and algae with chitosan nanocomposite were characterized using different physicochemical methods. The functional groups and chemical compounds found in algae, chitosan, chitosan algae, chitosan nanoparticle, and chitosan nanoparticle with algae were identified using FTIR, SEM, and TGADTA/DTG techniques. The optimal adsorption conditions, different dosages, pH and Temperature the amount of algae with chitosan nanocomposite were determined. At optimized conditions and the batch equilibrium studies more than 99% of the dye was removed. The adsorption process data matched well kinetics showed that the reaction order for dye varied with pseudo-first order and pseudo-second order. Furthermore, the maximum adsorption capacity of the algae with chitosan nanocomposite toward malachite green dye reached as high as 15.5mg/g, respectively. Finally, multiple times reusing of algae with chitosan nanocomposite and removing dye from a real wastewater has made it a promising and attractive option for further practical applications.
ENVIRONMENT~ Renewable Energy Sources and their future prospects.tiwarimanvi3129
This presentation is for us to know that how our Environment need Attention for protection of our natural resources which are depleted day by day that's why we need to take time and shift our attention to renewable energy sources instead of non-renewable sources which are better and Eco-friendly for our environment. these renewable energy sources are so helpful for our planet and for every living organism which depends on environment.
Presented by The Global Peatlands Assessment: Mapping, Policy, and Action at GLF Peatlands 2024 - The Global Peatlands Assessment: Mapping, Policy, and Action
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Joshua Orris
The incorporation of a 3DCSM and completion of HRSC provided a tool for enhanced, data-driven, decisions to support a change in remediation closure strategies. Currently, an approved pilot study has been obtained to shut-down the remediation systems (ISCO, P&T) and conduct a hydraulic study under non-pumping conditions. A separate micro-biological bench scale treatability study was competed that yielded positive results for an emerging innovative technology. As a result, a field pilot study has commenced with results expected in nine-twelve months. With the results of the hydraulic study, field pilot studies and an updated risk assessment leading site monitoring optimization cost lifecycle savings upwards of $15MM towards an alternatively evolved best available technology remediation closure strategy.
Climate Change All over the World .pptxsairaanwer024
Climate change refers to significant and lasting changes in the average weather patterns over periods ranging from decades to millions of years. It encompasses both global warming driven by human emissions of greenhouse gases and the resulting large-scale shifts in weather patterns. While climate change is a natural phenomenon, human activities, particularly since the Industrial Revolution, have accelerated its pace and intensity
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Joshua Orris
Results of geophysics and pneumatic injection pilot tests during 2003 – 2007 yielded significant positive results for injection delivery design and contaminant mass treatment, resulting in permanent shut-down of an existing groundwater Pump & Treat system.
Accessible source areas were subsequently removed (2011) by soil excavation and treated with the placement of Emulsified Vegetable Oil EVO and zero-valent iron ZVI to accelerate treatment of impacted groundwater in overburden and weathered fractured bedrock. Post pilot test and post remediation groundwater monitoring has included analyses of CVOCs, organic fatty acids, dissolved gases and QuantArray® -Chlor to quantify key microorganisms (e.g., Dehalococcoides, Dehalobacter, etc.) and functional genes (e.g., vinyl chloride reductase, methane monooxygenase, etc.) to assess potential for reductive dechlorination and aerobic cometabolism of CVOCs.
In 2022, the first commercial application of MetaArray™ was performed at the site. MetaArray™ utilizes statistical analysis, such as principal component analysis and multivariate analysis to provide evidence that reductive dechlorination is active or even that it is slowing. This creates actionable data allowing users to save money by making important site management decisions earlier.
The results of the MetaArray™ analysis’ support vector machine (SVM) identified groundwater monitoring wells with a 80% confidence that were characterized as either Limited for Reductive Decholorination or had a High Reductive Reduction Dechlorination potential. The results of MetaArray™ will be used to further optimize the site’s post remediation monitoring program for monitored natural attenuation.
