SlideShare a Scribd company logo
A
SEMINAR REPORT
ON
PRACTICAL TRAINING
AT
KALISINDH SUPER THERMAL POWER PLANT
In partial fulfilment for the award of the degree
Of
BACHELOR OF TECHNOLOGY
In
ELECTRICAL ENGINEERING
GOVT ENGINEERING COLLEGE JHALAWAR
SUBMITTED TO: SUBMITTED BY:
Mr Ashish Khandelwal Naval Kishor
Head of Department B. Tech. 4th Year
Department of Electrical Engineering Roll No. 2013UEE033
i
ACKNOWLEDGEMENT
I oblige to acknowledge my heartiest gratitude to all honourable people who helped me during
my summer training at KALISINDH THERMAL POWER PROJECT-JHALAWAR,
(RVUNL) RAJASTHAN.
I want to express my thanks to Mr. S. S. Meena (Chief Engineer of KaTPP), S. P. Meena
(Training Co-ordinator) for granting me the permission for doing summer training at this
project and to give their valuable time and kind co-operation.
I also thank a lot to other staff members of RRVUNL, BGR & TCE for their further co-
operation to gain the better knowledge about the excellent power plant project in Distt. –
Jhalawar, Rajasthan.
NAVAL KISHOR
B. Tech 4th Year
Electrical Engineering
ii
PREFACE
The rise in civilization is closely related to improvement in transportation and requirement of
energy that is not readily available in large quantities but is also readily transportable. A very
peculiar fact about electrical energy is that neither it is directly available in nature nor it is
finally used in this form, yet it is so widely produced and is the most popular high-grade energy.
The purpose behind this training is to understand the difficult concepts in a better way with
gain of knowledge. Report starts with a brief introduction about KALISINDH SUPER
THERMAL POWER PLANT followed by Lighting Arresters, Bus Bars, Insulators and Circuit
Breakers etc. While writing the report and while I was on my training, I was wondering that
science is ever expanding field and engineers are working hard day and night and makes the
life a gift for us.
iii
LIST OF CONTENTS
S. NO. NAME PAGE NO.
CHAPTER-1 INTRODUCTION 1-10
1.1 Contribution of TPP in India
1.2 Introduction to KaTPP
1.3 Energy generated in KaTPP
1.4 Plant Overview
1.5 Principle of Operation
1.6 Thermal plant operation procedure
1.7 Pulverised Coal Fuelled power plant
CHAPTER-2 COAL HANDLING PLANT 11-15
2.1 Introduction
2.1 Stages of CHP
CHAPTER-3 IMPORTANT PARS OF TPP 16-26
3.1 Boiler
3.2 Turbine
3.3 Generator
3.4 Condenser
3.5 Cooling Tower
3.6 Water treatment plant
CHAPTER-4 ESP & AHP SYSTEM 27-32
4.1 ESP System
4.2 AHP System
CHAPTER-5 CONTROL ROOM 33-34
5.1 Control & instrumentation system
CHAPTER-6 SWITCHING & TRANSMISSION SYSTEM 35-45
6.1 INTRODUCTION
6.2 Bus bars
6.3 Isolators
6.4 Insulators
6.5 Protective relays
6.6 Circuit Breakers
6.7 Lightening arresters
6.8 Current transformer
6.9 Potential transformer
6.10 CVT
6.11 Single line diagram
CHAPTER-7 EFFICIENCY 46
7.1 Efficiency
7.2 Cycle efficiency
iv
7.3 Boiler efficiency
7.4 Generator efficiency
7.5 Turbine efficiency
CONCLUSION 47
REFERENCE 48
v
LIST OF TABLES
S. NO. TABLE NAME PAGE NO.
1.1 Overview of KaTPP 4-5
2.1 Classification of coal 11
2.2 Wagon tippler 12
2.3 Crusher rating 12
3.1 15KW motor rating at KaTPP 16
3.2 Turbine specification 21
3.3 Generator specification 23
3.4 DG set parameters 24
6.1 Isolator rating 37
6.2 CB parameters 41
6.3 LA Parameters 42
6.4 CVT parameters 44
vi
LIST OF FIGURES
S. NO. FIGURE NAME PAGE NO.
1.1 Rankine cycle 1
1.2 Contribution of different power sectors in India 2
1.3 Route between GECJ and KaTPP 3
1.4 KaTPP at a glance 4
1.5 Working of KaTPP 6
1.6 Working by rankine cycle 8
1.7 Energy conversion 9
2.1 Coal handling plant 14
3.1 Water tube boiler 17
3.2 Turbine 20
3.3 Internal structure of turbine 21
3.4 Outview of generator 23
3.5 Cooling tower 25
4.1 ESP unit 30
4.2 Working of AHP 32
4.3 AHP at KaTPP 32
5.1 Control & instrumentation 34
6.1 Switchyard of KaTPP 36
6.2 Basic relay circuit 39
6.3 Buchholz relay 40
6.4 Current transformer 42
6.5 Potential transformer 43
6.6 Single line diagram of KaTPP Switchyard 45
1
CHAPTER-1
INTRODUCTION
Everybody must be having a thought that a thermal power plant is a place where electricity is
produced. However, do you know how it is produced? How the chemical energy stored in fuel
is converted into heat energy which forms the input of power plant i.e. steam and electrical
energy produced by generator? Power is the single most important necessity for common
people and industrial development of nation. In a conventional power plant, the energy is first
converted to a mechanical work and then is converted to electrical energy.
The first energy conversion takes place in Boiler or Steam Generator, second in Turbine and
the last conversion takes place in the Generator.
A thermal power station is a power plant in which the prime mover is steam driven.
Water is heated, turns into steam and rotates the turbine, which drives an electrical
generator after that steam pass through in a condenser where it condensed and recycled
to again in boiler this whole cycle is known as RANKINE CYCLE.
Fig. 1.1 Rankine Cycle
2
1.1) CONTRIBUTATION OF THERMAL POWER PLANT IN INDIA
In India, Thermal Power Plants contribute about 60% of the total electricity produced.
Pie chart shows the electricity production percentage by different sectors-
Fig. 1.2 Contribution of different sectors of power supply in India
1.2) INTRODUCATION OF KaTPP
Kalisindh Super Thermal Power Project is located in Jhalawar, Rajasthan. The project site is
about 12 km from Jhalawar Distt. Headquarter and 13 km from Govt. Engineering College
Jhalawar. Site comprises of five villages viz. Nimoda, Undal, Motipura, Singharia, and Devri.
It is 2 km from state highway no. 19 and 8 km from Ramganj Mandi-Bhopal broad gauge rail
line.
The site selection committee of Central Electricity Authority has visited the Nimoda and its
adjoining villages of Jhalawar Distt. In addition, site was found techno- economical feasible
for setting up of a Power Project. The Govt. of Raj. have included this project in 11th five-year
plan. The estimated revised cost of the project is Rs.9479 Crores. M/s. TCE Bangalore has been
3
appointed as the technical consultant for the project. The state irrigation department has allotted
1200 mcft water for the project from proposed Kalisindh dam.
Fig. 1.3 Route between GECJ to KaTPP
The origin of the Kalisindh River is from northern slop of Vindya Mountains. The river enters
from MP to Rajasthan near village Binda. After flowing 145 km in Rajasthan, the Kalisindh
River merges in Chambal River near Nanera village of Distt. Kota.Its catchment area is about
7944 sq.km in Jhalawar & Kota Distt. The existing Dam is located at Bhawarasa village,
primarily for P.H.E.D. purpose is being uplifted for providing a storage of 1200 mcft water for
this power project.
The GOR has allotted 842 Bigha Government land and acquired 1388 Bigha private khatedari
land for the thermal project. Phase-1 is constructed on 1400 Bigha land only.EPC contract has
been awarded to M/s. BGR Energy System Chennai on dt.09/07/08, through ICB route at cost
Rs.4900 Crores. Ministry of coal, Govt. of India has allotted Paras east and Kanta basin coal
blocks to RVUN in Chhattisgarh state. The RVUN has formed new company under joined
venture with M/s. Adani Enterprises for mining of coal blocks and new company started the
work. Annual coal requirement for the project is 56 Lacs TPA.GOR also decided to setup two
new units of 2x660 MW in next few years.
4
Fig. 1.4 KaTPP at a glance
1.3) ENERGY GENERATED IN KaTPP
 Number of units=2
 Electricity generated by one unit=600 MW
 Total electricity generated by plant=2x600=1200 MW
1.4) PLANT OVERVIEW
Table 1.1 Overview of KaTPP
Project Kalisindh Super Thermal Power Project Jhalawar Rajasthan
Capacity 1200MW (2x600 MW)
Project Site Village-Undel, Motipura, Nimoda, Singhania & Deveri of
Tehsil Jhalarapatan, Distt-Jhalawar
Project Location The project site is about 12 km from NH-12, 2km from state
highway and 8 km from proposed Ramganj Mandi-Bhopal
broad gauge rail line.
Land Area 2230 Bigha/564 Hq. (1400 Bigha/350 Hq. in I stage)
5
Water Source and
quantity
Dam on Kalisindh river and 3400 CuM/Hrs.
Fuel Source Main Fuel-Coal from captive coal blocks (Paras east and kanta
Basin in Chhattisgarh state) Secondary Fuel-FO/HSD
Quantity of fuel (at 80%
PLF)
Coal-56 Lacs TPA FO/HSD-13000-14000 KL/A
Electrostatic Precipator 99.9 % Capacity
Stack Height 275 Mtr
Estimated revised cost Rs.9479 Crores
1.5) PRINCIPLE OF OPERATION
For each process in a vapour power cycle, it is possible to assume a hypothetical or ideal
process which represents the basis intended operation and do not produce any extraneous effect
like heat loss.
1. For steam boiler, this would be a reversible constant pressure heating process of water
to form steam.
2. For turbine, the ideal process would be a reversible adiabatic expansion of steam.
3. For condenser, it would be a reversible constant pressure heat rejection as the steam
condenser until it becomes saturated liquid.
4. For pump, the ideal process would be the reversible adiabatic compression of liquid
ending at the initial pressure.
When all the above four cycles are combined, the cycle achieved is called RANKINE
CYCLE. Hence, the working of a thermal power plant is based upon Rankine Cycle with some
modification.
1.6) THERMAL PLANT OPERATION PROCEDURE
The basic understanding of the modern thermal power station in terms of major systems
involved can be done under three basic heads viz. generating steam from coal, conversion of
thermal energy to mechanical power and generation & load dispatch of electric power.
6
Fig. 1.5 Working of TPP
1.6.1) COAL TO STEAM- The coal is burnt at the rate up to 200 tonnes per hour. From
coal stores, the fuel is carried on convey or belts to bunkers through coal tipper. It
then falls in to coal pulverizing mill, where it is grounded into powder as fine as flour.
Air is drawn into the boiler house by drought fan and passed through Preheaters.
Some air is passed directly to bunker and rest, through primary air fan, to pulverizing
mill where it is mixed with powdered coal. The mixture is then carried to bunker of
furnace where it mixes with rest of the air and burns to great heat. This heats
circulating water and produces steam, which passes to steam drum at very high
pressure. The steam is then heated further in the Super heater and fed to high pressure
cylinder of steam turbine. The spent steam is sent to condenser, where it turns back
to water called condensate. Condensate is sent to lower part of steam drum through
feed heater and economizer. The flue gases leaving boiler are used for heating
purpose in feed heater, economizer, and air Preheater. The flue gases are then passed
to electro-static precipitator and then, through draught fan, to chimney.
7
1.6.2) STEAM TO MECHANICAL POWER- Steam first enters the high-pressure
cylinder of turbine where it passes over a ring of stationary/fixed blades, which acts
as nozzle and directs steam onto a ring of moving blades. Steam passes to the other
cylinders through reheater and the process is repeated repeatedly. This rotates the
turbine shaft up to 3000rpm. At each stage, steam expands, pressure decreases and
velocity increases.
1.6.3) MECHANICAL POWER TO ELECTRICAL POWER- To obtained the
electrical power from mechanical power we connect the shaft to an alternator’s
armature. When the armature is rotated and electric, current is produced in the stator’s
windings. The generated electricity is of order 25,000 volts.
1.6.4) SWITCHING AND TRANSMISSION-The produced electricity is cannot to
transmitted as this state so It is passed to a series of three switches called an isolator,
a circuit-breaker, and another isolator. From circuit breaker, current is taken to bus
bars and then to another circuit breaker with its associated isolator before being fed
to the main Grid. Each generator has its own switching and transmission arrangement.
Three-phase system is used for power transmission.
1.6.5) CONTROL AND INSTRUMENTATION- Control and Instrumentation (C & I)
systems are provided to enable the power station to be operated in a safe and efficient
manner while responding to the demands of the national grid system. These demands
have to be met without violating the safety or operational constraints of the plants.
For example, metallurgical limitations are important as they set limits on the
maximum permissible boiler metal temperature and the chemical constituents of the
Feed water. The control and Instrumentation system provides the means of the manual
and automatic control of plant operating conditions to maintain an adequate margin
from the safety and operational constraints. Monitor these margins and the plant
conditions, and provide immediate indications and permanent records. Draw the
attention of the operator by an alarm system to any unacceptable reduction in the
margins. Shut down the plant if the operating constraints are violated.
8
1.7) PULVERIZED COAL FUELED POWER PLANT
A typical pulverized coal fuelled power plant is based on Rankine Thermodynamic cycle. “A
Rankine cycle is a vapour cycle Furnace that relies on the isentropic expansion of high pressure
gas to produce work”. Let us see a super heat Rankine cycle:
Fig. 1.6 Working by Rankine Cycle
This facility first produces steam in a boiler (steam generator). This steam is used to
rotate turbine, which is connected to a shaft of generator. Hence, electricity is produced here.
The used steam is then condensed in a condenser and the condensed liquid is used again in the
steam generator. This is a simple phenomenon, understood by everybody.
For all this, we need a fuel. As the name suggest here coal is used as fuel. Coal is one of the
cheapest and most preferred fossil fuel used as a key to most of the power plants. Usually
delivered by train from Mines to the Coal Handing Plant (CHP). The CHP unloads this it
become more economical to unload the coal. Then the coal stacked, reclaimed, crushed, and
conveyed it to the storage silos near the steam generator. Then it is fed through the Feeder to
