The City of Edmonton was undertaking a project to widen Whitemud Drive and the Quesnell Bridge. The original design for the retaining wall presented constructability challenges. The HCM/Isherwood design-build team proposed an alternative design using a cast-in-place retaining wall supported by drilled caissons as a more feasible solution. Monitoring during construction identified weaker soil than expected, requiring design changes to ensure slope stability. The innovative design approach ultimately provided a safer and more constructable solution.
Top-down construction method as the name implies, is a construction method, which builds the permanent structure members of the basement along with the excavation from the top to the bottom. Top-down method is mainly used for two types of urban structures, tall buildings with deep basements and underground structures such as car parks, underpasses and subway stations.
top down construction technique
top down construction definition
top down building construction
top down construction method definition
up down construction
top down bridge construction technique
bottom up construction method
top down bridge construction
environmental engineering project topics
final year project topics
environmental topics for projects
environmental engineering research topics
engineering final year project ideas
environmental engineering projects
final year computer engineering projects
final year project for electrical engineering
top down construction method definition
top down construction video
top down building construction
top down bridge construction
top down construction technique
top down construction
top down design definition
top down management definition
Georesources Journal 3-2018 - Maccaferri ArticleMaccaferri World
The architects of Bridge “Brug van den Azijn” (Vinegar
Bridge) in Antwerp, Belgium, designed a
challenging facade. Maccaferri had to adapt the
Mechanically Stabilized Earth (MSE) wall system
“MacRes System” to meet the challenging requirements.
Top-down construction method as the name implies, is a construction method, which builds the permanent structure members of the basement along with the excavation from the top to the bottom. Top-down method is mainly used for two types of urban structures, tall buildings with deep basements and underground structures such as car parks, underpasses and subway stations.
top down construction technique
top down construction definition
top down building construction
top down construction method definition
up down construction
top down bridge construction technique
bottom up construction method
top down bridge construction
environmental engineering project topics
final year project topics
environmental topics for projects
environmental engineering research topics
engineering final year project ideas
environmental engineering projects
final year computer engineering projects
final year project for electrical engineering
top down construction method definition
top down construction video
top down building construction
top down bridge construction
top down construction technique
top down construction
top down design definition
top down management definition
Georesources Journal 3-2018 - Maccaferri ArticleMaccaferri World
The architects of Bridge “Brug van den Azijn” (Vinegar
Bridge) in Antwerp, Belgium, designed a
challenging facade. Maccaferri had to adapt the
Mechanically Stabilized Earth (MSE) wall system
“MacRes System” to meet the challenging requirements.
The project involved designing of two different types of Rigid pavements using the
AASHTOWare Pavement ME software.
1) JPCP (Jointed Plain Concrete Pavement) : It was designed as a three layered structure,
the layer distribution being as follows:
Layer 1 – PCC – 16 inch
Layer 2 – NonStabilized (Crushed gravel) – 8 inch
Layer 3 – Subgrade (A-1a) – Semi Infinite
Jointed plain concrete pavement uses contraction joints to control cracking and uses
reinforcing steel in form of dowel bars.
Transverse joint spacing is selected such that temperature and moisture stresses do not
produce intermediate cracking between joints.
This typically results in a spacing no longer than about 6.1 m (20 ft.).
2) CRCP (CONTINUOUSLY REINFORCED CONCRETE PAVEMENTS) : It was
designed as a 4 layered structure, the layer distribution being as follows:
Layer 1 – PCC – 11.3 inch
Layer 2 – Stabilized – 4 inch
Layer 3 – NonStabilized – 8 inch
Layer 4 – Subgrade – Semi infinite
CRCP is concrete pavement reinforced with continuous steel bars throughout its length.
Its design eliminates the need for transverse joints (other than at bridges and other
structures) and keeps cracks tight, resulting in a continuous, smooth-riding surface.