3. • A briefing regarding Financial Analysis of Sale/Purchase of Electricity
viz-a-viz Payment of Water Use Charges/Net Hydel Profit to AJ&K was
made to the Cabinet on August 24, 2017.
• Brief outline was follows:
i. Payment of Net Hydel Proceeds (i.e. Water Use Charges/ Net Hydel
Profit/Royalty) @ Rs.1.10/KWh to AJ&K on account of MHP & NJHPP
at par with provinces on the basis of equity and justice
ii. Determination of power purchase tariff as recommended by High Power
Committee constituted under clause 5.2(b) of Mangla Dam Raising
Agreement 2003
iii. Signing of Power Purchase Agreement for 30.4 MW Jagran-I hydel
power project
iv. On the basis of Arbitration Award 2006 claim of NHP/WUC against
Mangla HPP since 1990 would almost be Rs. 356.068 billion *
Background
* Source PDO
3
4. Decision of the Cabinet
• On the basis of analysis it was recommended that
• “The GoAJ&K may ask the GoP for the same treatment as is given
to Provinces/ DISCOS in term of :
• Sharing of benefits form Hydel Proceeds
• Sale & Purchase of Electricity”
4
5. Relevant Clauses of Mangla Dam Raising Agreement 2003
“Clause 5.2 (a)”
(a) “ At Present the Government of Pakistan has fixed the rate at Rs.4.20/KWh for
the AJ&K. The WAPDA shall bear Rs.0.71 on the basis of 17% losses. The
Government (AJ&K) shall pay Rs.2.44 and the Ministry (W&P) shall pick up
Rs.1.05 as subsidy. In case of budgetary constraints of the Government, the
Ministry shall pick up the additional liability of Rs.0.12. This rate shall be deemed
to have become effective from September 2002 and shall be frozen till September
2003”.
“Clause 5.2 (b)”
(b) “ The future power tariff (beyond September 2003) for Azad Jammu & Kashmir
shall be fixed by Govt. of Pakistan on recommendation of a Standing Sub-
Committee already notified by Ministry of KANA & SAFRON vide notification No.
F.3/10/92-F&B dated 6th June, 2003. Copy of which is appended with this
agreement”.
5
6. Relevant Clauses of Mangla Dam Raising Agreement 2003
“Clause 5.4”
“The responsibility of distribution of electricity may be withdrawn from
Government (AJK) and assigned to the AJ&K Council or any other relevant
organization. A study in this respect will be made by the Ministry KANA and
SAFRON/AJK Council and the Government”
“Clause 5.6”
The Government will get net hydel profit/water usage charges (royalty) from the
Mangla Dam with effect from the entry into force of this Agreement @ Rs.
0.15/KWh as per the policy laid down.
6
7. Deliberations
Accordingly, as per clause 5.2 (b) of Mangla Dam Raising Agreement 2003
power tariff for AJK was decided on the basis of following guidelines issued in
the meeting of Sub-Committee held on 11-09-2003:
i. The power tariff for AJ&K from 1st Oct 2003 shall be Rs. 2.59 per unit.
The basis of the decision was that WAPDA charges Rs. 2.58 per unit for
domestic consumers upto 100 units. The AJ&K Government agreed to
reduce losses from 37.5%* to 27%. Accordingly, the rate per unit should
be Rs. 2.60. The committee agreed to take the average of these two rates
at Rs. 2.59 per unit
ii. Since the AJ&K Government don't have provision in their current year’s
budget to pick up additional liability of Rs.0.27 per unit, the sub-
committee recommended that the finances required in this regard would
be provided by the Federal Government
iii. The reduction in losses will be reviewed on monthly basis and any
financial gains from reduced losses would be adjusted to reduce the
Government subsidy
* Current Losses 38.71% Condt…
7
8. Deliberations
• On December 08, 2015 the standing sub-committee recommended
revised tariff for AJ&K @ Rs. 5.79 per unit which is applicable rate of
1-100 units slab domestic category with the Analysis that majority of
electricity consumption in AJ&K falls in lower bracket of domestic
category in the schedule of electricity tariff.
