This document discusses safety issues related to Yankee cylinders used in papermaking. It identifies several common reasons for Yankee cylinder failures, including increased steam pressure inside the cylinder, increased condensate levels, increased touch roll loading, and increased moisture in the incoming paper web. It then provides recommendations to address each of these issues, such as installing pressure switches and safety valves, regularly inspecting condensate removal pipes and seals, and monitoring systems to detect changes in process variables. Detection techniques for non-condensable gases are also outlined, as well as methods for monitoring vibrations or load fluctuations that can indicate increased condensate levels inside the Yankee cylinder.
Pressure Relief Valve Sizing for Single Phase FlowVikram Sharma
This presentation file provides a quick refresher to pressure relief valve sizing for single phase flow. The calculation guideline is as per API Std 520.
Pressure Relief Valve Sizing for Single Phase FlowVikram Sharma
This presentation file provides a quick refresher to pressure relief valve sizing for single phase flow. The calculation guideline is as per API Std 520.
Pressure Safety Valve Sizing - API 520/521/526Vijay Sarathy
No chemical process facility is immune to the risk of overpressure to avoid dictating the necessity for overpressure protection. For every situation that demands safe containment of process gas, it becomes an obligation for engineers to equally provide pressure relieving and flaring provisions wherever necessary. The levels of protection are hierarchical, starting with designing an inherently safe process to avoid overpressure followed by providing alarms for operators to intervene and Emergency Shutdown provisions through ESD and SIL rated instrumentation. Beyond these design and instrument based protection measures, the philosophy of containment and abatement steps such as pressure relieving devices, flares, physical dikes and Emergency Response Services is employed
Safety is the most important factor in designing a process system. Some undesired conditions might happen leading to damage in a system. Control systems might be installed to prevent such conditions, but a second safety device is also needed. One kind of safety device which is commonly used in the processing industry is the relief valve. A relief valve is a type of valve to control or limit the pressure in a system by allowing the pressurised fluid to flow out from the system.
Basic Fluid Dynamics - Control Valves Brannon Gant
Setpoint Integrated Solutions is a industry leader in providing control valve solutions across industry segments.
Brannon Gant - Regional Sales Manager
Importance & requirement of Rupture Disk in Industry. Sizing and selection of Safety Relief valves and Rupture Disks. Selection and types of rupture disks. Sizing calculation of rupture disks, PRVs and determination of required relief load.
Eng handbook crosby pressure relief valve engineering handbookAli Meshaikhis
Reference is made to the ASME Boiler and Pressure Vessel Code, Section VIII, Pressure Vessels. The information in this handbook is not to be used for the application of overpressure protection to power boilers and nuclear power plant components which are addressed in the ASEM Boiler and Pressure Vessel Code Section I.
Advanced Anti surge Control System for Turbine Driven Centrifugal CompressorsArslan Ahmed Amin
Advanced Anti surge Control System for Turbine Driven Centrifugal Compressors
Please subscribe to my YouTube Channel for best training lectures:
https://www.youtube.com/channel/UCRkUJFOsyZG1E1LDWzUr_hw/playlists?view_as=subscriber
Pressure Safety Valve Sizing - API 520/521/526Vijay Sarathy
No chemical process facility is immune to the risk of overpressure to avoid dictating the necessity for overpressure protection. For every situation that demands safe containment of process gas, it becomes an obligation for engineers to equally provide pressure relieving and flaring provisions wherever necessary. The levels of protection are hierarchical, starting with designing an inherently safe process to avoid overpressure followed by providing alarms for operators to intervene and Emergency Shutdown provisions through ESD and SIL rated instrumentation. Beyond these design and instrument based protection measures, the philosophy of containment and abatement steps such as pressure relieving devices, flares, physical dikes and Emergency Response Services is employed
Safety is the most important factor in designing a process system. Some undesired conditions might happen leading to damage in a system. Control systems might be installed to prevent such conditions, but a second safety device is also needed. One kind of safety device which is commonly used in the processing industry is the relief valve. A relief valve is a type of valve to control or limit the pressure in a system by allowing the pressurised fluid to flow out from the system.
Basic Fluid Dynamics - Control Valves Brannon Gant
Setpoint Integrated Solutions is a industry leader in providing control valve solutions across industry segments.