Review of Analysis of Retaining Wall Under Static and Seismic Loadingijsrd.com
This paper presents a comparison of the various methods of analysis of retaining wallsunder seismic loads, which is considered to be very complex.As the soil-structure interaction during the earthquake is very complex, the most commonly used methods for the seismic design of retaining walls are the Pseudo static method, Seed and Whitman method and Mononobe and Okabe method. The retaining wall analysis includes determining the factor of safety for overturning, and sliding as well as the resultant location of the forces, which must be within the middle- third of the footing,. A concrete retaining wall is considered with a certain height and base width, and then analyzed for the static case as well as the earthquake loading condition. Based on this study, it is found that factor of safety obtained by Seed & Whitman method (1970) is lowest as compared to others methods.
The project involved designing of two different types of Rigid pavements using the
AASHTOWare Pavement ME software.
1) JPCP (Jointed Plain Concrete Pavement) : It was designed as a three layered structure,
the layer distribution being as follows:
Layer 1 – PCC – 16 inch
Layer 2 – NonStabilized (Crushed gravel) – 8 inch
Layer 3 – Subgrade (A-1a) – Semi Infinite
Jointed plain concrete pavement uses contraction joints to control cracking and uses
reinforcing steel in form of dowel bars.
Transverse joint spacing is selected such that temperature and moisture stresses do not
produce intermediate cracking between joints.
This typically results in a spacing no longer than about 6.1 m (20 ft.).
2) CRCP (CONTINUOUSLY REINFORCED CONCRETE PAVEMENTS) : It was
designed as a 4 layered structure, the layer distribution being as follows:
Layer 1 – PCC – 11.3 inch
Layer 2 – Stabilized – 4 inch
Layer 3 – NonStabilized – 8 inch
Layer 4 – Subgrade – Semi infinite
CRCP is concrete pavement reinforced with continuous steel bars throughout its length.
Its design eliminates the need for transverse joints (other than at bridges and other
structures) and keeps cracks tight, resulting in a continuous, smooth-riding surface.
Review of Analysis of Retaining Wall Under Static and Seismic Loadingijsrd.com
This paper presents a comparison of the various methods of analysis of retaining wallsunder seismic loads, which is considered to be very complex.As the soil-structure interaction during the earthquake is very complex, the most commonly used methods for the seismic design of retaining walls are the Pseudo static method, Seed and Whitman method and Mononobe and Okabe method. The retaining wall analysis includes determining the factor of safety for overturning, and sliding as well as the resultant location of the forces, which must be within the middle- third of the footing,. A concrete retaining wall is considered with a certain height and base width, and then analyzed for the static case as well as the earthquake loading condition. Based on this study, it is found that factor of safety obtained by Seed & Whitman method (1970) is lowest as compared to others methods.
Thanks to Tensar's SierraScape System, the owners of a Canadian Tire store in Ontario were able to build the new store they wanted – where they wanted – and still save more than $1 million (CDN).
this slides is about the technologies like using HPC, SCC, high performance steel, prefabricated deck panels, spot welding system,GSSI bridge scan system used in construction of bridges
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
Running Head: BRIDGE DESIGN 1
BRIDGE DESIGN 31
Title:
Student Name:
Institution:
Course:
Date:
BRIDGE DESIGN FOR THE MOTOR WAY BELOW
8m
Embankment
A
Motorway
16m
10m
Central Reservation
Motorway
16m
Grass Verge
Existing Factory Units
Footway
A
Carriagewaym
Existing Factory Units
Fixed Factory Entrance
Fixed Factory Entrance
3m
2m
3m
2m
10mm
Existing Highway to Proposed Bridge
Existing Development
Proposed Development
Existing Development
Existing Retaining Wall – 500mm thick rc construction indicated by old record drawings
Central Reservation
10m
10m
Section A-A
2m footway
1.2m high parapets
10m carriageway
Bridge Deck Section
Figure 1
Bridge design
Most suitable bridge forms
· Beam bridge
· Arch bridge
The beam bridge: Beam and slab with ladder decks
This form of bridges comprises of slab which sits on top of steel I-beams. This form is mostly used for mid span highway bridge which is where our required bridge falls in.