the Pulveriser. Feeder is mainly used to weight the amount of coal going to the Pulveriser per
hour. From the Feeder, the coal is fed to the Pulveriser, which powders it, and then it is carried
to the steam generator using pressurized air. Within the steam generator, the coal is atomized
and burned and the heat energy produced is used for producing steam. Here two types of steam
namely superheated & reheated steam are produced in a cycle. The steam turbine generator
9
converts the thermal energy of superheated and reheated steam to electrical energy. The first
energy conversion is carried in Boiler or steam generator; the second is carried out in Turbine
and the last one carried out in the Generator.
Initially the superheated steam is fed to High Pressure (HP) turbine. It has a temperature
of 540° C (approx.) and a pressure of about 140 Kg/cm2. Then the exhausted steam from it is
taken to the reheater so that it can be reheated and fed back to Intermediate Pressure (IP)
turbine. Here the temperature is maintained the same as that of superheated steam but pressure
is reduced to 35 Kg/cm2.
Fig. 1.7 Energy Conversion
Then the exhausted steam is directly fed to Low Pressure (LP) turbine having the reduced
temperature and pressure of about 1Kg/cm2. Then the exhausted steam from the LP section is
condensed in the condenser. Condensate Pumps move the condensed liquid from condenser
through Low Pressure Regenerative Feed water heaters to a Deaerator. Boiler Feed Pumps
(BFPs) moves the deaerated liquid through HP heaters to the steam generators. Extraction
steam is supplied to the LP & HP regenerative heaters to improve cycle efficiency. Then comes
to the system of fans which keeps the system working by providing the valuable air where
required.
There are three pairs of fans, namely, Forced Draft (FD) fan, Induced Draft (ID) fan, Primary
Air (PA) fan. FD fans supplies combustion air to the steam generator and PA fans transports
the coal into the steam generator. ID fans remove the flue gases from the steam generator and
exhaust it through chimney.
Cooling water for the condenser is supplied by the circulating water system, which takes the
heat removed from the condenser and rejects it to the cooling towers or other heat sink. This
10
all working is controlled from a single place called control room. It enables the operator to
direct the plant operation for reliable and efficient production of electrical energy. This is
achieved by the control system installed by the C & I group. These are DAS (Data Acquisition
System), ACS (Analog Control System), FSSS (Furnace Safeguard Supervisory System), and
other relays governing numerous activities.
Last but not the least is the switching and transmission methods used here. The generated power
cannot be transmitted as such. It is stepped up to 132 KV or 400 KV then passed through a
series of three switches an insulator, a circuit breaker and an isolator. Three-phase system is
used for the power transmission. Each generator has its own switchyard and transmission
arrangement.
11
CHAPTER-2
COAL HANDLING PLANT
2.1) INTRODUCTION
Every thermal power plant is based on steam produced on the expanse of heat
energy produced on combustion of fuel. Coal is categorized as follows depending upon fixed
carbon, volatile matter and moisture content:
Table 2.1 Classification of Coal
S. NO. NAME OF COAL % CARBON
1 Anthracite 86%
2 Bituminous 46 to 86%
3 Lignite 30%
4 Peat 5 to 10%
Coal from mines is transported to CHP in railway wagons. It is unloaded in track
hoppers. Each project requires transportation of large quantity of coal mines to the power
station site. Each project is established near coalmine, which meets the coal requirements for
the span of its entire operational life. For the purpose each plant has Merry Go-Round (MGR)
rail transportation system. The loading operation of the coal rake takes place while it is moving
under the silo at a present speed of 0.8 Km/hr. that the loading time for each wagon is one
minute. For unloading of coal from the wagons, an underground track hopper is provided at
the power station.
The term coal handling plant means to store and to handle the coal, which is transported
by the train, and convey to the bunkers with the help of belt conveyers. Through the bunkers,
coal is transferred to the coal mill and drifted to the furnace. The coal handling plant includes
wagon tippler, conveyer belt, crusher house, stacker & reclaimer, bunkers & coal mill.
 COAL SUPPLY IN KaTPP-Ministry of coal, Govt. of India has allotted Paras east and
Kanta basin coal blocks to RVUN in Chhattisgarh state.
2.2) STAGES OF COAL HANDLING PLANT
2.2.1) WAGON TIPPLER-The term Wagon Tippler contains two words WAGON &
TIPPLER. Wagon means the compartment of train, which is just like a container,
which is used to carry the coal from mines to generating stations, & the word Tippler
12
means a machine, which is used to unload the wagon into the hopper. Hopper is just
like a vessel, which is made of concrete, & it is covered with a thick iron net on its
top. Here big size coal pieces are hammered by the labors to dispose it into the hopper.
Table 2.2 Wagon Tippler
Capacity 90 tonnes
Types of Tipplers 1. Weighing type, 2. Non weighing type
Angle of Tip 30 ‘to 35’
Wire Ropes 1. Hoisting Ropes, 2. Counter Weight Ropes
Drive unit Motor 37.3 KW
Operating Cycle 10 wagons/Hour on 1 wagon Tippler
Time consume for one
cycle
6 minutes
2.2.2) FEEDER- It is used to control the supply of crushed coal to the mill depending upon
load condition. It is installed under wagon tippler and hopper. In KaTPP there are
four-unbalanced Motor Vibrating Feeder installed in unit 1st.
2.2.3) CHRUSHER/RING GRANULATOR-In ring granulator the material is fed in to
the crushing chamber and is crushed by the rind hammers with impact and rolling
action across the feed, with concentrated pressure. This cracks the coal producing a
granulator product with a minimum of fines upto 20 mm square.
Table 2.3 Crusher Rating
Capacity 500 Tonnes/hr.
Machine Weight 30 Tonnes(approx.)
Max Feed Rate 500 Tonnes/hr.
Rotor Speed 720 r.p.m.
Motor 550 HP
Volts 606 Kv
Phase 3 Phase motor
13
2.2.4) CONVEYORS-Conveyor belt is used to send the coal from coal storage yard and
used to send crushed coal from store to mill bunkers. The carrying capacity of
conveyors belt is 750 tonnes/hrs. that are installed in KaTPP.
Conveyor belt used in coal handling plant (CHP) are of two types
1. Five ply x1000 mm width with 5 mm rubber top side and 5 mm rubber bottom side.
Total thickness of belt: -17 to 18 mm
Power: -1000 KN/m2
2. Four Ply x1000 mm width with 5mm rubber top side and 5 mm rubber bottom side.
Total thickness of belt: -17mm
Power: -800KN/m2
Cold joints are used in joining the conveyor, conveyor belts run with the help of electric
motor, gearbox, fluid coupling geared coupling are installed at head of all conveyors.
2.2.4.1) PARTS OF CONVEYORS:
1) Flap Gate-it provide under coal transfer chutes for replacements of
crusher/conveyors.
2) Deflector Plate-Deflector plates are installed in the chutes coming on conveyors to
keep the coal direction in the centre of the conveyors.
3) Skirt board and Skirt Rubber-These are provided on tail end chutes to avoid
spillages of coal from Conveyors.
4) Stone Picker-Stone picker pick the stones from the running belt manually.
5) Metal Detector-Electromagnets are provided on conveyors to avoid and to save
crusher parts and entry of iron pieces in crusher. It also stops the entry of iron pieces
in coalbunker to save damage of coal mills.
6) Guide Idlers-These idlers help to train/guide the conveyors.
7) Return Idlers-These idlers carries the conveyors belts in return side.
8) R.T.I (Return Training Idler)-These idlers are provided on return side to guide
the conveyors.
14
9) Impact Idler-These Rubber idlers are provided under chutes through which coal
falls on conveyors.
10) Carrying Idlers-These are installed to run the conveyor.
Fig. 2.1 Coal Handling Plant
2.2.5) BUNKERS-Bunkers are fabricated to store the coal before sending to coal mills.
Coal is fed in the bunkers with the help of tripper trolleys installed at 37 m height for
unit 1st and 2nd.There are 20 bunkers for unit 1st and 2nd.
Capacity of a bunker=500 tonne/bunker.
2.2.6) COAL BUNKERS-These are in process storage used for storing crushed coal from
the handling system. Generally, these are made up of the welded steel plates with
vibrating arrangement of the outlet to avoid chocking of coal; normally there are six-
bunker supply coal to the corresponding mills. These are located on the top of mills
to add gravity feeding of coal.
2.2.7) RECLAIM YARD-After filing the coalbunkers extra coal is taken to reclaim yard
after crushing of coal to storage.
2.2.8) COAL CIRCULATION-Coal is transported from the coalmine with the help of
train. Train wagons are emptied with the help of wagon tipplers and sent to the
crusher for crushing. From coal crusher it goes to the bunker through conveyor belt
15
and from coalbunker, it moves to R.C feeder feeds coal to the coal mill, where the
coal is grinded in to powder form.
16
CHAPTER-3
IMPORTANT PARTS OF THERMAL POWER PLANT
3.1) BOILER
Boiler can simply be defined as the device where any liquid is boiled or Boiler may be
defined as a device that is used to transfer heat energy being produced by burning of fuel to
liquid, generally water, contended in it to cause its vaporization. Boiler, in simple terms, can
be called “Steam Generator”.
In simple way, boiler is a device used for producing steam. There are two types of boiler
(depending upon tube content):
a) Fire tube boiler
b) Water tube boiler
Here, boiler used is of water type. In the boiler, heat energy transfer takes place through tube
walls and drum. The gases lose their heat to water in the boiler or superheated. The escape heat
is used to heat the water through economizer.
ID and FD fans are used to produce artificial draught. The fuel oil is used to ignite the boiler
and pulverized coal is lifted from the coal mills by PA fans.
 WATER TUBE BOILER USED IN KaTPP WITH 97M HIGHT.
Various motors used in boiler are of different rating and parameters 32KW, 15KW, 11KW, &
3.3KW.
Parameter in 15KW motor
Table 3.1 15KW Motor Rating of KaTPP
Manufacturing CQ. GEAR BOX LTD.CHINA
Motor rating 15 KW
Speed 970 r.p.m
Rated voltage 416 V
17
Fig. 3.1 Water Tube Boiler
18
Rated current 28.4 A
Impedance voltage 80.0 %
Oil weight 20 Kg
Core winding weight 224 Kg
Total weight 600 Kg
Temp rise 50-55°C
3.1.1) BOILER AUXILIARIES-Efficiency of a system is of most concerned. Thus, it is
very important to maintain a system as efficient as possible. Therefore, Boiler
auxiliaries help in improving boiler’s efficiency. Following are the important
auxiliaries used
 ECONOMISER: Its purpose is to preheat feed water before it is introduced into
boiler drum by recovering heat from flue gases leaving the furnace.
 SUPER HEATER: It increase the temperature of steam to super-heated region.
 REHEATER: It is used for heat addition and increase the temperature of steam
coming from high-pressure turbine to 540°C.
 DRAFT FANS: They handle the supply of air and the pressure of furnace.
3.1.2) BOILER MOUNTINGS-These are used for the safe operation of boiler. Some
example of mountings used are water level indicator in drum, furnace temperature
probe, reheat release valve, pressure gauges indicating steam pressure etc.
3.2) TURBINE
Turbine is an m/c in which a shaft is rotated steadily by the impact of reaction of steam
of working substance upon blades of a wheel. It converts the potential energy or heat energy
of the working substance into mechanical energy. When working substance is steam, it is called
‘Steam Turbine’.
In the steam turbine, the pressure of the steam is utilized to overcome external
resistance and the dynamic action of the steam is negligibly small.
 Working principle of the steam turbine depends wholly upon the dynamic action of
steam. The steam is caused to fall with pressure in a passage of nozzle, due to this fall
in pressure, a whole amount of heat energy is converted into mechanical energy &
19
steam is set moving with the reactor velocity. The rapidly moving particle of steam
enter the moving part of turbine and here suffers a change in the direction of motion
which gives rise to change of momentum and therefore to a force. This constitutes a
driving force to a turbine.
The passage of them/through the moving part of the turbine commonly called the blade,
may take place in such a manner that the pressure at the outlet sides of the blade is equal to that
of the inlet side. Such a turbine is broadly termed as outlet turbine or Impulse type.
On the other hand, the pressure of the steam at outlet from the moving blade may be less
than that at type inlet side of the blade. The drop of pressure suffered by the steam during its
flow through the moving blades causes a further generation of kinetic energy within the blades
and adds to the propelling force, which is applied to the turbine rotor, such a turbine is broadly
termed as Reaction Turbine.
 Here in Kalisindh Thermal Power Project N600-16.7/587/537, Re-Het, Three Casing,
Four Exhaust, Tandem Compound Condenser Type Turbine Used.
The turbine is of tandem compound design with separate High Pressure (HP),
Intermediate Pressure (IP) and Low Pressure (LP) cylinders. The HP turbine is of Single Flow
type while IP and LP turbines are of Double Flow type. The turbine is condensing type with
single reheat. It is engineered on reaction principle with throttle governing. The stages are
arranged in HP, IP AND LP turbines driving alternating current full capacity turbo generator.
The readily designed HP, IP and LP turbines are combined and sized to required power
output, steam parameters and cycle configuration to give most economical turbine set. The
design and constructional feature prove their reliability in service and ensure trouble free
operation over long operating periods and at the same time ensuring high thermal efficiencies.
20
Fig. 3.2 Turbine
21
Fig. 3.3 Internal structure of Turbine
Table 3.2 Turbine Specification
Rated output with extraction flow 600 MW
Speed 3000 r.p.m