Brannon Gant - Regional Sales Manager
Importance & requirement of Rupture Disk in Industry. Sizing and selection of Safety Relief valves and Rupture Disks. Selection and types of rupture disks. Sizing calculation of rupture disks, PRVs and determination of required relief load.
Eng handbook crosby pressure relief valve engineering handbookAli Meshaikhis
Reference is made to the ASME Boiler and Pressure Vessel Code, Section VIII, Pressure Vessels. The information in this handbook is not to be used for the application of overpressure protection to power boilers and nuclear power plant components which are addressed in the ASEM Boiler and Pressure Vessel Code Section I.
Advanced Anti surge Control System for Turbine Driven Centrifugal CompressorsArslan Ahmed Amin
Advanced Anti surge Control System for Turbine Driven Centrifugal Compressors
Please subscribe to my YouTube Channel for best training lectures:
https://www.youtube.com/channel/UCRkUJFOsyZG1E1LDWzUr_hw/playlists?view_as=subscriber
“Antisurge Protection in action” for Compressors By Prem Baboo.pdfPremBaboo4
In any centrifugal compressor the Antisurge protection in action interlock is given for compressor safety. This logic is very typical and related to much input. Each input is very important for compressor life and internals. This paper intended how to work this logic. This paper explains surge protection in action phenomena and explains why the anti-surge protection system is a very important part of a compressor? The multi stage compressor has many stages for developing pressure and high rpm which is generated with steam turbine. Numbers of companies are available for controlling surging of compressor like CCC (Compressor Controls Corporation), USA. Woodward and Yokogawa, Turbo machinery control system etc. are provider solutions for compressor flow control device with software and hardware.
Stall can most easily be defined as a condition in which heat transfer equipment is unable to drain condensate and becomes flooded due to insufficient system pressure.
What causes stall?
Stall occurs primarily in heat transfer equipment where the steam pressure is modulated to obtain a desired output (i.e. product temperature). The pressure range of any such equipment ( coils, shell & tube, etc....) can be segmented into two (2) distinct operational modes: Operating and Stall
Operating: In the upper section of the pressure range the operating pressure (OP) of the equipment is greater than the back pressure (BP) present at the discharge of the steam trap. Therefore a positive pressure differential across the trap exists allowing for condensate to flow from the equipment to the condensate return line.
Stall: In the lower section of the pressure range the operating pressure (OP) of the equipment is less than or equal to the back pressure (BP) present at the discharge of the steam trap. Therefore a negative or no pressure differential exists, this does not allow condensate to be discharged to the return line and the condensate begins to collect and flood the equipment.
Properties of air – Perfect Gas Laws – Compressor – Filters, Regulator, Lubricator, Muffler, Air
control Valves, Quick Exhaust Valves, Pneumatic actuators, Design of Pneumatic circuit – Cascade method – Electro Pneumatic System – Elements – Ladder diagram – Problems,
Introduction to fluidics and pneumatic logic
100++-interview questions and answers on steam turbine.pdfmaheshwali1
100++-interview questions and answers on steam turbine
Is it possible to have a negative absolute pressure?
No, absolute pressure is measured with reference to a perfect vacuum so it is impossible for it to go negative. You can only measure negative pressure between two different pressures. For example if you allow atmospheric air to gradually flow into a vacuum vessel and measure pressure inside relative to outside it will show a negative pressure reading.
What type of problems do you face in steam turbines related to vacuum?
Problems such as:
· Low vacuum
· High exhaust pressure
· High exhaust temperature
· Higher specific steam consumption
· More cooling water circulation
· Hot well level variation
How do you create vacuum in steam condensers?
Vacuum is created in condenser by steam jet ejectors, where high pressure 8–12 kg/cm2 steam is passed through nozzle which is connected to air line from condenser. This creates high negative pressure there by evacuating air from condenser.
Generally there are Two Types of Ejectors:
Hogger Ejector: Initially this ejector is used for pulling vacuum. It has steam and air lines connections, steam is vented directly into atmosphere. It consumes more steam than main ejectors. It requires 20–30 minutes to create 85% of operating vacuum.
Main Ejector: It comes with first stage and second stage. Air line from surface condenser is given to 1st stage then again air from 1st stage is collected and discharged into 2nd stage. 2nd stage ejector has air vent line.