Slab in this system is supported on tow main girders with a spacing of about 3.5m and it lies longitudinally between the girders as per the below diagram.
Figure 1
The bridge will use plate girders giving us a scope to vary the flange and web sizes to fit and suit the bridge load carrying capabilities. In the design process, ability of the bridge to carry the maximum load expected and the loading at the various stages of construction will guide on the proportion of girders that is their depth, width of tension and compression flanges and web thickness.
The girders are erected firmly on the ground and have stud connectors welded on the top flange to provide composite action between the slab and girder. The number of studs and spacing vary depending on expected level of shear flow between steel girder and concrete slab.
The girders rest on bearings fastened to the bottom flange. The girders are stiffened to carry the bearing loads at these points. Some cases apply bracing between the girders at support to carry lateral forces and provide torsional restraint.
Bridge description
· The bridge will have a span of 50m.
· The bridge will be raised to a height of 10m on both sides to be in level with the existing highway. The girders will have constant height.
· The bridge cross section will have the reinforced concrete slab sitting on top of two main abutment substructures and an extra substructure which will be on the central reservation. The main substructure will be located at the embarkment of the road.
Construction sequence
Abutment substructure construction
Girder construction
The bridge will consist of two main girder I beams. The girders will be of the same height. To make the I-beam, steel plates will be used. The steel plate is cut into the required sizes for the bottom flange and top flange and for the web. The cut pieces are then fillet welded into the I-section. This is done either by machine manual assembling in jig or through improved pressing machine .
2. A Re-Design Proves to
be the Best Solution
Whitemud Drive Retaining Wall,
Edmonton, Alberta, Canada
by Martin Halliwell, P. Eng.,
Project Manager, HCM Contractors
Inc. and
Mark Spence, E.I.T., Project Manager,
Isherwood Associates
Project Summary
The City of Edmonton is undertaking a
multi-stage project, scheduled for comple-
tion in late 2010. This includes widening
both Whitemud Drive and the Quesnell
Bridge to ensure the transportation system
is safe and continues to keep pace with
rapid growth in Edmonton. The Quesnell
Bridge is the busiest bridge in Edmonton,
carrying approximately 120,000 vehicles
on an average day. The additional lanes and
widened shoulders will enhance traffic
flow and improve the overall safety of the
road. This project is the first major reha-
bilitation of the
Quesnell Bridge
since its con-
struction in 1967.
The widening
of the road north
of the Quesnell
Bridge is made
possible by a
cast-in-place re-
taining wall con-
structed in front
of a temporary
t i e b a c k / s o i l -
nailed shotcrete
shoring system.
The new retain-
ing wall replaces
a two-tier bin
wall that was in-
stalled in 1972 to
address a previ-
ous hillside fail-
ure. Analysis of
the slope failure
in 1971 gener-
ated soil strength
parameters is-
sued in the ten-
der soil report documents. In the field,
however, this was revealed to be incorrect;
the actual soil strength was found to be
much lower.
The HCM/Isherwood design-build team’s
innovative design for the retaining wall was
proposed to the City of Edmonton as an al-
ternative to the original tender. Figure 1
shows the original design concept: a series
of high-strength, interlocking secant walls to
depths of up to 25 metres (80 ft.), which
raised constructability concerns with bid-
ding contractors. Maintaining the original
concept’s geometry, the alternative wall con-
sists of 14 abutting arches with a total length
of approximately 250m (800 ft.), as shown
in Figure 2. The wall is supported on
COVER FEATURE
FOUNDATION DRILLING September/October 2009Page 2
(Continued on page 3)
The HCM/Isherwood design-
build team’s innovative design
for the retaining wall was pro-
posed to the City of Edmonton
as an alternative to the origi-
nal tender.
