SlideShare a Scribd company logo
1 of 9
 The impact of COVID-19 on the construction
industry was not anticipated and it is causing
delays and impacts to construction
operations which is outside of
contractor/owner’s control.
 A formal notice creates a productive
communication pathway regarding the
delays/costs incurred and ways to mitigate
them. Hence, the first step is to notify your
client that you are being delayed.
 Time Extensions: At a minimum, the event is
causing delay to project performance. As
such, an extension of the “Contract Time” is
required. Thus emphasis on the fact that the
delays caused by the COVID-19 epidemic
were unanticipated and beyond your control
shall form the premise of the intimation.
 Delay Costs: The contract may or may not
permit to recover costs. But, the reality is that
all project participants will incur some
additional labor, material, and equipment
cost. It will be in all parties best interest
to find ways to practice techniques of dispute
avoidance during this time period to the
extent possible. Nevertheless, it is prudent
to include in the notice letter that there is a
cost impact to your operations. Commitment
to provide an update regarding the costs
should be stated.
 The contract may also have particular
provisions regarding increased material
costs. If it does not, since there shall be
inevitable supply chain slowdowns and/or
increased costs, the same should be
included in the notice letter.
 The letter should tie the cause and effect
regarding how the COVID-19 measures are
directly impacting the project schedule and/or
causing increased costs. This does not have
to be a complete list, but some
consequences of the impact should be
incorporated, making the notice unique to the
facts of your contract and your contractual
performance. State that you will provide
periodic updates.
1) Majority of contracts would require the party
invoking a force majeure clause to
adequately apprise the counterparty, within
a stipulated time, regarding the event which
prompted invocation of force majeure
clause. Further, the invoking party would be
expected to outline an estimation of the
impact and duration of effects resulting from
the said event.
2) Nature of evidence on which the claim of
force majeure would be based is of utmost
importance. It is vital that the party invoking
the force majeure clause must keep all
documents related to the force majeure
event, which might be required in case a
dispute arises in future. In the present
scenario, the said documents may
include (i) national and state government
notice and guideline imposing restriction of
trade,
(ii) news articles related to COVID-19
outbreak, quarantines, restricted travel and
mandatory shutdown of airports, trains
stations and seaports, (iii) cargo and freight
booking, (iv) cancelled flight or train ticket or
anything other documents relating to travel
itinerary, and (iv) cancelled visa or rejected
visa application.
 The following sample letter attempts to
illustrate how the above mentioned points
can be encapsulated while conveying the
matter to the client.

More Related Content

Similar to Covid 19 & force majeure - power point presentation

Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Construction in Focus
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...Dr. Oliver Massmann
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Is COVID-19 a Force Majeure Event? – Legal & Statutory Position
Is COVID-19 a Force Majeure Event? – Legal & Statutory PositionIs COVID-19 a Force Majeure Event? – Legal & Statutory Position
Is COVID-19 a Force Majeure Event? – Legal & Statutory PositionDVSResearchFoundatio
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Vat Alert: Reverse Charge on Construction Services
Vat Alert: Reverse Charge on Construction ServicesVat Alert: Reverse Charge on Construction Services
Vat Alert: Reverse Charge on Construction ServicesGraham Brearley
 
COVID-19 and force majeure
COVID-19 and force majeureCOVID-19 and force majeure
COVID-19 and force majeureGabrielė Songin
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?EquiCorp Associates
 
Notices under FIDIC 1999 (2).pdf
Notices under FIDIC 1999 (2).pdfNotices under FIDIC 1999 (2).pdf
Notices under FIDIC 1999 (2).pdfmusthaq96
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidicAhmetArslan47
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014 Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014 Pedro N
 
Chapter 6 (General takaful).pptx
Chapter 6 (General takaful).pptxChapter 6 (General takaful).pptx
Chapter 6 (General takaful).pptxjaja37636
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.GE 94
 

Similar to Covid 19 & force majeure - power point presentation (20)

Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Is COVID-19 a Force Majeure Event? – Legal & Statutory Position
Is COVID-19 a Force Majeure Event? – Legal & Statutory PositionIs COVID-19 a Force Majeure Event? – Legal & Statutory Position
Is COVID-19 a Force Majeure Event? – Legal & Statutory Position
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Vat Alert: Reverse Charge on Construction Services
Vat Alert: Reverse Charge on Construction ServicesVat Alert: Reverse Charge on Construction Services
Vat Alert: Reverse Charge on Construction Services
 
COVID-19 and force majeure
COVID-19 and force majeureCOVID-19 and force majeure
COVID-19 and force majeure
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?
COVID-19: HOW DOES IT IMPACT YOUR COMMERCIAL LEASES?
 