Main steam throttle flow at HP Inlet 1848.5 TPH
Main steam pressure to HP turbine inlet 167 kg/sq.cm
Main steam temperature. to HP turbine inlet 538°C
Re-heater steam flow at IP inlet 1587.942 TPH
Re-heater steam temperature. at IP inlet 538°C
Steam pressure at LP inlet 35.12 kg/sq.cm
Steam flow at LP inlet 1353.7 TPH
Rotation Direction (view from turbine) anticlock wise
Number of stages 42
22
High pressure turbine-
a) Intermediate pressure
b) Low pressure turbine
c) Governing system
1 governing and 8 pressure
5 pressure stage
28 pressure stage
DEH (digital electro hydraulic)
Inlet steam flow governing type Nozzle+throttle
Rated exhaust pressure 0.09 kg/sq.cm
Type of bearing turbine 6 journal +1 thrust
Turbine allowable frequency 47.5 to 51.5 Hz
Turning gear rotation speed 1.5 r.p.m
Ist critical speed of HP & LP rotor 1722 r.p.m
Ist critical speed of LP-A rotor 1839 r.p.m
Ist critical speed of LP-B rotor 1903 r.p.m
Heat regenerative extraction system
3 HP heater +1 Deaerator +4 LP
heater
Final feed water temperature 274.9°C
Maximum bearing vibration 0.076 m
Maximum allowable exhaust temperature. 80°C
Cooling water design flow at condenser 70200 TPH
3.3) GENERATOR
Generator is the important part of thermal power plant. It is a device, which converts
the mechanical energy into electrical energy. Generator is driven by coupled steam turbine at
a speed of 3000 r.p.m. Due to rotation at high speed it gets heated. Therefore, there is cooling
construction enclosing the winding core of the generator. Therefore, during the operation is
being in normal temperature.
In KaTPP, each of the 2 units have been provided with 3-phase turbo generator rated
output 706MVA, 18.525KA, 22KV, 0.85 lagging p.f., 984 rpm and 50 cycles/sec. The
generator has closed loop of hydrogen gas system for cooling of the stator and rotor at a
pressure of 4.5kg/sq.-cm (g).
23
Fig. 3.4 Out view of Generator
Table 3.3 Generator Specification
Made By CQ. GEAR BOX LTD. CHINA
Type QFSN
Apparent output 706 MVA
Active output 600 MW
Power factor 0.85 lagging
Rated voltage 22 KV
Rated current 18525 Amp
Rated speed 3000 r.p.m
Frequency 50 Hz
Phase connections Double gen. star
Cooling mode H20-H2-H2
Rated H2 pressure 4.5 Kg/sq.-cm
Terminal in generator 6
24
3.3.1) DIESEL GENERATOR SET
It is used to emergency purpose to supply auxiliary system of power plant.3 Set Diesel
generator are use in which one is standby.
Table 3.4 DG Set Parameters
Made BY STAMFOARD MAHARASTRA INDIA
Rating 1900 KVA
Speed 1500 R.P.M
Rated Current 2643.37 A
Rated Temp 40°C
AMPS 3.6 A
3.4) CONDENSER
In condenser, the water passes through various tubes and steam passes through a chamber
containing a large number of water tubes (about 20000).
The steam is converted into water droplets, when steam meets water tubes. The
condensate is used again in boiler as it is dematerialized water and 5-6 heats the water, which
was in tubes, during the process of condensation. This water is sent to cooling tower.
Condenser is installed below the LP exhaust. The condenser is of surface type made of
fabricated construction in single shell. The tube is of divided type double pass arrangement,
having two independent cooling water inlet, outlet and reverse and water boxes. This
arrangement facilitates the operation of one-half of condenser when the other half is under
maintenance. The condenser is provided with integral air-cooling zone at the centre from where
air and non-condensable gases are continuously drawn out with the help of mechanical vacuum
pump.
 Area of condenser = 9655 sq. m
 Cooling water flow rate = 2400 cubic m/Hr.
3.5) COOLING TOWER
It is a structure of height 202 m (tallest in the world) designed to cool the water (coming
from condenser) by natural draught. The cross sectional area is less at the centre just to create
25
low pressure so that ate air can lift up due to natural draught and can carry heat from spherical
drops. The upper portion is also diverging for increasing the efficiency of cooling tower. Hence,
it is named as natural draught cooling tower.
 In KaTPP two natural draught cooling towers (2 NDCT) is present with height 202 m each
for each unit.
Fig. 3.5 Cooling Tower
3.6) WATER TREATMENT PLANT
As everyone, know that the cost of any thermal power plant is cores of rupees. So major
problem of any thermal power plant is that how to prevent the corrosion. The water available
cannot be used in boilers as such. The objective of water treatment plant is to produce the boiler
feed water so that there shall be.
26
 No scale formation ·
 No corrosion ·
 No priming or forming problems
Water used in thermal power plant is called ‘Dematerialized Water’ or DM Water.
27
CHAPTER-4
ESP AND AHP SYSTEM
4.1) ELECTROSTATIC PRECIPITATOR (ESP)
Electrostatic Precipitator (ESP) is equipment, which utilizes an intense electric force to
separate the suspended particle from the gases. In India, coal is widely used to generate power.
The exhaust gases are emitted directly into the atmosphere; it will cause great environmental
problems. Therefore, it is necessary to extract this dust and smoke before emitted the exhaust
gases into atmosphere. There are various methods of extracting dust but electrostatic
precipitator is the most widely used. It involves electric changing of suspended particle,
collection of charge particles and removal of charge particles from collecting electrode. Its
various other advantages are as follows:
 It has high efficiency i.e. about 99%
 Ability to treat large volume of gases at high temperature
 Ability to cope with the corrosive atmosphere.
 It offers low resistance to the flow of gases.
 It requires less maintenance.
4.1.1) WORKING PRINCIPLE- The electrostatic precipitator utilizes electrostatic forces
to separate dust particles from the gases to be cleaned. The gas is passed through a
chamber, which contains steel plates (vertical) curtains. Theses steel curtains divide
the chamber into number of parallel paths. The framework is held in place by four
insulators, which insulate it electrically from all parts, which are grounded. A high
voltage direct current is connected between the framework and the ground, thereby
creating strong electric field between the wires in the framework curtains.
Strong electric field develops near the surface of the wire creates Corona Discharge
along the wire. Thus ionized gas produces +ve and –ve ions. In the chamber plates are
positively charged whereas the wire is negatively charged. Positive ions are attracted towards
the wire whereas the negative ions are attracted towards the plates. On their way towards the
curtains, negative ions strike the dust particle and make them negatively charged. Thus is
collected on the steel curtains.
The whole process is divided into the following parts:
28
 Corona Generation
 Particle Charging
 Particle Collection
 Particle Removal
Details of the following are given below-
 Corona Generation- Corona is a gas discharge phenomenon associated with the
ionization of gas molecules by electron collision in regions of high electric field
strength. This process requires non-uniform electric field, which is obtained by the use
of small diameter wire as one electrode and a plate or cylinder as the other electrode.
The corona process is initiated by the presence of electron in strong electric field near
the wire. In this region of corona discharge, there are free electrons and positive ions.
Both positive and negative coronas are used in industrial gas cleaning.
In case of negative corona, positive ions generated are attracted towards the negative
electrode or wire electrons towards collecting plates. On impact of negative and serve
as principle means of charging dust.
 Particle Charging- These are two physical mechanisms by which gas ions impact
charge to dust particles in the ESP. Particles in an electric fields causes localized
distortion in an electric filed so that electric field lines intersect with the particles of
maximum voltage gradient, which is along electric field lines. Thus, ions will be
intercepted by the dust particles resulting in a net charge flow to the dust particles. The
ions will be held to the dust particles by an induced image charge force between the ion
and dust particle and become charged to a value sufficient to divert the electric field
lines from particles such that they do not intercept.
o Particle Collection- The forces acting on the charged particles are
Gravitational, Inertial, Electrostatic and Aerodynamically. The flow of gas
stream is turbulent flow because it causes the particles to flow in random path
through ESP. Particles will be collected at boundary layers of collector pates.
However, if flow is laminar, charge will act on particles in the direction of
collecting electrode. This force is opposite to viscous drag force and thus in the
short time, particle would achieve Terminal (Migration) velocity at which
29
electrical; and viscous forces are equal. Thus the flow of the charged particle is
decided by the vector sum of these forces i.e. Turbulent.
 Particle Removal- In dry removal of dust collected on plates, Rapping Mechanism is
used. It considers of a geared motor, which moves along shaft paced near the support
collector electrode and is provided with cylindrical hammer. On rotating of shaft these
hammers, strike the supports causes’ plate to vibrate and dust is removed from plates.
Removed dust is collected in the Hoppers below the precipitator. At the time of starting
of precipitation of dust from flue gases, the hoppers are at normal temperature but the
ash collected is very hot. So there is a chance of ash deposit at the exit of the hopper
thus causing problem of removing the ash. To avoid this, heaters are provided which
increase the temperature at the exit point of the hopper thus avoiding any undue
accumulation of ash at starting. In other method, the water is allowed to flow down the
collector electrode and hence dust is collected in hoppers below.
4.1.2) GENERAL DESCRIPTION-
The whole ESP is divided into two parts-
 Mechanical System
 Electrical System
Here we will discuss only Mechanical System (i.e. Precipitator Casing, Emitting and
Collecting System and Hopper).
 Precipitator Casing-Precipitator Casing is made of 6mm mild steel plates with
required stiffness. The precipitator casing is all welded construction comprising of pre-
fabricated walls and proof-panels. The roof carries the precipitator internals, insulator
housing, transformer etc. Both emitting and collecting systems are hung from the top
of the casing.
 Emitting and Collecting System- Emitting System is the most important part of ESP.
Emitting system consists of rigid emitting frame suspended from four points on the top
of rigid emitting electrodes in the form of open spiral. The four suspension points are
supported on support insulators to give electrical insulation to the emitting frame. The
frame is designed to take up the retention forces of the emitting electrode. The emitting
electrode consists of hard drawn spiral wires and are fastened with hooks to the
discharge frame.
30
Collecting system mainly consists of collecting suspension frame, collection electrodes
and shock bars. Collecting electrode are made of 1.6 mm thick Mild Steel sheets formed
in ‘G’ Profile of 400mm width. Hook and guide are welded on one end and shock iron
on the dipped in rust preventive oil tank. Collecting electrodes bundles are properly
bundled in order to avoid any damage to electrode.
 Hoppers- Hoppers are seized to hold the ash for 8-hour collection and is provided under
the casing of ESP. It is of Pyramidal Shape and is 56 in number. It is preferred to
evacuate the hoppers at the earliest as long storage of dust in hopper leads to clogging
of hopper. Also at the bottom of hopper, electrical heating is provided to avoid any
condensation, which could also lead to clogging of hopper. Baffle plates are provided
in each hopper to avoid gas leakage.
Fig. 4.1 Electrostatic Precipitation Unit
4.1.3) RAPPING MECAHISM FOR COLLECTING SYSTEM- During electrostatic
precipitation a fraction of dust will be collected on the discharge on the discharge
electrodes and the corona will be suppressed as the dust layer grows. So rapping is
done in order to remove this dust by hammering the electrodes.
31
As the shaft rotates, the hammer tumbles on to the shock bar that transmits the blow to the
electrode. The completely rapping mechanism is mounted on a single shaft, which is collection
of ash on the collecting electrode.
4.2) ASH HANDLING PLANT (AHP)
ESP collects the ash produced on the combustion of coal. This ash is now required to
dispose off. Ash Handling Plant (AHP) solves this purpose of ash disposal. There are two types
of ash handling process undertaken by AHP.
 Dry Ash System
 Ash Slurry System
4.2.1) DRY ASH SYSTEM- Dry ash is required in cement factories as it can be directly
added to cement. Hence, the dry ash collected in the ESP hopper is directly disposed
to silos using pressure pumps. The dry ash from these silos is transported to the
required destination.
4.2.2) ASH SLURRY SYSTEM- Ash from boiler is transported to ash dump areas by
means of sluicing type hydraulic system, which consists of two types of system-
 Bottom Ash System
 Ash Water System
 BOTTOM ASH SYSTEM- In this system, the ash slag discharged from the furnace is
collected in water-impounded scraper installed below bottom ash hopper. The ash
collected is transported to clinkers by chain conveyors. The clinker grinders churn ash,
which is then mixed with water to form slurry.
 ASH WATER SYSTEM-In this system, the ash collected in ESP hopper is passed to
flushing system. Here low pressure water is applied through nozzle directing
tangentially to the section of pipe to create turbulence and proper mixing of ash with
water to form slurry. Slurry formed in above processes is transported to ash slurry sump.
Here extra water is added to slurry if required and then is pumped to the dump area.
4.2.3) FLY ASH SYSTEM-Even though ESP is very efficient, there is still some ash, about
0.2%, left in flue gases. It is disposed to the atmosphere along with flue gases through
