1 2 3 4 5 6 7
Work Package
description
Mixed Gas Manifold Instrument Air & Dry Air Water System MV Distribution Substation EOT Cranes Lighting & Utility power Chiller Plant
Purpose
To provide Mixed gas as the
fuel for the Walking beam
furnace
To provide oxygen for gas
cutting and instrument air to
support various field
instruments in level -1
automation level
Providing direct & Indirect
cooling water for process needs
Providing power (11KV) to
variable loads as well as fixed
loads via two distinct Metalclad
Air Insulated Substations
For Maintenance of Mill
Equipments and Shipping of
materials from Storage Bay
Entire Plant illumination and
auxiliary power to Electrical
Overhaed cranes and Hoist
Water for plant Air Handling Unit
1 2 3 4 5 6 7
Design Supply Installation & Cold Trial Hot Trial Preliminary Acceptance Provisional Acceptance Final Acceptance
1) Assessment of project
requirements
1) Procuremnt of
Plant/equipment as per
approved drawing & scopeof
work
1) Completion of installation and
validation of scope & deliverables
1) To test the capacity of the
equipments to operate
smoothly with load
1) Beginning of transition from
project to operation through Start
up & Operation
1) Operation of plant by the
Client under supervision of
the Contractor
1) Start of Guarantee Period
2) Preparation of Billing
schedule for design & basic
engineering drawings
2)Prepare and finalize Billing
schedule in line with milestone
achievements
2) Completion of individual
system testing and certifying fit
for use
2) to ensure the operational
stability of electro-mechanical
systems
2) To achieve troble free
production of selected products
over asustained period as agreed
during contract
2) Commencement of Defect
liability period as stated in
the contract
2) Completion of liquidation of all
defects
3) Exchange of feedback data
3) Conduct Quality Inspection &
achieve Inspection Certificate
for Sl No 1 above
3) Checking of equipment
functionality & System
functionality
3) To ensure conformance with
Functional description &
sequence of process
3) Observation of process
performance
3) Rectification of defects
issed during PAC
3) Obtaining Financial closure,
Administrative & legal closure
4) Preparation of Detail
engineering
4) Submission of all third party
test reports of Sl No 1 above
4) Simulation of Automation
sequences of the process on a
stand alone basis
4) To perform integrated trial
run of the entire system over an
agreed period as per the terms
of contract
4) Issuance of defects and process
improvementcriteria
4) Preparation & submission
of As Built Drawings
indicating all changes that
occurred during execution.
4) Prepare & submit project
performance report
5) Review and approval of
drawings & documents
5) Procurement of
Plant/equipments as per
milestone and budget
5) Optimize the settings of
equipments & software for
trouble free operation
5) To perform endurance test to
conform quality and start
transition from project to
operation
5) Handingover the plant &
equipment to client & obtaining
Preliminary Acceptance Certificate
5) Undertaking Performance
Guarantee Test to show the
efficiency of the system
against the parameters
defined in the contract.
5) Archiving project documents &
collating lessons learned
6) Distribution of requisite
copies to concerned
department
6) Delivery & Storage at site
along with completion of
bailment agreement with client
6) Undertaking No Load trial for
an agreed period with validation
of the scope & deliverables
6) Validation of scope &
deliverables and obtaining
Provisional Acceptance
Certificate
6) Obtain feedback from client
700000 to 850000 TPY capacity having a 200 TPH Walking Beam furnace& equipped with Level-3 automation
Hot Rolling Steel Mill
Work Breakdown Structure of a Hot Rolling Steel Mill
Project Life Cycle of Steel Rolling Mill

Work breakdown structure & project life cycle

  • 1.
    1 2 34 5 6 7 Work Package description Mixed Gas Manifold Instrument Air & Dry Air Water System MV Distribution Substation EOT Cranes Lighting & Utility power Chiller Plant Purpose To provide Mixed gas as the fuel for the Walking beam furnace To provide oxygen for gas cutting and instrument air to support various field instruments in level -1 automation level Providing direct & Indirect cooling water for process needs Providing power (11KV) to variable loads as well as fixed loads via two distinct Metalclad Air Insulated Substations For Maintenance of Mill Equipments and Shipping of materials from Storage Bay Entire Plant illumination and auxiliary power to Electrical Overhaed cranes and Hoist Water for plant Air Handling Unit 1 2 3 4 5 6 7 Design Supply Installation & Cold Trial Hot Trial Preliminary Acceptance Provisional Acceptance Final Acceptance 1) Assessment of project requirements 1) Procuremnt of Plant/equipment as per approved drawing & scopeof work 1) Completion of installation and validation of scope & deliverables 1) To test the capacity of the equipments to operate smoothly with load 1) Beginning of transition from project to operation through Start up & Operation 1) Operation of plant by the Client under supervision of the Contractor 1) Start of Guarantee Period 2) Preparation of Billing schedule for design & basic engineering drawings 2)Prepare and finalize Billing schedule in line with milestone achievements 2) Completion of individual system testing and certifying fit for use 2) to ensure the operational stability of electro-mechanical systems 2) To achieve troble free production of selected products over asustained period as agreed during contract 2) Commencement of Defect liability period as stated in the contract 2) Completion of liquidation of all defects 3) Exchange of feedback data 3) Conduct Quality Inspection & achieve Inspection Certificate for Sl No 1 above 3) Checking of equipment functionality & System functionality 3) To ensure conformance with Functional description & sequence of process 3) Observation of process performance 3) Rectification of defects issed during PAC 3) Obtaining Financial closure, Administrative & legal closure 4) Preparation of Detail engineering 4) Submission of all third party test reports of Sl No 1 above 4) Simulation of Automation sequences of the process on a stand alone basis 4) To perform integrated trial run of the entire system over an agreed period as per the terms of contract 4) Issuance of defects and process improvementcriteria 4) Preparation & submission of As Built Drawings indicating all changes that occurred during execution. 4) Prepare & submit project performance report 5) Review and approval of drawings & documents 5) Procurement of Plant/equipments as per milestone and budget 5) Optimize the settings of equipments & software for trouble free operation 5) To perform endurance test to conform quality and start transition from project to operation 5) Handingover the plant & equipment to client & obtaining Preliminary Acceptance Certificate 5) Undertaking Performance Guarantee Test to show the efficiency of the system against the parameters defined in the contract. 5) Archiving project documents & collating lessons learned 6) Distribution of requisite copies to concerned department 6) Delivery & Storage at site along with completion of bailment agreement with client 6) Undertaking No Load trial for an agreed period with validation of the scope & deliverables 6) Validation of scope & deliverables and obtaining Provisional Acceptance Certificate 6) Obtain feedback from client 700000 to 850000 TPY capacity having a 200 TPH Walking Beam furnace& equipped with Level-3 automation Hot Rolling Steel Mill Work Breakdown Structure of a Hot Rolling Steel Mill Project Life Cycle of Steel Rolling Mill