It consumes less steam than hogger ejector. Generally an ejector come with 1W + 1S i.e. one working and one stand by.
Also vacuum pumps called liquid ring vacuum pumps are used to create vacuum in condensers. Which consume less energy than steam jet air ejector
How does low vacuum affect on turbine speed?
Lower vacuum creates back pressure on turbine blades and rotors. So in emergency, vacuum breaker valve is opened to bring down the turbine speed to zero in minimum time to avoid any further damages.
What is the effect of low vacuum & high exhaust pressure on steam turbine performance?
Low vacuum or high exhaust pressure & high exhaust temperatures lead to more steam consumption to generate unit power.
What are the potential reasons for lower vacuum in steam condenser?
· More condenser load than design
· Lesser amount of cooling water circulation in condenser
· Higher atmosphere temperature
· Location of the steam condenser at higher elevations.
· More exhaust temperature
· Air leakages in the system
· Lesser efficiency of steam ejector or vacuum pump
· Ejector inter condense (1st stage) condensate seal break
· Lesser pressure & temperature of motive steam at ejector inlet
· Worn out ejector nozzles
· Improper quality of motive steam
· Variation in condenser inlet & outlet cooling water temperatures
· Operation of Turbine at lower load
· Lower gland seal steam pressure
What are the effects of air le
Stack height often surprises me. Can we consider cutting short stacks of factories to reduce pollution, as the polluter would be faced to get into self compliance, willingly or unwillingly. Think.
Can we provide some space for viruses in our lives? A different thought, indicating what can be done to to live happily without a fear of virus and let it live its life.
Delhi-NCR air is becoming more and more polluted. We need to find a solution, that too very fast. The present concept note presents such a simple idea to solve the pollution problem.
When environment protection causes problemsDevesh Singhal
What happens when an industry starts treating effluent to achieve better and better than mandated norms? This is done by additional energy, capital cost and thus creates undesirable problems.
Voltage fluctuations and hence motor tripping is a serious problem particularly during rainy season. This presentation is just a small initiative to think and explore what can we do to reduce the problem.
Can our cooking create pollution?
While you prepare your delicious food, fumes containing particulate matter are added to atmosphere. Probably that is the reason that pollution index is generally found more in densely populated areas.
Have you faced problems of incorrect readings in displays, flickering of tubelights etc. Do you know, electrical pollution can be harmful for our lives also?
"𝑩𝑬𝑮𝑼𝑵 𝑾𝑰𝑻𝑯 𝑻𝑱 𝑰𝑺 𝑯𝑨𝑳𝑭 𝑫𝑶𝑵𝑬"
𝐓𝐉 𝐂𝐨𝐦𝐬 (𝐓𝐉 𝐂𝐨𝐦𝐦𝐮𝐧𝐢𝐜𝐚𝐭𝐢𝐨𝐧𝐬) is a professional event agency that includes experts in the event-organizing market in Vietnam, Korea, and ASEAN countries. We provide unlimited types of events from Music concerts, Fan meetings, and Culture festivals to Corporate events, Internal company events, Golf tournaments, MICE events, and Exhibitions.
𝐓𝐉 𝐂𝐨𝐦𝐬 provides unlimited package services including such as Event organizing, Event planning, Event production, Manpower, PR marketing, Design 2D/3D, VIP protocols, Interpreter agency, etc.
