SlideShare a Scribd company logo
1 of 23
Economy and Energy Security for Pakistan -
What lies ahead
COMSATS Institute of Information Technology
12 October 2013
• The Economic Survey of Pakistan recognizes that during 2012
around 2 percent of gross domestic product (GDP) was lost
due to the power sector outages.
• The petroleum crude and products contributed to a third of
total imports of Pakistan during 2012
• The transmission and distribution (T&D) losses were valued at
PKR 140 billion in 2012
• Issues being currently faced can be categorised into policy,
governance, technical and cost issues
2
Background
• Short-term situation analysis
• Limiting analysis to power sector
• Assumptions:
– It will be difficult to attract investment
– It will be difficult to bring legislative changes
– Will be difficult to change governance structures at generation and
distribution companies
• What lies ahead?
3
Sequence of Discussion
Circular Debt in Power Sector
111
145 161
236
366
538
872
0
100
200
300
400
500
600
700
800
900
1000
2006 2007 2008 2009 2010 2011 2012
PKRBillions
Source: Planning Commission 2013
Integrated Energy
Policy
Consolidate
fragmented energy
governance
Build capacity of
regulators
Deregulate energy
sector further
Reforms for
attracting
investment in
energy sector
Make generation
efficient
Reduce
transmission losses
Hydro, Coal and
other sources
Steps that were promised
These may be symptoms but are not causes of crisis
Unwillingess to
pay the price of
energy
Political
stubbornness
to maintain
subsidies
Administrative
and line losses
7
3 key causes
• Willingness and ability to pay for power
• Recoveries of some very large power distribution companies
have deteriorated over time
– In Hyderabad, for example, only 60% of the power supplied in 2012
was paid for – in a city of over 6.5 million people
• DISCOs are unable to adopt the normal commercial practices
in other countries of disconnecting customers for non-
payment because of unclear legislation and political pressure.
8
1. Unwillingness to pay for power
9
Source: SDPI Survey Unit 2013
No , 82%
Don't
Know, 6%
Yes,
12%
Will households pay if power cuts are
eliminated and tariff is increased by 10%
• The fundamental rationale for subsidising electricity tariffs is
to augment the paying capacity of the poorest of poor
• However once subsidies are provided across the board,
people start to demand them as their right and politicians feel
compelled to maintain this distortive fiscal burden to win
popularity.
• Do poor really get power subsidies in Pakistan
– Domestic lifeline consumers (1-100 units) only get 0.3% subsidy
10
2. Political stubbornness to maintain subsidies
Subsidybythegovernmentonpowerconsumption(Rs/kW)
LESCO GEPCO FESCO MEPCO HESCO SEPCO QESCO PESCO
1.Residential,<700units 0.4 1.4 1.4 2.9 3.9 3.9 1.4 4.4
2.Industrial,(66.132KV&above)-
TOU(Peak) 2.1 2.1 2.1 3.1 6.6 6.6 4.0 7.1
3.Agricultural,5KW&above-TOU
(Peak) 1.5 1.5 1.5 2.5 6.0 6.0 3.5 6.5
Source: Economic Survey of Pakistan, 2013
Electricity Shortfall & Subsidies
12
0
50
100
150
200
250
300
350
400
450
500
0
1000
2000
3000
4000
5000
6000
7000
2005 2006 2007 2008 2009 2010 2011 2012 2013
Subsidy(PKRBillion)
Deficit(MW)
Electricity Shortfall (MW) Subsidy to Power Sector
Source: NEPRA and Planning Commission 2013
• In August 2013, the Secretary of Water and Power
Ministry informed the Senate Standing Committee that
– Pakistan loses annually PKR 150 billion (USD 1.7 billion) in
line losses and power theft.
– Until August 23770 cases of theft were registered and
under trial
– But only 3 cases were punished. Moreover, the fine
imposed was under PKR 5000 in each case.
• Lacunae in the accountability mechanism. This requires
amendments in Pakistan Penal Code so that there is
certainty of effective punishment in cases of power
theft
13
3. Administrative & Line Losses (Theft)
14
Power T & D Losses (% of output)
0
5
10
15
20
25
30
35
40
1971
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
Percentage
Pakistan Bangladesh
15
35%
59%
6%
Yes No Don't Know
Do you know of power theft in your area?
Source: SDPI Survey Unit 2013
Tariffs and
Subsidies
Curbing
Theft
Creating
Competition
in power
sector
16
Hopes from National Power Policy
All subsidies (including hidden and cross subsidies) - except
a 100 unit lifeline block - should be phased out over the
next 24 months.
17
1. Tariffs and Subsidies
• Unaccounted-for-gas controls should be enforced and the saved
gas diverted to the power sector. The power ministry notes that
just a 10 percent diversion can produce an extra 2000MW.
• Performance contracts for grid stations under National
Transmission and Dispatch Company.
• Performance contracts should also be introduced for DISCOs.
Such a contract should have specific clauses on reduction in
distribution losses and full collection of receivables from
consumers.
• Accountability at XEN-level
• Role of provinces
• Social accountability tools
18
2. Curbing Loses
• Creating competition on distribution side is important but a
medium to longer term option
• What about creating competition in generation sector?
• The allocation of fuel to generation companies (GENCOs) should be
linked with their efficiency levels
• If the Independent Power Producers (IPPs) are better performing in
efficiency terms then fuel allocation may be in favour of IPPs
• According to Ministry of Water and Power’s own estimates a
4000mtoe shift from GENCOs to IPPs will save PKR 77 billion annually
• The current generation comparison reveals that PKR 13 billion per
month for GENCOs allows production of 650 MW and only PKR 10
million per month in case of IPPs produces 1150 MW.
19
3. Creating competition in power sector
20
Can I get cheaper power?
21
Who will do it?
• Who runs regulatory institutions?
• How is transmission optimized at power ministry?
• What about planners at Planning Commission?
• Reform of power generation and distribution companies
• Energy sector and civil service reforms
• Define limits of government in power sector
22
Who will do it?
www.sdpi.org, www.sdpi.tv 23
Thank You

