SlideShare a Scribd company logo
A Re-Design Proves to
be the Best Solution
Whitemud Drive Retaining Wall,
Edmonton, Alberta, Canada
by Martin Halliwell, P. Eng.,
Project Manager, HCM Contractors
Inc. and
Mark Spence, E.I.T., Project Manager,
Isherwood Associates
Project Summary
The City of Edmonton is undertaking a
multi-stage project, scheduled for comple-
tion in late 2010. This includes widening
both Whitemud Drive and the Quesnell
Bridge to ensure the transportation system
is safe and continues to keep pace with
rapid growth in Edmonton. The Quesnell
Bridge is the busiest bridge in Edmonton,
carrying approximately 120,000 vehicles
on an average day. The additional lanes and
widened shoulders will enhance traffic
flow and improve the overall safety of the
road. This project is the first major reha-
bilitation of the
Quesnell Bridge
since its con-
struction in 1967.
The widening
of the road north
of the Quesnell
Bridge is made
possible by a
cast-in-place re-
taining wall con-
structed in front
of a temporary
t i e b a c k / s o i l -
nailed shotcrete
shoring system.
The new retain-
ing wall replaces
a two-tier bin
wall that was in-
stalled in 1972 to
address a previ-
ous hillside fail-
ure. Analysis of
the slope failure
in 1971 gener-
ated soil strength
parameters is-
sued in the ten-
der soil report documents. In the field,
however, this was revealed to be incorrect;
the actual soil strength was found to be
much lower.
The HCM/Isherwood design-build team’s
innovative design for the retaining wall was
proposed to the City of Edmonton as an al-
ternative to the original tender. Figure 1
shows the original design concept: a series
of high-strength, interlocking secant walls to
depths of up to 25 metres (80 ft.), which
raised constructability concerns with bid-
ding contractors. Maintaining the original
concept’s geometry, the alternative wall con-
sists of 14 abutting arches with a total length
of approximately 250m (800 ft.), as shown
in Figure 2. The wall is supported on
COVER FEATURE
FOUNDATION DRILLING September/October 2009Page 2
(Continued on page 3)
The HCM/Isherwood design-
build team’s innovative design
for the retaining wall was pro-
posed to the City of Edmonton
as an alternative to the origi-
nal tender.
The completed shoring wall adjacent to Whitemud Drive.
Figure 1: Tendered Design of the Whitemud Drive Retaining Wall.
1200mm (48 inch) drilled caissons, capped
by robust ring footings that step downward
into the low slope as it approaches White-
mud Drive.
Existing Site Conditions,
Geology and History
Prior to construction, the existing slope
ranged from 19 to 24m high above the
Whitemud Drive’s elevation and ascended
to the roadway at an approximate overall
2H:1V slope. Existing grade was at eleva-
tion 660.0m +/- at the highest points along
the wall. The subsurface geology is com-
posed of fill material overlaying native silty
clay and glacial clay till overlaying Empress
sand to an elevation 630.0m +/- with
bedrock below.
The native silty clay extends to elevation
654.0m +/- and is typically stiff. The Stan-
dard Penetration Test (SPT) results ranged
from nine to 18 blows per foot with a nat-
ural moisture content ranging from 20% to
45%. Slickensides (polished shear surfaces
caused by previous shearing) were noted
to exist between the elevations of 655 and
657m during preliminary geotechnical in-
vestigations. The glacial clay till extends to
elevation 647m +/, is typically very stiff,
with SPT values generally between 30 to
50 blows per foot and a natural moisture
content between 13% to 21%.
The Empress sand extends to elevation
630.0m +/- and is comprised of two main
sub-strata. The first is an upper layer lo-
cated between 645 and 647m of elevation
and has a natural moisture content ranging
between 6% and 20%. The second layer, lo-
cated below 645m elevation, is composed
of dense to very dense sand. This second
layer has SPT values that are generally
higher than 40 blows per foot with natural
moisture content between 3% and 7%.
The upper sands layer, located between
645 and 647m of elevation, was of partic-
ular interest to the design-build team. A
slope failure occurred at the site in 1971
following the 1968 slope cutting for the
original construction of the Whitemud
freeway. A previous geotechnical investiga-
tion determined the slope failure was
caused by the stress reduction in the back-
slope soils resulting from a 24m high
2H:1V cut into the original ravine slope.
Following the landslide, the slope was sta-
bilized by the installation of a two-tiered
bin wall at the toe of the slope seven to
eight metres high with a 3H:1V regrading
of the hillside. Following its reconstruc-
tion, on-going inclinometer monitoring by
the City of Edmonton indicated the pres-
ence of shear movements at the elevation
of this upper sand layer at a rate of about
2mm/year. The inclinometer readings were
taken from 1984 to 2004, the year the in-
clinometers were damaged.
Concerns with Original
Retaining Wall Design
The expansion of the road required the
removal of the two-tiered bin walls that
were installed following the 1971 slide.
The new permanent retaining wall had to
be installed further up slope from the orig-
inal bin wall location. To improve slope
stability, the new retaining wall was re-
quired to penetrate the historical failure
plane in the upper sand layer and anchor
into the dense sands below. The tendered
retaining wall design used a secant pile
arch wall, consisting of 14 overlapping
arches, varying in their exposed height
above the final grade from 3.0 to 7.9m.
This initial retaining wall design consisted
of 600mm (24 inch) and 900mm (36 inch)
interlocking secant piles, with a “tripod”
arrangement of 1200mm (48 inch) secant
FOUNDATION DRILLING September/October 2009 Page 3
(Continued on page 4)
RE-DESIGN Contd.
Figure 2: 3D Rendering of Final Wall.
Figure 3: Elevation View of Tendered Whitemud Drive
Retaining Wall.
piles extending in front of the arch over-
laps, as shown in Figure 3. The secant pile
concrete strength was specified at 30 MPa
(4400 psi) with the deepest piles extend-
ing nearly 25m (80 ft.) below the existing
grade. A special curved concrete cap was
required to improve both the appearance
and the structural integrity of the wall, as
the secants alone had no lateral reinforce-
ment.
The tendered design presented several
constructability challenges to HCM. First,
maintaining the stability of the hillside and
equipment and worker safety with the as-
tendered design would have been difficult
due to the imported-fill platforms and
heavy equipment required to construct the
interlocking secants, especially given the
sliding history of the slope. Temporary
shoring was added to the original contract
scope as an addendum to accommodate
the fill platforms and would have been sub-
stantial in order to support the equipment
necessary to install the deep secants. Sec-
ondly, the required schedule for comple-
tion of the secant pile installation was nine
months, a figure that HCM estimated
would be exceeded by at least three
months due to the temporary shoring and
confined work areas present on the site.
Thirdly, the interlocking, high-strength se-
cant piles required to 25m design depths
were problematic due to the concrete
strength and severe tender penalties for
any non-interlocked final conditions. Fi-
nally, even with the highest quality stan-
dards met, a lack of control joints in the
design raised concerns about leakage at the
secant joints.
Innovative Solutions in Design
and Construction
The HCM/Isherwood design-build team
proposed an alternative that provided a sim-
ilar final geometry to that of the original de-
sign while providing higher structural in-
tegrity, an improved construction schedule,
and significant cost-savings for the Prime