Sports events - Golf competitions/billiards competitions/company sports events: dynamic and challenging
⭐ 𝐅𝐞𝐚𝐭𝐮𝐫𝐞𝐝 𝐩𝐫𝐨𝐣𝐞𝐜𝐭𝐬:
➢ 2024 BAEKHYUN [Lonsdaleite] IN HO CHI MINH
➢ SUPER JUNIOR-L.S.S. THE SHOW : Th3ee Guys in HO CHI MINH
➢FreenBecky 1st Fan Meeting in Vietnam
➢CHILDREN ART EXHIBITION 2024: BEYOND BARRIERS
➢ WOW K-Music Festival 2023
➢ Winner [CROSS] Tour in HCM
➢ Super Show 9 in HCM with Super Junior
➢ HCMC - Gyeongsangbuk-do Culture and Tourism Festival
➢ Korean Vietnam Partnership - Fair with LG
➢ Korean President visits Samsung Electronics R&D Center
➢ Vietnam Food Expo with Lotte Wellfood
"𝐄𝐯𝐞𝐫𝐲 𝐞𝐯𝐞𝐧𝐭 𝐢𝐬 𝐚 𝐬𝐭𝐨𝐫𝐲, 𝐚 𝐬𝐩𝐞𝐜𝐢𝐚𝐥 𝐣𝐨𝐮𝐫𝐧𝐞𝐲. 𝐖𝐞 𝐚𝐥𝐰𝐚𝐲𝐬 𝐛𝐞𝐥𝐢𝐞𝐯𝐞 𝐭𝐡𝐚𝐭 𝐬𝐡𝐨𝐫𝐭𝐥𝐲 𝐲𝐨𝐮 𝐰𝐢𝐥𝐥 𝐛𝐞 𝐚 𝐩𝐚𝐫𝐭 𝐨𝐟 𝐨𝐮𝐫 𝐬𝐭𝐨𝐫𝐢𝐞𝐬."
Putting the SPARK into Virtual Training.pptxCynthia Clay
This 60-minute webinar, sponsored by Adobe, was delivered for the Training Mag Network. It explored the five elements of SPARK: Storytelling, Purpose, Action, Relationships, and Kudos. Knowing how to tell a well-structured story is key to building long-term memory. Stating a clear purpose that doesn't take away from the discovery learning process is critical. Ensuring that people move from theory to practical application is imperative. Creating strong social learning is the key to commitment and engagement. Validating and affirming participants' comments is the way to create a positive learning environment.
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
[Note: This is a partial preview. To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
Sustainability has become an increasingly critical topic as the world recognizes the need to protect our planet and its resources for future generations. Sustainability means meeting our current needs without compromising the ability of future generations to meet theirs. It involves long-term planning and consideration of the consequences of our actions. The goal is to create strategies that ensure the long-term viability of People, Planet, and Profit.
Leading companies such as Nike, Toyota, and Siemens are prioritizing sustainable innovation in their business models, setting an example for others to follow. In this Sustainability training presentation, you will learn key concepts, principles, and practices of sustainability applicable across industries. This training aims to create awareness and educate employees, senior executives, consultants, and other key stakeholders, including investors, policymakers, and supply chain partners, on the importance and implementation of sustainability.
LEARNING OBJECTIVES
1. Develop a comprehensive understanding of the fundamental principles and concepts that form the foundation of sustainability within corporate environments.
2. Explore the sustainability implementation model, focusing on effective measures and reporting strategies to track and communicate sustainability efforts.
3. Identify and define best practices and critical success factors essential for achieving sustainability goals within organizations.
CONTENTS
1. Introduction and Key Concepts of Sustainability
2. Principles and Practices of Sustainability
3. Measures and Reporting in Sustainability
4. Sustainability Implementation & Best Practices
To download the complete presentation, visit: https://www.oeconsulting.com.sg/training-presentations
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
VAT Registration Outlined In UAE: Benefits and Requirementsuae taxgpt
Vat Registration is a legal obligation for businesses meeting the threshold requirement, helping companies avoid fines and ramifications. Contact now!
https://viralsocialtrends.com/vat-registration-outlined-in-uae/
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
What is the TDS Return Filing Due Date for FY 2024-25.pdfseoforlegalpillers
It is crucial for the taxpayers to understand about the TDS Return Filing Due Date, so that they can fulfill your TDS obligations efficiently. Taxpayers can avoid penalties by sticking to the deadlines and by accurate filing of TDS. Timely filing of TDS will make sure about the availability of tax credits. You can also seek the professional guidance of experts like Legal Pillers for timely filing of the TDS Return.
B2B payments are rapidly changing. Find out the 5 key questions you need to be asking yourself to be sure you are mastering B2B payments today. Learn more at www.BlueSnap.com.
Company Valuation webinar series - Tuesday, 4 June 2024FelixPerez547899
This session provided an update as to the latest valuation data in the UK and then delved into a discussion on the upcoming election and the impacts on valuation. We finished, as always with a Q&A
2. Disclaimer
This presentation is supplied as a self learning presentation, and is
subjected to the condition that the author accepts no liability
from the use of the same or from the techniques or information
provided within the same.