More Related Content

What's hot

Energy crisis in Pakistan and its management
Energy crisis in Pakistan and its managementEnergy crisis in Pakistan and its management
Energy crisis in Pakistan and its managementpakistanvisionaryforum
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power PolicyPRIYANK JAIN
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in Indiamohkab1
 
power sector
power sectorpower sector
power sectoryzag66
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisArjun Yadav
 
Circular Debt in Pakistan
Circular Debt in PakistanCircular Debt in Pakistan
Circular Debt in PakistanAli Asad Sahu
 
Kigali | Sep-15 | Uganda country view
Kigali | Sep-15 | Uganda country viewKigali | Sep-15 | Uganda country view
Kigali | Sep-15 | Uganda country viewSmart Villages
 
Class 3 the power sector in india
Class 3   the power sector in indiaClass 3   the power sector in india
Class 3 the power sector in indiarajranjang
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reformsPSPCL
 
Why Circular Debt Burgeons in the Power Sector? Case of Pakistan
Why Circular Debt Burgeons in the Power Sector? Case of PakistanWhy Circular Debt Burgeons in the Power Sector? Case of Pakistan
Why Circular Debt Burgeons in the Power Sector? Case of Pakistanmaktahirkheli
 
Day-3, Mr. Rajiv Yadav
Day-3, Mr. Rajiv YadavDay-3, Mr. Rajiv Yadav
Day-3, Mr. Rajiv YadavIPPAI
 
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Fernando Penarroyo
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power PlantsKoos Smit
 
Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)KAMALAKKANNAN G
 
Day-4, Mr. MG Raout
Day-4, Mr. MG RaoutDay-4, Mr. MG Raout
Day-4, Mr. MG RaoutIPPAI
 
Indian power market design
Indian power market designIndian power market design
Indian power market designNavajyoti Martha
 

