SlideShare a Scribd company logo
1 of 14
1
WIND POWER DEVELOPMENT: INDIA STATUS REPORT
G M Pillai
Founder Director General
World Institute of Sustainable Energy (WISE), PUNE,
INDIA
Email- gmpillai@wisein.org
Website:www.wisein.org
Presentation for
‘Quantum Leap in Wind Power in Asia’
Asian Development Bank, Manila,
20-21 June 2011
2
INDIA MARKET OVERVIEW
• CWET/MNRE estimated potential of
49,130 MW.
• Wind power development in 8 states
only.
• Cumulative installed capacity: 14,000+
MW (March 2011).
• Annual installation in FY 2010/11:
2351 MW.
• National Action Plan on Climate
Change (NAPCC): target of 15%
renewable energy by 2020.
• Dynamic RPS targets set in 25 states
by state regulators.
• More than 50,000 MW additional wind
power requirement to meet the 2020
target.
• New frameworks: Generation-based
incentive, Tradable RECs.
Note: Installed capacity and projects in the pipeline, as on March 2011, tariff/RPS as on 15 June 2011
3
INDUSTRY DEVELOPMENTS
• Indian Wind Industry Developments: Major three phases
- Prior to 1994/95: Demonstration phase driven by 100% AD and Sales Tax benefits.
- 1995 to 2003: Energy purchase price by government, tax regime changed, boom-bust cycle.
- 2003 onwards: After Electricity Act, 2003, feed-in tariff and RPS/RPO movement, 84%
cumulative capacity added.
First feed-in tariff
order in
Maharashtra in
2003/04
Private Power
Policy 1991
MNRE tariff
guidelines
4
INSTITUTIONAL MECHANISM
Appeal
Institutional
Framework
Centre
Traders
Appellate Tribunal
Appellate Tribunal
5
WIND RESOURCE POTENTIAL
 Wind monitoring is being carried out by the Centre for Wind
Energy Technology (C-WET), a federal government
institution.
 C-WET published the Indian Wind Atlas, showing areas with
average WPD > 200 w/sq.m. at 50 m above ground level.
 Wind monitoring done at 618 sites, out of which 233 sites
declared as wind potential sites having WPD >200 w/sq.m.
 In addition, wind turbine manufacturers and developers are
also doing wind monitoring.
 Different agencies have projected different estimates for wind
potential in India. C-WET 49.13 GW, World Institute of
Sustainable Energy (WISE) – 100 GW, Global Wind Energy
Council (GWEC) > 160 GW. Hence, detailed reassessment is
required in the immediate future.
Wind Resource Map of
India
6
WTG MANUFACTURING
• The annual wind turbine manufacturing capacity in India is about 9000 MW.
• Likely to increase to 17,000+ MW per annum by 2012 to make pace with the annual installations which
are slated to go up from present 1,500 MW–1,600 MW to 5,000 MW by 2014-15 and catering to the
export market in Asian region and other developed markets.
• More than 9 new wind turbine manufacturers are slated to enter the market in addition to the 17 existing
manufacturers, taking the total number of turbine manufacturers to 26 by 2012/13.
• Altogether, about 35 wind turbine models may be on offer from the existing and new wind turbine
manufacturers by 2012.
• India has already exported turbines of value $750 million to countries like USA, Brazil, Australia,
Bulgaria, China, and Japan, besides exporting almost $220 million worth of wind power related
components during April 2009 to December 2009.
• Export projection for 2010/11: US $1400 million.
• Huge export / import opportunity to /by Asian countries.
7
POLICIES, REGULATIONS AND INCENTIVES
POLICIES & INCENTIVES
• Electricity Act 2003: Feed-in tariffs (FITs), mandatory quotas, delicensing and open access.
• National Action Plan on Climate Change (NAPCC): national target of 15% renewable power by 2020.
• Allowance of 80% Accelerated Depreciation (AD) for wind power projects.
• 10 year tax holiday.
• Generation Based incentive of INR 0.5 /kWh for wind power projects not availing accelerated
depreciation.
• Creation of NCEF (National Clean Energy Fund) to support RE.
• Central financial fund allocation of $1100 million (INR 5000 crore) to states doing well in grid
connected RE.
• Concessions on import duty on certain wind turbine components.
• Allowance of 100% FDI in RE generation projects.
• Special incentives for setting up projects/manufacturing in special economic zones (SEZs).
8
POWER SALE OPTIONS
Indian Wind Power Investor
Type of Investor Corporate (Tax appetite)
Independent Power Producer/
Foreign Investor
Power Sale Options
Captive Captive
Third party Third party
PPA at FIT PPA at FIT
PPA at APPC
and sale of REC
PPA at APPC
and sale of REC
POLICIES, REGULATIONS AND INCENTIVES
• CERC (Central Electricity Regulatory Commission) – wind power feed-in tariff ranging from $0.078/kWh
to $0.117/kWh on wind power density based zoning.
• Various SERC (State Electricity Regulatory Commissions) – specific wind power feed-in tariffs that
range from $0.074/kWh to $0.117/kWh.
• 25 SERCs have specified renewable purchase quotas ranging from 1% to 14%.
• Tradable renewable energy certificates (RECs) have been declared to facilitate obligated utilities to fulfill
