SlideShare a Scribd company logo
PRESENTATION ON SUMMER INTERNSHIP
Prepared by : Mr. Udbhav
Institution : ------
Class : ------
Enrollment No.: ------
SUMMER INTERNSHIP
Company : NTPC Badarpur
Location : Badarpur, Delhi
Period : 26th May to 7th July
(6 weeks)
1. ABOUT THE COMPANY
 NTPC is India’s largest power producer, it was
established in 1975.
 It is an Indian Central Public Sector Undertaking
under the Ministry of Power, engaged in the business
of generation of electricity and allied activities. It is a
company incorporated under the Companies Act
1956.
 The total installed capacity of the company is 45,048
MW with 18 coal based and 7 gas based stations.
 It has been ranked as “6th Best Company to work for
in India” among the PSU and Large Enterprises for the
year 2014, by the Great Places to Work Institute,
India.
2. THE BADARPUR THERMAL POWER STATION
 It is one of the oldest power station in whole of
asia, its construction began in 1968 and first
unit was commissioned in 1973.
 It is a coal fired power station.
 It comprises of three unit’s each of 95MW
capacity and two unit’s each of 210MW
capacity.
 Its overall capacity 705MW, with an efficiency
of 36%.
3. POWER CYCLES
 The steam plant operates upon Rankine cycle
which is a vapour power cycle. Modification is
done to increase efficiency.
 It comprises of two isentropic compression and
expansion processes and two isobaric heat
transfer processes.
 Reheating is done by passing the steam to
boiler after 1st H.P. turbine and then passing
through a second L.P. turbine.
 In Regeneration some of the steam is bled off
and used to partially reheat the feed water.
Fig. 1 Plant Layout(acc. To cycle)
4. SOME TERMS INVOLVED
 Unit heat rate: The heat rate of a power plant
is the amount of chemical energy that must be
supplied to produce one unit of electrical
energy.
 Plant Load Factor(PLF): is a measure of
average capacity utilization. If can be affected
by non-availability of fuel, maintenance shut-
down, unplanned break down,etc. But since
power cannot be stored the generation has to
be adjusted. The formula = Gross Generation
/ (Installed Capacity * Number of Hours)
TERMS (contd.)
 Specific Fuel Consumption: This is the
amount of fuel(coal) used to produce a unit
power, for NTPC badarpur it is 0.6kg/kWh.
 Planned Maintenance: It is a planned,
documented and scheduled procedure to be
completed before a breakdown occurs.
 Forced Outage: It is the shutdown condition of
a power station when the generating unit is
unavailable to produce power due to
unexpected breakdown. It can be caused by
equipment failures, disruption in fuel supply,
operator errors etc.
5. COMPONENTS
 Boilers burn the fuel transferred from the tank
and use the resulting heat to convert water
into steam. Inside the boilers are tens of
thousands of water-carrying tubes. When
combustion commences, the temperature
inside the boilers rises to between 1,100 and
1,500°C, the water inside the tubes is turned
into high-temperature and high-pressure
steam, and the steam is transferred to the
steam turbines.
COMPONENTS (contd.)
 Turbines The steam rotates the turbine blades
at a high speed of 3,000 rpm. This turns the
power generator, which is directly connected to
the turbines, and electricity is produced as a
result. This electric power is then delivered
along power transmission lines and through
substations to the homes of customers. The
steam is cooled by seawater in a condenser,
restored to water, and then returned to the
boiler for reuse. This cycle of water to steam to
water is repeated over and over again.
COMPONENTS (contd.)
 Generator: An Electrical generator is a device
that converts kinetic energy to electrical
energy, generally using electromagnetic
induction. the generators must rotate at
constant synchronous speeds according to the
frequency of the electric power system, the
most common speeds are 3000 r/min for 50 Hz
systems.
 Plant Auxiliary: It comprises of all other
features like water treatment plant, feedwater,
cooling towers, ash handling, repair shops, etc.
6. MAINTENANCE OBJECTIVES
 To prevent plant breakdown.
 To increase the reliability of operating
functions.
 To minimize production loss due to failures.
 To keep the equipment safe and prevent safety
hazards.
 To improve the product quality and maximize
production utilization.
7. TYPES OF MAINTENACE PROCESS
8. CONCLUSION
The six week summer internship was
a great opportunity to analyze the
working of a thermal power plant and
recognize the commitment of the
work-force involved there.
THANK
YOU

More Related Content

What's hot

NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
Shrey Dhasmana
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial Training
Abhitendra Singh
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
Anubhav Ghosh
 

What's hot (20)

Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
ntpc
ntpcntpc
ntpc
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
NTPC Auraiya Industrial Training
NTPC Auraiya Industrial TrainingNTPC Auraiya Industrial Training
NTPC Auraiya Industrial Training
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivank
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Ntpc ppt
Ntpc pptNtpc ppt
Ntpc ppt
 
Ntpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training pptNtpc unchahar summer or vocational training ppt
Ntpc unchahar summer or vocational training ppt
 

Similar to Udbhav's presentation on ntpc

kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar
hariom nagar
 
6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP
Amit Bansal
 

Similar to Udbhav's presentation on ntpc (20)

report on VTPS
report on VTPSreport on VTPS
report on VTPS
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdfShivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
Shivam Dubey trainees mechanical engineering NTPC ltd.Vindhyachal .pdf
 
kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP6 weeks summer Training report on thermal power plant in DCPP
6 weeks summer Training report on thermal power plant in DCPP
 