What's hot (20)

Energy crisis in Pakistan and its management
Energy crisis in Pakistan and its managementEnergy crisis in Pakistan and its management
Energy crisis in Pakistan and its management
 
Captive power Policy
Captive power PolicyCaptive power Policy
Captive power Policy
 
Power Sector Reform in India
Power Sector Reform in IndiaPower Sector Reform in India
Power Sector Reform in India
 
power sector
power sectorpower sector
power sector
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry Analysis
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Circular Debt in Pakistan
Circular Debt in PakistanCircular Debt in Pakistan
Circular Debt in Pakistan
 
Kigali | Sep-15 | Uganda country view
Kigali | Sep-15 | Uganda country viewKigali | Sep-15 | Uganda country view
Kigali | Sep-15 | Uganda country view
 
Class 3 the power sector in india
Class 3   the power sector in indiaClass 3   the power sector in india
Class 3 the power sector in india
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
 
Why Circular Debt Burgeons in the Power Sector? Case of Pakistan
Why Circular Debt Burgeons in the Power Sector? Case of PakistanWhy Circular Debt Burgeons in the Power Sector? Case of Pakistan
Why Circular Debt Burgeons in the Power Sector? Case of Pakistan
 
Day-3, Mr. Rajiv Yadav
Day-3, Mr. Rajiv YadavDay-3, Mr. Rajiv Yadav
Day-3, Mr. Rajiv Yadav
 
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...
Renewable Energy Act of 2008: Hits and Misses for the Philippine Geothermal I...
 
pdt 2018 in india
pdt 2018 in indiapdt 2018 in india
pdt 2018 in india
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power Plants
 
Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)Detailed Analysis Of Power Plant Equipments (Power Sector)
Detailed Analysis Of Power Plant Equipments (Power Sector)
 
Lucy Stevens - Green Growth Diagnostics for Africa
Lucy Stevens - Green Growth Diagnostics for AfricaLucy Stevens - Green Growth Diagnostics for Africa
Lucy Stevens - Green Growth Diagnostics for Africa
 
Day-4, Mr. MG Raout
Day-4, Mr. MG RaoutDay-4, Mr. MG Raout
Day-4, Mr. MG Raout
 
Indian power market design
Indian power market designIndian power market design
Indian power market design
 

Similar to Energy comsats 12_oct13_2

Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionIPPAI
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptxRAMAPANDA6
 
Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in PakistanUzma Fatima Ch.
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardIPPAI
 
Power sector ,devlopment
Power sector ,devlopmentPower sector ,devlopment
Power sector ,devlopmentBhakti Parida
 
AECT Electricity 101
AECT Electricity 101AECT Electricity 101
AECT Electricity 101aectnet
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...OECD Environment
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyTNenergy
 
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...Atif Ahmad
 
Stellaris Covid-19 Nigeria energy update 2020
Stellaris Covid-19 Nigeria energy update 2020Stellaris Covid-19 Nigeria energy update 2020
Stellaris Covid-19 Nigeria energy update 2020Chinedu Igbokwe
 
Praveen NMEEE Environment Science.ppt
Praveen NMEEE Environment Science.pptPraveen NMEEE Environment Science.ppt
Praveen NMEEE Environment Science.pptpraveen gautam
 
QLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjQLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjbitseeeRandD
 
Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.D.Pawan Kumar
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorVijay Menghani
 

Similar to Energy comsats 12_oct13_2 (20)

Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptx
 
Energy distribution in Pakistan
Energy distribution in PakistanEnergy distribution in Pakistan
Energy distribution in Pakistan
 
Ppt nep n ntp
Ppt nep n ntpPpt nep n ntp
Ppt nep n ntp
 
Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
The Computable General Equilibrium Analysis of Electricity Subsidies: The Per...
 