(The same could not be actualized yet due to delay in final approval by the
respective fora of GoP as well as reservations of Finance Division GoP)
• Losses reported against purchase and sale of electricity for the last 18
years are almost 39%
• Outstanding liabilities against electricity charges claimed by WAPDA
are almost Rs. 80.739 billion
8
9. Sale of Electricity From Jagran-1 HPP
• Power Purchase Agreement (PPA) of Jagran-1 HPP not being
signed on the pretext of GoAJ&K being defaulter and beneficiary
of low tariff
• Annual loss of approximately Rs. 700 million due to non signing
of PPA
• Due to delay in signing of PPA of 30.4 MW Jagran-I HPP
outstanding amount on account of energy charges since Aug. 2010
is Rs. 3.778 billion
Deliberations
9
10. Basis of Deliberations/Discussion
• In line with the decision of CCI, KP and Punjab provinces are being
paid NHP @ Rs.1.10/KWh
• According to clause 5.6 of Mangla Dam Raising Agreement 2003, Net
Hydel Profit/Water Usage Charges (Royalty) (NHP/WUC) is being paid
to GoAJ&K @ Rs. 0.15/KWh
• “Clause 5.6 of Mangla Dam Raising Agreement”
The Government will get net hydel profit/water usage charges
(royalty) from the Mangla Dam with effect from the entry into force of this
Agreement @ Rs. 0.15/KWh as per the policy laid down.
• The stance of AJ&K is for treatment of AJ&K at par with provinces in
accordance with the administrative arrangements issued by the Cabinet
Division on June 24, 1970 and May 11, 1971.
10
11. Current Power Supply System in AJ&K
• AJK Electricity Department (AJKED) purchases major portion of
energy from DISCOs (97%) and a small quantity from AJK Power
Development Organization(AJKPDO) (3%).
• DISCOs supply power at 132 /33/11 kV grid stations and AJKED has
built its own 11/ 0.4 kV Power Distribution Network to deliver energy
to end consumer.
• AJKED applies the same consumer tariff in AJ&K as being used by
IESCO (DISCOs).
• AJKED pays to DISCOs on Special Power Supply Tariff fixed
according to Mangla Dam Raising Agreement signed in 2003 (revision
proposed in 2015).
11
12. Budgetary Status for Annual Receipts from WUC
HPP Project
Agreed
@ 0.15/KWh /
@ 0.425/KWh
Proposed
@1.10/KWh
Net
Enhancement
Mangla HPP
(5992 M. Units)
898.800 6591.200 5692.400
NJHPP
(5150 M. Units)
2188.750 5665.000 3476.250
Total 3087.550 12256.200 9168.650
Rs. in million
12
13. Analysis of Purchase and Sale of Electricity
Scenario
at
Tariff
Rate/
KWh
Purchase
Price
(1590.121
MKWH)
Admin
Exp.
Total Exp.
Income from
Sale of Ele.
(998.684
MKWH)
Net Income
Loss
2.59 4118.413 2445.187 6563.600 8628.771 2065.171
(4510.358)
5.79 9206.801 2445.187 11651.988 8628.771
-3023.22
(-578.033)
8.25 13118.498 2445.187 15563.685 8628.771
-6934.91
(-4489.723)
Rs. in million
13
14. Financial Impact Analysis
Scenario at
Tariff Rate/
KWh
Net
Income/
Loss
Agreed Net Income from
WUC @0.15/KWh/
@0.425/KWh
(MHP and NJHPP)
Projected Net
Income from
WUC
@1.10/KWh
Net Benefit
2.59 2065.171 3087.550 -- 5152.721*
5.79 -3023.22 3087.550 -- 57.330
5.79 -3023.22 12256.200 9232.980
8.25 -6934.91 -- 12256.200 5321.290
Rs. in million
*Including outstanding claims from 2003 to 2017 payable to DISCOs for Rs.80.739
billion on account of unsettled subsidy pending by FD-GoP and WAPDA
14
15. • Accordingly, series of meetings of the committee constituted by the Prime
Minister Office Islamabad comprising of Secretary, Finance GoP as
convener Secretary Ministry of Water & Power and Chief Secretary
GoAJ&K as its members were convened and discussions were made to
arrive upon consensus for resolution of the matter.