chimney.
32
Fig. 4.2 Working of Ash Handling Plant
Fig. 4.3 Ash Handling Plant at KaTPP
33
CHAPTER-5
CONTROL ROOM
5.1) CONTROL AND INSTRUMENTATION SYSTEM
Control and Instrumentation (C & I) systems are provided to enable the power station to
be operated in a safe and efficient manner while responding to the demands of the national grid
system. These demands have to be met without violating the safety or operational constraints
of the plants.
For example, metallurgical limitations are important as they set limits on the maximum
permissible boiler metal temperature and the chemical constituents of the Feed water. The
control and Instrumentation system provides the means of the manual and automatic control of
plant operating conditions to maintain an adequate margin from the safety and operational
constraints. Monitor these margins and the plant conditions, and provide immediate indications
and permanent records. Draw the attention of the operator by an alarm system to any
unacceptable reduction in the margins. Shut down the plant if the operating constraints are
violated.
Most of the power plant operational controls are automatic. However, at times, manual
intervention may be required. Thus, the plant is provided with monitors and alarm systems that
alert the plant operators when certain operating parameters are seriously deviating from their
normal range.
.
34
Fig. 5.1 Control & Instrumentation System
35
CHAPTER-6
SWITCHING AND TRANSMISSION
6.1) INTRODUCTION
The electricity is usually produced in the stator winding of the large modern generators
at about 22,000 volts and is fed through terminal connections to one side of a generator
transformer that steps up the voltage 132000, 220000 or 400000 volts. From here conductors
carry it to a series of three switches comprising an insulator, a circuit breaker and another
isolator.
The circuit breaker, which is a heavy-duty switch capable of operating in a fraction of a
second, is used to switch off the current flowing to the transmission lines. Once the current has
been interrupted, the isolators can be opened. These isolate the circuit breaker from all outside
electrical sources.
From the circuit breaker, the current is taken to the bus bars-conductors, which run the length
of the switching compound and then to another circuit breaker with its associated isolates
before feeding to the grid.
Three wires are used in a ‘three=phase’ system for large power transmission. The centre of the
power station is the control room. Here engineers monitor the output of electricity, supervising
and controlling the operation of the generation plant and high voltage switchgear and directing
power to the grid system as required.
6.2) BUS BARS
Bus Bars are the common electrical component through which a large no. of feeders
operating at same voltage have to be connected.
If the bus bars are of rigid type (Aluminium types), the structure heights are low and
minimum clearance is required. While in case of strain type of bus bars suitable ACSR
conductors are strung / tensioned by tension insulator discs according to system voltages. In
the widely used strain type bus bars, stringing tension is about 500 - 900 kg depending upon
the size of conductor used.
36
Fig. 6.1 Switchyard of KaTPP
6.2.1) BUS BAR ARRANGEMENT MAY BE OF FOLLOWING TYPES, WHICH
ARE BEING USED IN KaTPP
1.) Single bus bar arrangement.
2.) Double bus bar arrangement.
a) Main bus with transformer bus.
b.) Main bus-I with Main bus-II.
3.) Double bus bar arrangement with auxiliary bus.
6.3) ISOLATORS
Isolators which are also called disconnect switches or air break switches after the
assembly as per drawings on the leveled structures the adjustment of connecting pipes, moving
and fixed contacts is done so that all the three phase of the isolator close and open
simultaneously and there is a full surface contact between moving and fixed contacts. Such
switches are generally used on both sides of equipment in order that repairs and replacement
37
of the equipment can be made without any danger. They should never be opened until the
equipment in the same circuit has been turned off and should always be closed before the
equipment is turned on.
The adjustment of the tendon pipes levelling of post insulator, stop holts in the fixed contacts
etc. is done for smooth operation of insulator. Following type of insulator are being used in
KaTPP-
a) Isolator without earth blades.
b) Isolator with earth blade.
c) Tendon isolator.
Table 6.1 Isolator Ratings
Type VB
Manufacturing by GR-power switchgear ltd Hyderabad
Rated voltage 420/245 KV
Rating 400/200A
Impulse voltage 1050KVp
Total weight 1300/950kg
Short time current 40KA for 3 sec
Control voltage 220V DC
6.4) INSULATORS
The insulators for the overhead lines provide insulation to the power conductors from
the ground so that currents from conductors do not flow to earth through supports. The
insulators are connected to the cross arm of supporting structure and the power conductors
passes through the clamp of the insulator. The insulators provide necessary insulation between
line conductors and supports and thus prevent any leakage current from conductors to earth. In
general, the insulators should have the following desirable properties:
38
1 High mechanical strength in order to withstand conductor load, wind load etc.
2 High electrical resistance of insulator material in order to avoid leakage currents to earth.
3 High relative permittivity of insulator material in order that dielectric strength is high.
4 The insulator material should be non-porous; free from impurities and cracks otherwise the
permittivity will be lowered.
5 High ratio of puncture strength to flash over.
6.4.1) TYPE OF INSULATORS
There are three types of insulators used for overhead lines:
 Pin Type
 Strain Type
 Suspension Type
6.5) PROTECTIVE RELAYS
A Protective relay is a device that detects the fault and initiates the operation of the circuit
breaker to isolate the defective element from the rest of the system.
The relays detect the abnormal condition in the electrical circuits by constantly measuring the
electrical quantities i.e. voltage, current, frequency, phase angle which are different under
normal and fault conditions. Having detected the fault, the relay operates to close the trip circuit
of the breaker, which results in opening of the breaker and disconnection of the faulty circuit.
Relay circuit connections can be divided in three parts:
1.) Primary winding of a C.T. that is connected in series with the line to be protected.
2.) Secondary winding of C.T. and the relay operating coil.
3.) Third part is the tripping circuit, which may be either a.c. or d.c... It consists of a source of
a supply, the trip coil of a circuit breaker and the relays stationary contacts.
When a short circuit occurs at point F on the transmission line the current increases to enormous
value. This results in a heavy current flow through the relay coil, causing the relay to operate
by closing its contacts. This in turn closes the trip circuit of the breaker, making the C.B. open
and isolating the family section from the rest of the system. In this way, the relay ensures the
safety of the circuit equipment from damage and normal working of the healthy portion of the
system.
39
Fig. 6.2 Basic Relay Circuit
Basic qualities that a protective relay must possess are:
1.) Selectivity
2.) Speed
3.) Sensitivity
4.) Reliability
5.) Simplicity
6.) Economy
6.5.1) BUCHHOLZ RELAY
It is a gas-actuated relay installed in oil-immersed transformers for protection against
all kinds of faults. It is used to give an alarm in case of incipient (i.e. slow developing) faults
in the transformer and to disconnect the transformer from the supply in the event of severe
40
internal faults. It is usually installed in the pipe connecting the conservator to the main tank. It
is a universal practice to use BUCHHOLZ relay on all such oil-immersed transformers having
ratings in excess of 750kVA.
Fig. 6.3 Buchholz Relay
6.6) CIRCUIT BREAKER
Circuit breakers are used for switching & protection of various parts of power
system. Circuit breaker is a piece of equipment, which can
1) Make or break a circuit manually or automatically under normal condition.
2) Break a circuit automatically under fault condition.
3) Make a circuit either manually or by remote control under fault conditions.
6.6.1) CLASSIFICATION OF CIRCUIT BREAKERS
They are generally classified based on the medium used for arc elimination
(i) Oil circuit breakers, which employ some insulating oil for arc extinction.
(ii) Air-blast circuit breakers in which high-pressure air blast is used for extinguishing the arc.
(iii) Sulphur hexa fluoride C.B. in which SF6 gas is used for arc extinction.
(iv) Vacuum C.B. in which vacuum is used for arc extinction.
 Here in KaTPP 3AP1FI/3AP2FI type CB are used for 400KV &220KV Switchyard.
41
Table 6.2 Parameter of CB
Parameters 400KV yard For 220KV yard
Type 3AP2FI 3AP1FI
Rated voltage 420KV 245KV
Rated lighting impulse
withstand voltage
1425KVp 1050KVp
Rated power frequency
withstand voltage
610KV 460KV
Frequency 50Hz 50Hz
Rated nominal current 3150A 3150A
Rated short circuit breaking
current
50KA 40KA
Rated short circuit time
duration
3 sec 3 sec
Rated out of phase breaking
current
12.5A 10KA
First pole to clear factor 1.3 1.3
Rated single capacitor bank
break current
400A 125A
Rated line charging break
current
600A 400A
DC component 46% 25%
Rated operation sequence o-.3s-co- 0-.3S-CO-3M-CO
Weight of SF6 6.0 bar rel 6.0bar rel
42
Total weight 39kg 22kg
Control voltage 5400kg 3000kg
Operation
mechanism/heating voltage
220V DC
240V AC
220V DC
240V AC
6.7) LIGHTENING ARRESTORS
An electric discharge between cloud and earth, between clouds or between the charge
of the same cloud is known is as Lightening.
A Lightening Arrester or a surge diverter is a protective device, which conducts the high
voltage surges on the power system to the ground.
Table 6.3 Parameters of LA
Type A
Maximum Voltage 245KV
MAX Current 2000A
RELAY Maximum Current 40A
Rating 165KW
Total weight 215kg
6.8) CURRENT TRANSFORMER
Fig. 6.4 Current Transformer
43
Current transformer is used for monitoring the current for the purpose of measuring and
protection. The dead tank current transformer accommodate the secondary cores inside the
tank, which is at ground potential. CT used current ratio 1000:1 and range is 1A-5A.CT
connected in series while PT in parallel.
6.9) POTENTIAL TRANSFORMER
These transformers are extremely accurate ratio step down transformers and are used
in conjunction with standard low range voltmeter (usually 150 volt) whose deflection when
divided by voltage transformation ratio, gives the true voltage on the high voltage side. In
general, they are of the shell type and do not differ much from the ordinary two winding
transformer, except that their power rating is extremely small.
Fig. 6.5 Potential Transformer
Up to voltage of 5000 potential transformers are usually of dry type, between 5000 and 13800
volts, they may be either dry type or oil immersed type, although for voltage above 13800 they
are oil type. Since their secondary windings are required to operate instruments, relays or pilot
lights, their ratings are usually 42 to 100 watts.
6.10) CAPACITIVE VOLTAGE TRANSFORMER
Capacitive voltage transformers are special kind of power transformers using
capacitors to step down the voltage.
44
APPLICATION
1. Capacitive voltage transformers can be effectively as potential sources for measuring,
metering, protection, carrier communication and other vital functions of an electrical
network.
2. CVT are constructed in single or multi-unit porcelain housing with their associated
magnetic units. For EHV system cuts are always supplied in multi-unit construction.
3. In case of EHV cuts, the multi-unit system has many advantage easy to transport and
storing, convenience in handling.
Table 6.4 CVT Specification
Type 10SK-245/460/1050
Rated voltage 245KV
Frequency 50Hz
Current 40KA for 3 sec
Rated primary current 2000A
Continues current 2400A
Insulation class A
Secondary terminal rating 2A
Oil weight 210kg
Total weight 850 kg
6.11) SINGLE LINE DIAGRAM
45
Fig. 6.6 Single Line Diagram of KaTPP Switchyard
46
CHAPTER-7
EFFICIENCY
7.1) EFFICIENCY
Efficiency is defined as the ratio of output to input. Efficiency of any thermal power
plant can be divided into four parts-
1) Cycle Efficiency
2) Boiler Efficiency
3) Generator Efficiency
4) Turbine Efficiency
Efficiency of thermal power plant is defined as in the term of overall efficiency i.e.
Overall efficiency = cycle × boiler × generator × turbine efficiency
7.2) CYCLE EFFICIENCY- Cycle efficiency is defined as the ration of energy available
for conversion in work to the heat supplied to the boiler.
7.3) BOILER EFFICIENCY- Efficiency of boiler depends upon the following factors:
a) Dry flue gas loss: Increase by excess air in boiler.
b) Wet flue gas loss: Moisture in coal.
c) Moisture in combustion loss: Hydrogen loss.
7.4) GENERATOR EFFICIENCY- Efficiency of generator is about 98% also its
efficiency depends upon:
a) Copper and iron loss
b) Windage losses
7.5) TURBINE EFFICIENCY-It means the efficiency of steam turbine in converting the
heat energy made available in the cycle into actual mechanical work.
47
CONCLUSION
This is my first practical training in which I learned lot of things and seen lot of huge
machine like Turbine, Boiler, Generator, cooling tower and many other things.
The architecture of the power plant, the way various units are linked and the way
working of whole plant is controlled make the student realize that engineering is not just
learning the structure description and working of various machine but the great part is of
planning proper and management.
I think training has essential for any student. It has allowed an opportunity to get an
exposure of the practical implementation to theoretical fundamentals.
48
REFERENCE
 www.rvunl.com
 www.googleindia.com
 Generation of electrical power By B. R. Gupta, S CHAND PUBLICATION
 Steam and Gas Turbine By R. Yadav, CPH
 Engineering Thermodynamics By P. K. Nag, TMH