quota obligation. Floor price of $0.033 (INR 1.5/kWh), and Cap price of $0.086 (INR 3.9/kWh).
REGULATIONS:
9
NEW OPPORTUNITIES: REPOWERING
• Potential for repowering – 1400 MW
The best windy sites have the oldest machines (low capacity and efficiency)…about 46%
machines rated below 500 kW.
Scope for improving overall system efficiency/capacity and investment returns and most importantly,– land
utilisation.
• Barriers
Regulatory/policy barriers – No guidelines on incentives, PPA extension/modification, etc.
Legal and administrative challenges – Turbine ownership, land lease extension, etc.
Technical issues – Limited possibility to retrofit, system redesigning, capacity upgradation, disposal.
• Repowering in India - Status
All the major WTG manufacturers are interested. One project on repowering has already been commissioned
by Gamesa India in Tirupur district of Tamil Nadu.
Parameter Before
repowering
After
repowering
Machines 8 nos of 300 kW
and 2 nos of 500
kW
15 nos of
850 kW (DFIG)
PLF range (%) 12%-17% 25%-27%*
Generation (MUs) 12.5 30*
* Expected figures as per data by Gamesa India
10
• India has a coastline of 7516 kms.
• Despite vast coastline, offshore potential is limited,
upwards of 3000 MW. Actual assessment not carried
out.
• Few detailed studies done, MNRE has constituted a
committee for exploring pilot project development
and policy development.
• No policy targets, no regulation.
• Several potential zones for offshore wind have been
mapped off the coast of Gujarat, Maharashtra, and
south of Tamil Nadu.
• Two offshore pilot projects planned by MNRE; one
each in Tamil Nadu and Gujarat.
NEW OPPORTUNITIES: OFFSHORE
11
• The Indian market was traditionally
dominated by large corporates with
tax appetites, who accounted for
>70% of the market.
• The advent of Independent Power
Producers (IPPs) is an indication of
the maturity of the wind power sector
in India and growing awareness
about RE.
• Considering the existing business
plans, IPPs are expected to
command 40%-60% market share in
the next 3-4 years.
NEW OPPORTUNITIES: IPP DEVELOPMENT
(with AD) (with AD)
(with AD) (with AD)
12
Year 09/10 10/11 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20
Required
* (BU)
848 906 969 1035 1105 1181 1262 1348 1440 1538 1643
RE Share
(%) as
per
NAPCC
5 6 7 8 9 10 11 12 13 14 15
RE
Quantum
(BU)
42.42 54.38 67.81 82.79 99.49 118.10 138.78 161.74 187.19 215.35 246.49
Additional RE capacity for meeting NAPCC Target
(Requirement in Billion Units)
* All India energy requirement as per CEA
Estimated Technology-wise Cumulative Capacity Addition Required by 2020
RE Technology Assumed Plant Load
Factor
(%)
Capacity required
(MW)
Units Generation
(BU)
Wind 25 65,000 142.35
Solar 21 35,000 64.39
Biomass &
Cogeneration
64 5,100 28.59
Small Hydro
Power
38 3,600 11.98
TOTAL 1,08,700 247.31
15% RE BY 2020: ROLE OF WIND POWER
Source: WISE
15% RE by 2020 Needs 50 GW Additional Wind Power in India
13
2005/
06
2006/
07
2007/
08
2008/
09
2009/
10
2010/
11*
2011/
12
2012/
13
2013/
14
2014/
15
2015/
16
2016/
17
2017/
18
2018/
19
2019/
20
Annual capacity, MW 1716 1742 1663 1485 1565 2500 2900 3364 3902 4527 5251 6091 7066 8196 9507
Cumulative capacity, MW 5352 7094 8757 10242 11807 14307 17207 20571 24473 29000 34251 40342 47407 55603 65111
Annual market growth rate, % 1.5 -4.5 -10.7 5.4 59.7 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0
-20.0
-10.0
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
0
10000
20000
30000
40000
50000
60000
70000
Annual
Market
Growth
rate,
%
Capacity
addition
in
MW
Indian Wind Power Capacity Addition 2005-2020
Actual Projection
15% RE BY 2020: ROLE OF WIND POWER (contd…)
Note: FY 2010/11: WISE estimate, Actual annual capacity addition was 2351 MW, growth rate > 50% on previous year.
Just 16% year-on-year growth rate in annual wind power capacity addition from now till
2020 can achieve the target! Growth rate in FY 2010/11 was ~ 50%
14
MARKET CHALLENGES
Grid Infrastructure
- Inadequate evacuation capacity.
- Lack of transmission planning.
- Cost burden of grid augmentation on
developers.
Project Financing
- Bias against stand alone projects as they are
deemed risky.
- Financing is at a premium as wind is still not
mainstream.
- Lower loan tenures and higher interest rates.
Regulatory compliance
- Delay in payments
- Risk of non compliance of RPO by state
owned utilities
- Delay in signing of PPAs
Wind power Forecasting
As per IEGC (Indian Electricity Grid
Code), 2010, wind power producers are
expected to forecast generation from
April 2012. Deviation beyond +/- 30% of
the forecast will be subjected to UI
(unscheduled interchange) charges.
These additional costs may impact wind
power economics substantially.
Shortage of Trained/Skilled Human
Resources.
Protracted approval processes,
administrative hurdles and land
issues.
THANK YOU !