Contractor. The HCM/Isherwood team de-
livered a solution when no other party
would tender the base design with confi-
dence.
Temporary Shotcrete Shoring
The tight schedule requirements were
addressed by employing temporary shot-
crete shoring. The shotcrete shoring was
advantageous for two reasons: First, it
could commence without any low slope
shoring, greatly improving hillside stabil-
ity. Second, excavation could commence si-
multaneously with the temporary shoring
installation, as opposed to waiting for pil-
ing to be completed, greatly improving the
construction schedule.
The alignment of the temporary shot-
crete wall was established to allow two-
sided forming with 1200mm (4 ft.) of
free-draining backfill material. This elimi-
nated the need for the concrete swale orig-
inally designed behind the top of the wall.
The base of the shotcrete wall would be
stepped towards the low slope direction to
act as a backside form and create a one-
sided forming solution for the foundation
of the permanent structure, as shown in
Figure 4. The temporary shoring system
employed R38 hollow bar micropiles sup-
plied by Dywidag Systems International
(DSI)* to reinforce the earth mass behind
the 150mm (6 inch) thick shotcrete face.
FOUNDATION DRILLING September/October 2009Page 4
RE-DESIGN Contd.
(Continued on page 5)
Figure 4: Typical Arch Section.
Figure 5: PLAXIS Modeling of Stress Distribution.
Vertical R38 micropiles were used to add
vertical capacity to the shotcrete face and
to act as layout points for the irregular
geometry of the arches. Longer, 1500kN
(340 kip) capacity, T76S (DSI) tension mi-
cropiles were installed at a 35- degree in-
clination to actively anchor the reinforced
soil mass to the underlying dense sands.
The tension micropiles are permanent ele-
ments used in both the upper temporary
shotcrete wall and the permanent ring
footing.
The stressing and pre-loading program
designed by HCM/Isherwood used both
the active resistance of a pre-loaded mi-
cropile system and a passively reinforced
soil-nail wall with 50% of the calculated de-
sign load locked in to avoid any tendency for
vertical settlement of the temporary wall.
Permanent Retaining Wall
HCM/Isherwood designed the perma-
nent retaining wall alternative in partner-
ship with Peter Sheffield and Associates,
one of Canada’s leading structural engi-
neers. The final wall would consist of a
600mm (24 inch) thick cast-in-place arch
that would maintain the tripod concept
with one distinct difference: the new de-
sign would implement construction joints
in between arch pairs to allow the loading
of the tripods to occur inside of each arch
as a “horseshoe” instead of the outside of
the overlapping arches as originally de-
signed. This approach would improve
crack control in the extreme freeze-thaw
environment of Edmonton. Maintenance
on the wall would be simplified as arches
acting individually could be repaired with
fewer complications should problems arise
in the future. The lateral reinforcement of
a cast-in-place wall improved the structural
integrity of the wall, eliminating the struc-
tural requirement of the wall cap. Addi-
tionally, 600mm (30 inch) drainage tubes
positioned below the shotcrete wall and
behind the permanent structure would
prevent the build-up of hydrostatic pres-
sure from ground water.
The exposed portion of the wall would
be built upon a curved footing that would
step down to match the final 3H:1V slope
profile in front of the wall. Tension mi-
cropiles, to be installed at 35 degrees, were
designed to mitigate total deflection and
potential creep of the final structure, as
well as tie the ring footing into the dense
sands 9m below. 1200mm diameter, heav-
ily reinforced concrete caissons developed
into the dense sands would support the
ring footing. The sands were deemed by
the HCM/Isherwood design-build team to
be more consistent than the bedrock and
capable of high capacity at low strain. The
FOUNDATION DRILLING September/October 2009 Page 5
Figure 6: Excavator-mounted TEI Drill.
Figure 7: Mid-December Inclinometer Plot.
(Continued on page 6)
RE-DESIGN Contd.
arches, anchored in the dense sands, would
transfer active soils loads to the concrete
piles pivoting between the upper and lower
extremes of the arch and tripod support.
The arches were designed with seven to
nine caissons each and assumed a non-
soil-flow rheology between the piles. Piles
were spaced on average at two pile diame-
ters. Assuming a conservative N value of
two, the design incorporated the mobiliza-
tion of the entire passive resistance of the
soil.
Computer Modeling
and Monitoring
The HCM/Isherwood design-build team
relied on deformation modeling and sub-
sequent construction slope monitoring to
ensure stable performance of the shoring
system and confirm the models and design
parameters. Loading and resultant deflec-
tions for the design were modeled using
standard slope stability analysis (limit-
equilibrium) and the finite element
method to provide guidance for construc-
tion progress and staging. Modeling with
PLAXIS, a finite-element package used to
analyze deformation and stability in geo-
technical applications, enabled Isherwood/-
Sheffield to model the interaction of the
structures and the soil.
The historical behavior of the hillside
slope presented significant risks to the
project team. As such, a monitoring pro-
gram was implemented to provide reliable
information pertaining to shoring per-
formance and the behavior of the suspect
upper sands as excavation proceeded.
Movement data was collected via nine deep
inclinometers installed along the back of
the shotcrete wall to depths of 21m (70 ft.),
extending past the toe elevation of the cais-
sons. The inclinometers were read weekly
to supply valuable movement data on the
excavated slope. Total Station Targets were
also installed on the shotcrete face to mon-
itor real displacements. Employing Peck’s
Observational Method, Isherwood ana-
lyzed the data on an ongoing basis during
construction to verify design assumptions,
compare with deformation modeling re-
sults, monitor shoring performance, and
ensure the safety of workers and the pub-
lic on the Whitemud freeway.
The HCM/Isherwood alternative design
was accepted by the City of Edmonton’s
consulting team and construction began.
Initial Construction
HCM began construction in October
2008 with the installation of vertical R38
micropiles. These elements were installed
between 12m (40 ft.) and 21m (70 ft.)
deep into the dense sands by three TEI
550* drills mounted on Caterpillar 320 ex-
cavators, as shown in Figure 6. The pair-
ing of the drill attachments to the highly
maneuverable excavators facilitated instal-
lation of the verticals on the sloped hillside
and required minimal excavation prior to
drilling. Once verticals were completed,
horizontal R38 anchors were installed at
FOUNDATION DRILLING September/October 2009Page 6
(Continued on page 7)
RE-DESIGN Contd.
Figure 8: Pipe Connection Detail.
Figure 9: Hillside Congestion.
1.5m (5 ft.) spacing. Initially, a panel se-
quence of shotcrete application was em-
ployed to understand how the upper clays
would respond to the excavation. Once it
was apparent the soils were capable of han-
dling ribbon-style excavation, production
was ramped up and subsequent lifts of the
arches were completed one row at a time.
All anchors were spaced in a regular grid
pattern (1.5m by 1.5m), which simplified
layout and helped protect the inclinometer
casings.
Changed Soil Conditions
As excavation advanced to 6m below the
original grade, the inclinometers along the
south half of the wall indicated surpris-
ingly large movements over a short verti-
cal distance near the elevation 645.0m, as
shown in Figure 7. This coincided with
the elevation of the shear movements
