SlideShare a Scribd company logo
1 of 7
BASIC CONSIDERATION FOR POWER LOADING OF AN
ELECTRICAL SWITCHBOARD
While assessing the load on a power system simple
arithmetic sum of each individual load is not a correct
approach of evaluation. Two (2) factors namely:
Diversity i.e. non simultaneous operation of load
equipments
and
Utilization i.e. operation of a load equipment beyond
its full load capability
must be considered so that a global value to a
system can be specified. Let us consider the above
said factors in more detail.
FACTOR OF UTILIZATION (KU)
Under normal operation it is the percentage
loading individual equipment is subjected to.
For
motors used in industry ku = 0.75 on an
average.
Likewise for light (incandescent type) ku = 1 on
an average.
DIVERSITY FACTOR (KS):
 It is the ratio of the sum of the individual non-
coincident maximum loads of various subdivisions
of the system to the maximum demand of the
complete system.
 But, it is obvious that all loads connected to a
system will not peak simultaneously at a given
point of time. IEC-60050 introduces the uses the
concept of reciprocal of the diversity factor and
terms it as coincidence factor. Coincidence factor
(1/ks) also sometimes referred as Simultaneity
factor is thus the ratio of maximum demand on the
complete system over a period of time to individual
non-coincident maximum loads of various
subdivisions of the system.
COINCIDENCE FACTOR (1/KS)
 So whereas Diversity factor (ks) is always
greater than 1 the Coincidence factor (1/ks) is
always less than 1.
 IEC 61439 - 2 uses the concept factor (1/ks) for
distribution switchboards. It states that when
there is no agreement between manufacturer
and user regarding the actual load current, the
assumed loading of the outgoing circuits of the
assembly or the group of outgoing circuits shall
follow table 101 which is reproduced here:
TABLE-101
Number of Distribution
Circuits
Assumed Coincidence
factor (1/ks)
2 – 3 0.9
4 – 5 0.8
6 - 9 0.7
>10 0.6
Motors <100 KW 0.8
Motors >100 KW 1
Lights 1
IN EXAMPLE OF APPLICATION OF
FACTORS KU AND KS, THE TOTAL
INSTALLED APPARENT POWER IS 45
KVA, WHICH CORRESPONDS TO AN
ACTUAL (ESTIMATED) MAXIMUM VALUE
AT THE LV TERMINALS OF THE MAIN
DISTRIBUTION BOARD OF 18.9 KVA
ONLY.
Load
Description
Installed
Apparent
Power
(KVA)
Utilization
Factor
Apparent
max
Demand
(KVA)
Diversity
factor of
Sub
Distribution
Boards
Apparent
Power
Demand
(KVA)
Diversity
factor of
Main
distribution
Board
Actual
Max
Demand
(KVA)
Motor-1 5 0.8 4
0.75
0.9
Motor-2 5 0.8 4
Motor-3 5 0.8 4 14.4
Motor-4 5 0.8 4
Motor-5 2 0.8 1.6
Motor-6 2 0.8 1.6 18.9
Sockets 18 1 18 0.2 3.6
Lights 3 1 3 1 3
Total
installed
capacity
(KVA)
45

More Related Content

What's hot

Home electrical installations
Home electrical installationsHome electrical installations
Home electrical installationstecnoloxias2
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devicesPrakash_13209
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its typesJay Ranvir
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a SubstationMd. Atiqur Rahman
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformerRitesh Verma
 
Powerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsPowerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsSuresh Mohta
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221saikrishna kandhikatla
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentationNikhil Kachare
 
Principles and Design of LV System
Principles and Design of LV SystemPrinciples and Design of LV System
Principles and Design of LV SystemYE MYO
 
Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electricalasmjewel
 
Substations
SubstationsSubstations
Substationsitfakash
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Over current Relays
Over current RelaysOver current Relays
Over current RelaysASWANTH6270
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenancekarikalan123
 
Cpc 100 user manual
Cpc 100 user manualCpc 100 user manual
Cpc 100 user manualSARAVANAN A
 

What's hot (20)

Home electrical installations
Home electrical installationsHome electrical installations
Home electrical installations
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
 