Pcci energy committe twg on power
Pcci energy committe   twg on powerPcci energy committe   twg on power
Pcci energy committe twg on power
 
Ntpc business strategy
Ntpc business strategyNtpc business strategy
Ntpc business strategy
 
Power sector ,devlopment
Power sector ,devlopmentPower sector ,devlopment
Power sector ,devlopment
 
AECT Electricity 101
AECT Electricity 101AECT Electricity 101
AECT Electricity 101
 
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
Mylene Capongol, Department of Energy - Philippine Experience in Furthering R...
 
Energy efficiency in the tennessee valley
Energy efficiency in the tennessee valleyEnergy efficiency in the tennessee valley
Energy efficiency in the tennessee valley
 
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...Pakistan 2013 -  Ministry Power & Water - Roadmap to reform Power & Utility s...
Pakistan 2013 - Ministry Power & Water - Roadmap to reform Power & Utility s...
 
Stellaris Covid-19 Nigeria energy update 2020
Stellaris Covid-19 Nigeria energy update 2020Stellaris Covid-19 Nigeria energy update 2020
Stellaris Covid-19 Nigeria energy update 2020
 
Praveen NMEEE Environment Science.ppt
Praveen NMEEE Environment Science.pptPraveen NMEEE Environment Science.ppt
Praveen NMEEE Environment Science.ppt
 
QLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjjQLW C9 India Mr G M Pillai asdfggjjjkjjj
QLW C9 India Mr G M Pillai asdfggjjjkjjj
 
Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.Indian energy efficiency scene..a macro perspective.
Indian energy efficiency scene..a macro perspective.
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
A present energy scenario
A present energy scenarioA present energy scenario
A present energy scenario
 
Presentation steel
 Presentation steel  Presentation steel
Presentation steel
 

More from Faizan Shabbir

Components of-crankshaft
Components of-crankshaftComponents of-crankshaft
Components of-crankshaftFaizan Shabbir
 
4th edition mechanics of materials by beer johnston (solution manual)
4th edition mechanics of materials by beer johnston (solution manual)4th edition mechanics of materials by beer johnston (solution manual)
4th edition mechanics of materials by beer johnston (solution manual)Faizan Shabbir
 
Logic gates pin_configuration
Logic gates pin_configurationLogic gates pin_configuration
Logic gates pin_configurationFaizan Shabbir
 
Determining the mechanical power of turbine
Determining the mechanical power of turbineDetermining the mechanical power of turbine
Determining the mechanical power of turbineFaizan Shabbir
 
Efficiency of change of state of gases apparatus
Efficiency of change of state of gases apparatusEfficiency of change of state of gases apparatus
Efficiency of change of state of gases apparatusFaizan Shabbir
 
Homogeneous charge compression ignition hcci Engines
Homogeneous charge compression ignition hcci EnginesHomogeneous charge compression ignition hcci Engines
Homogeneous charge compression ignition hcci EnginesFaizan Shabbir
 
Writing correspondence
Writing correspondenceWriting correspondence
Writing correspondenceFaizan Shabbir
 
Womens political participation
Womens political participationWomens political participation
Womens political participationFaizan Shabbir
 
The collapse-of-the-soviet-union
The collapse-of-the-soviet-unionThe collapse-of-the-soviet-union
The collapse-of-the-soviet-unionFaizan Shabbir
 
Lines and planes in space
Lines and planes in spaceLines and planes in space
Lines and planes in spaceFaizan Shabbir
 
Lines and planes in space
Lines and planes in spaceLines and planes in space
Lines and planes in spaceFaizan Shabbir
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistanFaizan Shabbir
 
Database management system
Database management systemDatabase management system
Database management systemFaizan Shabbir
 

More from Faizan Shabbir (20)

Components of-crankshaft
Components of-crankshaftComponents of-crankshaft
Components of-crankshaft
 
4th edition mechanics of materials by beer johnston (solution manual)
4th edition mechanics of materials by beer johnston (solution manual)4th edition mechanics of materials by beer johnston (solution manual)
4th edition mechanics of materials by beer johnston (solution manual)
 
Water level indicator
Water level indicatorWater level indicator
Water level indicator
 