Notices under FIDIC 1999 (2).pdf
Notices under FIDIC 1999 (2).pdfNotices under FIDIC 1999 (2).pdf
Notices under FIDIC 1999 (2).pdf
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014 Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014
Oil and Gas Contract Law_Contratual Risks Operators and Contrators_Dez. 2014
 
Chapter 6 (General takaful).pptx
Chapter 6 (General takaful).pptxChapter 6 (General takaful).pptx
Chapter 6 (General takaful).pptx
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
 

More from Sayandeep Dasgupta

Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Sayandeep Dasgupta
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboardSayandeep Dasgupta
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycleSayandeep Dasgupta
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel millSayandeep Dasgupta
 

More from Sayandeep Dasgupta (8)

Concession Agreement.pptx
Concession Agreement.pptxConcession Agreement.pptx
Concession Agreement.pptx
 
Force Majeure.pptx
Force Majeure.pptxForce Majeure.pptx
Force Majeure.pptx
 
Conditions Precedent.pptx
 Conditions Precedent.pptx Conditions Precedent.pptx
Conditions Precedent.pptx
 
Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis
 
Rated diversity factor of a switchboard
Rated diversity factor of a switchboardRated diversity factor of a switchboard
Rated diversity factor of a switchboard
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycle
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel mill
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
 

Recently uploaded

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 

Recently uploaded (15)

Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

Covid 19 & force majeure - power point presentation

  • 1.  The impact of COVID-19 on the construction industry was not anticipated and it is causing delays and impacts to construction operations which is outside of contractor/owner’s control.  A formal notice creates a productive communication pathway regarding the delays/costs incurred and ways to mitigate them. Hence, the first step is to notify your client that you are being delayed.
  • 2.  Time Extensions: At a minimum, the event is causing delay to project performance. As such, an extension of the “Contract Time” is required. Thus emphasis on the fact that the delays caused by the COVID-19 epidemic were unanticipated and beyond your control shall form the premise of the intimation.
  • 3.  Delay Costs: The contract may or may not permit to recover costs. But, the reality is that all project participants will incur some additional labor, material, and equipment cost. It will be in all parties best interest to find ways to practice techniques of dispute avoidance during this time period to the extent possible. Nevertheless, it is prudent to include in the notice letter that there is a cost impact to your operations. Commitment to provide an update regarding the costs should be stated.
  • 4.  The contract may also have particular provisions regarding increased material costs. If it does not, since there shall be inevitable supply chain slowdowns and/or increased costs, the same should be included in the notice letter.
  • 5.  The letter should tie the cause and effect regarding how the COVID-19 measures are directly impacting the project schedule and/or causing increased costs. This does not have to be a complete list, but some consequences of the impact should be incorporated, making the notice unique to the facts of your contract and your contractual performance. State that you will provide periodic updates.
  • 6. 1) Majority of contracts would require the party invoking a force majeure clause to adequately apprise the counterparty, within a stipulated time, regarding the event which prompted invocation of force majeure clause. Further, the invoking party would be expected to outline an estimation of the impact and duration of effects resulting from the said event.
  • 7. 2) Nature of evidence on which the claim of force majeure would be based is of utmost importance. It is vital that the party invoking the force majeure clause must keep all documents related to the force majeure event, which might be required in case a dispute arises in future. In the present scenario, the said documents may include (i) national and state government notice and guideline imposing restriction of trade,
  • 8. (ii) news articles related to COVID-19 outbreak, quarantines, restricted travel and mandatory shutdown of airports, trains stations and seaports, (iii) cargo and freight booking, (iv) cancelled flight or train ticket or anything other documents relating to travel itinerary, and (iv) cancelled visa or rejected visa application.
  • 9.  The following sample letter attempts to illustrate how the above mentioned points can be encapsulated while conveying the matter to the client.