More Related Content

What's hot

Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
Nikhil Singh
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
Tarun Kumar
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
ADITYA ARYAN
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
Er. Aman Agrawal
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC Faridabad
Pawan Agrawal
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
Ishant Gautam.
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
Vimal Tripathi
 
kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar
hariom nagar
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
Ranjeet1501
 
Muneer GTPS
Muneer GTPSMuneer GTPS
Muneer GTPS
Muneer Ahmed
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
sanjeevps12345
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
Rajan Kumar Choudhary
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
Anil Jadon
 
Project report of kota super thermal power plant
Project report of kota super thermal power plantProject report of kota super thermal power plant
Project report of kota super thermal power plant
Hîmãńshu Mêęńä
 
Reports ntpc
Reports ntpcReports ntpc
Reports ntpc
Ashish Agarwal
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
Ashish Uppu
 
Training Report on Barauni Thermal Power Station
Training Report on Barauni Thermal Power StationTraining Report on Barauni Thermal Power Station
Training Report on Barauni Thermal Power Station
Gulshan Singh
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
pratikguptateddy
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
abdul mohammad
 

What's hot (20)

Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
kota super thermal Power station training report
kota super thermal Power station training reportkota super thermal Power station training report
kota super thermal Power station training report
 
Industrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC FaridabadIndustrial Training Report on NTPC Faridabad
Industrial Training Report on NTPC Faridabad
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar kalisindh thermal report by hariom nagar
kalisindh thermal report by hariom nagar
 
A summer training report on NTPC
A summer training report on NTPCA summer training report on NTPC
A summer training report on NTPC
 
Muneer GTPS
Muneer GTPSMuneer GTPS
Muneer GTPS
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
 
Project report of kota super thermal power plant
Project report of kota super thermal power plantProject report of kota super thermal power plant
Project report of kota super thermal power plant
 
Reports ntpc
Reports ntpcReports ntpc
Reports ntpc
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
Training Report on Barauni Thermal Power Station
Training Report on Barauni Thermal Power StationTraining Report on Barauni Thermal Power Station
Training Report on Barauni Thermal Power Station
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 

Similar to Training reporton ka tpp by naval kishor

Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
DS Group (Dharampal Satyapal Limited)
 
Sagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full reportSagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full report
Sagar Mehta
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
Dilip kumar
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
Sagar Mehta
 
training reportON Thermal power plantt (nashik tps)pdf
 training reportON Thermal power plantt (nashik tps)pdf training reportON Thermal power plantt (nashik tps)pdf
training reportON Thermal power plantt (nashik tps)pdf
Sagar Mehta
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
Rahul Kurapati
 
kota super thermal power station
kota super thermal power stationkota super thermal power station
kota super thermal power station
deeanshu
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
guru nanak institute of technology
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house ppt
Er Sagar
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
Amit Kumar
 
Final report on ntpc faridabad
Final report on ntpc faridabadFinal report on ntpc faridabad
Final report on ntpc faridabad
Pawan Agrawal
 
CESC Report
CESC ReportCESC Report
CESC Report
Debokti Ghosh
 
ntpc
ntpcntpc
Udbhav's presentation on ntpc
Udbhav's presentation on ntpcUdbhav's presentation on ntpc
Udbhav's presentation on ntpc
Udbhav garg
 
Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power Plant
Girish Gupta
 
Project report on MTPS
Project report on MTPSProject report on MTPS
Project report on MTPS
Suvajit Cazador
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015
LekhraJ Meena
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
ravi kant
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
ravi kant
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
haxxo24
 

Similar to Training reporton ka tpp by naval kishor (20)

Summer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power PlantSummer Training Report On Kalisindh Thermal Power Plant
Summer Training Report On Kalisindh Thermal Power Plant
 
Sagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full reportSagar mehta summer training thermal power station full report
Sagar mehta summer training thermal power station full report
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
 
training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...training report on thermal power plant & thermal power generation by sagar me...
training report on thermal power plant & thermal power generation by sagar me...
 
training reportON Thermal power plantt (nashik tps)pdf
 training reportON Thermal power plantt (nashik tps)pdf training reportON Thermal power plantt (nashik tps)pdf
training reportON Thermal power plantt (nashik tps)pdf
 
Themal power plant NTPC
Themal power plant NTPCThemal power plant NTPC
Themal power plant NTPC
 
kota super thermal power station
kota super thermal power stationkota super thermal power station
kota super thermal power station
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 
Rajghat power house ppt
Rajghat power house pptRajghat power house ppt
Rajghat power house ppt
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
Final report on ntpc faridabad
Final report on ntpc faridabadFinal report on ntpc faridabad
Final report on ntpc faridabad
 
CESC Report
CESC ReportCESC Report
CESC Report
 
ntpc
ntpcntpc
ntpc
 
Udbhav's presentation on ntpc
Udbhav's presentation on ntpcUdbhav's presentation on ntpc
Udbhav's presentation on ntpc
 
Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power Plant
 
Project report on MTPS
Project report on MTPSProject report on MTPS
Project report on MTPS
 
NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015NPCIL-Summer Training Report-2015
NPCIL-Summer Training Report-2015
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
 
Hindustan zinc report
Hindustan zinc reportHindustan zinc report
Hindustan zinc report
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 

Recently uploaded

Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 

Recently uploaded (20)

Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 

Training reporton ka tpp by naval kishor

  • 1. A SEMINAR REPORT ON PRACTICAL TRAINING AT KALISINDH SUPER THERMAL POWER PLANT In partial fulfilment for the award of the degree Of BACHELOR OF TECHNOLOGY In ELECTRICAL ENGINEERING GOVT ENGINEERING COLLEGE JHALAWAR SUBMITTED TO: SUBMITTED BY: Mr Ashish Khandelwal Naval Kishor Head of Department B. Tech. 4th Year Department of Electrical Engineering Roll No. 2013UEE033
  • 2. i ACKNOWLEDGEMENT I oblige to acknowledge my heartiest gratitude to all honourable people who helped me during my summer training at KALISINDH THERMAL POWER PROJECT-JHALAWAR, (RVUNL) RAJASTHAN. I want to express my thanks to Mr. S. S. Meena (Chief Engineer of KaTPP), S. P. Meena (Training Co-ordinator) for granting me the permission for doing summer training at this project and to give their valuable time and kind co-operation. I also thank a lot to other staff members of RRVUNL, BGR & TCE for their further co- operation to gain the better knowledge about the excellent power plant project in Distt. – Jhalawar, Rajasthan. NAVAL KISHOR B. Tech 4th Year Electrical Engineering
  • 3. ii PREFACE The rise in civilization is closely related to improvement in transportation and requirement of energy that is not readily available in large quantities but is also readily transportable. A very peculiar fact about electrical energy is that neither it is directly available in nature nor it is finally used in this form, yet it is so widely produced and is the most popular high-grade energy. The purpose behind this training is to understand the difficult concepts in a better way with gain of knowledge. Report starts with a brief introduction about KALISINDH SUPER THERMAL POWER PLANT followed by Lighting Arresters, Bus Bars, Insulators and Circuit Breakers etc. While writing the report and while I was on my training, I was wondering that science is ever expanding field and engineers are working hard day and night and makes the life a gift for us.
  • 4. iii LIST OF CONTENTS S. NO. NAME PAGE NO. CHAPTER-1 INTRODUCTION 1-10 1.1 Contribution of TPP in India 1.2 Introduction to KaTPP 1.3 Energy generated in KaTPP 1.4 Plant Overview 1.5 Principle of Operation 1.6 Thermal plant operation procedure 1.7 Pulverised Coal Fuelled power plant CHAPTER-2 COAL HANDLING PLANT 11-15 2.1 Introduction 2.1 Stages of CHP CHAPTER-3 IMPORTANT PARS OF TPP 16-26 3.1 Boiler 3.2 Turbine 3.3 Generator 3.4 Condenser 3.5 Cooling Tower 3.6 Water treatment plant CHAPTER-4 ESP & AHP SYSTEM 27-32 4.1 ESP System 4.2 AHP System CHAPTER-5 CONTROL ROOM 33-34 5.1 Control & instrumentation system CHAPTER-6 SWITCHING & TRANSMISSION SYSTEM 35-45 6.1 INTRODUCTION 6.2 Bus bars 6.3 Isolators 6.4 Insulators 6.5 Protective relays 6.6 Circuit Breakers 6.7 Lightening arresters 6.8 Current transformer 6.9 Potential transformer 6.10 CVT 6.11 Single line diagram CHAPTER-7 EFFICIENCY 46 7.1 Efficiency 7.2 Cycle efficiency
  • 5. iv 7.3 Boiler efficiency 7.4 Generator efficiency 7.5 Turbine efficiency CONCLUSION 47 REFERENCE 48
  • 6. v LIST OF TABLES S. NO. TABLE NAME PAGE NO. 1.1 Overview of KaTPP 4-5 2.1 Classification of coal 11 2.2 Wagon tippler 12 2.3 Crusher rating 12 3.1 15KW motor rating at KaTPP 16 3.2 Turbine specification 21 3.3 Generator specification 23 3.4 DG set parameters 24 6.1 Isolator rating 37 6.2 CB parameters 41 6.3 LA Parameters 42 6.4 CVT parameters 44
  • 7. vi LIST OF FIGURES S. NO. FIGURE NAME PAGE NO. 1.1 Rankine cycle 1 1.2 Contribution of different power sectors in India 2 1.3 Route between GECJ and KaTPP 3 1.4 KaTPP at a glance 4 1.5 Working of KaTPP 6 1.6 Working by rankine cycle 8 1.7 Energy conversion 9 2.1 Coal handling plant 14 3.1 Water tube boiler 17 3.2 Turbine 20 3.3 Internal structure of turbine 21 3.4 Outview of generator 23 3.5 Cooling tower 25 4.1 ESP unit 30 4.2 Working of AHP 32 4.3 AHP at KaTPP 32 5.1 Control & instrumentation 34 6.1 Switchyard of KaTPP 36 6.2 Basic relay circuit 39 6.3 Buchholz relay 40 6.4 Current transformer 42 6.5 Potential transformer 43 6.6 Single line diagram of KaTPP Switchyard 45
  • 8. 1 CHAPTER-1 INTRODUCTION Everybody must be having a thought that a thermal power plant is a place where electricity is produced. However, do you know how it is produced? How the chemical energy stored in fuel is converted into heat energy which forms the input of power plant i.e. steam and electrical energy produced by generator? Power is the single most important necessity for common people and industrial development of nation. In a conventional power plant, the energy is first converted to a mechanical work and then is converted to electrical energy. The first energy conversion takes place in Boiler or Steam Generator, second in Turbine and the last conversion takes place in the Generator. A thermal power station is a power plant in which the prime mover is steam driven. Water is heated, turns into steam and rotates the turbine, which drives an electrical generator after that steam pass through in a condenser where it condensed and recycled to again in boiler this whole cycle is known as RANKINE CYCLE. Fig. 1.1 Rankine Cycle
  • 9. 2 1.1) CONTRIBUTATION OF THERMAL POWER PLANT IN INDIA In India, Thermal Power Plants contribute about 60% of the total electricity produced. Pie chart shows the electricity production percentage by different sectors- Fig. 1.2 Contribution of different sectors of power supply in India 1.2) INTRODUCATION OF KaTPP Kalisindh Super Thermal Power Project is located in Jhalawar, Rajasthan. The project site is about 12 km from Jhalawar Distt. Headquarter and 13 km from Govt. Engineering College Jhalawar. Site comprises of five villages viz. Nimoda, Undal, Motipura, Singharia, and Devri. It is 2 km from state highway no. 19 and 8 km from Ramganj Mandi-Bhopal broad gauge rail line. The site selection committee of Central Electricity Authority has visited the Nimoda and its adjoining villages of Jhalawar Distt. In addition, site was found techno- economical feasible for setting up of a Power Project. The Govt. of Raj. have included this project in 11th five-year plan. The estimated revised cost of the project is Rs.9479 Crores. M/s. TCE Bangalore has been
  • 10. 3 appointed as the technical consultant for the project. The state irrigation department has allotted 1200 mcft water for the project from proposed Kalisindh dam. Fig. 1.3 Route between GECJ to KaTPP The origin of the Kalisindh River is from northern slop of Vindya Mountains. The river enters from MP to Rajasthan near village Binda. After flowing 145 km in Rajasthan, the Kalisindh River merges in Chambal River near Nanera village of Distt. Kota.Its catchment area is about 7944 sq.km in Jhalawar & Kota Distt. The existing Dam is located at Bhawarasa village, primarily for P.H.E.D. purpose is being uplifted for providing a storage of 1200 mcft water for this power project. The GOR has allotted 842 Bigha Government land and acquired 1388 Bigha private khatedari land for the thermal project. Phase-1 is constructed on 1400 Bigha land only.EPC contract has been awarded to M/s. BGR Energy System Chennai on dt.09/07/08, through ICB route at cost Rs.4900 Crores. Ministry of coal, Govt. of India has allotted Paras east and Kanta basin coal blocks to RVUN in Chhattisgarh state. The RVUN has formed new company under joined venture with M/s. Adani Enterprises for mining of coal blocks and new company started the work. Annual coal requirement for the project is 56 Lacs TPA.GOR also decided to setup two new units of 2x660 MW in next few years.
  • 11. 4 Fig. 1.4 KaTPP at a glance 1.3) ENERGY GENERATED IN KaTPP  Number of units=2  Electricity generated by one unit=600 MW  Total electricity generated by plant=2x600=1200 MW 1.4) PLANT OVERVIEW Table 1.1 Overview of KaTPP Project Kalisindh Super Thermal Power Project Jhalawar Rajasthan Capacity 1200MW (2x600 MW) Project Site Village-Undel, Motipura, Nimoda, Singhania & Deveri of Tehsil Jhalarapatan, Distt-Jhalawar Project Location The project site is about 12 km from NH-12, 2km from state highway and 8 km from proposed Ramganj Mandi-Bhopal broad gauge rail line. Land Area 2230 Bigha/564 Hq. (1400 Bigha/350 Hq. in I stage)
  • 12. 5 Water Source and quantity Dam on Kalisindh river and 3400 CuM/Hrs. Fuel Source Main Fuel-Coal from captive coal blocks (Paras east and kanta Basin in Chhattisgarh state) Secondary Fuel-FO/HSD Quantity of fuel (at 80% PLF) Coal-56 Lacs TPA FO/HSD-13000-14000 KL/A Electrostatic Precipator 99.9 % Capacity Stack Height 275 Mtr Estimated revised cost Rs.9479 Crores 1.5) PRINCIPLE OF OPERATION For each process in a vapour power cycle, it is possible to assume a hypothetical or ideal process which represents the basis intended operation and do not produce any extraneous effect like heat loss. 1. For steam boiler, this would be a reversible constant pressure heating process of water to form steam. 2. For turbine, the ideal process would be a reversible adiabatic expansion of steam. 3. For condenser, it would be a reversible constant pressure heat rejection as the steam condenser until it becomes saturated liquid. 4. For pump, the ideal process would be the reversible adiabatic compression of liquid ending at the initial pressure. When all the above four cycles are combined, the cycle achieved is called RANKINE CYCLE. Hence, the working of a thermal power plant is based upon Rankine Cycle with some modification. 1.6) THERMAL PLANT OPERATION PROCEDURE The basic understanding of the modern thermal power station in terms of major systems involved can be done under three basic heads viz. generating steam from coal, conversion of thermal energy to mechanical power and generation & load dispatch of electric power.
  • 13. 6 Fig. 1.5 Working of TPP 1.6.1) COAL TO STEAM- The coal is burnt at the rate up to 200 tonnes per hour. From coal stores, the fuel is carried on convey or belts to bunkers through coal tipper. It then falls in to coal pulverizing mill, where it is grounded into powder as fine as flour. Air is drawn into the boiler house by drought fan and passed through Preheaters. Some air is passed directly to bunker and rest, through primary air fan, to pulverizing mill where it is mixed with powdered coal. The mixture is then carried to bunker of furnace where it mixes with rest of the air and burns to great heat. This heats circulating water and produces steam, which passes to steam drum at very high pressure. The steam is then heated further in the Super heater and fed to high pressure cylinder of steam turbine. The spent steam is sent to condenser, where it turns back to water called condensate. Condensate is sent to lower part of steam drum through feed heater and economizer. The flue gases leaving boiler are used for heating purpose in feed heater, economizer, and air Preheater. The flue gases are then passed to electro-static precipitator and then, through draught fan, to chimney.
  • 14. 7 1.6.2) STEAM TO MECHANICAL POWER- Steam first enters the high-pressure cylinder of turbine where it passes over a ring of stationary/fixed blades, which acts as nozzle and directs steam onto a ring of moving blades. Steam passes to the other cylinders through reheater and the process is repeated repeatedly. This rotates the turbine shaft up to 3000rpm. At each stage, steam expands, pressure decreases and velocity increases. 1.6.3) MECHANICAL POWER TO ELECTRICAL POWER- To obtained the electrical power from mechanical power we connect the shaft to an alternator’s armature. When the armature is rotated and electric, current is produced in the stator’s windings. The generated electricity is of order 25,000 volts. 1.6.4) SWITCHING AND TRANSMISSION-The produced electricity is cannot to transmitted as this state so It is passed to a series of three switches called an isolator, a circuit-breaker, and another isolator. From circuit breaker, current is taken to bus bars and then to another circuit breaker with its associated isolator before being fed to the main Grid. Each generator has its own switching and transmission arrangement. Three-phase system is used for power transmission. 1.6.5) CONTROL AND INSTRUMENTATION- Control and Instrumentation (C & I) systems are provided to enable the power station to be operated in a safe and efficient manner while responding to the demands of the national grid system. These demands have to be met without violating the safety or operational constraints of the plants. For example, metallurgical limitations are important as they set limits on the maximum permissible boiler metal temperature and the chemical constituents of the Feed water. The control and Instrumentation system provides the means of the manual and automatic control of plant operating conditions to maintain an adequate margin from the safety and operational constraints. Monitor these margins and the plant conditions, and provide immediate indications and permanent records. Draw the attention of the operator by an alarm system to any unacceptable reduction in the margins. Shut down the plant if the operating constraints are violated.