measured during the 1971 slide, raising
concerns as the partially excavated geome-
try should have provided a high factor of
safety. A stop excavation order was put in
place for Arches C6 to C14 to allow for
back-calculation of soil-strength parame-
ters as a function of the observed hillside
deformations. Isherwood immediately
began a limit equilibrium analysis based on
the as-built condition. The analysis indi-
cated the soil strength parameters of the
upper sands to be significantly lower than
originally reported in the tender geotech-
nical report. The actual soil strength pa-
rameters of the slope were established
assuming that plasticity had occurred
within the observed movement layer and,
using the limit equilibrium model, deter-
mining what soil strength parameters
would yield a factor of safety of 1.0. The
results of the analysis indicated a signifi-
cant reduction in the internal angle of fric-
tion of the upper clay-seamed sands
between the elevations 645 and 646m. The
available passive resistance of the soil
above this layer was significantly reduced
by the weak layer. As an analogy, the re-
sistance of the clay soils above the weak
layer could be imagined as a block being
pushed on asphalt. Between the elevations
645 and 646 m, it was as if the block was
suddenly being pushed on a surface of ice.
In order to return the factor of safety for
both the temporary shoring and perma-
nent retaining wall to acceptable levels,
four main measures were added to supple-
ment the original design:
• Temporary 750mm (30 inch) caissons
with HP360x152 steel reinforcement were
installed from Arches C6 to C14 before ex-
cavation was allowed to continue.
• Four additional 1200mm structural
caissons were added to the highest arches
in the middle of the wall.
• Ring footings, originally designed
with a combination of R38 and T76 mi-
cropiles to resist lateral movements, were
upgraded to use T76 micropiles through-
out.
• In an effort to maintain the hillside
stability during the temporary shoring in-
stallation, structural caissons were in-
stalled from a grade 1.5m higher than
originally designed.
In short, the strategy was to create sup-
plementary shear-resistance across the de-
veloping slip-surface, which would not be
fully loaded until excavation of the slope
below the wall was completed and the ex-
isting bin walls were removed.
Construction Completion
HCM had to respond to the changed hill-
side stability conditions proactively. De-
spite the partnering approach implemented
by the City of Edmonton, the HCM/Isher-
wood Team was pressured to find solutions
quickly. There were numerous project de-
lays; for example, the construction of the
temporary wall was delayed due to ex-
tended approvals, and the hillside move-
ment in December 2008 stopped the
shotcrete work. These delays, coupled with
hillside stability concerns, resulted in the
caissons being drilled from a higher eleva-
tion and more than half of the shotcrete
work being done concurrently during the
winter months.
HCM innovated a new micropile con-
FOUNDATION DRILLING September/October 2009 Page 7
(Continued on page 8)
RE-DESIGN Contd.
Figure 10: Arch C9 Inclinometer Plot.
nection at the onset of winter conditions
to enable soil cutting and shotcrete appli-
cation prior to drilling micropiles. Figure
8 shows a 600kN connection that was de-
veloped and tested to 900kN on the shot-
crete face for the tension piles that were
part of the temporary system.
Caisson construction occurred concur-
rently with rebar detailing, necessitating
drawings to be released on a daily basis.
Designers in Toronto were working over-
time to produce rebar details to maintain
production. Some of the revised reinforce-
ment for the caissons in the highest arches
were 60-35M (1.5 inch) bars with hori-
zontal tie spacing reduced to as low as
75mm (3 inch) in the areas of greatest
loading.
Caissons were installed through the old
failure plane and into the dense sands by
pre-drilling the very stiff upper clay and
then driving 1200mm (48 inch) liners with
an APE 200* on an 80-ton crane. The
dense sands required top head drive rigs
and careful drilling below the liner to
achieve penetration.
HCM added further innovation on the
project by stepping the base of the shot-
crete wall in to act as a back-side form for
the ring footing and to be used as a swale
to carry surface water through the granular
backfill and out from behind the perma-
nent retaining wall via weeping tile. HCM
employed two Casagrande M9* hydraulic
tieback drills to install the high capacity
T76 self-drilling permanent micropiles
prior to footing installation. To minimize
schedule impacts, multiple operations
were run concurrently, which resulted in
high hillside congestion, as shown in Fig-
ure 8.
By working overtime and on weekends,
HCM was able to restore most of the lost
time that resulted from the late start and
the hillside movement delay. The comple-
tion of the project at the end of April 2009
was one month late from what HCM orig-
inally forecasted. The formed wall was
judged sufficient for the final appearance,
which allowed the elimination of the con-
crete cap from the design. This allowed for
the complete restoration of the original
project schedule.
Shoring Performance
At the time of completion, the maximum
movement detected along the shotcrete
wall was 27 mm (1.1 inches). Figure 9
shows the deep-seated movement near el-
evation 645m at Arch C9. The upper tier
of the double bin wall was removed first,
the monitoring observed and then, with all
ring footings in place, the complete low
slope was removed. Performance has
proven to be stable and no creep has been
observed, demonstrating a successful con-
clusion to a logistically difficult and tech-
nically challenging project.
Concluding Remarks
The final project product is visible to
many commuters and the City of Edmon-
ton received a long-term, maintenance-free
product. Figure 10 shows the unique
geometry and aesthetically pleasing design
of the finished structure. The calculation
of the reduced phi angle and soil strength
became a fundamental argument in the
later stages of the project. This presented
disagreements between the design-build
contractor and the owner with respect to
responsibilities for changes in the soil con-
ditions from what was presented in the
tender documents. The matter was delib-
erated as work continued in order to miti-
gate any potential impact on the project
schedule. Test pits dug upon completion of
the slope regrading revealed strain-weak-
ened thin layers of slickensided clay that
were not identified at the time of tender,
improving the case by the contractors for
changed conditions.
The Whitemud project is a unique ex-
ample of a hill stability challenge and sig-
nificant knowledge was gained for future
projects. It is expected that more advanced
technical papers will be tabled in the future
and it is likely that several graduate stu-
dents will proceed with thesis work in the
years following completion.
*Indicates ADSC Members.I
FOUNDATION DRILLING September/October 2009Page 8
RE-DESIGN Contd.
PROJECT TEAM
Shoring Design-Build HCM Contractors Inc.*
Contractor Martin Halliwell, P. Eng., Project Manager
Geoff Jilg, Operations Manager
Jeff Gibbs, Superintendent
Shoring/Retaining Isherwood Associates*
Wall Designer Matthew Janes, P. Eng., Senior Engineer
Mark Spence, P.Eng., Project Manager
Peter Sheffield, P. Eng., Structural Engineer
Monitoring Micro EnGEO Inc.
Mohamed El Habiby, Project Manager
HCM Contractors Inc.*
Brendan Lemieux, Site Engineer
Construction Manager ConCreate USL Ltd.
Stewart Nelson, P. Eng., Project Manager
Borje McKinnon, Operations Manager
Geotechnical Design Thurber Engineering Ltd.*
Robin Tweedie, P.Eng., Project Manager
Linda Bobey, P.Eng., Project Engineer
*Indicates ADSC Members

