This document discusses how to implement Simplified Drum-Buffer-Rope (SDBR) production planning for rapid response (RR) projects while maintaining commitments to regular orders. It proposes reserving capacity on the capacity-constrained resource (CCR) for RR orders so they do not impact regular order due dates. A planned load concept is used to determine safe due dates for regular orders based on projected CCR workload rather than a detailed schedule. The document outlines calculating planned load, quoting safe due dates, reserving CCR capacity for RR orders, and execution rules for the implementation.
Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in scheduling and placing orders for items of dependent demand.
Material requirements planning (MRP) is a computer-based inventory management system designed to assist production managers in scheduling and placing orders for items of dependent demand.
โASRS - Automated Storage/Retrieval System is defined as a storage system that performs storage and retrieval operations with speed and accuracy under a defined degree of automation.โ
โASRS - Automated Storage/Retrieval System is defined as a storage system that performs storage and retrieval operations with speed and accuracy under a defined degree of automation.โ
Crude-Oil Blend Scheduling Optimization: An Application with Multi-Million D...Alkis Vazacopoulos
ย
The economic and operability benefits associated with better crude-oil blend scheduling are numerous and significant. The crude-oils that arrive at the oil-refinery to be processed into the various refined-oils must be carefully handled and mixed before they are charged to the atmospheric and vacuum distillation unit or pipestill. The intent of this article is to highlight the importance and details of optimizing the scheduling of an oil-refineryโs crude-oil feedstocks from the receipt to the charging of the pipestills.
Forward scheduling vs. backward scheduling in production planningMRPeasy
ย
Forward scheduling and backward scheduling are key concepts in production planning. What are the differences between the two approaches and which one should you choose for your manufacturing business?
Processing Semantically-Ordered Streams in Financial ServicesFlink Forward
ย
Flink Forward San Francisco 2022.
What if my data is already in order? Stream Processing has given us an elegant and powerful solution for running analytic queries and logic over high volumes of continuously arriving data. However, in both Apache Flink and Apache Beam, the notion of time-ordering is baked in at a very low level, making it difficult to express computations that are interested in a semantic-, rather than time-ordering of the data. In financial services, what often matters the most about the data moving between systems is not when the data was created, but in what order, to the extent that many institutions engineer a global sequencing over all data entering and produced by their systems to achieve complete determinism. How, then, can financial institutions and others best employ Stream Processing on streams of data that are already ordered? I will cover various techniques that can make this work, as well as seek input from the community on how Flink might be improved to better support these use-cases.
by
Patrick Lucas
Similar to Using sdbr in rapid response project (20)
Endรผstri Mรผhendisliฤi - Yรถneylem teknikleriyle Saฤlฤฑk Tedarik Zinciri Modellemesidir. Maalesef dรผnya bu yรถntemleri taลฤฑyacak kadar deterministik deฤildir. Zaten sonraki aลamada fiili model denemesi planlanmฤฑล.
Tahmin ve internet tabanlฤฑ kolaylaลtฤฑrmaya dayalฤฑ bir รงalฤฑลma. Haiti' de elektrik kesintileri, internet eriลim kesintileri, ฤฐngilizce - Fransฤฑzca - yerel dil, dรผลรผk eฤitim profili, ada olmaktan kaynaklanan lojistik zorluk, fakirlik, kolera salgฤฑnฤฑ,... engellere raฤmen iyileลme saฤlanmฤฑล.
DMO, diฤer OECD รผlkelerindeki gibi merkezi alฤฑm ve kamu iรงin ortak tedarikรงi olma eฤilimindedir. Bรถylece stoklar paylaลฤฑlabilecek, aลฤฑrฤฑ alฤฑmlar bitecek, รถlรงek ekonomisi saฤlanacaktฤฑr. ฤฐlaรง ve Tฤฑbbi Sarf Malzemesi DMO gรผndemindedir.
Business Valuation Principles for EntrepreneursBen Wann
ย
This insightful presentation is designed to equip entrepreneurs with the essential knowledge and tools needed to accurately value their businesses. Understanding business valuation is crucial for making informed decisions, whether you're seeking investment, planning to sell, or simply want to gauge your company's worth.
Putting the SPARK into Virtual Training.pptxCynthia Clay
ย
This 60-minute webinar, sponsored by Adobe, was delivered for the Training Mag Network. It explored the five elements of SPARK: Storytelling, Purpose, Action, Relationships, and Kudos. Knowing how to tell a well-structured story is key to building long-term memory. Stating a clear purpose that doesn't take away from the discovery learning process is critical. Ensuring that people move from theory to practical application is imperative. Creating strong social learning is the key to commitment and engagement. Validating and affirming participants' comments is the way to create a positive learning environment.
As a business owner in Delaware, staying on top of your tax obligations is paramount, especially with the annual deadline for Delaware Franchise Tax looming on March 1. One such obligation is the annual Delaware Franchise Tax, which serves as a crucial requirement for maintaining your companyโs legal standing within the state. While the prospect of handling tax matters may seem daunting, rest assured that the process can be straightforward with the right guidance. In this comprehensive guide, weโll walk you through the steps of filing your Delaware Franchise Tax and provide insights to help you navigate the process effectively.
