SlideShare a Scribd company logo
Innovative Solutions to Today’s Geotechnical Demands
Soil Mixing on Berths 57/58 with 55/56 (cranes) in background
Previous Raito Project (lower
right) hosts world’s largest
cranes
• A soil-cement buttress
(grid) was constructed
using CDSM (Cement
Deep Soil Mixing)
technology to improve
weak and potentially
liquefiable soil condi-
tions along the Port of
Oakland shoreline.
• The CDSM buttress ex-
tended for 2,400 feet
and drilled to a
maximum depth of 88
feet. Over 60,000
cubic yards of soil was
improved for ground
stabilization and lique-
faction prevention dur-
ing and after an
earthquake.
Two Raito Soil-Mixing rigs improving ground for Berths 57/58
• The CDSM buttress construction exceeded all geometric,
strength design and uniformity requirements.
• Repeat client for CDSM production.
• Project Owner: Port of
Oakland, Oakland, CA
• Geotechnical Engineer:
Geomatrix, Oakland, CA
Innovative Solutions to Today’s Geotechnical Demands
Port of Oakland Berths 57/58
The construction of Berths 57/58 at the Port of
Oakland required the stabilization of a cut slope under
a proposed container wharf extending 2,400 feet. The
cut slope was constructed to transition soil backlands
to the design dredge depth for a maximum slope
height of 65 feet.
Soil conditions encountered on the project consisted
of surface fill, Bay Mud and Young Bay Deposits
described as soft, weak and/or susceptible to
seismically induced liquefaction and lateral spreading.
This condition posed a potential threat to the stability
of the proposed wharf structures during and after
major earthquakes. A CDSM buttress system was
proposed to provide shoreline stabilization and control
lateral spreading.
The soil-cement buttress consisted of a rectangular
grid of Cement Deep Soil Mixing (CDSM) walls
formed using 3-foot diameter columns spaced on 2-
foot centers. In the shallow Bay Mud area, the grid
consisted of two longitudinal walls parallel to the
shoreline spaced 31 feet apart, and a series of
transverse walls perpendicular to the shoreline spaced twelve feet apart. In the deep Bay Mud area, the width of the
CDSM grid was increased by extending the transverse walls in the direction of the shoreline slope. When the width of the
CDSM grid was greater than 68.5 feet, a third longitudinal wall was added. The maximum treatment depth in the deep
Bay Mud area was 88 feet.
(Courtesy of Geomatrix Consultants)
Over 60,000 cubic yards of CDSM ground stabilization was constructed over a
period of five months. Triple-shaft CDSM equipment with a real-time monitoring
system was used for ground stabilization.
Test specimens for unconfined compressive strength were retrieved by a triple barrel
coring system, and exceeded the acceptance criteria of an average of 150 psi at 28
days.
Grid in deep Bay Mud area
Pacific Division
Corporate Headquarters
1660 Factor Avenue
San Leandro, CA 94577
510-346-9840
510-346-9841 fax
Atlantic Division
6210 North King’s Highway
Alexandria, VA 22303
703-718-0755
703-718-0744 fax
Toll Free: 1-866-DEEPMIX
Website: www.raitoinc.com

More Related Content

What's hot

In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour systemKotesh Bhukya
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )Kamel Elsayed
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining StudyOnur Tuncay
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingTim Leung
 
Offshore Drilling rigs (6) i
Offshore Drilling rigs (6) iOffshore Drilling rigs (6) i
Offshore Drilling rigs (6) iSolomon Okoro
 
Mining Methods
Mining MethodsMining Methods
Mining MethodsVR M
 
Reconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised MayhewReconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised Mayhewmayhew50
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsInfocengrs63
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam miningSafdar Ali
 
Open pit mining
Open pit miningOpen pit mining
Open pit mininggereltuya
 

What's hot (20)

In pit crusher conveyour system
In pit crusher conveyour systemIn pit crusher conveyour system
In pit crusher conveyour system
 
The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )The Road to Saqqara ( Jack-up units and Move )
The Road to Saqqara ( Jack-up units and Move )
 
Underground Coal Mining Study
Underground Coal Mining StudyUnderground Coal Mining Study
Underground Coal Mining Study
 
Mining methods
Mining methodsMining methods
Mining methods
 
Jack up
Jack upJack up
Jack up
 
Backhoe Dredger
Backhoe Dredger Backhoe Dredger
Backhoe Dredger
 
Expl 2-jb-57-e
Expl 2-jb-57-eExpl 2-jb-57-e
Expl 2-jb-57-e
 
Spe 172724-ms
Spe 172724-msSpe 172724-ms
Spe 172724-ms
 
Ground Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional Drilling
 
Jamrani dam ppt
Jamrani dam pptJamrani dam ppt
Jamrani dam ppt
 
Offshore Drilling rigs (6) i
Offshore Drilling rigs (6) iOffshore Drilling rigs (6) i
Offshore Drilling rigs (6) i
 