More Related Content

What's hot

Civil Engineering
Civil EngineeringCivil Engineering
Civil Engineering
Assad Khattak
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 
Top down construction
Top down constructionTop down construction
Top down construction
ANUPAM TIWARI
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
Latif Hyder Wadho
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Chapter 10 structure construction
Chapter 10  structure constructionChapter 10  structure construction
Chapter 10 structure construction
mohdasrimohdhasim
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
vietcgxd
 
Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)
Ahmed Towfeequllah Siddiqui
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
Sai Towers P Ltd.
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
Riaz Zalil
 
Top down construction presentation
Top down construction presentationTop down construction presentation
Top down construction presentation
HERITAGE INFRASPACE INDIA PRIVATE LIMITED
 
Nebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementNebraska Precast Concrete Pavement
Nebraska Precast Concrete Pavement
Jill Reeves
 
prevention of flood using reataining wall
prevention of flood using reataining wallprevention of flood using reataining wall
prevention of flood using reataining wall
tp jayamohan
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
Rutting In Flexible Pavement ppt
Rutting In Flexible Pavement pptRutting In Flexible Pavement ppt
Rutting In Flexible Pavement ppt
PrashantHangal
 
Kissner Paving - Brief Introduction About Pavement Design
Kissner Paving - Brief Introduction About Pavement Design Kissner Paving - Brief Introduction About Pavement Design
Kissner Paving - Brief Introduction About Pavement Design
Kissner Paving
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 

What's hot (20)

Civil Engineering
Civil EngineeringCivil Engineering
Civil Engineering
 
Pavement design
Pavement designPavement design
Pavement design
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Chapter 10 structure construction
Chapter 10  structure constructionChapter 10  structure construction
Chapter 10 structure construction
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)Design of a rigid pavement (jpcp & crcp)
Design of a rigid pavement (jpcp & crcp)
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
Top down construction presentation
Top down construction presentationTop down construction presentation
Top down construction presentation
 
Nebraska Precast Concrete Pavement
Nebraska Precast Concrete PavementNebraska Precast Concrete Pavement
Nebraska Precast Concrete Pavement
 
prevention of flood using reataining wall
prevention of flood using reataining wallprevention of flood using reataining wall
prevention of flood using reataining wall
 
S7
S7S7
S7
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Rutting In Flexible Pavement ppt
Rutting In Flexible Pavement pptRutting In Flexible Pavement ppt
Rutting In Flexible Pavement ppt
 
Kissner Paving - Brief Introduction About Pavement Design
Kissner Paving - Brief Introduction About Pavement Design Kissner Paving - Brief Introduction About Pavement Design
Kissner Paving - Brief Introduction About Pavement Design
 
Auckland
AucklandAuckland
Auckland
 
1115
11151115
1115
 
Pavement design
Pavement designPavement design
Pavement design
 

Viewers also liked

Port of oakland berths 57 58
Port of oakland berths 57   58Port of oakland berths 57   58
Port of oakland berths 57 58
Jim McMullan
 
Review of Analysis of Retaining Wall Under Static and Seismic Loading
Review of Analysis of Retaining Wall Under Static and Seismic LoadingReview of Analysis of Retaining Wall Under Static and Seismic Loading
Review of Analysis of Retaining Wall Under Static and Seismic Loading
ijsrd.com
 
Nchrp rpt 611-seismic analysis and design of retaining walls
Nchrp rpt 611-seismic analysis and design of retaining wallsNchrp rpt 611-seismic analysis and design of retaining walls
Nchrp rpt 611-seismic analysis and design of retaining walls
Jose Carlos Calisto da Silva
 
Sachpazis: Sloped rear face retaining wall example
Sachpazis: Sloped rear face retaining wall exampleSachpazis: Sloped rear face retaining wall example
Sachpazis: Sloped rear face retaining wall example
Dr.Costas Sachpazis
 
Anchors rock anchors
Anchors rock anchorsAnchors rock anchors
Anchors rock anchors
Dr Fereidoun Dejahang
 
Reinforced and prestressed concrete kong & evans
Reinforced and prestressed concrete   kong & evansReinforced and prestressed concrete   kong & evans
Reinforced and prestressed concrete kong & evans
bridemcdamian
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
Ravi Savani
 
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
Dr.Costas Sachpazis
 

Viewers also liked (8)

Port of oakland berths 57 58
Port of oakland berths 57   58Port of oakland berths 57   58
Port of oakland berths 57 58
 