The completed shoring wall adjacent to Whitemud Drive.
Figure 1: Tendered Design of the Whitemud Drive Retaining Wall.
3. 1200mm (48 inch) drilled caissons, capped
by robust ring footings that step downward
into the low slope as it approaches White-
mud Drive.
Existing Site Conditions,
Geology and History
Prior to construction, the existing slope
ranged from 19 to 24m high above the
Whitemud Drive’s elevation and ascended
to the roadway at an approximate overall
2H:1V slope. Existing grade was at eleva-
tion 660.0m +/- at the highest points along
the wall. The subsurface geology is com-
posed of fill material overlaying native silty
clay and glacial clay till overlaying Empress
sand to an elevation 630.0m +/- with
bedrock below.
The native silty clay extends to elevation
654.0m +/- and is typically stiff. The Stan-
dard Penetration Test (SPT) results ranged
from nine to 18 blows per foot with a nat-
ural moisture content ranging from 20% to
45%. Slickensides (polished shear surfaces
caused by previous shearing) were noted
to exist between the elevations of 655 and
657m during preliminary geotechnical in-
vestigations. The glacial clay till extends to
elevation 647m +/, is typically very stiff,
with SPT values generally between 30 to
50 blows per foot and a natural moisture
content between 13% to 21%.
The Empress sand extends to elevation
630.0m +/- and is comprised of two main
sub-strata. The first is an upper layer lo-
cated between 645 and 647m of elevation
and has a natural moisture content ranging
between 6% and 20%. The second layer, lo-
cated below 645m elevation, is composed
of dense to very dense sand. This second
layer has SPT values that are generally
higher than 40 blows per foot with natural
moisture content between 3% and 7%.
The upper sands layer, located between
645 and 647m of elevation, was of partic-
ular interest to the design-build team. A
slope failure occurred at the site in 1971
following the 1968 slope cutting for the
original construction of the Whitemud
freeway. A previous geotechnical investiga-
tion determined the slope failure was
caused by the stress reduction in the back-
slope soils resulting from a 24m high
2H:1V cut into the original ravine slope.
Following the landslide, the slope was sta-
bilized by the installation of a two-tiered
bin wall at the toe of the slope seven to
eight metres high with a 3H:1V regrading
of the hillside. Following its reconstruc-
tion, on-going inclinometer monitoring by
the City of Edmonton indicated the pres-
ence of shear movements at the elevation
of this upper sand layer at a rate of about
2mm/year. The inclinometer readings were
taken from 1984 to 2004, the year the in-
clinometers were damaged.
Concerns with Original
Retaining Wall Design
The expansion of the road required the
removal of the two-tiered bin walls that
were installed following the 1971 slide.
The new permanent retaining wall had to
be installed further up slope from the orig-
inal bin wall location. To improve slope
stability, the new retaining wall was re-
quired to penetrate the historical failure
plane in the upper sand layer and anchor
into the dense sands below. The tendered
retaining wall design used a secant pile
arch wall, consisting of 14 overlapping
arches, varying in their exposed height
above the final grade from 3.0 to 7.9m.
This initial retaining wall design consisted
of 600mm (24 inch) and 900mm (36 inch)
interlocking secant piles, with a “tripod”
arrangement of 1200mm (48 inch) secant
FOUNDATION DRILLING September/October 2009 Page 3
(Continued on page 4)
RE-DESIGN Contd.
Figure 2: 3D Rendering of Final Wall.
Figure 3: Elevation View of Tendered Whitemud Drive
Retaining Wall.
4. piles extending in front of the arch over-
laps, as shown in Figure 3. The secant pile
concrete strength was specified at 30 MPa
(4400 psi) with the deepest piles extend-
ing nearly 25m (80 ft.) below the existing
grade. A special curved concrete cap was
required to improve both the appearance
and the structural integrity of the wall, as
the secants alone had no lateral reinforce-
ment.