Discover the innovative and creative projects that highlight my journey throu...dylandmeas
ย
Discover the innovative and creative projects that highlight my journey throughย Full Sail University. Below, youโll find a collection of my work showcasing my skills and expertise in digital marketing, event planning, and media production.
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...PaulBryant58
ย
This article provides a comprehensive guide on how to
effectively manage the convert Accpac to QuickBooks , with a particular focus on utilizing online accounting services to streamline the process.
Explore our most comprehensive guide on lookback analysis at SafePaaS, covering access governance and how it can transform modern ERP audits. Browse now!
"๐ฉ๐ฌ๐ฎ๐ผ๐ต ๐พ๐ฐ๐ป๐ฏ ๐ป๐ฑ ๐ฐ๐บ ๐ฏ๐จ๐ณ๐ญ ๐ซ๐ถ๐ต๐ฌ"
๐๐ ๐๐จ๐ฆ๐ฌ (๐๐ ๐๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐๐๐ญ๐ข๐จ๐ง๐ฌ) is a professional event agency that includes experts in the event-organizing market in Vietnam, Korea, and ASEAN countries. We provide unlimited types of events from Music concerts, Fan meetings, and Culture festivals to Corporate events, Internal company events, Golf tournaments, MICE events, and Exhibitions.
๐๐ ๐๐จ๐ฆ๐ฌ provides unlimited package services including such as Event organizing, Event planning, Event production, Manpower, PR marketing, Design 2D/3D, VIP protocols, Interpreter agency, etc.
Sports events - Golf competitions/billiards competitions/company sports events: dynamic and challenging
โญ ๐ ๐๐๐ญ๐ฎ๐ซ๐๐ ๐ฉ๐ซ๐จ๐ฃ๐๐๐ญ๐ฌ:
โข 2024 BAEKHYUN [Lonsdaleite] IN HO CHI MINH
โข SUPER JUNIOR-L.S.S. THE SHOW : Th3ee Guys in HO CHI MINH
โขFreenBecky 1st Fan Meeting in Vietnam
โขCHILDREN ART EXHIBITION 2024: BEYOND BARRIERS
โข WOW K-Music Festival 2023
โข Winner [CROSS] Tour in HCM
โข Super Show 9 in HCM with Super Junior
โข HCMC - Gyeongsangbuk-do Culture and Tourism Festival
โข Korean Vietnam Partnership - Fair with LG
โข Korean President visits Samsung Electronics R&D Center
โข Vietnam Food Expo with Lotte Wellfood
"๐๐ฏ๐๐ซ๐ฒ ๐๐ฏ๐๐ง๐ญ ๐ข๐ฌ ๐ ๐ฌ๐ญ๐จ๐ซ๐ฒ, ๐ ๐ฌ๐ฉ๐๐๐ข๐๐ฅ ๐ฃ๐จ๐ฎ๐ซ๐ง๐๐ฒ. ๐๐ ๐๐ฅ๐ฐ๐๐ฒ๐ฌ ๐๐๐ฅ๐ข๐๐ฏ๐ ๐ญ๐ก๐๐ญ ๐ฌ๐ก๐จ๐ซ๐ญ๐ฅ๐ฒ ๐ฒ๐จ๐ฎ ๐ฐ๐ข๐ฅ๐ฅ ๐๐ ๐ ๐ฉ๐๐ซ๐ญ ๐จ๐ ๐จ๐ฎ๐ซ ๐ฌ๐ญ๐จ๐ซ๐ข๐๐ฌ."
Skye Residences | Extended Stay Residences Near Toronto Airportmarketingjdass
ย
Experience unparalleled EXTENDED STAY and comfort at Skye Residences located just minutes from Toronto Airport. Discover sophisticated accommodations tailored for discerning travelers.
Website Link :
https://skyeresidences.com/
https://skyeresidences.com/about-us/
https://skyeresidences.com/gallery/
https://skyeresidences.com/rooms/
https://skyeresidences.com/near-by-attractions/
https://skyeresidences.com/commute/
https://skyeresidences.com/contact/
https://skyeresidences.com/queen-suite-with-sofa-bed/
https://skyeresidences.com/queen-suite-with-sofa-bed-and-balcony/
https://skyeresidences.com/queen-suite-with-sofa-bed-accessible/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-king-queen-suite-with-sofa-bed/
https://skyeresidences.com/2-bedroom-deluxe-queen-suite-with-sofa-bed-accessible/
#Skye Residences Etobicoke, #Skye Residences Near Toronto Airport, #Skye Residences Toronto, #Skye Hotel Toronto, #Skye Hotel Near Toronto Airport, #Hotel Near Toronto Airport, #Near Toronto Airport Accommodation, #Suites Near Toronto Airport, #Etobicoke Suites Near Airport, #Hotel Near Toronto Pearson International Airport, #Toronto Airport Suite Rentals, #Pearson Airport Hotel Suites
Falcon stands out as a top-tier P2P Invoice Discounting platform in India, bridging esteemed blue-chip companies and eager investors. Our goal is to transform the investment landscape in India by establishing a comprehensive destination for borrowers and investors with diverse profiles and needs, all while minimizing risk. What sets Falcon apart is the elimination of intermediaries such as commercial banks and depository institutions, allowing investors to enjoy higher yields.