Review of Analysis of Retaining Wall Under Static and Seismic Loading
Review of Analysis of Retaining Wall Under Static and Seismic LoadingReview of Analysis of Retaining Wall Under Static and Seismic Loading
Review of Analysis of Retaining Wall Under Static and Seismic Loading
 
Nchrp rpt 611-seismic analysis and design of retaining walls
Nchrp rpt 611-seismic analysis and design of retaining wallsNchrp rpt 611-seismic analysis and design of retaining walls
Nchrp rpt 611-seismic analysis and design of retaining walls
 
Sachpazis: Sloped rear face retaining wall example
Sachpazis: Sloped rear face retaining wall exampleSachpazis: Sloped rear face retaining wall example
Sachpazis: Sloped rear face retaining wall example
 
Anchors rock anchors
Anchors rock anchorsAnchors rock anchors
Anchors rock anchors
 
Reinforced and prestressed concrete kong & evans
Reinforced and prestressed concrete   kong & evansReinforced and prestressed concrete   kong & evans
Reinforced and prestressed concrete kong & evans
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
Sachpazis_Pile Analysis & Design example According to EN 1997-1_2004_March-2017
 

Similar to Whitemud Drive Retaining Wall

Burj al arab
Burj al arabBurj al arab
Burj al arab
Rajat Nainwal
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal reportConor Meaney
 
Structural strengthening Westfield
Structural strengthening WestfieldStructural strengthening Westfield
Structural strengthening Westfield
rgaskill
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1
Tensar
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Tonyamis
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
ShahidAmeen10
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
Miklos Peller, Sr.
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
IRJET Journal
 
Project
ProjectProject
Project
Sallim Abdi
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
Srinivasulu Srinu
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDDean Bassett
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
SachinHM14
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
Dr Mazin Alhamrany
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
Onur Tuncay
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
SaurabhSingh20590
 

Similar to Whitemud Drive Retaining Wall (20)

Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
Structural strengthening Westfield
Structural strengthening WestfieldStructural strengthening Westfield
Structural strengthening Westfield
 
Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1Gen geot cs_sscanada_16.1
Gen geot cs_sscanada_16.1
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
 
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptxMECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
MECHANICALLY STABILIZED EARTH WALLS AND REINFORCED SOIL SLOPES (1).pptx
 
Ground Treatment
Ground TreatmentGround Treatment
Ground Treatment
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Project
ProjectProject
Project
 
fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHED
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
State of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical DesignState of the Art and Practice Geotechnical Design
State of the Art and Practice Geotechnical Design
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
PROJECT
PROJECTPROJECT
PROJECT
 

More from Jim McMullan

Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
Jim McMullan
 
Rock Excavation
Rock ExcavationRock Excavation
Rock Excavation
Jim McMullan
 
Driven Pipe Pile Installation
Driven Pipe Pile InstallationDriven Pipe Pile Installation
Driven Pipe Pile Installation
Jim McMullan
 
Shotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation SupportShotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation Support
Jim McMullan
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
Jim McMullan
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
Jim McMullan
 
Precast over Structural Steel Bridge
Precast over Structural Steel BridgePrecast over Structural Steel Bridge
Precast over Structural Steel Bridge
Jim McMullan
 
Retaining Wall
Retaining WallRetaining Wall
Retaining Wall
Jim McMullan
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket Piling
Jim McMullan
 
Vibro Replacement Ground Treatment
Vibro Replacement Ground TreatmentVibro Replacement Ground Treatment
Vibro Replacement Ground Treatment
Jim McMullan
 
Marine Battered Pile Installation
Marine Battered Pile InstallationMarine Battered Pile Installation
Marine Battered Pile Installation
Jim McMullan
 
Triple Axle Deep Soil Mixing
Triple Axle Deep Soil MixingTriple Axle Deep Soil Mixing
Triple Axle Deep Soil Mixing
Jim McMullan
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
Jim McMullan
 
Deep Soil Mixing
Deep Soil MixingDeep Soil Mixing
Deep Soil Mixing
Jim McMullan
 
Deep Soil Mix Grout Plants
Deep Soil Mix Grout PlantsDeep Soil Mix Grout Plants
Deep Soil Mix Grout Plants
Jim McMullan
 
Marine Piling
Marine PilingMarine Piling
Marine Piling
Jim McMullan
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining Wall
Jim McMullan
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
Jim McMullan
 
Excavation Support
Excavation SupportExcavation Support
Excavation Support
Jim McMullan
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
Jim McMullan
 

More from Jim McMullan (20)

Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Rock Excavation
Rock ExcavationRock Excavation
Rock Excavation
 
Driven Pipe Pile Installation
Driven Pipe Pile InstallationDriven Pipe Pile Installation
Driven Pipe Pile Installation
 
Shotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation SupportShotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation Support
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 
Precast over Structural Steel Bridge
Precast over Structural Steel BridgePrecast over Structural Steel Bridge
Precast over Structural Steel Bridge
 
Retaining Wall
Retaining WallRetaining Wall
Retaining Wall
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket Piling
 
Vibro Replacement Ground Treatment
Vibro Replacement Ground TreatmentVibro Replacement Ground Treatment
Vibro Replacement Ground Treatment
 
Marine Battered Pile Installation
Marine Battered Pile InstallationMarine Battered Pile Installation
Marine Battered Pile Installation
 
Triple Axle Deep Soil Mixing
Triple Axle Deep Soil MixingTriple Axle Deep Soil Mixing
Triple Axle Deep Soil Mixing
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
 
Deep Soil Mixing
Deep Soil MixingDeep Soil Mixing
Deep Soil Mixing
 
Deep Soil Mix Grout Plants
Deep Soil Mix Grout PlantsDeep Soil Mix Grout Plants
Deep Soil Mix Grout Plants
 
Marine Piling
Marine PilingMarine Piling
Marine Piling
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining Wall
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 
Excavation Support
Excavation SupportExcavation Support
Excavation Support
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 