More Related Content

Similar to QLW C9 India Mr G M Pillai asdfggjjjkjjj

Indian power market demand forecast l www.masterfoxconsultinggroup.com
Indian power market demand forecast l www.masterfoxconsultinggroup.comIndian power market demand forecast l www.masterfoxconsultinggroup.com
Indian power market demand forecast l www.masterfoxconsultinggroup.comMasterfox Consulting Group(MCG)
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Mahesh Chandra Manav
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistanFaizan Shabbir
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Faizan Shabbir
 
Infrastructure development in india
Infrastructure development in indiaInfrastructure development in india
Infrastructure development in indiaMukesh Khinchi
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sectorRahul Gupta
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy ScenarioAvdesh Mandal
 
Renewables & disruptive technologies
Renewables & disruptive technologiesRenewables & disruptive technologies
Renewables & disruptive technologiesShivam Pandey
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptxRAMAPANDA6
 
Modern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaModern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaAdityaDesai77
 
Renewable energy - India- future
Renewable energy - India- futureRenewable energy - India- future
Renewable energy - India- futureH Janardan Prabhu
 
Make in india and future of renewable energy
Make in india and future of renewable energyMake in india and future of renewable energy
Make in india and future of renewable energyManoj Bhambu
 
StocksInsights Hidden Treasure November 2015 pick - Techno Electric
StocksInsights Hidden Treasure November 2015 pick - Techno ElectricStocksInsights Hidden Treasure November 2015 pick - Techno Electric
StocksInsights Hidden Treasure November 2015 pick - Techno ElectricStocksInsights
 

Similar to QLW C9 India Mr G M Pillai asdfggjjjkjjj (20)