The tendered design presented several
constructability challenges to HCM. First,
maintaining the stability of the hillside and
equipment and worker safety with the as-
tendered design would have been difficult
due to the imported-fill platforms and
heavy equipment required to construct the
interlocking secants, especially given the
sliding history of the slope. Temporary
shoring was added to the original contract
scope as an addendum to accommodate
the fill platforms and would have been sub-
stantial in order to support the equipment
necessary to install the deep secants. Sec-
ondly, the required schedule for comple-
tion of the secant pile installation was nine
months, a figure that HCM estimated
would be exceeded by at least three
months due to the temporary shoring and
confined work areas present on the site.
Thirdly, the interlocking, high-strength se-
cant piles required to 25m design depths
were problematic due to the concrete
strength and severe tender penalties for
any non-interlocked final conditions. Fi-
nally, even with the highest quality stan-
dards met, a lack of control joints in the
design raised concerns about leakage at the
secant joints.
Innovative Solutions in Design
and Construction
The HCM/Isherwood design-build team
proposed an alternative that provided a sim-
ilar final geometry to that of the original de-
sign while providing higher structural in-
tegrity, an improved construction schedule,
and significant cost-savings for the Prime
Contractor. The HCM/Isherwood team de-
livered a solution when no other party
would tender the base design with confi-
dence.
Temporary Shotcrete Shoring
The tight schedule requirements were
addressed by employing temporary shot-
crete shoring. The shotcrete shoring was
advantageous for two reasons: First, it
could commence without any low slope
shoring, greatly improving hillside stabil-
ity. Second, excavation could commence si-
multaneously with the temporary shoring
installation, as opposed to waiting for pil-
ing to be completed, greatly improving the
construction schedule.
The alignment of the temporary shot-
crete wall was established to allow two-
sided forming with 1200mm (4 ft.) of
free-draining backfill material. This elimi-
nated the need for the concrete swale orig-
inally designed behind the top of the wall.
The base of the shotcrete wall would be
stepped towards the low slope direction to
act as a backside form and create a one-
sided forming solution for the foundation
of the permanent structure, as shown in
Figure 4. The temporary shoring system
employed R38 hollow bar micropiles sup-
plied by Dywidag Systems International
(DSI)* to reinforce the earth mass behind
the 150mm (6 inch) thick shotcrete face.
FOUNDATION DRILLING September/October 2009Page 4
RE-DESIGN Contd.
(Continued on page 5)
Figure 4: Typical Arch Section.
Figure 5: PLAXIS Modeling of Stress Distribution.
5. Vertical R38 micropiles were used to add
vertical capacity to the shotcrete face and
to act as layout points for the irregular
geometry of the arches. Longer, 1500kN
(340 kip) capacity, T76S (DSI) tension mi-
cropiles were installed at a 35- degree in-
clination to actively anchor the reinforced
soil mass to the underlying dense sands.
The tension micropiles are permanent ele-
ments used in both the upper temporary
shotcrete wall and the permanent ring
footing.
The stressing and pre-loading program
designed by HCM/Isherwood used both
the active resistance of a pre-loaded mi-
cropile system and a passively reinforced
soil-nail wall with 50% of the calculated de-
sign load locked in to avoid any tendency for
vertical settlement of the temporary wall.
Permanent Retaining Wall
HCM/Isherwood designed the perma-
nent retaining wall alternative in partner-
ship with Peter Sheffield and Associates,
one of Canada’s leading structural engi-
neers. The final wall would consist of a
600mm (24 inch) thick cast-in-place arch
that would maintain the tripod concept
with one distinct difference: the new de-
sign would implement construction joints
in between arch pairs to allow the loading
of the tripods to occur inside of each arch
as a “horseshoe” instead of the outside of
the overlapping arches as originally de-
signed. This approach would improve
crack control in the extreme freeze-thaw
environment of Edmonton. Maintenance
on the wall would be simplified as arches
acting individually could be repaired with
fewer complications should problems arise
in the future. The lateral reinforcement of
a cast-in-place wall improved the structural
integrity of the wall, eliminating the struc-
tural requirement of the wall cap. Addi-
tionally, 600mm (30 inch) drainage tubes
positioned below the shotcrete wall and
behind the permanent structure would
prevent the build-up of hydrostatic pres-
sure from ground water.