Improving profitability for small businessBen Wann
ย
In this comprehensive presentation, we will explore strategies and practical tips for enhancing profitability in small businesses. Tailored to meet the unique challenges faced by small enterprises, this session covers various aspects that directly impact the bottom line. Attendees will learn how to optimize operational efficiency, manage expenses, and increase revenue through innovative marketing and customer engagement techniques.
Buy Verified PayPal Account | Buy Google 5 Star Reviewsusawebmarket
ย
Buy Verified PayPal Account
Looking to buy verified PayPal accounts? Discover 7 expert tips for safely purchasing a verified PayPal account in 2024. Ensure security and reliability for your transactions.
PayPal Services Features-
๐ข Email Access
๐ข Bank Added
๐ข Card Verified
๐ข Full SSN Provided
๐ข Phone Number Access
๐ข Driving License Copy
๐ข Fasted Delivery
Client Satisfaction is Our First priority. Our services is very appropriate to buy. We assume that the first-rate way to purchase our offerings is to order on the website. If you have any worry in our cooperation usually You can order us on Skype or Telegram.
24/7 Hours Reply/Please Contact
usawebmarketEmail: support@usawebmarket.com
Skype: usawebmarket
Telegram: @usawebmarket
WhatsApp: +1โช(218) 203-5951โฌ
USA WEB MARKET is the Best Verified PayPal, Payoneer, Cash App, Skrill, Neteller, Stripe Account and SEO, SMM Service provider.100%Satisfection granted.100% replacement Granted.
Memorandum Of Association Constitution of Company.pptseri bangash
ย
www.seribangash.com
A Memorandum of Association (MOA) is a legal document that outlines the fundamental principles and objectives upon which a company operates. It serves as the company's charter or constitution and defines the scope of its activities. Here's a detailed note on the MOA:
Contents of Memorandum of Association:
Name Clause: This clause states the name of the company, which should end with words like "Limited" or "Ltd." for a public limited company and "Private Limited" or "Pvt. Ltd." for a private limited company.
https://seribangash.com/article-of-association-is-legal-doc-of-company/
Registered Office Clause: It specifies the location where the company's registered office is situated. This office is where all official communications and notices are sent.
Objective Clause: This clause delineates the main objectives for which the company is formed. It's important to define these objectives clearly, as the company cannot undertake activities beyond those mentioned in this clause.
www.seribangash.com
Liability Clause: It outlines the extent of liability of the company's members. In the case of companies limited by shares, the liability of members is limited to the amount unpaid on their shares. For companies limited by guarantee, members' liability is limited to the amount they undertake to contribute if the company is wound up.
https://seribangash.com/promotors-is-person-conceived-formation-company/
Capital Clause: This clause specifies the authorized capital of the company, i.e., the maximum amount of share capital the company is authorized to issue. It also mentions the division of this capital into shares and their respective nominal value.
Association Clause: It simply states that the subscribers wish to form a company and agree to become members of it, in accordance with the terms of the MOA.
Importance of Memorandum of Association:
Legal Requirement: The MOA is a legal requirement for the formation of a company. It must be filed with the Registrar of Companies during the incorporation process.
Constitutional Document: It serves as the company's constitutional document, defining its scope, powers, and limitations.
Protection of Members: It protects the interests of the company's members by clearly defining the objectives and limiting their liability.
External Communication: It provides clarity to external parties, such as investors, creditors, and regulatory authorities, regarding the company's objectives and powers.
https://seribangash.com/difference-public-and-private-company-law/
Binding Authority: The company and its members are bound by the provisions of the MOA. Any action taken beyond its scope may be considered ultra vires (beyond the powers) of the company and therefore void.
Amendment of MOA:
While the MOA lays down the company's fundamental principles, it is not entirely immutable. It can be amended, but only under specific circumstances and in compliance with legal procedures. Amendments typically require shareholder
What is the TDS Return Filing Due Date for FY 2024-25.pdfseoforlegalpillers
ย
It is crucial for the taxpayers to understand about the TDS Return Filing Due Date, so that they can fulfill your TDS obligations efficiently. Taxpayers can avoid penalties by sticking to the deadlines and by accurate filing of TDS. Timely filing of TDS will make sure about the availability of tax credits. You can also seek the professional guidance of experts like Legal Pillers for timely filing of the TDS Return.
What is the TDS Return Filing Due Date for FY 2024-25.pdf
ย
Using sdbr in rapid response project
1. 1
Using SDBR in Rapid Response Projects
By Eli Schragenheim
Introduction
Simplified DBR (SDBR) has become the standard production planning method for all VV
projects. This document describes the make-to-order aspects of implementing SDBR. The
make-to-stock aspects will be dealt later in time. Many implementations use both make-to-stock
and make-to-order. This document makes only brief comments on how to handle both.