Mining Methods
Mining MethodsMining Methods
Mining Methods
 
Ijaret 06 07_009
Ijaret 06 07_009Ijaret 06 07_009
Ijaret 06 07_009
 
Reconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised MayhewReconstruction Of Veterans Lane Revised Mayhew
Reconstruction Of Veterans Lane Revised Mayhew
 
Building a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sandsBuilding a mega-power plant on liquefiable sands
Building a mega-power plant on liquefiable sands
 
Ijaret 06 07_008
Ijaret 06 07_008Ijaret 06 07_008
Ijaret 06 07_008
 
longwall mining
longwall mininglongwall mining
longwall mining
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
In-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying SystemsIn-Pit Crushing and Conveying Systems
In-Pit Crushing and Conveying Systems
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 

Similar to Port of oakland berths 57 58

Dim cs whynes_12.07
Dim cs whynes_12.07Dim cs whynes_12.07
Dim cs whynes_12.07Tensar
 
Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Tensar
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farmEMIN Sistemas Geotecnicos
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining WallJim McMullan
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuVishweshwar Rao Narla
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002William Godwin
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 
Dm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prDm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prTensar
 
Triton cs collins_11.07
Triton cs collins_11.07Triton cs collins_11.07
Triton cs collins_11.07Tensar
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the portNECB
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 

Similar to Port of oakland berths 57 58 (20)

07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
07 soil-grout threadbar
 
Dim cs whynes_12.07
Dim cs whynes_12.07Dim cs whynes_12.07
Dim cs whynes_12.07
 
Dim cs whynes_12.07-2
Dim cs whynes_12.07-2Dim cs whynes_12.07-2
Dim cs whynes_12.07-2
 
Emin sg sistema dimension caso west hynes tank farm
Emin sg   sistema dimension caso west hynes tank farmEmin sg   sistema dimension caso west hynes tank farm
Emin sg sistema dimension caso west hynes tank farm
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Whitemud Drive Retaining Wall
Whitemud Drive Retaining WallWhitemud Drive Retaining Wall
Whitemud Drive Retaining Wall
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
OCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil MixingOCPW Wintersburg Channel Deep Soil Mixing
OCPW Wintersburg Channel Deep Soil Mixing
 
SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002ASCE PL Div 2001 40574-017-002
ASCE PL Div 2001 40574-017-002
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
CC Intro
CC IntroCC Intro
CC Intro
 
Dm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-prDm ms-tren-urbano-san-juan-pr
Dm ms-tren-urbano-san-juan-pr
 
Triton cs collins_11.07
Triton cs collins_11.07Triton cs collins_11.07
Triton cs collins_11.07
 
Mahi ppt suez (2)
Mahi ppt suez (2)Mahi ppt suez (2)
Mahi ppt suez (2)
 
Interlocking concrete pavement for the port
Interlocking concrete pavement for the portInterlocking concrete pavement for the port
Interlocking concrete pavement for the port
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 

More from Jim McMullan

Driven Pipe Pile Installation
Driven Pipe Pile InstallationDriven Pipe Pile Installation
Driven Pipe Pile InstallationJim McMullan
 
Shotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation SupportShotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation SupportJim McMullan
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump ConstructionJim McMullan
 
Precast over Structural Steel Bridge
Precast over Structural Steel BridgePrecast over Structural Steel Bridge
Precast over Structural Steel BridgeJim McMullan
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket PilingJim McMullan
 
Vibro Replacement Ground Treatment
Vibro Replacement Ground TreatmentVibro Replacement Ground Treatment
Vibro Replacement Ground TreatmentJim McMullan
 
Marine Battered Pile Installation
Marine Battered Pile InstallationMarine Battered Pile Installation
Marine Battered Pile InstallationJim McMullan
 
Triple Axle Deep Soil Mixing
Triple Axle Deep Soil MixingTriple Axle Deep Soil Mixing
Triple Axle Deep Soil MixingJim McMullan
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump ConstructionJim McMullan
 
Deep Soil Mix Grout Plants
Deep Soil Mix Grout PlantsDeep Soil Mix Grout Plants
Deep Soil Mix Grout PlantsJim McMullan
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining WallJim McMullan
 
Excavation Support
Excavation SupportExcavation Support
Excavation SupportJim McMullan
 

More from Jim McMullan (19)

Rock Excavation
Rock ExcavationRock Excavation
Rock Excavation
 
Driven Pipe Pile Installation
Driven Pipe Pile InstallationDriven Pipe Pile Installation
Driven Pipe Pile Installation
 
Shotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation SupportShotcrete & Soil Anchor Excavation Support
Shotcrete & Soil Anchor Excavation Support
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 
Precast over Structural Steel Bridge
Precast over Structural Steel BridgePrecast over Structural Steel Bridge
Precast over Structural Steel Bridge
 
Retaining Wall
Retaining WallRetaining Wall
Retaining Wall
 
Rock Socket Piling
Rock Socket PilingRock Socket Piling
Rock Socket Piling
 
Vibro Replacement Ground Treatment
Vibro Replacement Ground TreatmentVibro Replacement Ground Treatment
Vibro Replacement Ground Treatment
 
Marine Battered Pile Installation
Marine Battered Pile InstallationMarine Battered Pile Installation
Marine Battered Pile Installation
 
Triple Axle Deep Soil Mixing
Triple Axle Deep Soil MixingTriple Axle Deep Soil Mixing
Triple Axle Deep Soil Mixing
 
Olympic Ski Jump Construction
Olympic Ski Jump ConstructionOlympic Ski Jump Construction
Olympic Ski Jump Construction
 
Deep Soil Mixing
Deep Soil MixingDeep Soil Mixing
Deep Soil Mixing
 
Deep Soil Mix Grout Plants
Deep Soil Mix Grout PlantsDeep Soil Mix Grout Plants
Deep Soil Mix Grout Plants
 
Marine Piling
Marine PilingMarine Piling
Marine Piling
 
Sheet Pile Retaining Wall
Sheet Pile Retaining WallSheet Pile Retaining Wall
Sheet Pile Retaining Wall
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 
Excavation Support
Excavation SupportExcavation Support
Excavation Support
 
CIDH Construction
CIDH ConstructionCIDH Construction
CIDH Construction
 

Recently uploaded

Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdfKamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfKamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisDr. Radhey Shyam
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 

Recently uploaded (20)

Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

Port of oakland berths 57 58

  • 1. Innovative Solutions to Today’s Geotechnical Demands Soil Mixing on Berths 57/58 with 55/56 (cranes) in background Previous Raito Project (lower right) hosts world’s largest cranes • A soil-cement buttress (grid) was constructed using CDSM (Cement Deep Soil Mixing) technology to improve weak and potentially liquefiable soil condi- tions along the Port of Oakland shoreline. • The CDSM buttress ex- tended for 2,400 feet and drilled to a maximum depth of 88 feet. Over 60,000 cubic yards of soil was improved for ground stabilization and lique- faction prevention dur- ing and after an earthquake. Two Raito Soil-Mixing rigs improving ground for Berths 57/58 • The CDSM buttress construction exceeded all geometric, strength design and uniformity requirements. • Repeat client for CDSM production. • Project Owner: Port of Oakland, Oakland, CA • Geotechnical Engineer: Geomatrix, Oakland, CA
  • 2. Innovative Solutions to Today’s Geotechnical Demands Port of Oakland Berths 57/58 The construction of Berths 57/58 at the Port of Oakland required the stabilization of a cut slope under a proposed container wharf extending 2,400 feet. The cut slope was constructed to transition soil backlands to the design dredge depth for a maximum slope height of 65 feet. Soil conditions encountered on the project consisted of surface fill, Bay Mud and Young Bay Deposits described as soft, weak and/or susceptible to seismically induced liquefaction and lateral spreading. This condition posed a potential threat to the stability of the proposed wharf structures during and after major earthquakes. A CDSM buttress system was proposed to provide shoreline stabilization and control lateral spreading. The soil-cement buttress consisted of a rectangular grid of Cement Deep Soil Mixing (CDSM) walls formed using 3-foot diameter columns spaced on 2- foot centers. In the shallow Bay Mud area, the grid consisted of two longitudinal walls parallel to the shoreline spaced 31 feet apart, and a series of transverse walls perpendicular to the shoreline spaced twelve feet apart. In the deep Bay Mud area, the width of the CDSM grid was increased by extending the transverse walls in the direction of the shoreline slope. When the width of the CDSM grid was greater than 68.5 feet, a third longitudinal wall was added. The maximum treatment depth in the deep Bay Mud area was 88 feet. (Courtesy of Geomatrix Consultants) Over 60,000 cubic yards of CDSM ground stabilization was constructed over a period of five months. Triple-shaft CDSM equipment with a real-time monitoring system was used for ground stabilization. Test specimens for unconfined compressive strength were retrieved by a triple barrel coring system, and exceeded the acceptance criteria of an average of 150 psi at 28 days. Grid in deep Bay Mud area Pacific Division Corporate Headquarters 1660 Factor Avenue San Leandro, CA 94577 510-346-9840 510-346-9841 fax Atlantic Division 6210 North King’s Highway Alexandria, VA 22303 703-718-0755 703-718-0744 fax Toll Free: 1-866-DEEPMIX Website: www.raitoinc.com