  • 15. 8 1.7) PULVERIZED COAL FUELED POWER PLANT A typical pulverized coal fuelled power plant is based on Rankine Thermodynamic cycle. “A Rankine cycle is a vapour cycle Furnace that relies on the isentropic expansion of high pressure gas to produce work”. Let us see a super heat Rankine cycle: Fig. 1.6 Working by Rankine Cycle This facility first produces steam in a boiler (steam generator). This steam is used to rotate turbine, which is connected to a shaft of generator. Hence, electricity is produced here. The used steam is then condensed in a condenser and the condensed liquid is used again in the steam generator. This is a simple phenomenon, understood by everybody. For all this, we need a fuel. As the name suggest here coal is used as fuel. Coal is one of the cheapest and most preferred fossil fuel used as a key to most of the power plants. Usually delivered by train from Mines to the Coal Handing Plant (CHP). The CHP unloads this it become more economical to unload the coal. Then the coal stacked, reclaimed, crushed, and conveyed it to the storage silos near the steam generator. Then it is fed through the Feeder to the Pulveriser. Feeder is mainly used to weight the amount of coal going to the Pulveriser per hour. From the Feeder, the coal is fed to the Pulveriser, which powders it, and then it is carried to the steam generator using pressurized air. Within the steam generator, the coal is atomized and burned and the heat energy produced is used for producing steam. Here two types of steam namely superheated & reheated steam are produced in a cycle. The steam turbine generator
  • 16. 9 converts the thermal energy of superheated and reheated steam to electrical energy. The first energy conversion is carried in Boiler or steam generator; the second is carried out in Turbine and the last one carried out in the Generator. Initially the superheated steam is fed to High Pressure (HP) turbine. It has a temperature of 540° C (approx.) and a pressure of about 140 Kg/cm2. Then the exhausted steam from it is taken to the reheater so that it can be reheated and fed back to Intermediate Pressure (IP) turbine. Here the temperature is maintained the same as that of superheated steam but pressure is reduced to 35 Kg/cm2. Fig. 1.7 Energy Conversion Then the exhausted steam is directly fed to Low Pressure (LP) turbine having the reduced temperature and pressure of about 1Kg/cm2. Then the exhausted steam from the LP section is condensed in the condenser. Condensate Pumps move the condensed liquid from condenser through Low Pressure Regenerative Feed water heaters to a Deaerator. Boiler Feed Pumps (BFPs) moves the deaerated liquid through HP heaters to the steam generators. Extraction steam is supplied to the LP & HP regenerative heaters to improve cycle efficiency. Then comes to the system of fans which keeps the system working by providing the valuable air where required. There are three pairs of fans, namely, Forced Draft (FD) fan, Induced Draft (ID) fan, Primary Air (PA) fan. FD fans supplies combustion air to the steam generator and PA fans transports the coal into the steam generator. ID fans remove the flue gases from the steam generator and exhaust it through chimney. Cooling water for the condenser is supplied by the circulating water system, which takes the heat removed from the condenser and rejects it to the cooling towers or other heat sink. This
  • 17. 10 all working is controlled from a single place called control room. It enables the operator to direct the plant operation for reliable and efficient production of electrical energy. This is achieved by the control system installed by the C & I group. These are DAS (Data Acquisition System), ACS (Analog Control System), FSSS (Furnace Safeguard Supervisory System), and other relays governing numerous activities. Last but not the least is the switching and transmission methods used here. The generated power cannot be transmitted as such. It is stepped up to 132 KV or 400 KV then passed through a series of three switches an insulator, a circuit breaker and an isolator. Three-phase system is used for the power transmission. Each generator has its own switchyard and transmission arrangement.
  • 18. 11 CHAPTER-2 COAL HANDLING PLANT 2.1) INTRODUCTION Every thermal power plant is based on steam produced on the expanse of heat energy produced on combustion of fuel. Coal is categorized as follows depending upon fixed carbon, volatile matter and moisture content: Table 2.1 Classification of Coal S. NO. NAME OF COAL % CARBON 1 Anthracite 86% 2 Bituminous 46 to 86% 3 Lignite 30% 4 Peat 5 to 10% Coal from mines is transported to CHP in railway wagons. It is unloaded in track hoppers. Each project requires transportation of large quantity of coal mines to the power station site. Each project is established near coalmine, which meets the coal requirements for the span of its entire operational life. For the purpose each plant has Merry Go-Round (MGR) rail transportation system. The loading operation of the coal rake takes place while it is moving under the silo at a present speed of 0.8 Km/hr. that the loading time for each wagon is one minute. For unloading of coal from the wagons, an underground track hopper is provided at the power station. The term coal handling plant means to store and to handle the coal, which is transported by the train, and convey to the bunkers with the help of belt conveyers. Through the bunkers, coal is transferred to the coal mill and drifted to the furnace. The coal handling plant includes wagon tippler, conveyer belt, crusher house, stacker & reclaimer, bunkers & coal mill.  COAL SUPPLY IN KaTPP-Ministry of coal, Govt. of India has allotted Paras east and Kanta basin coal blocks to RVUN in Chhattisgarh state. 2.2) STAGES OF COAL HANDLING PLANT 2.2.1) WAGON TIPPLER-The term Wagon Tippler contains two words WAGON & TIPPLER. Wagon means the compartment of train, which is just like a container, which is used to carry the coal from mines to generating stations, & the word Tippler
  • 19. 12 means a machine, which is used to unload the wagon into the hopper. Hopper is just like a vessel, which is made of concrete, & it is covered with a thick iron net on its top. Here big size coal pieces are hammered by the labors to dispose it into the hopper. Table 2.2 Wagon Tippler Capacity 90 tonnes Types of Tipplers 1. Weighing type, 2. Non weighing type Angle of Tip 30 ‘to 35’ Wire Ropes 1. Hoisting Ropes, 2. Counter Weight Ropes Drive unit Motor 37.3 KW Operating Cycle 10 wagons/Hour on 1 wagon Tippler Time consume for one cycle 6 minutes 2.2.2) FEEDER- It is used to control the supply of crushed coal to the mill depending upon load condition. It is installed under wagon tippler and hopper. In KaTPP there are four-unbalanced Motor Vibrating Feeder installed in unit 1st. 2.2.3) CHRUSHER/RING GRANULATOR-In ring granulator the material is fed in to the crushing chamber and is crushed by the rind hammers with impact and rolling action across the feed, with concentrated pressure. This cracks the coal producing a granulator product with a minimum of fines upto 20 mm square. Table 2.3 Crusher Rating Capacity 500 Tonnes/hr. Machine Weight 30 Tonnes(approx.) Max Feed Rate 500 Tonnes/hr. Rotor Speed 720 r.p.m. Motor 550 HP Volts 606 Kv Phase 3 Phase motor
  • 20. 13 2.2.4) CONVEYORS-Conveyor belt is used to send the coal from coal storage yard and used to send crushed coal from store to mill bunkers. The carrying capacity of conveyors belt is 750 tonnes/hrs. that are installed in KaTPP. Conveyor belt used in coal handling plant (CHP) are of two types 1. Five ply x1000 mm width with 5 mm rubber top side and 5 mm rubber bottom side. Total thickness of belt: -17 to 18 mm Power: -1000 KN/m2 2. Four Ply x1000 mm width with 5mm rubber top side and 5 mm rubber bottom side. Total thickness of belt: -17mm Power: -800KN/m2 Cold joints are used in joining the conveyor, conveyor belts run with the help of electric motor, gearbox, fluid coupling geared coupling are installed at head of all conveyors. 2.2.4.1) PARTS OF CONVEYORS: 1) Flap Gate-it provide under coal transfer chutes for replacements of crusher/conveyors. 2) Deflector Plate-Deflector plates are installed in the chutes coming on conveyors to keep the coal direction in the centre of the conveyors. 3) Skirt board and Skirt Rubber-These are provided on tail end chutes to avoid spillages of coal from Conveyors. 4) Stone Picker-Stone picker pick the stones from the running belt manually. 5) Metal Detector-Electromagnets are provided on conveyors to avoid and to save crusher parts and entry of iron pieces in crusher. It also stops the entry of iron pieces in coalbunker to save damage of coal mills. 6) Guide Idlers-These idlers help to train/guide the conveyors. 7) Return Idlers-These idlers carries the conveyors belts in return side. 8) R.T.I (Return Training Idler)-These idlers are provided on return side to guide the conveyors.
  • 21. 14 9) Impact Idler-These Rubber idlers are provided under chutes through which coal falls on conveyors. 10) Carrying Idlers-These are installed to run the conveyor. Fig. 2.1 Coal Handling Plant 2.2.5) BUNKERS-Bunkers are fabricated to store the coal before sending to coal mills. Coal is fed in the bunkers with the help of tripper trolleys installed at 37 m height for unit 1st and 2nd.There are 20 bunkers for unit 1st and 2nd. Capacity of a bunker=500 tonne/bunker. 2.2.6) COAL BUNKERS-These are in process storage used for storing crushed coal from the handling system. Generally, these are made up of the welded steel plates with vibrating arrangement of the outlet to avoid chocking of coal; normally there are six- bunker supply coal to the corresponding mills. These are located on the top of mills to add gravity feeding of coal. 2.2.7) RECLAIM YARD-After filing the coalbunkers extra coal is taken to reclaim yard after crushing of coal to storage. 2.2.8) COAL CIRCULATION-Coal is transported from the coalmine with the help of train. Train wagons are emptied with the help of wagon tipplers and sent to the crusher for crushing. From coal crusher it goes to the bunker through conveyor belt
  • 22. 15 and from coalbunker, it moves to R.C feeder feeds coal to the coal mill, where the coal is grinded in to powder form.
  • 23. 16 CHAPTER-3 IMPORTANT PARTS OF THERMAL POWER PLANT 3.1) BOILER Boiler can simply be defined as the device where any liquid is boiled or Boiler may be defined as a device that is used to transfer heat energy being produced by burning of fuel to liquid, generally water, contended in it to cause its vaporization. Boiler, in simple terms, can be called “Steam Generator”. In simple way, boiler is a device used for producing steam. There are two types of boiler (depending upon tube content): a) Fire tube boiler b) Water tube boiler Here, boiler used is of water type. In the boiler, heat energy transfer takes place through tube walls and drum. The gases lose their heat to water in the boiler or superheated. The escape heat is used to heat the water through economizer. ID and FD fans are used to produce artificial draught. The fuel oil is used to ignite the boiler and pulverized coal is lifted from the coal mills by PA fans.  WATER TUBE BOILER USED IN KaTPP WITH 97M HIGHT. Various motors used in boiler are of different rating and parameters 32KW, 15KW, 11KW, & 3.3KW. Parameter in 15KW motor Table 3.1 15KW Motor Rating of KaTPP Manufacturing CQ. GEAR BOX LTD.CHINA Motor rating 15 KW Speed 970 r.p.m Rated voltage 416 V
  • 24. 17 Fig. 3.1 Water Tube Boiler