The exposed portion of the wall would
be built upon a curved footing that would
step down to match the final 3H:1V slope
profile in front of the wall. Tension mi-
cropiles, to be installed at 35 degrees, were
designed to mitigate total deflection and
potential creep of the final structure, as
well as tie the ring footing into the dense
sands 9m below. 1200mm diameter, heav-
ily reinforced concrete caissons developed
into the dense sands would support the
ring footing. The sands were deemed by
the HCM/Isherwood design-build team to
be more consistent than the bedrock and
capable of high capacity at low strain. The
FOUNDATION DRILLING September/October 2009 Page 5
Figure 6: Excavator-mounted TEI Drill.
Figure 7: Mid-December Inclinometer Plot.
(Continued on page 6)
RE-DESIGN Contd.
6. arches, anchored in the dense sands, would
transfer active soils loads to the concrete
piles pivoting between the upper and lower
extremes of the arch and tripod support.
The arches were designed with seven to
nine caissons each and assumed a non-
soil-flow rheology between the piles. Piles
were spaced on average at two pile diame-
ters. Assuming a conservative N value of
two, the design incorporated the mobiliza-
tion of the entire passive resistance of the
soil.
Computer Modeling
and Monitoring
The HCM/Isherwood design-build team
relied on deformation modeling and sub-
sequent construction slope monitoring to
ensure stable performance of the shoring
system and confirm the models and design
parameters. Loading and resultant deflec-
tions for the design were modeled using
standard slope stability analysis (limit-
equilibrium) and the finite element
method to provide guidance for construc-
tion progress and staging. Modeling with
PLAXIS, a finite-element package used to
analyze deformation and stability in geo-
technical applications, enabled Isherwood/-
Sheffield to model the interaction of the
structures and the soil.
The historical behavior of the hillside
slope presented significant risks to the
project team. As such, a monitoring pro-
gram was implemented to provide reliable
information pertaining to shoring per-
formance and the behavior of the suspect
upper sands as excavation proceeded.
Movement data was collected via nine deep
inclinometers installed along the back of
the shotcrete wall to depths of 21m (70 ft.),
extending past the toe elevation of the cais-
sons. The inclinometers were read weekly
to supply valuable movement data on the
excavated slope. Total Station Targets were
also installed on the shotcrete face to mon-
itor real displacements. Employing Peck’s
Observational Method, Isherwood ana-
lyzed the data on an ongoing basis during
construction to verify design assumptions,
compare with deformation modeling re-
sults, monitor shoring performance, and
ensure the safety of workers and the pub-
lic on the Whitemud freeway.
The HCM/Isherwood alternative design
was accepted by the City of Edmonton’s
consulting team and construction began.
Initial Construction
HCM began construction in October
2008 with the installation of vertical R38
micropiles. These elements were installed
between 12m (40 ft.) and 21m (70 ft.)
deep into the dense sands by three TEI
550* drills mounted on Caterpillar 320 ex-
cavators, as shown in Figure 6. The pair-
ing of the drill attachments to the highly
maneuverable excavators facilitated instal-
lation of the verticals on the sloped hillside
and required minimal excavation prior to
drilling. Once verticals were completed,
horizontal R38 anchors were installed at
FOUNDATION DRILLING September/October 2009Page 6
(Continued on page 7)
RE-DESIGN Contd.
Figure 8: Pipe Connection Detail.
Figure 9: Hillside Congestion.