One of the necessary conditions for offering successfully RR orders is being able to maintain
close to 100% reliability of the regular orders. To achieve such reliability we have to be able to
quote safe due-dates that are reasonable to the customers while taking the capacity of the CCR
(capacity-constraint resource) into account.
The next stage is to see how can we offer RR orders while NOT tampering with the
commitments already given for the regular orders.
The following document first presents the definition of SDBR relative to the traditional DBR, the
planned load concept and how it relates to the finite-capacity schedule of the CCR.
Then the technique for providing safe due-dates for regular orders is discussed. This section also
makes the distinction between the production lead-time and quoted-lead-time.
Next the need for reserving capacity on the CCR is presented, and the proposed process is
discussed. Determining the release dates for the RR orders and other orders that take advantage
of the reserved capacity.
The last part discusses the execution rules for such an implementation.
SDBR, DBR and the planned load
Simplified DBR includes only one buffer: the shipping buffer. This is true for both MTO
(make-to-order) orders and MTS (make-to-stock, or rather make-to-availability). This is
certainly applicable when there is enough protected capacity even on โthe weakest linkโ in the
shop floor, so there is no need to protect the limited capacity of any resource within the shop.
We now propose that SDBR could be used effectively also when an internal capacity-constraint-resource
(CCR) is active.
Traditional DBR uses a 3-buffer system to protect both the due-dates AND the detailed finite-capacity
schedule of the CCR. This is far more protection than just keeping the CCR from
starvation due to a delay, or lack of priorities, on the non-constraints. The CCR buffer is used to
keep the actual sequence intact. Now, when we use only one buffer, protecting the due-date, we
should have two concerns:
2. 2
1. Failing to properly exploit the CCR capacity, especially causing starvation of the CCR or
having too much setup time on the CCR.
2. Being unable to smooth the load through the planning time frame. The undesired result
could be that we stick to a too long time-buffer or quote an unrealistic due-date.
The first concern could and should be handle by the foremen and the production manager as
part of the execution process. In any VV project we recognize the market demand as the only
constraint. That means we cannot tolerate true bottlenecks in the shop floor. In other words, we
should have protected capacity even on the weakest link in the shop floor. It still does not mean
we can ignore any capacity considerations, but it means we are reluctant to give up valid market
demand because of lack of capacity.
So, how should we monitor the capacity of a fairly loaded CCR?
We expect the production manager to monitor the smooth CCR execution by avoiding starvation
as possible, bearing in mind that when the demand is relatively low some starvation on the
weakest link (the resource we treat as a CCR) would naturally happen. But we do not need to
determine the exact sequence at the CCR ahead of time. The actual sequence should be
impacted by the buffer management priorities and possible by setup time considerations when
merging some orders to save setup time does not cause serious red penetration into the shipping
buffer.
In too many times the actual sequence on the CCR has to be determined by the operators! This
is especially true in complex operational environments where the sequence has huge
ramifications on quality and on setup and process times. Most such complex environments do
not have generic software that can handle the complexity. For instance, I donโt know of any
current DBR software that is capable to schedule a CCR that consists of several ovens, which are
not identical, and in which several orders are grouped together based on their volume and quality
considerations. In such a case you should provide a long enough shipping buffer that would
naturally provide enough choice for the foreman for real time decisions. Trusting the knowledge
of the people on the floor
To handle the second concern we need, first of all, a tool to identify situations where too much
load threatens the standard time for deliveries. Identifying this situation is the first task of the
planned load.
Definition: Planned load is the accumulation of the derived load on the CCR (the
weakest link) for all the firm orders that have to be delivered within certain
horizon of time.
For instance, suppose we have to deliver four orders within the standard time of one week.
Order1 needs 10 hours of work on the CCR. Order2 requires 15 hours, Order3 only 4 hours and
Order4 10 hours. The planned load is simply the total of 10+15+4+10=39 hours.
Planned load is expressed in hours or days of work. Naturally it should be, at all times, less than
the standard quoted lead-time offered to the market. The amount of time difference between
3. 3
the standard quoted-lead-time and the planned load represents the current amount of protected
capacity on the CCR and thus on the shop floor. Certainly we must have a minimum time
difference between the planned load and the standard lead-time to ensure that the last firm order
would still have enough time from the CCR until completion. Take the above example. If the
regular week is made of five working days, eight hours a day, than the standard lead-time is 40
hours. But, the planned load of 39 hours seems too long to ensure safe delivery of all orders
within a week.
While the planned load isnโt a โscheduleโ, it does have some key characteristics of a finite
capacity schedule. The most important one: assuming the CCR is able to work continuously, it
signals the reasonable time when the CCR is able to work on a new order, assuming no
special priority for that order. This means we can assess a safe completion time taking the
planned load into consideration and adding some time buffer to provide enough time for the non-constraints
downstream of the CCR. Weโll detail the process of quoting due-dates later in this
document.
Thus weโve overcome the two main concerns from not scheduling the CCR.