Whitemud Drive Retaining Wall

  • 1.
  • 2. A Re-Design Proves to be the Best Solution Whitemud Drive Retaining Wall, Edmonton, Alberta, Canada by Martin Halliwell, P. Eng., Project Manager, HCM Contractors Inc. and Mark Spence, E.I.T., Project Manager, Isherwood Associates Project Summary The City of Edmonton is undertaking a multi-stage project, scheduled for comple- tion in late 2010. This includes widening both Whitemud Drive and the Quesnell Bridge to ensure the transportation system is safe and continues to keep pace with rapid growth in Edmonton. The Quesnell Bridge is the busiest bridge in Edmonton, carrying approximately 120,000 vehicles on an average day. The additional lanes and widened shoulders will enhance traffic flow and improve the overall safety of the road. This project is the first major reha- bilitation of the Quesnell Bridge since its con- struction in 1967. The widening of the road north of the Quesnell Bridge is made possible by a cast-in-place re- taining wall con- structed in front of a temporary t i e b a c k / s o i l - nailed shotcrete shoring system. The new retain- ing wall replaces a two-tier bin wall that was in- stalled in 1972 to address a previ- ous hillside fail- ure. Analysis of the slope failure in 1971 gener- ated soil strength parameters is- sued in the ten- der soil report documents. In the field, however, this was revealed to be incorrect; the actual soil strength was found to be much lower. The HCM/Isherwood design-build team’s innovative design for the retaining wall was proposed to the City of Edmonton as an al- ternative to the original tender. Figure 1 shows the original design concept: a series of high-strength, interlocking secant walls to depths of up to 25 metres (80 ft.), which raised constructability concerns with bid- ding contractors. Maintaining the original concept’s geometry, the alternative wall con- sists of 14 abutting arches with a total length of approximately 250m (800 ft.), as shown in Figure 2. The wall is supported on COVER FEATURE FOUNDATION DRILLING September/October 2009Page 2 (Continued on page 3) The HCM/Isherwood design- build team’s innovative design for the retaining wall was pro- posed to the City of Edmonton as an alternative to the origi- nal tender. The completed shoring wall adjacent to Whitemud Drive. Figure 1: Tendered Design of the Whitemud Drive Retaining Wall.
  • 3. 1200mm (48 inch) drilled caissons, capped by robust ring footings that step downward into the low slope as it approaches White- mud Drive. Existing Site Conditions, Geology and History Prior to construction, the existing slope ranged from 19 to 24m high above the Whitemud Drive’s elevation and ascended to the roadway at an approximate overall 2H:1V slope. Existing grade was at eleva- tion 660.0m +/- at the highest points along the wall. The subsurface geology is com- posed of fill material overlaying native silty clay and glacial clay till overlaying Empress sand to an elevation 630.0m +/- with bedrock below. The native silty clay extends to elevation 654.0m +/- and is typically stiff. The Stan- dard Penetration Test (SPT) results ranged from nine to 18 blows per foot with a nat- ural moisture content ranging from 20% to 45%. Slickensides (polished shear surfaces caused by previous shearing) were noted to exist between the elevations of 655 and 657m during preliminary geotechnical in- vestigations. The glacial clay till extends to elevation 647m +/, is typically very stiff, with SPT values generally between 30 to 50 blows per foot and a natural moisture content between 13% to 21%. The Empress sand extends to elevation 630.0m +/- and is comprised of two main sub-strata. The first is an upper layer lo- cated between 645 and 647m of elevation and has a natural moisture content ranging between 6% and 20%. The second layer, lo- cated below 645m elevation, is composed of dense to very dense sand. This second layer has SPT values that are generally higher than 40 blows per foot with natural moisture content between 3% and 7%. The upper sands layer, located between 645 and 647m of elevation, was of partic- ular interest to the design-build team. A slope failure occurred at the site in 1971 following the 1968 slope cutting for the original construction of the Whitemud freeway. A previous geotechnical investiga- tion determined the slope failure was caused by the stress reduction in the back- slope soils resulting from a 24m high 2H:1V cut into the original ravine slope. Following the landslide, the slope was sta- bilized by the installation of a two-tiered bin wall at the toe of the slope seven to eight metres high with a 3H:1V regrading of the hillside. Following its reconstruc- tion, on-going inclinometer monitoring by the City of Edmonton indicated the pres- ence of shear movements at the elevation of this upper sand layer at a rate of about 2mm/year. The inclinometer readings were taken from 1984 to 2004, the year the in- clinometers were damaged. Concerns with Original Retaining Wall Design The expansion of the road required the removal of the two-tiered bin walls that were installed following the 1971 slide. The new permanent retaining wall had to be installed further up slope from the orig- inal bin wall location. To improve slope stability, the new retaining wall was re- quired to penetrate the historical failure plane in the upper sand layer and anchor into the dense sands below. The tendered retaining wall design used a secant pile arch wall, consisting of 14 overlapping arches, varying in their exposed height above the final grade from 3.0 to 7.9m. This initial retaining wall design consisted of 600mm (24 inch) and 900mm (36 inch) interlocking secant piles, with a “tripod” arrangement of 1200mm (48 inch) secant FOUNDATION DRILLING September/October 2009 Page 3 (Continued on page 4) RE-DESIGN Contd. Figure 2: 3D Rendering of Final Wall. Figure 3: Elevation View of Tendered Whitemud Drive Retaining Wall.
  • 4. piles extending in front of the arch over- laps, as shown in Figure 3. The secant pile concrete strength was specified at 30 MPa (4400 psi) with the deepest piles extend- ing nearly 25m (80 ft.) below the existing grade. A special curved concrete cap was required to improve both the appearance and the structural integrity of the wall, as the secants alone had no lateral reinforce- ment. The tendered design presented several constructability challenges to HCM. First, maintaining the stability of the hillside and equipment and worker safety with the as- tendered design would have been difficult due to the imported-fill platforms and heavy equipment required to construct the interlocking secants, especially given the sliding history of the slope. Temporary shoring was added to the original contract scope as an addendum to accommodate the fill platforms and would have been sub- stantial in order to support the equipment necessary to install the deep secants. Sec- ondly, the required schedule for comple- tion of the secant pile installation was nine months, a figure that HCM estimated would be exceeded by at least three months due to the temporary shoring and confined work areas present on the site. Thirdly, the interlocking, high-strength se- cant piles required to 25m design depths were problematic due to the concrete strength and severe tender penalties for any non-interlocked final conditions. Fi- nally, even with the highest quality stan- dards met, a lack of control joints in the design raised concerns about leakage at the secant joints. Innovative Solutions in Design and Construction The HCM/Isherwood design-build team proposed an alternative that provided a sim- ilar final geometry to that of the original de- sign while providing higher structural in- tegrity, an improved construction schedule, and significant cost-savings for the