The information provided herewith is supplied exclusively for mild
steel fabricated yankee cylinders, and expected to be beneficial
to the users, however in case of any problem, may it be
operational, mechanical, breakdown or any other type, the
author cannot be held responsible for the same. Users are
welcome to consult the author in case any problem is observed.
It is strongly recommended to consult your machinery supplier,
yankee supplier, mechanical engineer, and process engineer
etc., before making any changes to the existing system.
3. Issues…
To protect yankee from unwanted
maintenance, e.g. grinding etc.
To ensure proper safety of two “M”s
Man and Machine.
4. Common Reasons for
failure…
Increased steam pressure inside
yankee.
Increased condensate level inside
yankee.
Increased touch roll loading.
Increased moisture with incoming paper
web.
5. Pressure inside yankee
Pressure is normally controlled using a
manual globe valve or alternatively with
a pneumatically controlled valve set at
desired setpoint.
Manual control has its own limitations,
while pneumatic control may allow more
steam to enter yankee cylinder in case
of a malfunction.
6. Increased Condensate
Level…
Increased condensate level can be due
to following reasons1. Siphon pipes leakage or broken.
2. Steam trap failure, strainer chocking
etc.
3. Rotary joint sealing or guide rings
broken.
7. Increased Condensate
Level…
In most of the cases, an increase in
condensate level remains unnoticed.
This results undesirable load due to
both increased weight of yankee as well
as increased pressure inside yankee to
compensate for reduced heat transfer
area due to condensate.
8. Increased Touch Roll Loading
Sometimes, in case of pneumatic or
hydraulic system failure (as the case
may be), the load on touch roll may
increase beyond permissible limits.
9. Increased Moisture
This is also possible that due to sudden
change in vacuum, or some other
process variables, the paper web
moisture content increases suddenly
resulting in undesirable stress on
yankee.
11. Steam Pressure Control
It is strongly recommended to check all
upstream side valves, pressure gauges etc.
periodically to minimize the probability of
failure of the same. Pressure gauges must be
calibrated at regular intervals.
One mill reportedly uses two pressure
gauges, one for normal use and another
(normally valve shut off) for cross checking in
case the reading of the first is doubtful.
12. Steam Pressure Control
In addition, a pressure switch should be
installed at steam inlet line after final control
valve, but before rotary joint.
This switch should be connected to an alarm
to activate if the pressure increases beyond
limit. Any increase in steam pressure to MG
will therefore help the operators to do
corrective action.
13. Steam Pressure Control
A safety valve should also be installed
at the same line as above, set to bleed
off some amount of steam from yankee
in case steam pressure increases.
Since, this is very rarely to operate,
periodic checking and calibration of the
same MUST be done.
15. Increased Condensate Level
In case siphon pipe or trey is broken or
cracked, it becomes impossible for the
condensate to reach to rotary joint. As a
result, condensate level increases.
These should be checked periodically,
at least once a year to ensure these are
properly welded/bolted.
16. Increased Condensate Level
In case of plugged strainers, or
malfunctioning of steam traps,
condensate cannot be removed from
yankee, and hence water level
increases. Such situation occurs in
case of air locking, steam locking,
mechanical failure of trap or scaling
deposition in steam trap and strainers.
17. Increased Condensate Level
Rotary joint carbon rings (seal rings and
guide rings) if broken, may allow a part of
steam from inlet side to escape from the
condensate side without entering yankee at
all.
Such a situation will result in increased
pressure at condensate line, and hence
condensate will not be removed from yankee.
19. Increased Touch Roll Loading
Malfunctioning of pressure regulating
valve in hydraulic or pneumatic system
may result in sudden increase in touch
roll loading.
In one study, it has been observed that
out of total forces acting on a yankee,
the touch roll loading accounts for
nearly 24% of load.
20. Increased Touch Roll Loading
Carefully designed hydraulic or pneumatic
systems with provision to control the pressure
beyond a certain value are a must.
It has been observed that presence of
moisture in pneumatic system results in
premature failure of regulators. Air should be
free from moisture.
In case of hydraulic system, periodical
cleaning of oil filter should be done to avoid
any oil contamination.
22. Increased Moisture
Sudden reduction in touch roll load,
vacuum or some other process variable
may result in increased moisture in
paper web. Due to increased moisture,
when a hot yankee comes in contact
with plenty of moisture, its surface
temperature reduces significantly. This
thermal shock can also affect yankee
adversely.