But, what do we gain by using just one buffer without a detailed schedule of the CCR?
Finite-capacity-scheduling of the CCR is based on the orders and priorities as known at the time
of the planning. Any request for a change would either be ignored until the next scheduling
session, or necessitates re-scheduling, which results in a shuffle of the older schedule. This
means that any local noise would impact the whole system, rather then just the local area. Thus
even a small change, like bringing one order backwards in time, creates quite a lot of noise in the
shop. The more troubling point is that the โsafe due-datesโ that were given based on the CCR
detailed schedule are not truly โsafeโ.
Scheduling the CCR is especially problematic in make-to-stock, because the priorities could
change significantly from one day to another because of a sudden surge of sales.
Hence, the move to SDBR, with the usage of the planned load to determine safe due-dates, and
with the capabilities of reserving capacity for rapid-response orders and some other types of
orders, seems as a superior method for VV projects when the linkage between Operations and
Sales is under full control.
Quoting Safe Due-dates for Regular Orders
The shipping buffer is a liberal estimation of the time required from material release until the
safe completion of the order.
We have several key assumptions when we determine the shipping buffer:
1. All known policy constraints have been eliminated. Policies like batching norms, transfer
batch made equal to the process batch and early release of orders. The assumption is that
4. 4
those flawed policies, norms and behaviors that are derived by the efficiency
measurements have been eliminated.
2. We control the amount of work-in-process by choking the release of orders according to
the load on the CCR. This means that the shipping buffer can be much shorter than the
quoted lead-time, because the quoted lead-time has to consider the wait time for the
order to be released to the floor as the CCR has many prior orders to work on. The
shipping buffer only considers the time from actual release to completion, taking into
account just enough WIP to ensure the smooth work of the CCR.
The current planned load, the accumulation of the load on the CCR, from all the firm orders,
looks like the following chart:
The front of the planned load signals when, on average, the CCR would be able to work on the
new order. This is, of course, a very approximate estimation. We do not know the exact
sequence the CCR would work on the previous orders. We do not really know how much setup
time will be required for the actual sequence, and we are not absolutely certain that the
processing time data is precise, even though we like it to be as accurate as possible. So, what we
have is a good assumption regarding the timing the CCR could work on the next order to be
received.
As we have only one buffer, letโs decide to release the materials ยฝ the time-buffer prior to the
time the CCR is supposed to work on it. This is not a very critical assumption, as the timing on
the CCR is not all that concrete. We assume that within ยฝ of the overall shipping buffer enough
orders will show up at the CCR to prevent unnecessary starvation. Note that when the CCR is
not truly active, meaning it does have significant amount of excess capacity, it should be idle
from time to time.
Here it is how it looks like:
Time (days)
Load
We can commit available
capacity from here
Accumulated
load of all
orders in the
system
Daily
capacity
5. 5
50% buffer
Time (days)
Load
We release
the order
here
Planned Load
A clarification may be in place here. In the traditional DBR the CCR buffer is designed to
protect the detailed schedule of the CCR โ not just prevent starvation. The CCR buffer is put
specifically for each instruction in the schedule, where in SDBR we use half of the total buffer
(the shipping buffer covers the whole route from raw materials to completion) to determine the
material release. All the materials get the same time release for an order. The release is dictated
by the front planned load before the new order is added to it.
When should be promise the order? It seems now obvious that we could get a safe delivery time
by adding ยฝ a shipping buffer to the current front of the planned load.
This is how it looks like in the graph.
50% of buffer
50% of buffer
full buffer
Time (days)
Load
We can
csaafne ly
deliver here
Release
point
Note that we CAN safely deliver at that time, question is: should we promise to deliver at that
date?
6. 6
The point is that we do not want to offer a very early delivery time, safe as it may be in that point
of time, which is earlier than the standard time. When we have rapid response in mind, we better
not spoil our future customers with too early delivery.
So, if the safely time is shorter than the standard time then we should extend the buffer until the
standard time.
Addition
to Additional
full buffer tbtohu eff ebru ffer
release llead ttiime
point
Time
(days)
Load
Safe
delivery
Standard
lead time
We
promise
standard
The idea here is to release the order early enough to ensure the CCR is not starved, hoping more
demand will show up in the short term. If weโd delay the material release to provide the regular
buffer, the possible negative branch is a waste of the CCR capacity. This would happen when a
low demand period is followed by a very high demand period. If the capacity of the CCR was
properly used in the low period, then it could do more in the high period without threatening the
safe delivery within acceptable quoted lead-time.
An example to demonstrate the process:
Suppose that right now we have 30 open regular orders that should take 320 hours on the CCR.
The standard lead-time for regular orders is 6 weeks. The factory works 6 days a week with two
8-hours shifts a day. The shipping buffer is 10 days, or 20 shifts.
When can we offer a reliable delivery date for a regular order?
The front of the planned load is at 320 hours from now. We have available capacity of 16 hours
(2 shifts) a day. That means 20 days. We work 6 days a week, so the planned load is at 3 weeks
and 2 days from now. The reliable due-date is the planned load plus half of the buffer: plus 5
days. So, the safe date is 4 weeks and one day from the current date.