Switchgear Equipment in a Substation
Switchgear Equipment in a SubstationSwitchgear Equipment in a Substation
Switchgear Equipment in a Substation
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
Powerpoint Presentation on Series Reactors
Powerpoint Presentation on Series ReactorsPowerpoint Presentation on Series Reactors
Powerpoint Presentation on Series Reactors
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221electrical distribution system ppt/13b61a0221
electrical distribution system ppt/13b61a0221
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Principles and Design of LV System
Principles and Design of LV SystemPrinciples and Design of LV System
Principles and Design of LV System
 
Commercial load estimation for electrical
Commercial load estimation for electricalCommercial load estimation for electrical
Commercial load estimation for electrical
 
Substations
SubstationsSubstations
Substations
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenance
 
Cpc 100 user manual
Cpc 100 user manualCpc 100 user manual
Cpc 100 user manual
 

Similar to Rated diversity factor of a switchboard

Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...
Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...
Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...ijtsrd
 
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...AEIJjournal2
 
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...AEIJjournal2
 
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...IAEME Publication
 
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEMLOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEMELELIJ
 
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...Design of Full Order Optimal Controller for Interconnected Deregulated Power ...
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...ijceronline
 
Soft power factor modification using static
Soft power factor modification using staticSoft power factor modification using static
Soft power factor modification using staticchodachude
 
Improvement the voltage stability margin of Iraqi power system using the opti...
Improvement the voltage stability margin of Iraqi power system using the opti...Improvement the voltage stability margin of Iraqi power system using the opti...
Improvement the voltage stability margin of Iraqi power system using the opti...IJECEIAES
 
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...paperpublications3
 
Differential game approach for the analysis of two area load frequency control
Differential game approach for the analysis of two area load frequency controlDifferential game approach for the analysis of two area load frequency control
Differential game approach for the analysis of two area load frequency controlIRJET Journal
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Prof.Nagnath Khandekar
 
Optimal design &amp; analysis of load frequency control for two interconnecte...
Optimal design &amp; analysis of load frequency control for two interconnecte...Optimal design &amp; analysis of load frequency control for two interconnecte...
Optimal design &amp; analysis of load frequency control for two interconnecte...ijctet
 
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdf
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdfH8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdf
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdfEMERSON EDUARDO RODRIGUES
 

Similar to Rated diversity factor of a switchboard (20)

Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...
Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...
Reactive Power Compensation and Power Factor Correction by Reactive VAR Compe...
 
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
 
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
TRANSIENT STABILITY IMPROVEMENT OF POWER SYSTEMS BY OPTIMAL SIZING AND ALLOCA...
 
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...
Comparision of pi, fuzzy & neuro fuzzy controller based multi converter unifi...
 
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEMLOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
LOAD SHEDDING DESIGN FOR AN INDUSTRIAL COGENERATION SYSTEM
 
diversity
diversitydiversity
diversity
 
Thyristor switched capacitor
Thyristor switched capacitorThyristor switched capacitor
Thyristor switched capacitor
 
Reactive power management in india
Reactive power  management in indiaReactive power  management in india
Reactive power management in india
 
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...Design of Full Order Optimal Controller for Interconnected Deregulated Power ...
Design of Full Order Optimal Controller for Interconnected Deregulated Power ...
 
Soft power factor modification using static
Soft power factor modification using staticSoft power factor modification using static
Soft power factor modification using static
 
Realization of Multi Converter Using Unified Power Quality Conditioning System
Realization of Multi Converter Using Unified Power Quality Conditioning SystemRealization of Multi Converter Using Unified Power Quality Conditioning System
Realization of Multi Converter Using Unified Power Quality Conditioning System
 
Improvement the voltage stability margin of Iraqi power system using the opti...
Improvement the voltage stability margin of Iraqi power system using the opti...Improvement the voltage stability margin of Iraqi power system using the opti...
Improvement the voltage stability margin of Iraqi power system using the opti...
 
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...
Voltage Regulators Placement in Unbalanced Radial Distribution Systems for Lo...
 
Differential game approach for the analysis of two area load frequency control
Differential game approach for the analysis of two area load frequency controlDifferential game approach for the analysis of two area load frequency control
Differential game approach for the analysis of two area load frequency control
 
Hq3513331337
Hq3513331337Hq3513331337
Hq3513331337
 
Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration Power system -Economic Aspect of Electric power Genration
Power system -Economic Aspect of Electric power Genration
 
Optimal design &amp; analysis of load frequency control for two interconnecte...
Optimal design &amp; analysis of load frequency control for two interconnecte...Optimal design &amp; analysis of load frequency control for two interconnecte...
Optimal design &amp; analysis of load frequency control for two interconnecte...
 