23. Increased Moisture
To avoid such situations, system must be
audited for its safeguards against failures.
In a typical case, it was noticed that the touch
roll load reduced to such a low value that it
lowered resulting in paper web break at
yankee section, and chocked uhle boxes.
Only a timely emergency stoppage could
protect felts from permanent damage.
24. Increased Moisture
For the case above, the mill installed a
pressure switch in pneumatic pipeline to
activate an alarm if the pneumatic
pressure reduced below minimum
desired pressure. Compressor failure,
severe leakage in pneumatic piping etc.
result in alarm so that the machine
operator can take a corrective or
preventive action as the case may be.
27. PRESSURE INSIDE YANKEE
An inlet pipeline is given on the
following slide to illustrate how pressure
measurement and control can be
effectively done for a yankee.
28. Typical Yankee Inlet Piping
Schematic
PS
To
Yankee
SV
CV
Hooter
PS: Pressure Switch
PI: Pressure Gauge
SV: Safety Valve
CV: Control Valve
PI
CV
From
Steam
Header
29. Yankee Inlet Piping
It is very important to understand that the
pressure indicated by a pressure gauge -may
it be a bourdon tube type, or a pressure
transmitter with indicator or controller- is NOT
the pressure inside yankee as it is
considered. It IS the pressure at inlet of rotary
joint, and the pressure inside yankee would
be gauge pressure minus pressure drop
across rotary joint.
30. Yankee Inlet Piping
As the steam consumption, and hence steam flow
rate increases through yankee, this pressure drop
across rotary joint increases. That means, you
actually provide much lower pressure inside yankee
than the pressure gauge indicates.
Though seem unbelievable, this pressure drop may
be to the tune of half of the gauge reading in some of
the cases, i.e., if the gauge indicates an inlet
pressure of 3.2 Kg/cm2, fair chances are that the inlet
pressure id 1.8-2.0 Kg/cm2 only.
31. Measuring Actual Yankee Inlet
Pressure
Well, it is not practically possible, and
advisable too, to install a pressure gauge on
rotating yankee. But the same can be done
using a trick.
Condensate is removed form a cylinder at a
temperature corresponding to the saturation
temperature of steam at that pressure.
If a temperature gauge is installed just after
rotary joint, we can find out the steam
pressure inside yankee.
32. Measuring Actual Yankee
Pressure
The results obtained by this technique are
often surprising. In some cases, it has been
found that the hydraulic testing of yankee at
the fabricator site had been done at a
pressure 8 or 10 times more than that is
required for papermaking.
But, does that mean yankee is safe?
33. Yankee Pressure- Operational
Vs. Intermittent
In most of the cases, when the paper is
not running on machine, heat losses
through yankee shall are low, and
hence steam flow rate. That is why, the
pressure drop through rotary joint
reduces and pressure inside yankee
increase, even though the pressure
gauge indicates a reduction in the
same.
34. Yankee Pressure: A Typical
Case
In a particular case, a fabricated yankee was
analyzed as discussed above. The design
and operating data are as underDiameter:
4.2M
Shall Thickness:
62mm
Material:
A36 (ASTM)
Pressure at Inlet Piping:
3.3-3.7Kg/cm2
35. Yankee Pressure: A Typical
Case
That mill earlier considered that the
pressure inside yankee is to the tune of
3.3-3.7Kg/cm2. But, considering the
above, temperature measurement of
the condensate just after rotary joint
was done, and found that the
condensate temperature was to the
tune of 127-128°C. This corresponds to
2.0Kg/cm2.
36. Why to Install Safety Valve?
In case of paper running over yankee, it
extracts heat from yankee, as a result
of which, pressure reduces. But when
the paper is not there, e.g., in case of a
paper break, the pressure inside
yankee may increase and affect the
yankee adversely. To avoid the same, a
safety valve or pressure switch
connected to an alarm is
recommended.
37. Non-Condensable Gases
Non condensable gases are another major
source of pressure increase in yankee.
A minute quantity of non condensable gases
can easily reduce down heat transfer rates
significantly, due to which the operator is
bound to increase steam pressure to maintain
the desired production rates.
