1. ANURAG SINGH
Mobile: 09826824877
E – Mail: anurag.anu.rit@gmail.com
MIDDLE MANAGEMENT PROFESSIONAL
P R O F I L E S U M M A R Y
• Nearly 5 years of experience in power plant; expertise entail:
Maintenance Production Planning General Administration
Installation Research & Development Contract Management
Factory Operations Site Management Resource Deployment
• Managed project activities, streamlining processes / procedures to facilitate smooth
maintenance process, enhance productivity and cost reduction
• Proven success in planning & implementing the preventive, predictive & breakdown
maintenance schedules for improving overall reliability and safety of plant equipment
& machinery
• Well versed with Steel Structural, GA Drawings, Detailed Drawings, Piping GA
Drawings, ISO Metric Drawings and P & ID
• Proven success in managing operations involving resource planning, materials
planning, in-process inspection, team building and co-ordination with the internal
departments
• Efficient organizer, motivator, team player and a decisive leader with the ability to
motivate teams to excel and win
C O R E C O M P E T E N C I E S
Maintenance
• Managing the functions of troubleshooting and predictive / preventive / condition based maintenance for reducing machinery
downtime to minimum; undertaking various retrofitting works and overhauling of machines; inspecting machines at vendors’
end and at line setup; carrying out regular health check-up of all machinery and equipment
• Conducting process audits; reviewing existing processes and re-designing the same for enhancing operational efficacy
Production Planning
• Overseeing operations right from planning to execution including finalization of specifications, procurement / supply of raw
materials, stage inspections, progress monitoring & manpower planning
• Planning day-to-day production related activities and allocating work for achieving production target
Project Execution
• Developing proposals and creating budget; planning for material and cash flow for the completion of work; interfacing between
internal technical teams, internal projects teams, consultants & contractors for requirement capturing, building out
specifications & scoping of projects
• Monitoring the project to meet committed timelines; ensuring project quality with adherence to EHS standards
W O R K E X P E R I E N C E
2. Since Oct’14: Doosan Power System India Pvt. Ltd., Kudgi (Bijapur), Karnataka as Planning
Engineer-Project
Role:
• Performing gamut of operations pertaining to:
o Office supply bill & MRC bill, development of reports on daily and weekly basis
o Cash inflow and outflow statements as well as monthly RA bills
• Informing the client for the monthly progressive invoices, variation orders and their approvals
• Reviewing and assessing:
o Engineering and Procurement status in line with erection sequence
o Sub-contractor bill preparation
Highlights:
• Reduced downtime by 70% through measures
• Executed plant expansion / modification / upgradation projects
• Escalated Overall Operating Efficiency (OEE) by 70% through measures
• Recognised for increasing in-plant capability by 80% by effective maintenance; was appreciated for the same
Feb’10-Sep’14: Indian Oil Tanking Engineering Projects Limited, Barh (Patna) as Junior Manager –
Project
Role:
• Conducted the study of the Technical Bid Document to acknowledge the complete scope and requirements of the contract
• Implemented the designed construction procedure and inspection test plan for steel structure work as well as interacted and
coordinated with client for its approval
• Formulated and prepared BOM for all steel bars, sections, plates and other miscellaneous items as anchor fasteners,
machined fasteners, etc.
• Led the erection and alignment activities of heavy structures as per AFC drawing and the provision of relevant IS code 800 / 801 /
802 / 806 like columns, towers, trusses, gantry girder / rails, offsite pipe racks and internal cable bridge / rack
• Initiated the erection of Ducting, stack, hopper, transition piece, equipment platforms, ladder, pipe support, grating and handrail
• Completed the grouting work as per spec and lab test of cube in accordance with the weather temperature condition
• Interfaced and inspection during shop fabrication / prior to erection / during erection / after erection and installation as per
approved ITP
• Maintained the necessary engineering records and protocols as per specification and IS codes
• Executed miscellaneous activities related to site closure – material reconciliation and provided the final documents to client
• Handled pre - assembly of pressure part of boiler such as ducting, economizer, water wall panel, hot suspension as a
quality part
• Evaluated GAD, P &I D, Line List, Isometrics and all technical inputs from the client
• Estimated and prepared the BOM - Pipe Materials, Fittings, Valves, Special Items (Strainer) and Support Materials for the
entire project
• Performed:
o Punching the clearance & activity of box-up
o Welder Qualification Test
o Inspection of the Weld Visual, Fit up, Hardness & PMI
E D U C A T I O N
2009
B.E. (Mechanical)
R.I.T. (Rishiraj Institute of Technology), Indore, R.G.T.U. University
3. IT S k i l l s
• Expertise in:
o Microsoft Windows XP Professional 2002
o MS Office 2007
o Internet Applications
P E R S O N A L D E T A I L S
Date of Birth: 22th
October 1988
Address: 24 / 209 Arjun Nagar, Rewa, M.P., India – 486001
Languages Known: English and Hindi
Passport no: J1415883
Please refer to the annexure for the project details
4. ANNEXURE
Highlights:
P R O J E C T S H A N D L E D
Title: Super Thermal Power Plant
Client: N.T.P.C. Kudgi (Bijapur) Karnataka (3 x 800 MW)
EPCC: Doosan Power System India Pvt. Ltd
Period: Oct’14-till now
Title: Super Thermal Power Plant
Client: N.T.P.C., Barh, Patna (3 x 660 MW)
Consultant: T.P.E.
Period: Nov12 – Sep’14
Title: DFCU & AU Projects – Samsung Engineering Constructions Limited
Client: ONGC Petro Additions Limited (OPAL)
Consultant: Engineers India Limited
Period: Jun’10 – Oct’12
Title: IRUP-EPCC-6B Off-Site Pipe Rack & Utility Piping
Client: IOCL - Gujarat Refinery
Consultant: Toyo Engineering India Limited
Period: Feb’10 – Jun’10
I N D U S T R I A L T R A I N I N G
Title: Production of Cements
Organization: J.P. Cement, Rewa, M.P.
Period: 1.5 Months
Description: Acquired exposure to manufacturing process of different types of Cement