Indian power market demand forecast l www.masterfoxconsultinggroup.com
Indian power market demand forecast l www.masterfoxconsultinggroup.comIndian power market demand forecast l www.masterfoxconsultinggroup.com
Indian power market demand forecast l www.masterfoxconsultinggroup.com
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)
 
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum SectorVibrant Gujarat Summit Profile for Energy Spectrum Sector
Vibrant Gujarat Summit Profile for Energy Spectrum Sector
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistan
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
 
Infrastructure development in india
Infrastructure development in indiaInfrastructure development in india
Infrastructure development in india
 
Economy and Energy Security for Pakistan - What lies ahead
Economy and Energy Security for Pakistan -What lies aheadEconomy and Energy Security for Pakistan -What lies ahead
Economy and Energy Security for Pakistan - What lies ahead
 
India : Power Sector Report_August 2013
India : Power Sector Report_August 2013India : Power Sector Report_August 2013
India : Power Sector Report_August 2013
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
Nepal Energy Scenario
Nepal Energy ScenarioNepal Energy Scenario
Nepal Energy Scenario
 
Renewables & disruptive technologies
Renewables & disruptive technologiesRenewables & disruptive technologies
Renewables & disruptive technologies
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptx
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Union budget 2014 15
Union budget 2014 15Union budget 2014 15
Union budget 2014 15
 
Modern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis IndiaModern Energy Transport - Country Analysis India
Modern Energy Transport - Country Analysis India
 
Renewable energy - India- future
Renewable energy - India- futureRenewable energy - India- future
Renewable energy - India- future
 
Make in india and future of renewable energy
Make in india and future of renewable energyMake in india and future of renewable energy
Make in india and future of renewable energy
 
StocksInsights Hidden Treasure November 2015 pick - Techno Electric
StocksInsights Hidden Treasure November 2015 pick - Techno ElectricStocksInsights Hidden Treasure November 2015 pick - Techno Electric
StocksInsights Hidden Treasure November 2015 pick - Techno Electric
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