In this case weโll stick to the standard time of 6 weeks from now.
The order will be released to the floor according to the planned load minus half of the shipping
buffer: 20 days minus 5 days: 15 days โ two weeks and three days from now.
As the delivery date is 6 weeks from now (36 days), the specific order will have a larger than
usual buffer of: 36-15=21 days instead of the regular buffer of 10 days. This means we have a
7. 7
substantial amount of excess capacity, which would enable offering the rapid response offer,
provided excellent due-date performance is established.
Offering the RR
Ensuring very high reliability of on time delivery is absolutely necessary for launching the RR
offering. But, even from just an operational perspective, it is not sufficient.
In order to commit to certain clients, whenever the need arises, safe delivery in fast and even in
super-fast time frame, the production lead-time must be short enough to provide the ability to do
that.
How fast the production lead-time needs to be? The shipping buffer, the liberal estimation of the
production lead-time, needs to be about the length of super-fast time frame.
One could argue that in many DBR implementations we sometimes accept an order to be
delivered in significantly less than the regular shipping buffer. The rational is that the buffer
length contains a lot of protection and most orders do not even penetrate into the red zone.
Hence, when we are faced with lucrative order to be delivered in, say half of the regular shipping
buffer, it is a โmission possibleโ. Of course, we assume that naturally such an order, which
penetrates into 50% of the buffer from day one, would get high priority, and other orders would
โpave the wayโ for it to reach completion on time.
While this is quite true for an incidental opportunity, it is quite a different case to commit to such
a delivery on a regular basis. It is possible to promise and deliver a very fast delivery once at a
time without disrupting the on time delivery of regular orders.
But, how many orders, whose quoted lead-times are about half of the shipping buffer, can you
handle at the same time? When you have several โsuper-priorityโ orders then there is a real risk
that some of the regular orders will be late. And when this happens โ your reputation as a very
reliable supplier goes away.
Thus we need to have a reliable production lead-time that is approximately the same as the
super-fast quoted lead-time. That means we need to reduce the production lead-time to about
a quarter (1/4!) of the standard lead-time. This would ensure that a new super-fast order
would be released immediately, but not automatically get higher priority than regular order that
was released at the same day.
Still, even with very short production lead-time we must ensure enough capacity to supply all
orders: the fast ones as well as the regular ones upon which the reputation of being very reliable
is based on.
When we commit to deliver at a certain date we take into account the current orders in the
logbook. If we might get orders whose delivery dates are definitely earlier than the date we just
promised, there is a real risk that we wonโt be able to keep our promise. To overcome this risk
we must ensure that capacity commitments will be preserved. Hence, we have to reserve a
certain amount of capacity to the RR orders when we consider the safe delivery dates for regular
orders.
8. 8
The idea is to calculate the planned load for regular orders on only 70 or 80% of the available
capacity, leaving 20-30% of the capacity for the RR orders (and some other orders as weโll see
later).
Onlly thiis portiion iis free for allllocatiion to
normal orders
Reserved
Super fast Fast Standard lead time
A simple example to illustrate the notion of capacity reservation:
Letโs continue the previous example. The standard quoted lead-time is 6 weeks. The shipping
buffer is 10 days (20 shifts). The shop works 6 days a week, two shifts a day.
The Fast RR offer is for 3 weeks delivery. The Super-fast offer is for 1.5 weeks, which means 9
working days. Just one day less than the shipping buffer.
Suppose we already launched the RR offer, and we decided to reserve 25% of the total capacity
for the RR orders.
Today we have 396 hours of CCR load from firm regular orders in the logbook (yes, the demand
went up since the reliability was established and recognized). Then we have also 20 hours of the
CCR for Super-Fast orders and another 40 hours for Fast orders.
First letโs calculate when can we promise safe delivery of a new regular order. As 25% of the
capacity is reserved, we have only 12 hours per day (16 hours minus 25%) for regular orders.
So, in order for the CCR to process all the existing regular order it would take: 396:12=33 days.
To promise safe delivery we need to add half of the shipping buffer: another 5 days. So, we
come now to 38 working days from today, or 6 weeks plus 2 days. So, reserving 25% of the
capacity means having to quote a somewhat later delivery than the standard. However, that date
is fully guarantied. The order will be released 33-5=28 days from now, and the whole shipping
buffer will be the regular 10 days buffer.
Now, suppose an additional Super-Fast order is received today. The delivery date is fixed: 9
working days from now.
The order material release is based on the due-date minus the shipping buffer. In this case it is
clear we must release the order TODAY. The buffer status for that order is (10-9)*100/10=10%
(10% penetration into the buffer due to the requirement to deliver in 9 days rather than 10 days).
9. 9
So, any new Super-Fast order has some small precedence on other orders that are released today.
But, thatโs not too much to cause any real problems.
A Fast order received today is to be delivered in 3 weeks: 18 working days. The buffer is 10
days, so weโll release the order only 8 working days later than today! See, the reduced shipping
buffer allows us to wait until we release an order that is part of the RR offering and we get much
better price for it.