7. 1.5m (5 ft.) spacing. Initially, a panel se-
quence of shotcrete application was em-
ployed to understand how the upper clays
would respond to the excavation. Once it
was apparent the soils were capable of han-
dling ribbon-style excavation, production
was ramped up and subsequent lifts of the
arches were completed one row at a time.
All anchors were spaced in a regular grid
pattern (1.5m by 1.5m), which simplified
layout and helped protect the inclinometer
casings.
Changed Soil Conditions
As excavation advanced to 6m below the
original grade, the inclinometers along the
south half of the wall indicated surpris-
ingly large movements over a short verti-
cal distance near the elevation 645.0m, as
shown in Figure 7. This coincided with
the elevation of the shear movements
measured during the 1971 slide, raising
concerns as the partially excavated geome-
try should have provided a high factor of
safety. A stop excavation order was put in
place for Arches C6 to C14 to allow for
back-calculation of soil-strength parame-
ters as a function of the observed hillside
deformations. Isherwood immediately
began a limit equilibrium analysis based on
the as-built condition. The analysis indi-
cated the soil strength parameters of the
upper sands to be significantly lower than
originally reported in the tender geotech-
nical report. The actual soil strength pa-
rameters of the slope were established
assuming that plasticity had occurred
within the observed movement layer and,
using the limit equilibrium model, deter-
mining what soil strength parameters
would yield a factor of safety of 1.0. The
results of the analysis indicated a signifi-
cant reduction in the internal angle of fric-
tion of the upper clay-seamed sands
between the elevations 645 and 646m. The
available passive resistance of the soil
above this layer was significantly reduced
by the weak layer. As an analogy, the re-
sistance of the clay soils above the weak
layer could be imagined as a block being
pushed on asphalt. Between the elevations
645 and 646 m, it was as if the block was
suddenly being pushed on a surface of ice.
In order to return the factor of safety for
both the temporary shoring and perma-
nent retaining wall to acceptable levels,
four main measures were added to supple-
ment the original design:
• Temporary 750mm (30 inch) caissons
with HP360x152 steel reinforcement were
installed from Arches C6 to C14 before ex-
cavation was allowed to continue.
• Four additional 1200mm structural
caissons were added to the highest arches
in the middle of the wall.
• Ring footings, originally designed
with a combination of R38 and T76 mi-
cropiles to resist lateral movements, were
upgraded to use T76 micropiles through-
out.
• In an effort to maintain the hillside
stability during the temporary shoring in-
stallation, structural caissons were in-
stalled from a grade 1.5m higher than
originally designed.
In short, the strategy was to create sup-
plementary shear-resistance across the de-
veloping slip-surface, which would not be
fully loaded until excavation of the slope
below the wall was completed and the ex-
isting bin walls were removed.
Construction Completion
HCM had to respond to the changed hill-
side stability conditions proactively. De-
spite the partnering approach implemented
by the City of Edmonton, the HCM/Isher-
wood Team was pressured to find solutions
quickly. There were numerous project de-
lays; for example, the construction of the
temporary wall was delayed due to ex-
tended approvals, and the hillside move-
ment in December 2008 stopped the
shotcrete work. These delays, coupled with
hillside stability concerns, resulted in the
caissons being drilled from a higher eleva-
tion and more than half of the shotcrete
work being done concurrently during the
winter months.
HCM innovated a new micropile con-
FOUNDATION DRILLING September/October 2009 Page 7
(Continued on page 8)
RE-DESIGN Contd.
Figure 10: Arch C9 Inclinometer Plot.
8. nection at the onset of winter conditions
to enable soil cutting and shotcrete appli-
cation prior to drilling micropiles. Figure
8 shows a 600kN connection that was de-
veloped and tested to 900kN on the shot-
crete face for the tension piles that were
part of the temporary system.
Caisson construction occurred concur-
rently with rebar detailing, necessitating
drawings to be released on a daily basis.