NTPC Training Report
NTPC Training ReportNTPC Training Report
NTPC Training Report
 
Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Training reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishorTraining reporton ka tpp by naval kishor
Training reporton ka tpp by naval kishor
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
mosebaer report
mosebaer reportmosebaer report
mosebaer report
 
Kota tharmal plant new.pdf
Kota tharmal plant new.pdfKota tharmal plant new.pdf
Kota tharmal plant new.pdf
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
Thermal power plant.pptx
Thermal power plant.pptxThermal power plant.pptx
Thermal power plant.pptx
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
Kamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 

Recently uploaded (20)

NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdfDanfoss NeoCharge Technology -A Revolution in 2024.pdf
Danfoss NeoCharge Technology -A Revolution in 2024.pdf
 
Arduino based vehicle speed tracker project
Arduino based vehicle speed tracker projectArduino based vehicle speed tracker project
Arduino based vehicle speed tracker project
 
shape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptxshape functions of 1D and 2 D rectangular elements.pptx
shape functions of 1D and 2 D rectangular elements.pptx
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 

Udbhav's presentation on ntpc

  • 1. PRESENTATION ON SUMMER INTERNSHIP Prepared by : Mr. Udbhav Institution : ------ Class : ------ Enrollment No.: ------
  • 2. SUMMER INTERNSHIP Company : NTPC Badarpur Location : Badarpur, Delhi Period : 26th May to 7th July (6 weeks)
  • 3. 1. ABOUT THE COMPANY  NTPC is India’s largest power producer, it was established in 1975.  It is an Indian Central Public Sector Undertaking under the Ministry of Power, engaged in the business of generation of electricity and allied activities. It is a company incorporated under the Companies Act 1956.  The total installed capacity of the company is 45,048 MW with 18 coal based and 7 gas based stations.  It has been ranked as “6th Best Company to work for in India” among the PSU and Large Enterprises for the year 2014, by the Great Places to Work Institute, India.
  • 4. 2. THE BADARPUR THERMAL POWER STATION  It is one of the oldest power station in whole of asia, its construction began in 1968 and first unit was commissioned in 1973.  It is a coal fired power station.  It comprises of three unit’s each of 95MW capacity and two unit’s each of 210MW capacity.  Its overall capacity 705MW, with an efficiency of 36%.
  • 5. 3. POWER CYCLES  The steam plant operates upon Rankine cycle which is a vapour power cycle. Modification is done to increase efficiency.  It comprises of two isentropic compression and expansion processes and two isobaric heat transfer processes.  Reheating is done by passing the steam to boiler after 1st H.P. turbine and then passing through a second L.P. turbine.  In Regeneration some of the steam is bled off and used to partially reheat the feed water.
  • 6. Fig. 1 Plant Layout(acc. To cycle)
  • 7. 4. SOME TERMS INVOLVED  Unit heat rate: The heat rate of a power plant is the amount of chemical energy that must be supplied to produce one unit of electrical energy.  Plant Load Factor(PLF): is a measure of average capacity utilization. If can be affected by non-availability of fuel, maintenance shut- down, unplanned break down,etc. But since power cannot be stored the generation has to be adjusted. The formula = Gross Generation / (Installed Capacity * Number of Hours)
  • 8. TERMS (contd.)  Specific Fuel Consumption: This is the amount of fuel(coal) used to produce a unit power, for NTPC badarpur it is 0.6kg/kWh.  Planned Maintenance: It is a planned, documented and scheduled procedure to be completed before a breakdown occurs.  Forced Outage: It is the shutdown condition of a power station when the generating unit is unavailable to produce power due to unexpected breakdown. It can be caused by equipment failures, disruption in fuel supply, operator errors etc.
  • 9. 5. COMPONENTS  Boilers burn the fuel transferred from the tank and use the resulting heat to convert water into steam. Inside the boilers are tens of thousands of water-carrying tubes. When combustion commences, the temperature inside the boilers rises to between 1,100 and 1,500°C, the water inside the tubes is turned into high-temperature and high-pressure steam, and the steam is transferred to the steam turbines.
  • 10. COMPONENTS (contd.)  Turbines The steam rotates the turbine blades at a high speed of 3,000 rpm. This turns the power generator, which is directly connected to the turbines, and electricity is produced as a result. This electric power is then delivered along power transmission lines and through substations to the homes of customers. The steam is cooled by seawater in a condenser, restored to water, and then returned to the boiler for reuse. This cycle of water to steam to water is repeated over and over again.
  • 11. COMPONENTS (contd.)  Generator: An Electrical generator is a device that converts kinetic energy to electrical energy, generally using electromagnetic induction. the generators must rotate at constant synchronous speeds according to the frequency of the electric power system, the most common speeds are 3000 r/min for 50 Hz systems.  Plant Auxiliary: It comprises of all other features like water treatment plant, feedwater, cooling towers, ash handling, repair shops, etc.
  • 12. 6. MAINTENANCE OBJECTIVES  To prevent plant breakdown.  To increase the reliability of operating functions.  To minimize production loss due to failures.  To keep the equipment safe and prevent safety hazards.  To improve the product quality and maximize production utilization.
  • 13. 7. TYPES OF MAINTENACE PROCESS
  • 14. 8. CONCLUSION The six week summer internship was a great opportunity to analyze the working of a thermal power plant and recognize the commitment of the work-force involved there.