Hdpe pipe industry
Hdpe pipe industryHdpe pipe industry
Hdpe pipe industry
 
Logic gates pin_configuration
Logic gates pin_configurationLogic gates pin_configuration
Logic gates pin_configuration
 
Gas turbine
Gas turbineGas turbine
Gas turbine
 
Stirling engine
Stirling engineStirling engine
Stirling engine
 
Determining the mechanical power of turbine
Determining the mechanical power of turbineDetermining the mechanical power of turbine
Determining the mechanical power of turbine
 
Efficiency of change of state of gases apparatus
Efficiency of change of state of gases apparatusEfficiency of change of state of gases apparatus
Efficiency of change of state of gases apparatus
 
Homogeneous charge compression ignition hcci Engines
Homogeneous charge compression ignition hcci EnginesHomogeneous charge compression ignition hcci Engines
Homogeneous charge compression ignition hcci Engines
 
Head losses
Head lossesHead losses
Head losses
 
Writing correspondence
Writing correspondenceWriting correspondence
Writing correspondence
 
Womens political participation
Womens political participationWomens political participation
Womens political participation
 
The collapse-of-the-soviet-union
The collapse-of-the-soviet-unionThe collapse-of-the-soviet-union
The collapse-of-the-soviet-union
 
Technical pres
Technical presTechnical pres
Technical pres
 
Skills
SkillsSkills
Skills
 
Lines and planes in space
Lines and planes in spaceLines and planes in space
Lines and planes in space
 
Lines and planes in space
Lines and planes in spaceLines and planes in space
Lines and planes in space
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistan
 
Database management system
Database management systemDatabase management system
Database management system
 