Designers in Toronto were working over-
time to produce rebar details to maintain
production. Some of the revised reinforce-
ment for the caissons in the highest arches
were 60-35M (1.5 inch) bars with hori-
zontal tie spacing reduced to as low as
75mm (3 inch) in the areas of greatest
loading.
Caissons were installed through the old
failure plane and into the dense sands by
pre-drilling the very stiff upper clay and
then driving 1200mm (48 inch) liners with
an APE 200* on an 80-ton crane. The
dense sands required top head drive rigs
and careful drilling below the liner to
achieve penetration.
HCM added further innovation on the
project by stepping the base of the shot-
crete wall in to act as a back-side form for
the ring footing and to be used as a swale
to carry surface water through the granular
backfill and out from behind the perma-
nent retaining wall via weeping tile. HCM
employed two Casagrande M9* hydraulic
tieback drills to install the high capacity
T76 self-drilling permanent micropiles
prior to footing installation. To minimize
schedule impacts, multiple operations
were run concurrently, which resulted in
high hillside congestion, as shown in Fig-
ure 8.
By working overtime and on weekends,
HCM was able to restore most of the lost
time that resulted from the late start and
the hillside movement delay. The comple-
tion of the project at the end of April 2009
was one month late from what HCM orig-
inally forecasted. The formed wall was
judged sufficient for the final appearance,
which allowed the elimination of the con-
crete cap from the design. This allowed for
the complete restoration of the original
project schedule.
Shoring Performance
At the time of completion, the maximum
movement detected along the shotcrete
wall was 27 mm (1.1 inches). Figure 9
shows the deep-seated movement near el-
evation 645m at Arch C9. The upper tier
of the double bin wall was removed first,
the monitoring observed and then, with all
ring footings in place, the complete low
slope was removed. Performance has
proven to be stable and no creep has been
observed, demonstrating a successful con-
clusion to a logistically difficult and tech-
nically challenging project.
Concluding Remarks
The final project product is visible to
many commuters and the City of Edmon-
ton received a long-term, maintenance-free
product. Figure 10 shows the unique
geometry and aesthetically pleasing design
of the finished structure. The calculation
of the reduced phi angle and soil strength
became a fundamental argument in the
later stages of the project. This presented
disagreements between the design-build
contractor and the owner with respect to
responsibilities for changes in the soil con-
ditions from what was presented in the
tender documents. The matter was delib-
erated as work continued in order to miti-
gate any potential impact on the project
schedule. Test pits dug upon completion of
the slope regrading revealed strain-weak-
ened thin layers of slickensided clay that
were not identified at the time of tender,
improving the case by the contractors for
changed conditions.
The Whitemud project is a unique ex-
ample of a hill stability challenge and sig-
nificant knowledge was gained for future
projects. It is expected that more advanced
technical papers will be tabled in the future
and it is likely that several graduate stu-
dents will proceed with thesis work in the
years following completion.
*Indicates ADSC Members.I
FOUNDATION DRILLING September/October 2009Page 8
RE-DESIGN Contd.
PROJECT TEAM
Shoring Design-Build HCM Contractors Inc.*
Contractor Martin Halliwell, P. Eng., Project Manager
Geoff Jilg, Operations Manager
Jeff Gibbs, Superintendent
Shoring/Retaining Isherwood Associates*
Wall Designer Matthew Janes, P. Eng., Senior Engineer
Mark Spence, P.Eng., Project Manager
Peter Sheffield, P. Eng., Structural Engineer
Monitoring Micro EnGEO Inc.
Mohamed El Habiby, Project Manager
HCM Contractors Inc.*
Brendan Lemieux, Site Engineer
Construction Manager ConCreate USL Ltd.
Stewart Nelson, P. Eng., Project Manager
Borje McKinnon, Operations Manager
Geotechnical Design Thurber Engineering Ltd.*
Robin Tweedie, P.Eng., Project Manager
Linda Bobey, P.Eng., Project Engineer
*Indicates ADSC Members