Main
MainMain
Main
 
Main
MainMain
Main
 
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdf
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdfH8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdf
H8 ACTIVE POWER AND EMERSON EDUARDO RODRIGUES.pdf
 

More from Sayandeep Dasgupta

Covid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationCovid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationSayandeep Dasgupta
 
Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Sayandeep Dasgupta
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycleSayandeep Dasgupta
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel millSayandeep Dasgupta
 

More from Sayandeep Dasgupta (8)

Concession Agreement.pptx
Concession Agreement.pptxConcession Agreement.pptx
Concession Agreement.pptx
 
Force Majeure.pptx
Force Majeure.pptxForce Majeure.pptx
Force Majeure.pptx
 
Conditions Precedent.pptx
 Conditions Precedent.pptx Conditions Precedent.pptx
Conditions Precedent.pptx
 
Covid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentationCovid 19 & force majeure - power point presentation
Covid 19 & force majeure - power point presentation
 
Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis Switchgear & Switchboard- A comparative analysis
Switchgear & Switchboard- A comparative analysis
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycle
 
Overiew of a hot rolling steel mill
Overiew of a hot rolling steel millOveriew of a hot rolling steel mill
Overiew of a hot rolling steel mill
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
 

Recently uploaded

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 

Recently uploaded (20)

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 

Rated diversity factor of a switchboard

  • 1. BASIC CONSIDERATION FOR POWER LOADING OF AN ELECTRICAL SWITCHBOARD While assessing the load on a power system simple arithmetic sum of each individual load is not a correct approach of evaluation. Two (2) factors namely: Diversity i.e. non simultaneous operation of load equipments and Utilization i.e. operation of a load equipment beyond its full load capability must be considered so that a global value to a system can be specified. Let us consider the above said factors in more detail.
  • 2. FACTOR OF UTILIZATION (KU) Under normal operation it is the percentage loading individual equipment is subjected to. For motors used in industry ku = 0.75 on an average. Likewise for light (incandescent type) ku = 1 on an average.
  • 3. DIVERSITY FACTOR (KS):  It is the ratio of the sum of the individual non- coincident maximum loads of various subdivisions of the system to the maximum demand of the complete system.  But, it is obvious that all loads connected to a system will not peak simultaneously at a given point of time. IEC-60050 introduces the uses the concept of reciprocal of the diversity factor and terms it as coincidence factor. Coincidence factor (1/ks) also sometimes referred as Simultaneity factor is thus the ratio of maximum demand on the complete system over a period of time to individual non-coincident maximum loads of various subdivisions of the system.
  • 4. COINCIDENCE FACTOR (1/KS)  So whereas Diversity factor (ks) is always greater than 1 the Coincidence factor (1/ks) is always less than 1.  IEC 61439 - 2 uses the concept factor (1/ks) for distribution switchboards. It states that when there is no agreement between manufacturer and user regarding the actual load current, the assumed loading of the outgoing circuits of the assembly or the group of outgoing circuits shall follow table 101 which is reproduced here:
  • 5. TABLE-101 Number of Distribution Circuits Assumed Coincidence factor (1/ks) 2 – 3 0.9 4 – 5 0.8 6 - 9 0.7 >10 0.6 Motors <100 KW 0.8 Motors >100 KW 1 Lights 1
  • 6. IN EXAMPLE OF APPLICATION OF FACTORS KU AND KS, THE TOTAL INSTALLED APPARENT POWER IS 45 KVA, WHICH CORRESPONDS TO AN ACTUAL (ESTIMATED) MAXIMUM VALUE AT THE LV TERMINALS OF THE MAIN DISTRIBUTION BOARD OF 18.9 KVA ONLY.
  • 7. Load Description Installed Apparent Power (KVA) Utilization Factor Apparent max Demand (KVA) Diversity factor of Sub Distribution Boards Apparent Power Demand (KVA) Diversity factor of Main distribution Board Actual Max Demand (KVA) Motor-1 5 0.8 4 0.75 0.9 Motor-2 5 0.8 4 Motor-3 5 0.8 4 14.4 Motor-4 5 0.8 4 Motor-5 2 0.8 1.6 Motor-6 2 0.8 1.6 18.9 Sockets 18 1 18 0.2 3.6 Lights 3 1 3 1 3 Total installed capacity (KVA) 45