Energy comsats 12_oct13_2

  • 1. Economy and Energy Security for Pakistan - What lies ahead COMSATS Institute of Information Technology 12 October 2013
  • 2. • The Economic Survey of Pakistan recognizes that during 2012 around 2 percent of gross domestic product (GDP) was lost due to the power sector outages. • The petroleum crude and products contributed to a third of total imports of Pakistan during 2012 • The transmission and distribution (T&D) losses were valued at PKR 140 billion in 2012 • Issues being currently faced can be categorised into policy, governance, technical and cost issues 2 Background
  • 3. • Short-term situation analysis • Limiting analysis to power sector • Assumptions: – It will be difficult to attract investment – It will be difficult to bring legislative changes – Will be difficult to change governance structures at generation and distribution companies • What lies ahead? 3 Sequence of Discussion
  • 4. Circular Debt in Power Sector 111 145 161 236 366 538 872 0 100 200 300 400 500 600 700 800 900 1000 2006 2007 2008 2009 2010 2011 2012 PKRBillions Source: Planning Commission 2013
  • 5. Integrated Energy Policy Consolidate fragmented energy governance Build capacity of regulators Deregulate energy sector further Reforms for attracting investment in energy sector Make generation efficient Reduce transmission losses Hydro, Coal and other sources Steps that were promised
  • 6. These may be symptoms but are not causes of crisis
  • 7. Unwillingess to pay the price of energy Political stubbornness to maintain subsidies Administrative and line losses 7 3 key causes
  • 8. • Willingness and ability to pay for power • Recoveries of some very large power distribution companies have deteriorated over time – In Hyderabad, for example, only 60% of the power supplied in 2012 was paid for – in a city of over 6.5 million people • DISCOs are unable to adopt the normal commercial practices in other countries of disconnecting customers for non- payment because of unclear legislation and political pressure. 8 1. Unwillingness to pay for power
  • 9. 9 Source: SDPI Survey Unit 2013 No , 82% Don't Know, 6% Yes, 12% Will households pay if power cuts are eliminated and tariff is increased by 10%
  • 10. • The fundamental rationale for subsidising electricity tariffs is to augment the paying capacity of the poorest of poor • However once subsidies are provided across the board, people start to demand them as their right and politicians feel compelled to maintain this distortive fiscal burden to win popularity. • Do poor really get power subsidies in Pakistan – Domestic lifeline consumers (1-100 units) only get 0.3% subsidy 10 2. Political stubbornness to maintain subsidies
  • 11. Subsidybythegovernmentonpowerconsumption(Rs/kW) LESCO GEPCO FESCO MEPCO HESCO SEPCO QESCO PESCO 1.Residential,<700units 0.4 1.4 1.4 2.9 3.9 3.9 1.4 4.4 2.Industrial,(66.132KV&above)- TOU(Peak) 2.1 2.1 2.1 3.1 6.6 6.6 4.0 7.1 3.Agricultural,5KW&above-TOU (Peak) 1.5 1.5 1.5 2.5 6.0 6.0 3.5 6.5 Source: Economic Survey of Pakistan, 2013
  • 12. Electricity Shortfall & Subsidies 12 0 50 100 150 200 250 300 350 400 450 500 0 1000 2000 3000 4000 5000 6000 7000 2005 2006 2007 2008 2009 2010 2011 2012 2013 Subsidy(PKRBillion) Deficit(MW) Electricity Shortfall (MW) Subsidy to Power Sector Source: NEPRA and Planning Commission 2013
  • 13. • In August 2013, the Secretary of Water and Power Ministry informed the Senate Standing Committee that – Pakistan loses annually PKR 150 billion (USD 1.7 billion) in line losses and power theft. – Until August 23770 cases of theft were registered and under trial – But only 3 cases were punished. Moreover, the fine imposed was under PKR 5000 in each case. • Lacunae in the accountability mechanism. This requires amendments in Pakistan Penal Code so that there is certainty of effective punishment in cases of power theft 13 3. Administrative & Line Losses (Theft)
  • 14. 14 Power T & D Losses (% of output) 0 5 10 15 20 25 30 35 40 1971 1974 1977 1980 1983 1986 1989 1992 1995 1998 2001 2004 2007 2010 Percentage Pakistan Bangladesh
  • 15. 15 35% 59% 6% Yes No Don't Know Do you know of power theft in your area? Source: SDPI Survey Unit 2013
  • 17. All subsidies (including hidden and cross subsidies) - except a 100 unit lifeline block - should be phased out over the next 24 months. 17 1. Tariffs and Subsidies
  • 18. • Unaccounted-for-gas controls should be enforced and the saved gas diverted to the power sector. The power ministry notes that just a 10 percent diversion can produce an extra 2000MW. • Performance contracts for grid stations under National Transmission and Dispatch Company. • Performance contracts should also be introduced for DISCOs. Such a contract should have specific clauses on reduction in distribution losses and full collection of receivables from consumers. • Accountability at XEN-level • Role of provinces • Social accountability tools 18 2. Curbing Loses
  • 19. • Creating competition on distribution side is important but a medium to longer term option • What about creating competition in generation sector? • The allocation of fuel to generation companies (GENCOs) should be linked with their efficiency levels • If the Independent Power Producers (IPPs) are better performing in efficiency terms then fuel allocation may be in favour of IPPs • According to Ministry of Water and Power’s own estimates a 4000mtoe shift from GENCOs to IPPs will save PKR 77 billion annually • The current generation comparison reveals that PKR 13 billion per month for GENCOs allows production of 650 MW and only PKR 10 million per month in case of IPPs produces 1150 MW. 19 3. Creating competition in power sector
  • 20. 20 Can I get cheaper power?
  • 22. • Who runs regulatory institutions? • How is transmission optimized at power ministry? • What about planners at Planning Commission? • Reform of power generation and distribution companies • Energy sector and civil service reforms • Define limits of government in power sector 22 Who will do it?

Editor's Notes

  1. You have the paper
  2. So privatization is not an option in the short term.
  3. They didn’t have time to write a legal draft…so the document of policy is a power point document
  4. The policy wishes to keep it to 200 units. It also wants 3 years to phase out. Subsidizing a commodity much more distortive than giving cash…like BISP