• In the meeting held on October 28, 2017, the committee assigned the
responsibilities to a sub-committee for detailed deliberation. The meeting
of technical Sub-committee was held on November 03, 2017 and
following proposal was given by FD-GoP.
Current Status
15
16. WUC on Neelum Jhelum HPP
i. The Govt of AJK is of the view that Power Policy 2015 envisages WUC
@ 0.425/kwh for private sector projects only and does not cover public
sector projects. Therefore, AJK has requested that WUC for NJHPP
being a public sector project may also be considered at par with NHP
rate being paid on account of Terbela HPP and Ghazi Barotha HPP i.e
Rs. 1.10/kwh.
ii. Considering views of WAPDA, NEPRA and Law & Justice Division, the
WUC rate for HPP is proposed to be considered at par with other HPP
projects, subject to approval of the competent forum.
Proposal of FD-GoP
16
17. Proposal of FD-GoP
i. WUC @1.10/KWh for MHP may be determined for AJ&K at par with
provinces subject to the approval of CCI.
ii. Clause 5.4 of Mangla Raising Agreement, 2003 provides that
“the responsibility of distribution of electricity may be withdrawn from
Government (AJK) and assigned to the AJ&K Council or any other
relevant organization.”
Thus Electricity Department of AJK may be declared as DISCO and
NEPRA may be allowed to determine tariff for Electricity supply to
AJ&K, consistent with other DISCOs.
WUC on MHP and Determination of Tariff Rate
17
18. iii. Electricity supply to AJ&K may be charged at respective DISCOs
rates prospectively as determined by NEPRA and GoP notified rates,
w.e.f the date of approval of the competent forum instead of
Rs.2.59/kwh on provisional basis till Electricity Department of AJK
has been given a status of DISCO like EXWAPDA distribution
companies as operational in four provinces of Pakistan. This will
eliminate DISCOs Receivables towards AJK, which is being picked-
up by the GoP.
iv. Subject to approval of above proposal, the GoP will continue to
provide TDS support to Electricity Department of AJK as is being
provided to XWAPDA DISCOs.
Proposal of FD-GoP
18
21. POWER BILLING & COLLECTION AS PER GoP
NOTIFIED TARIFF AND SUPPORT TO AJ&K
(2003 TO 2017)
(Rs. in million)
Name of
DISCOs
Opening
Balance
Units
Billed
(M/kwh)
Average
Notified
Rate
/kwh
Billing
AJK
Rate
/kwh
Collection
from AJK
Subsidy by
(GoP &
WAPDA)
GEPCO 59 2,431 6.45 15,682 2.59 6,297 9,444
IESCO 433 15,713 6.05 95,036 2.59 40,698 54,771
PESCO 103 3,869 6.83 26,440 2.59 10,022 16,521
Total 22,014 137,158 57,017 80,736
Back
Source: Finance Division, GoP
21
22. TDS VIDE NEPRA DETERMINED AND GOP
NOTIFIED TARIFF PAID BY MoF
PERIOD Rs. in Million
Feb, 07 to June,10 11,638.751
Jul, 10 to June, 11 * 4,403.644
Jul,11 to June,15 18,332.36
Total 34,374.75
Adjustment Jul'15
to June, 17
(3,827.605)
Net TDS Paid by GoP 30,547.15
* Paid by M/o W&P as the budget was allocated to them
Back
22
23. Composition of sub committee
Dated 06-june-2003
1) Secretary, Water and Power Chairman
2) Chairman, WAPDA Member
3) Chief Secretary, AJ&K Government Member
4) Joint Secretary (PF) Finance Division Member
5) Joint Secretary, KANA & SAFRON Member
TORs:
• Consumption pattern of AJ&K
• Acceptable line losses in AJ&K
• Mangla Dam Agreement of 1967
• Any other relevant point.
Back
23