Prime Contractor. The HCM/Isherwood team de- livered a solution when no other party would tender the base design with confi- dence. Temporary Shotcrete Shoring The tight schedule requirements were addressed by employing temporary shot- crete shoring. The shotcrete shoring was advantageous for two reasons: First, it could commence without any low slope shoring, greatly improving hillside stabil- ity. Second, excavation could commence si- multaneously with the temporary shoring installation, as opposed to waiting for pil- ing to be completed, greatly improving the construction schedule. The alignment of the temporary shot- crete wall was established to allow two- sided forming with 1200mm (4 ft.) of free-draining backfill material. This elimi- nated the need for the concrete swale orig- inally designed behind the top of the wall. The base of the shotcrete wall would be stepped towards the low slope direction to act as a backside form and create a one- sided forming solution for the foundation of the permanent structure, as shown in Figure 4. The temporary shoring system employed R38 hollow bar micropiles sup- plied by Dywidag Systems International (DSI)* to reinforce the earth mass behind the 150mm (6 inch) thick shotcrete face. FOUNDATION DRILLING September/October 2009Page 4 RE-DESIGN Contd. (Continued on page 5) Figure 4: Typical Arch Section. Figure 5: PLAXIS Modeling of Stress Distribution.
  • 5. Vertical R38 micropiles were used to add vertical capacity to the shotcrete face and to act as layout points for the irregular geometry of the arches. Longer, 1500kN (340 kip) capacity, T76S (DSI) tension mi- cropiles were installed at a 35- degree in- clination to actively anchor the reinforced soil mass to the underlying dense sands. The tension micropiles are permanent ele- ments used in both the upper temporary shotcrete wall and the permanent ring footing. The stressing and pre-loading program designed by HCM/Isherwood used both the active resistance of a pre-loaded mi- cropile system and a passively reinforced soil-nail wall with 50% of the calculated de- sign load locked in to avoid any tendency for vertical settlement of the temporary wall. Permanent Retaining Wall HCM/Isherwood designed the perma- nent retaining wall alternative in partner- ship with Peter Sheffield and Associates, one of Canada’s leading structural engi- neers. The final wall would consist of a 600mm (24 inch) thick cast-in-place arch that would maintain the tripod concept with one distinct difference: the new de- sign would implement construction joints in between arch pairs to allow the loading of the tripods to occur inside of each arch as a “horseshoe” instead of the outside of the overlapping arches as originally de- signed. This approach would improve crack control in the extreme freeze-thaw environment of Edmonton. Maintenance on the wall would be simplified as arches acting individually could be repaired with fewer complications should problems arise in the future. The lateral reinforcement of a cast-in-place wall improved the structural integrity of the wall, eliminating the struc- tural requirement of the wall cap. Addi- tionally, 600mm (30 inch) drainage tubes positioned below the shotcrete wall and behind the permanent structure would prevent the build-up of hydrostatic pres- sure from ground water. The exposed portion of the wall would be built upon a curved footing that would step down to match the final 3H:1V slope profile in front of the wall. Tension mi- cropiles, to be installed at 35 degrees, were designed to mitigate total deflection and potential creep of the final structure, as well as tie the ring footing into the dense sands 9m below. 1200mm diameter, heav- ily reinforced concrete caissons developed into the dense sands would support the ring footing. The sands were deemed by the HCM/Isherwood design-build team to be more consistent than the bedrock and capable of high capacity at low strain. The FOUNDATION DRILLING September/October 2009 Page 5 Figure 6: Excavator-mounted TEI Drill. Figure 7: Mid-December Inclinometer Plot. (Continued on page 6) RE-DESIGN Contd.
  • 6. arches, anchored in the dense sands, would transfer active soils loads to the concrete piles pivoting between the upper and lower extremes of the arch and tripod support. The arches were designed with seven to nine caissons each and assumed a non- soil-flow rheology between the piles. Piles were spaced on average at two pile diame- ters. Assuming a conservative N value of two, the design incorporated the mobiliza- tion of the entire passive resistance of the soil. Computer Modeling and Monitoring The HCM/Isherwood design-build team relied on deformation modeling and sub- sequent construction slope monitoring to ensure stable performance of the shoring system and confirm the models and design parameters. Loading and resultant deflec- tions for the design were modeled using standard slope stability analysis (limit- equilibrium) and the finite element method to provide guidance for construc- tion progress and staging. Modeling with PLAXIS, a finite-element package used to analyze deformation and stability in geo- technical applications, enabled Isherwood/- Sheffield to model the interaction of the structures and the soil. The historical behavior of the hillside slope presented significant risks to the project team. As such, a monitoring pro- gram was implemented to provide reliable information pertaining to shoring per- formance and the behavior of the suspect upper sands as excavation proceeded. Movement data was collected via nine deep inclinometers installed along the back of the shotcrete wall to depths of 21m (70 ft.), extending past the toe elevation of the cais- sons. The inclinometers were read weekly to supply valuable movement data on the excavated slope. Total Station Targets were also installed on the shotcrete face to mon- itor real displacements. Employing Peck’s Observational Method, Isherwood ana- lyzed the data on an ongoing basis during construction to verify design assumptions, compare with deformation modeling re- sults, monitor shoring performance, and ensure the safety of workers and the pub- lic on the Whitemud freeway. The HCM/Isherwood alternative design was accepted by the City of Edmonton’s consulting team and construction began. Initial Construction HCM began construction in October 2008 with the installation of vertical R38 micropiles. These elements were installed between 12m (40 ft.) and 21m (70 ft.) deep into the dense sands by three TEI 550* drills mounted on Caterpillar 320 ex- cavators, as shown in Figure 6. The pair- ing of the drill attachments to the highly maneuverable excavators facilitated instal- lation of the verticals on the sloped hillside and required minimal excavation prior to drilling. Once verticals were completed, horizontal R38 anchors were installed at FOUNDATION DRILLING September/October 2009Page 6 (Continued on page 7) RE-DESIGN Contd. Figure 8: Pipe Connection Detail. Figure 9: Hillside Congestion.