Launching the RR Offers
We need to be somewhat careful when we tell the first time the prospects for the RR that we are
ready to accept any order for Fast or Super-Fast delivery. At that time the orders in the
logbook were given dates based the full amount of CCR capacity. Hence, there is a need to
reserve the capacity for the RR and the earliest time we can be certain to have the reservation is
the current planned load time.
Hence, the RR launch date from when we decide we are absolutely ready is the front of the
planned load.
If we take the above example, assume we have 396 hours of the CCR planned-load, based only
on regular orders. That means, according to 16 hours a day (no reservation of capacity yet) the
calculation come to: 25 working days from now (no need to be more precise).
So, 25 working days of the full CCR capacity are already committed. We can accept Fast and
Super Fast order starting from that date! Any new regular order coming today should be based
on 25 days from now, plus 75% of the CCR capacity from that day onward.
Managing the RR orders
Once orders are released to the floor, the priorities in the floor are dictated by their buffer
statuses. RR orders do not have special priority. In no way the CCR should stick to the
sequence that appeared in the planned load. Certainly we do not mean to tell the CCR, or any
other resource, to work 75% of the day on regular orders and 25% of the RR orders.
Naturally when there are no RR orders the CCR works 100% of its available capacity on regular
orders. When this happens then the planned load gets shorter in time, because the calculations
consider capacity reservation.
When many RR orders show up they could consume more capacity of the CCR than what was
reserved. Then the planned load would increase and new orders would get a later date. The
existing regular orders would be squeezed to some degree (as less capacity of the CCR is used
for the regular orders), but the shipping buffer and buffer management should be able to support
the on time delivery of all orders.
But, we need a mechanism to determine whether the reservation percentage is about right.
10. 10
The planned load as was defined above contains only the regular orders. The RR orders are
supposed to be done by the use of the reserved capacity. Hence, we could fill in the reservation
part with the Super-Fast and Super orders and see where it could take us.
In the following figure we show the two load representations: the regular orders planned load,
and the reservations part, partially filled in. This is because every order in the reservation part
has to be delivered within the Fast time, while the regular planned load includes orders to be
delivered up to the standard time.
Order1 Order2 Order3 Order4 Order5 Order6 Order7
RR1 RR3 RR4 Reserved capacity
Standard
time
Super Fast Fast time
time
RR2
What can we deduce from the above graph? It seems there is no clear threat to the regular orders
coming from the amount of Fast and Super-Fast orders. Of course, if all the four RR orders are
Super Fast orders then we could have a problem. In such a case all the CCR capacity within the
Super-Fast time would be dedicated, first of all, to the orders that are due within very short time.
That means certainly the Super-Fast orders, but could be also some regular orders. According to
the graph Order1 might be to be delivered before the Super-Fast time also. Such a short term
peak could cause a growing pressure on the CCR and a threat to the timely delivery of Order2.
Other orders might not be in trouble at all, as currently the reserved capacity is not fully taken.
Certainly we need buffer management on top of the above graphs to manage all the orders, and
we need POOGI to have a clearer idea whether the amount of reservations is too high or too low.
For a short-term capacity control a picture of all the orders that are due within the red-zone of the
shipping buffer, and a picture of all the orders due in full shipping buffer time is quite relevant.
The planned load procedure ensures no peaks of loads on the CCR due to regular orders, but the
RR orders might cause temporary peak of load, especially within the short time frame of one
shipping buffer.
This kind of graph showing the short-term load should take into account ALL orders, both
regular or rapid response, that their respective due-date falls within the specified horizon.
Suppose that in the above graph, all RR orders are Super-Fast, and Order1 is also due in the time
frame of Super-Fast from now. Taking all orders and all available capacity we get this
relationship of CCR capacity to the time frame:
11. 11
Order1
R
R2
R
R1
R
R3
Standard
time
Super Fast Fast time
time
RR4
It is sensible to assume the CCR would first work on those five orders, which are due before the
other orders and thus we expect their buffer status reflect higher priority.
Are we certain that those five orders will all be delivered on time? This is definitely a
problematic situation, and we better not let this state to happen. The problem is clear because
there is not much time left for RR4 to provide enough time to reach completion. We need the
exact buffer management statuses to really assess the situation.
Another question is whether the short-term peak of load wonโt have a negative impact on other
orders, those that should be delivered sometime later to the Super-Fast time, but not much later.
Certainly having the CCR work solely on orders that are due very soon endangers orders that are
due later. To have a better idea we should look for the total planned load of all orders that are
due in Fast time frame:
Order1
R
R2
R
R1
R
R3
RR4 Order2 Order3
Super Fast Fast time
time
Here the difference between the Fast Time and the CCR load of orders due before or at the Fast
time looks reasonable. Actually weโd like to see that there is half a shipping buffer difference to
feel about right.
So, right now the Fast time frame looks about right. But, it is quite heavy when you consider the
possibility that if more Super-Fast order would show up and take the rest of the capacity. Hence,
a good capacity control should deduce that there is a need for higher level of reserved capacity
OR elevate the CCR capacity.