38. From Where NonCondensable Gases Appear?
In case where boiler feed water is hard, and
boiler water is also highly contaminated,
some de-scaling chemicals generate gases
like CO2 etc.
Also, if boiler feedwater temperature is very
low, presence of dissolved oxygen and air in
feedwater is released within boiler and these
gases travel alongwith the steam to enter
yankee. From the yankee, these cannot be
easily removed as steam trap does not
normally allow these gases to escape out.
39. Condensable Gases in the
System
Often it is very difficult to detect
presence of these gases within the
system, particularly if there is a scope of
increasing production rates.
On machines where the production is
limited by drying capacity, an increase
in pressure could be an indication for
the same.
40. Detection Techniques
For every grade of paper, and for every
speed and basis weight, note down the
normal operating pressure.
In absence of any other system, any
increase in pressure could be a
possible indication of presence of noncondensable gases in the system.
41. Detection Techniques
Here, the properties of steam can be used to detect
the presence of non-condensable in steam.
We know that Boiling point of water increases with
increase in pressure.
Hence, the temperature of condensate just after the
rotary joint increases with increase in pressure inside
yankee.
Due to presence of non-condensable gases, heat
transfer is reduces, which is compensated by
increasing steam pressure inside yankee.
42. Using Condensate
Temperature…
Thus, regular monitoring can reveal
presence of non-condensable gases in
yankee.
For example, if normally the
condensate temperature id to the tune
of 125-127°C, any increase beyond 5°C
can be considered possibly due to the
same.
43. Minimizing Non-Condensable
Gases
The first step is to minimize the
generation of these from the boiler
itself.
Desired number of blowdown, use of
suitable descaling and scale preventing
chemicals, timely descaling, maintaining
appropriate feedwater temperature
should be observed.
44. Minimizing Non-Condensable
Gases
In case non-condensable gases have entered
the system, another simple technique is to let
it blow away. This can be done by bypassing
steam trap in the condensate line. Though
this may lead to minor steam leakage, yet in
many cases, the effect is noticeable, and
condensate temperature decreases indicating
clearly that the heat transfer has improved
substantially.
46. Increased Condensate Level
The problem with increased condensate
level is that in most of the cases, it go
unnoticed for a long time. It is quite
possible that machine is running
smooth without a break of paper for a
long time, and sudden effect of
condensate level increase is noticed.
47. Increased Condensate Level
In a typical case, vibrations started to
appear in yankee framings, and it was
decided to shut the machine and check
yankee internally. Boiler steam supply
was discontinued, and it was decided to
run the paper without steam as long as
possible to get yankee cooled down
early.
48. Increased Condensate Level
Under that situation, machine could be run for
nearly 30-40 minutes without steam.
On checking, it was found that the yankee
was ¾ full (height wise).
One can understand how dangerous it can be
to operate a yankee under such
circumstances, but without knowing the
condensate level in yankee what can be
done?
49. Condensate Removal per
Rotation of Yankee
It is easy to estimate condensate
removed from yankee per revolution.
Divide machine speed with yankee
circumference to achieve yankee RPM.
Now divide condensate removal (or
steam consumption) per hour and
divide the same with 60 (to convert
hours to minutes) and then with yankee
RPM.
50. Condensate Removal per
Rotation of Yankee
For a typical case, steam consumption was
3000 kg/Hr. Machine speed was 210mpm
and yankee circumference was 13.3M.
So the condensate removal per yankee
rotation would be calculated asYankee RPM = 210/13.3 =15.79 rpm
Condensate = 3000/(60*15.79) = 3.16 kg per
revolution.
51. Condensate Removal per
Rotation of Yankee
As one can see that this is a very small
quantity. Also, considering two treys in
a yankee, the water to be lifted per trey
operation is less than two liters.
52. Effect of Condensate Level
Increase
While condensate level is increased,
the trey do lift condensate to transfer
the same to siphon pipe, from where it
cannot move forward, and fells back
into yankee. But due to the size of
treys, these bear a resistance to move,
which can be observed by fluctuating
drive load. The more is the trey size, the
more would be load fluctuation.
53. Effect of Condensate Level
Increase
With increase in condensate level,
some vibrations do start in the yankee
framings. In case the mill has installed
vibration analyzers, any increase in
condensate level can be easily noticed.
For the mills which do not have installed
vibration analyzers in yankee framings,
or do not intend to do so due to high
cost, here is a simple solution.