QLW C9 India Mr G M Pillai asdfggjjjkjjj

  • 1. 1 WIND POWER DEVELOPMENT: INDIA STATUS REPORT G M Pillai Founder Director General World Institute of Sustainable Energy (WISE), PUNE, INDIA Email- gmpillai@wisein.org Website:www.wisein.org Presentation for ‘Quantum Leap in Wind Power in Asia’ Asian Development Bank, Manila, 20-21 June 2011
  • 2. 2 INDIA MARKET OVERVIEW • CWET/MNRE estimated potential of 49,130 MW. • Wind power development in 8 states only. • Cumulative installed capacity: 14,000+ MW (March 2011). • Annual installation in FY 2010/11: 2351 MW. • National Action Plan on Climate Change (NAPCC): target of 15% renewable energy by 2020. • Dynamic RPS targets set in 25 states by state regulators. • More than 50,000 MW additional wind power requirement to meet the 2020 target. • New frameworks: Generation-based incentive, Tradable RECs. Note: Installed capacity and projects in the pipeline, as on March 2011, tariff/RPS as on 15 June 2011
  • 3. 3 INDUSTRY DEVELOPMENTS • Indian Wind Industry Developments: Major three phases - Prior to 1994/95: Demonstration phase driven by 100% AD and Sales Tax benefits. - 1995 to 2003: Energy purchase price by government, tax regime changed, boom-bust cycle. - 2003 onwards: After Electricity Act, 2003, feed-in tariff and RPS/RPO movement, 84% cumulative capacity added. First feed-in tariff order in Maharashtra in 2003/04 Private Power Policy 1991 MNRE tariff guidelines
  • 5. 5 WIND RESOURCE POTENTIAL  Wind monitoring is being carried out by the Centre for Wind Energy Technology (C-WET), a federal government institution.  C-WET published the Indian Wind Atlas, showing areas with average WPD > 200 w/sq.m. at 50 m above ground level.  Wind monitoring done at 618 sites, out of which 233 sites declared as wind potential sites having WPD >200 w/sq.m.  In addition, wind turbine manufacturers and developers are also doing wind monitoring.  Different agencies have projected different estimates for wind potential in India. C-WET 49.13 GW, World Institute of Sustainable Energy (WISE) – 100 GW, Global Wind Energy Council (GWEC) > 160 GW. Hence, detailed reassessment is required in the immediate future. Wind Resource Map of India
  • 6. 6 WTG MANUFACTURING • The annual wind turbine manufacturing capacity in India is about 9000 MW. • Likely to increase to 17,000+ MW per annum by 2012 to make pace with the annual installations which are slated to go up from present 1,500 MW–1,600 MW to 5,000 MW by 2014-15 and catering to the export market in Asian region and other developed markets. • More than 9 new wind turbine manufacturers are slated to enter the market in addition to the 17 existing manufacturers, taking the total number of turbine manufacturers to 26 by 2012/13. • Altogether, about 35 wind turbine models may be on offer from the existing and new wind turbine manufacturers by 2012. • India has already exported turbines of value $750 million to countries like USA, Brazil, Australia, Bulgaria, China, and Japan, besides exporting almost $220 million worth of wind power related components during April 2009 to December 2009. • Export projection for 2010/11: US $1400 million. • Huge export / import opportunity to /by Asian countries.
  • 7. 7 POLICIES, REGULATIONS AND INCENTIVES POLICIES & INCENTIVES • Electricity Act 2003: Feed-in tariffs (FITs), mandatory quotas, delicensing and open access. • National Action Plan on Climate Change (NAPCC): national target of 15% renewable power by 2020. • Allowance of 80% Accelerated Depreciation (AD) for wind power projects. • 10 year tax holiday. • Generation Based incentive of INR 0.5 /kWh for wind power projects not availing accelerated depreciation. • Creation of NCEF (National Clean Energy Fund) to support RE. • Central financial fund allocation of $1100 million (INR 5000 crore) to states doing well in grid connected RE. • Concessions on import duty on certain wind turbine components. • Allowance of 100% FDI in RE generation projects. • Special incentives for setting up projects/manufacturing in special economic zones (SEZs).
  • 8. 8 POWER SALE OPTIONS Indian Wind Power Investor Type of Investor Corporate (Tax appetite) Independent Power Producer/ Foreign Investor Power Sale Options Captive Captive Third party Third party PPA at FIT PPA at FIT PPA at APPC and sale of REC PPA at APPC and sale of REC POLICIES, REGULATIONS AND INCENTIVES • CERC (Central Electricity Regulatory Commission) – wind power feed-in tariff ranging from $0.078/kWh to $0.117/kWh on wind power density based zoning. • Various SERC (State Electricity Regulatory Commissions) – specific wind power feed-in tariffs that range from $0.074/kWh to $0.117/kWh. • 25 SERCs have specified renewable purchase quotas ranging from 1% to 14%. • Tradable renewable energy certificates (RECs) have been declared to facilitate obligated utilities to fulfill quota obligation. Floor price of $0.033 (INR 1.5/kWh), and Cap price of $0.086 (INR 3.9/kWh). REGULATIONS:
  • 9. 9 NEW OPPORTUNITIES: REPOWERING • Potential for repowering – 1400 MW The best windy sites have the oldest machines (low capacity and efficiency)…about 46% machines rated below 500 kW. Scope for improving overall system efficiency/capacity and investment returns and most importantly,– land utilisation. • Barriers Regulatory/policy barriers – No guidelines on incentives, PPA extension/modification, etc. Legal and administrative challenges – Turbine ownership, land lease extension, etc. Technical issues – Limited possibility to retrofit, system redesigning, capacity upgradation, disposal. • Repowering in India - Status All the major WTG manufacturers are interested. One project on repowering has already been commissioned by Gamesa India in Tirupur district of Tamil Nadu. Parameter Before repowering After repowering Machines 8 nos of 300 kW and 2 nos of 500 kW 15 nos of 850 kW (DFIG) PLF range (%) 12%-17% 25%-27%* Generation (MUs) 12.5 30* * Expected figures as per data by Gamesa India
  • 10. 10 • India has a coastline of 7516 kms. • Despite vast coastline, offshore potential is limited, upwards of 3000 MW. Actual assessment not carried out. • Few detailed studies done, MNRE has constituted a committee for exploring pilot project development and policy development. • No policy targets, no regulation. • Several potential zones for offshore wind have been mapped off the coast of Gujarat, Maharashtra, and south of Tamil Nadu. • Two offshore pilot projects planned by MNRE; one each in Tamil Nadu and Gujarat. NEW OPPORTUNITIES: OFFSHORE
  • 11. 11 • The Indian market was traditionally dominated by large corporates with tax appetites, who accounted for >70% of the market. • The advent of Independent Power Producers (IPPs) is an indication of the maturity of the wind power sector in India and growing awareness about RE. • Considering the existing business plans, IPPs are expected to command 40%-60% market share in the next 3-4 years. NEW OPPORTUNITIES: IPP DEVELOPMENT (with AD) (with AD) (with AD) (with AD)
  • 12. 12 Year 09/10 10/11 11/12 12/13 13/14 14/15 15/16 16/17 17/18 18/19 19/20 Required * (BU) 848 906 969 1035 1105 1181 1262 1348 1440 1538 1643 RE Share (%) as per NAPCC 5 6 7 8 9 10 11 12 13 14 15 RE Quantum (BU) 42.42 54.38 67.81 82.79 99.49 118.10 138.78 161.74 187.19 215.35 246.49 Additional RE capacity for meeting NAPCC Target (Requirement in Billion Units) * All India energy requirement as per CEA Estimated Technology-wise Cumulative Capacity Addition Required by 2020 RE Technology Assumed Plant Load Factor (%) Capacity required (MW) Units Generation (BU) Wind 25 65,000 142.35 Solar 21 35,000 64.39 Biomass & Cogeneration 64 5,100 28.59 Small Hydro Power 38 3,600 11.98 TOTAL 1,08,700 247.31 15% RE BY 2020: ROLE OF WIND POWER Source: WISE 15% RE by 2020 Needs 50 GW Additional Wind Power in India
  • 13. 13 2005/ 06 2006/ 07 2007/ 08 2008/ 09 2009/ 10 2010/ 11* 2011/ 12 2012/ 13 2013/ 14 2014/ 15 2015/ 16 2016/ 17 2017/ 18 2018/ 19 2019/ 20 Annual capacity, MW 1716 1742 1663 1485 1565 2500 2900 3364 3902 4527 5251 6091 7066 8196 9507 Cumulative capacity, MW 5352 7094 8757 10242 11807 14307 17207 20571 24473 29000 34251 40342 47407 55603 65111 Annual market growth rate, % 1.5 -4.5 -10.7 5.4 59.7 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 16.0 -20.0 -10.0 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 0 10000 20000 30000 40000 50000 60000 70000 Annual Market Growth rate, % Capacity addition in MW Indian Wind Power Capacity Addition 2005-2020 Actual Projection 15% RE BY 2020: ROLE OF WIND POWER (contd…) Note: FY 2010/11: WISE estimate, Actual annual capacity addition was 2351 MW, growth rate > 50% on previous year. Just 16% year-on-year growth rate in annual wind power capacity addition from now till 2020 can achieve the target! Growth rate in FY 2010/11 was ~ 50%
  • 14. 14 MARKET CHALLENGES Grid Infrastructure - Inadequate evacuation capacity. - Lack of transmission planning. - Cost burden of grid augmentation on developers. Project Financing - Bias against stand alone projects as they are deemed risky. - Financing is at a premium as wind is still not mainstream. - Lower loan tenures and higher interest rates. Regulatory compliance - Delay in payments - Risk of non compliance of RPO by state owned utilities - Delay in signing of PPAs Wind power Forecasting As per IEGC (Indian Electricity Grid Code), 2010, wind power producers are expected to forecast generation from April 2012. Deviation beyond +/- 30% of the forecast will be subjected to UI (unscheduled interchange) charges. These additional costs may impact wind power economics substantially. Shortage of Trained/Skilled Human Resources. Protracted approval processes, administrative hurdles and land issues. THANK YOU !