All in all we do get signals when capacity pressure starts to build. If there is a quick way to
increase capacity when truly needed then the above situation could be easily handled.
Otherwise, we need to employ a more cautious capacity planning, reserving more capacity for
the RR orders, to ensure we do not threaten the due-date performance of all orders and
commitments.
More needs for capacity reservation
12. 12
The need to reserve capacity on the CCR stems from committing to ship certain future orders
earlier than the current planned load of the CCR. In other words, the current planned load shows
only part of the actual load, and thus committing to a due-date based on it is not really safe.
The RR orders are typical to such orders that, once they are received, we must ship them earlier
than the dates we already quoted to regular orders. There are other types of orders like this:
Strategic clients with whom we have a fixed delivery time.
Products that have significantly shorter standard lead-times than the main bulk of orders.
Products that are made to stock (MTS).
Letโs deal first with short-lead-time products. Suppose that while the regular orders have
standard lead-time of 6 weeks, a more routine type of products have industry standard lead-time
of only 3 weeks. Both types need the CCR, but the routine products need very short processing
time, hence the perception in the market is that these products should be delivered pretty fast.
As long as the front of the planned load is such that 3 weeks would still be safe due-date,
meaning the front of the planned load is appropriately earlier than 3 weeks then there is no
problem. We still would promise safe due-dates to all regular orders within the time frame of the
standard lead-time and be very reliable on time delivery.
So, the problem is valid only when the planned load of the CCR goes beyond the standard lead-times
of the short-lead-time products. Then when you promise delivery to a long-standard-lead-time
item you donโt know how many short-lead-time items you might get. Of course you could
quote all delivery times based on planned load even when the standard time is short.
You are invited to construct the cloud: quote a shorter lead-time to a routine order versus quote a
time based on the planned load.
There are two obvious solutions:
1. Tackle the cause of the problem. If the real constraint is market demand, why do we
need to be constrained by a capacity constraint? If we add capacity to the CCR, the
planned load would be within the time that would allow us to quote the standard lead-times
without any compromises.
2. Use the idea of capacity reservation for those products as well as for the RR orders.
The above discussion is valid for the strategic customers as well.
The make-to-stock products is a different case. It is quite common to have a hybrid environment
that has both MTO and MTS. Thus we might have a VV implementation with both RR and
VMI.
The concept behind producing to stock is to replenish frequently and quickly. The expectations
are to release daily orders for the stocked products based on the sales of yesterday. But, those
orders to not have a definite due-date, their respective priority will be determine according to
tomorrowโs sales.
13. 13
Of course, the production manager actually releases to the floor MTS orders considering the load
on the CCR and the relative priority of the stocked products. Once additional MTS orders are
released, some of them would spend more time in the shop and others would be expedited.
So, how should we handle the case of orders without definite due-dates?
I think we need to consider some amount of reserved capacity to ensure the ability to respond to
the MTS priorities. But, this amount is lower than the ratio of the load generated by MTS orders
to the total load. Thus, once MTS orders are generated their respective load on the CCR should
be included in the regular planned load. But, we have to reserve some amount to be able to
respond faster when necessary, without sacrificing the reliability of the RR and regular MTO
orders.
One important observation: It does not make sense to manage separate capacity reservations.
Certainly we can put all of them into one ratio of reserved capacity. Then we should monitor the
total amount of reserved capacity by watching the summation of the reserved orders actual load,
as was described above.
Simple versus sophisticated solution
Here is a generic cloud for many TOC practitioners, and too many other practitioners.
The relevancy of the cloud to the process described is that we have chosen many simplifying
steps and guidelines and some might be tempted to โimproveโ them. For instance, when we
determine the safe due-date we do not consider the net processing time of the order itself. Why?
Because it cannot be very significant relative to the buffer size (we still assume it is
manufacturing) and many times when we consider an order that was not formally received, we
do not know the amount of work on the CCR.
Also, the decision to use ยฝ of the shipping buffer to dictate the due-date and the release time is
also a very simplifying rule, but do we really need to go into details and ask what is the location
of the CCR in the routing? I certainly do not think so.
conflict
Have a successful
working solution in
place
Ensure smooth
execution of the
process
Implement a
very SIMPLE
solution
Draw the best
results out of
the solution
Implement a
sophisticated
solution
A
B D
C D'
14. 14
The injection of the cloud is to challenge the assumption that โIt is possible to get a significant
improvement over the simple solution.โ The challenge is to recognize the amount of the โnoiseโ
in the system and if the โsignificant improvementโ is not larger than the noise than weโll not be
able to really materialize the improvement.
Be aware to the amount of noise we have in a typical RR implementation. Usually the
assessments of how much CCR time we need are not very good (most of the RR orders are
customized products), the assessment of the buffer is very approximate, we have very vague idea
how many RR orders will be received etc. Sticking to the simple straightforward solution is so
much easier to implement and ensure the people in the floor wonโt distort it in the future, which
is a very serious threat to the implementation.