54. Indicating Vibrations in
Yankee Framings
If any member such as angle or
channel is mounted with yankee
framings in such a way that it is
supported at one end, and the other
end is free, it will oscillate due to
vibrations. A regular observation to its
other end if vibrating severely will
indicate the possibility of some problem
such as condensate filling inside
yankee.
56. Using Ampere Meters….
In some cases, the yankee framings may be
so rigid that there are no significant vibrations
observed in case condensate gets filled up in
yankee. An alternate to the technique shown
above is to put an analogue ampere meter for
yankee drive load. A fluctuation in load,
particularly twice in every rotation of yankee
(For two treys) is a clear indication for the
same.
57. Using Ampere Meters….
In case the dimension of treys is relatively
small, these will not create any resistance to
condensate and hence amperage fluctuation
as indicated above would be very small. As
the trey has to handle only a very small
amount of condensate every time, there is no
need to increase trey size. So another
technique is proposed here to get informed in
case of condensate level increase.
58. A Design Modification
The treys are normally designed in such a
way that the condensate collected by these is
immediately transferred to siphon pipes, from
where it can be removed through rotary joint.
In case some of the condensate does not
move to siphon pipe, it falls back inside
yankee shall, but it does apply some extra
load on drive system.A similar design with
increased area will create more resistance to
drive.
61. Proposed Baffles
As indicated in the drawing in the previous
slide, the dimensions of the same are
designed considering the steam
consumption, yankee dimensions, trey
dimensions, drive system (whether sectional
or line shaft) etc. This baffles are not welded
to shall hence one can be assured that there
would be no surface deformation. Yet, as a
matter of precaution, baffles must be welded
before yankee grinding.
62. Before Installation
Before installation of baffle, one must ensure that the
yankee is balanced.For the same, all other driven
elements, e.g. wire part, press part, pope reel etc. are
stopped in case of a line shaft drive. Yankee is
rotated at very slow speed with all doctor blades
unloaded, and touch roll lowered.
Any unbalance will result in fluctuation of load
(amperage) once for every revolution of yankee
multiplied by number of baffles.
Baffle should be installed only after balancing.
63. Baffle Commissioning
After installation of baffle, first of all, balancing of
yankee has to be checked. Having done that, the
baffles should be checked for suitability. For the
same, water is filled inside yankee, and condensate
line is flanged dummy. This way, no condensate
(water) can be removed from yankee. Now yankee is
rotated at different speeds, and fluctuation in load
(difference between maximum and minimum
amperes) is noted.This load fluctuation will be more
at higher speeds than that at lower speeds.
64. Baffle Commissioning
From the noted amperage fluctuation values,
it must be ensured that the drive should not
trip at maximum load condition.
Also, baffles should be mechanically strong
enough to withstand shock load that may
arise during operation in case of flooding
yankee.
It should also be checked that the baffles do
not obstruct condensate flow in case of
normal operation of yankee.
65. Conclusion
The basic approach to be followed is to
detect, measure and correct for any
action that has to be done for the safety
of any equipment.
Above all, a team work and association
of every individual towards the goal of
COMPLETE SAFETY is a must.
67. Feedback
Please send your feedback to:
D K Singhal
Deveshksinghal@rediffmail.com
Deveshksinghal@gmail.com
68. D K Singhal
Basically an M.E. (Pulp & Paper) from Institute of Paper Technology, (University
of Roorkee, now IIT, Roorkee), Saharanpur, 1993. Did B.E. (Pulp & Paper) from
the same institute in 1990. Certified Energy Auditor from Bureau of Energy
Efficiency (BEE), India.
Having about 15 years of experience and author of more than three dozen
technical & research papers covering a vide range of topics including waste
paper sorting, pulping, waste paper recycling, energy conservation, optimization,
chemical recovery, paper mill electricals, power generation, rewinder
optimization for trim loss minimization, paper making, process instrumentation &
automation, computer simulation, quality monitoring etc.
Contact:
D K Singhal, Sargam Theatre,
Chandpur 247 625, Dist. Bijnor
Phone: 01345:220140,222330 (O)
Fax: 01345:224140 Mobile: 09412713426
E-mail: deveshksinghal@rediffmail.com chandpurpapers@yahoo.com