  • 7. 1.5m (5 ft.) spacing. Initially, a panel se- quence of shotcrete application was em- ployed to understand how the upper clays would respond to the excavation. Once it was apparent the soils were capable of han- dling ribbon-style excavation, production was ramped up and subsequent lifts of the arches were completed one row at a time. All anchors were spaced in a regular grid pattern (1.5m by 1.5m), which simplified layout and helped protect the inclinometer casings. Changed Soil Conditions As excavation advanced to 6m below the original grade, the inclinometers along the south half of the wall indicated surpris- ingly large movements over a short verti- cal distance near the elevation 645.0m, as shown in Figure 7. This coincided with the elevation of the shear movements measured during the 1971 slide, raising concerns as the partially excavated geome- try should have provided a high factor of safety. A stop excavation order was put in place for Arches C6 to C14 to allow for back-calculation of soil-strength parame- ters as a function of the observed hillside deformations. Isherwood immediately began a limit equilibrium analysis based on the as-built condition. The analysis indi- cated the soil strength parameters of the upper sands to be significantly lower than originally reported in the tender geotech- nical report. The actual soil strength pa- rameters of the slope were established assuming that plasticity had occurred within the observed movement layer and, using the limit equilibrium model, deter- mining what soil strength parameters would yield a factor of safety of 1.0. The results of the analysis indicated a signifi- cant reduction in the internal angle of fric- tion of the upper clay-seamed sands between the elevations 645 and 646m. The available passive resistance of the soil above this layer was significantly reduced by the weak layer. As an analogy, the re- sistance of the clay soils above the weak layer could be imagined as a block being pushed on asphalt. Between the elevations 645 and 646 m, it was as if the block was suddenly being pushed on a surface of ice. In order to return the factor of safety for both the temporary shoring and perma- nent retaining wall to acceptable levels, four main measures were added to supple- ment the original design: • Temporary 750mm (30 inch) caissons with HP360x152 steel reinforcement were installed from Arches C6 to C14 before ex- cavation was allowed to continue. • Four additional 1200mm structural caissons were added to the highest arches in the middle of the wall. • Ring footings, originally designed with a combination of R38 and T76 mi- cropiles to resist lateral movements, were upgraded to use T76 micropiles through- out. • In an effort to maintain the hillside stability during the temporary shoring in- stallation, structural caissons were in- stalled from a grade 1.5m higher than originally designed. In short, the strategy was to create sup- plementary shear-resistance across the de- veloping slip-surface, which would not be fully loaded until excavation of the slope below the wall was completed and the ex- isting bin walls were removed. Construction Completion HCM had to respond to the changed hill- side stability conditions proactively. De- spite the partnering approach implemented by the City of Edmonton, the HCM/Isher- wood Team was pressured to find solutions quickly. There were numerous project de- lays; for example, the construction of the temporary wall was delayed due to ex- tended approvals, and the hillside move- ment in December 2008 stopped the shotcrete work. These delays, coupled with hillside stability concerns, resulted in the caissons being drilled from a higher eleva- tion and more than half of the shotcrete work being done concurrently during the winter months. HCM innovated a new micropile con- FOUNDATION DRILLING September/October 2009 Page 7 (Continued on page 8) RE-DESIGN Contd. Figure 10: Arch C9 Inclinometer Plot.
  • 8. nection at the onset of winter conditions to enable soil cutting and shotcrete appli- cation prior to drilling micropiles. Figure 8 shows a 600kN connection that was de- veloped and tested to 900kN on the shot- crete face for the tension piles that were part of the temporary system. Caisson construction occurred concur- rently with rebar detailing, necessitating drawings to be released on a daily basis. Designers in Toronto were working over- time to produce rebar details to maintain production. Some of the revised reinforce- ment for the caissons in the highest arches were 60-35M (1.5 inch) bars with hori- zontal tie spacing reduced to as low as 75mm (3 inch) in the areas of greatest loading. Caissons were installed through the old failure plane and into the dense sands by pre-drilling the very stiff upper clay and then driving 1200mm (48 inch) liners with an APE 200* on an 80-ton crane. The dense sands required top head drive rigs and careful drilling below the liner to achieve penetration. HCM added further innovation on the project by stepping the base of the shot- crete wall in to act as a back-side form for the ring footing and to be used as a swale to carry surface water through the granular backfill and out from behind the perma- nent retaining wall via weeping tile. HCM employed two Casagrande M9* hydraulic tieback drills to install the high capacity T76 self-drilling permanent micropiles prior to footing installation. To minimize schedule impacts, multiple operations were run concurrently, which resulted in high hillside congestion, as shown in Fig- ure 8. By working overtime and on weekends, HCM was able to restore most of the lost time that resulted from the late start and the hillside movement delay. The comple- tion of the project at the end of April 2009 was one month late from what HCM orig- inally forecasted. The formed wall was judged sufficient for the final appearance, which allowed the elimination of the con- crete cap from the design. This allowed for the complete restoration of the original project schedule. Shoring Performance At the time of completion, the maximum movement detected along the shotcrete wall was 27 mm (1.1 inches). Figure 9 shows the deep-seated movement near el- evation 645m at Arch C9. The upper tier of the double bin wall was removed first, the monitoring observed and then, with all ring footings in place, the complete low slope was removed. Performance has proven to be stable and no creep has been observed, demonstrating a successful con- clusion to a logistically difficult and tech- nically challenging project. Concluding Remarks The final project product is visible to many commuters and the City of Edmon- ton received a long-term, maintenance-free product. Figure 10 shows the unique geometry and aesthetically pleasing design of the finished structure. The calculation of the reduced phi angle and soil strength became a fundamental argument in the later stages of the project. This presented disagreements between the design-build contractor and the owner with respect to responsibilities for changes in the soil con- ditions from what was presented in the tender documents. The matter was delib- erated as work continued in order to miti- gate any potential impact on the project schedule. Test pits dug upon completion of the slope regrading revealed strain-weak- ened thin layers of slickensided clay that were not identified at the time of tender, improving the case by the contractors for changed conditions. The Whitemud project is a unique ex- ample of a hill stability challenge and sig- nificant knowledge was gained for future projects. It is expected that more advanced technical papers will be tabled in the future and it is likely that several graduate stu- dents will proceed with thesis work in the years following completion. *Indicates ADSC Members.I FOUNDATION DRILLING September/October 2009Page 8 RE-DESIGN Contd. PROJECT TEAM Shoring Design-Build HCM Contractors Inc.* Contractor Martin Halliwell, P. Eng., Project Manager Geoff Jilg, Operations Manager Jeff Gibbs, Superintendent Shoring/Retaining Isherwood Associates* Wall Designer Matthew Janes, P. Eng., Senior Engineer Mark Spence, P.Eng., Project Manager Peter Sheffield, P. Eng., Structural Engineer Monitoring Micro EnGEO Inc. Mohamed El Habiby, Project Manager HCM Contractors Inc.* Brendan Lemieux, Site Engineer Construction Manager ConCreate USL Ltd. Stewart Nelson, P. Eng., Project Manager Borje McKinnon, Operations Manager Geotechnical Design Thurber Engineering Ltd.* Robin Tweedie, P.Eng., Project Manager Linda Bobey, P.Eng., Project Engineer *Indicates ADSC Members