  • 25. 18 Rated current 28.4 A Impedance voltage 80.0 % Oil weight 20 Kg Core winding weight 224 Kg Total weight 600 Kg Temp rise 50-55°C 3.1.1) BOILER AUXILIARIES-Efficiency of a system is of most concerned. Thus, it is very important to maintain a system as efficient as possible. Therefore, Boiler auxiliaries help in improving boiler’s efficiency. Following are the important auxiliaries used  ECONOMISER: Its purpose is to preheat feed water before it is introduced into boiler drum by recovering heat from flue gases leaving the furnace.  SUPER HEATER: It increase the temperature of steam to super-heated region.  REHEATER: It is used for heat addition and increase the temperature of steam coming from high-pressure turbine to 540°C.  DRAFT FANS: They handle the supply of air and the pressure of furnace. 3.1.2) BOILER MOUNTINGS-These are used for the safe operation of boiler. Some example of mountings used are water level indicator in drum, furnace temperature probe, reheat release valve, pressure gauges indicating steam pressure etc. 3.2) TURBINE Turbine is an m/c in which a shaft is rotated steadily by the impact of reaction of steam of working substance upon blades of a wheel. It converts the potential energy or heat energy of the working substance into mechanical energy. When working substance is steam, it is called ‘Steam Turbine’. In the steam turbine, the pressure of the steam is utilized to overcome external resistance and the dynamic action of the steam is negligibly small.  Working principle of the steam turbine depends wholly upon the dynamic action of steam. The steam is caused to fall with pressure in a passage of nozzle, due to this fall in pressure, a whole amount of heat energy is converted into mechanical energy &
  • 26. 19 steam is set moving with the reactor velocity. The rapidly moving particle of steam enter the moving part of turbine and here suffers a change in the direction of motion which gives rise to change of momentum and therefore to a force. This constitutes a driving force to a turbine. The passage of them/through the moving part of the turbine commonly called the blade, may take place in such a manner that the pressure at the outlet sides of the blade is equal to that of the inlet side. Such a turbine is broadly termed as outlet turbine or Impulse type. On the other hand, the pressure of the steam at outlet from the moving blade may be less than that at type inlet side of the blade. The drop of pressure suffered by the steam during its flow through the moving blades causes a further generation of kinetic energy within the blades and adds to the propelling force, which is applied to the turbine rotor, such a turbine is broadly termed as Reaction Turbine.  Here in Kalisindh Thermal Power Project N600-16.7/587/537, Re-Het, Three Casing, Four Exhaust, Tandem Compound Condenser Type Turbine Used. The turbine is of tandem compound design with separate High Pressure (HP), Intermediate Pressure (IP) and Low Pressure (LP) cylinders. The HP turbine is of Single Flow type while IP and LP turbines are of Double Flow type. The turbine is condensing type with single reheat. It is engineered on reaction principle with throttle governing. The stages are arranged in HP, IP AND LP turbines driving alternating current full capacity turbo generator. The readily designed HP, IP and LP turbines are combined and sized to required power output, steam parameters and cycle configuration to give most economical turbine set. The design and constructional feature prove their reliability in service and ensure trouble free operation over long operating periods and at the same time ensuring high thermal efficiencies.
  • 28. 21 Fig. 3.3 Internal structure of Turbine Table 3.2 Turbine Specification Rated output with extraction flow 600 MW Speed 3000 r.p.m Main steam throttle flow at HP Inlet 1848.5 TPH Main steam pressure to HP turbine inlet 167 kg/sq.cm Main steam temperature. to HP turbine inlet 538°C Re-heater steam flow at IP inlet 1587.942 TPH Re-heater steam temperature. at IP inlet 538°C Steam pressure at LP inlet 35.12 kg/sq.cm Steam flow at LP inlet 1353.7 TPH Rotation Direction (view from turbine) anticlock wise Number of stages 42
  • 29. 22 High pressure turbine- a) Intermediate pressure b) Low pressure turbine c) Governing system 1 governing and 8 pressure 5 pressure stage 28 pressure stage DEH (digital electro hydraulic) Inlet steam flow governing type Nozzle+throttle Rated exhaust pressure 0.09 kg/sq.cm Type of bearing turbine 6 journal +1 thrust Turbine allowable frequency 47.5 to 51.5 Hz Turning gear rotation speed 1.5 r.p.m Ist critical speed of HP & LP rotor 1722 r.p.m Ist critical speed of LP-A rotor 1839 r.p.m Ist critical speed of LP-B rotor 1903 r.p.m Heat regenerative extraction system 3 HP heater +1 Deaerator +4 LP heater Final feed water temperature 274.9°C Maximum bearing vibration 0.076 m Maximum allowable exhaust temperature. 80°C Cooling water design flow at condenser 70200 TPH 3.3) GENERATOR Generator is the important part of thermal power plant. It is a device, which converts the mechanical energy into electrical energy. Generator is driven by coupled steam turbine at a speed of 3000 r.p.m. Due to rotation at high speed it gets heated. Therefore, there is cooling construction enclosing the winding core of the generator. Therefore, during the operation is being in normal temperature. In KaTPP, each of the 2 units have been provided with 3-phase turbo generator rated output 706MVA, 18.525KA, 22KV, 0.85 lagging p.f., 984 rpm and 50 cycles/sec. The generator has closed loop of hydrogen gas system for cooling of the stator and rotor at a pressure of 4.5kg/sq.-cm (g).
  • 30. 23 Fig. 3.4 Out view of Generator Table 3.3 Generator Specification Made By CQ. GEAR BOX LTD. CHINA Type QFSN Apparent output 706 MVA Active output 600 MW Power factor 0.85 lagging Rated voltage 22 KV Rated current 18525 Amp Rated speed 3000 r.p.m Frequency 50 Hz Phase connections Double gen. star Cooling mode H20-H2-H2 Rated H2 pressure 4.5 Kg/sq.-cm Terminal in generator 6
  • 31. 24 3.3.1) DIESEL GENERATOR SET It is used to emergency purpose to supply auxiliary system of power plant.3 Set Diesel generator are use in which one is standby. Table 3.4 DG Set Parameters Made BY STAMFOARD MAHARASTRA INDIA Rating 1900 KVA Speed 1500 R.P.M Rated Current 2643.37 A Rated Temp 40°C AMPS 3.6 A 3.4) CONDENSER In condenser, the water passes through various tubes and steam passes through a chamber containing a large number of water tubes (about 20000). The steam is converted into water droplets, when steam meets water tubes. The condensate is used again in boiler as it is dematerialized water and 5-6 heats the water, which was in tubes, during the process of condensation. This water is sent to cooling tower. Condenser is installed below the LP exhaust. The condenser is of surface type made of fabricated construction in single shell. The tube is of divided type double pass arrangement, having two independent cooling water inlet, outlet and reverse and water boxes. This arrangement facilitates the operation of one-half of condenser when the other half is under maintenance. The condenser is provided with integral air-cooling zone at the centre from where air and non-condensable gases are continuously drawn out with the help of mechanical vacuum pump.  Area of condenser = 9655 sq. m  Cooling water flow rate = 2400 cubic m/Hr. 3.5) COOLING TOWER It is a structure of height 202 m (tallest in the world) designed to cool the water (coming from condenser) by natural draught. The cross sectional area is less at the centre just to create
  • 32. 25 low pressure so that ate air can lift up due to natural draught and can carry heat from spherical drops. The upper portion is also diverging for increasing the efficiency of cooling tower. Hence, it is named as natural draught cooling tower.  In KaTPP two natural draught cooling towers (2 NDCT) is present with height 202 m each for each unit. Fig. 3.5 Cooling Tower 3.6) WATER TREATMENT PLANT As everyone, know that the cost of any thermal power plant is cores of rupees. So major problem of any thermal power plant is that how to prevent the corrosion. The water available cannot be used in boilers as such. The objective of water treatment plant is to produce the boiler feed water so that there shall be.
  • 33. 26  No scale formation ·  No corrosion ·  No priming or forming problems Water used in thermal power plant is called ‘Dematerialized Water’ or DM Water.
  • 34. 27 CHAPTER-4 ESP AND AHP SYSTEM 4.1) ELECTROSTATIC PRECIPITATOR (ESP) Electrostatic Precipitator (ESP) is equipment, which utilizes an intense electric force to separate the suspended particle from the gases. In India, coal is widely used to generate power. The exhaust gases are emitted directly into the atmosphere; it will cause great environmental problems. Therefore, it is necessary to extract this dust and smoke before emitted the exhaust gases into atmosphere. There are various methods of extracting dust but electrostatic precipitator is the most widely used. It involves electric changing of suspended particle, collection of charge particles and removal of charge particles from collecting electrode. Its various other advantages are as follows:  It has high efficiency i.e. about 99%  Ability to treat large volume of gases at high temperature  Ability to cope with the corrosive atmosphere.  It offers low resistance to the flow of gases.  It requires less maintenance. 4.1.1) WORKING PRINCIPLE- The electrostatic precipitator utilizes electrostatic forces to separate dust particles from the gases to be cleaned. The gas is passed through a chamber, which contains steel plates (vertical) curtains. Theses steel curtains divide the chamber into number of parallel paths. The framework is held in place by four insulators, which insulate it electrically from all parts, which are grounded. A high voltage direct current is connected between the framework and the ground, thereby creating strong electric field between the wires in the framework curtains. Strong electric field develops near the surface of the wire creates Corona Discharge along the wire. Thus ionized gas produces +ve and –ve ions. In the chamber plates are positively charged whereas the wire is negatively charged. Positive ions are attracted towards the wire whereas the negative ions are attracted towards the plates. On their way towards the curtains, negative ions strike the dust particle and make them negatively charged. Thus is collected on the steel curtains. The whole process is divided into the following parts:
  • 35. 28  Corona Generation  Particle Charging  Particle Collection  Particle Removal Details of the following are given below-  Corona Generation- Corona is a gas discharge phenomenon associated with the ionization of gas molecules by electron collision in regions of high electric field strength. This process requires non-uniform electric field, which is obtained by the use of small diameter wire as one electrode and a plate or cylinder as the other electrode. The corona process is initiated by the presence of electron in strong electric field near the wire. In this region of corona discharge, there are free electrons and positive ions. Both positive and negative coronas are used in industrial gas cleaning. In case of negative corona, positive ions generated are attracted towards the negative electrode or wire electrons towards collecting plates. On impact of negative and serve as principle means of charging dust.  Particle Charging- These are two physical mechanisms by which gas ions impact charge to dust particles in the ESP. Particles in an electric fields causes localized distortion in an electric filed so that electric field lines intersect with the particles of maximum voltage gradient, which is along electric field lines. Thus, ions will be intercepted by the dust particles resulting in a net charge flow to the dust particles. The ions will be held to the dust particles by an induced image charge force between the ion and dust particle and become charged to a value sufficient to divert the electric field lines from particles such that they do not intercept. o Particle Collection- The forces acting on the charged particles are Gravitational, Inertial, Electrostatic and Aerodynamically. The flow of gas stream is turbulent flow because it causes the particles to flow in random path through ESP. Particles will be collected at boundary layers of collector pates. However, if flow is laminar, charge will act on particles in the direction of collecting electrode. This force is opposite to viscous drag force and thus in the short time, particle would achieve Terminal (Migration) velocity at which
  • 36. 29 electrical; and viscous forces are equal. Thus the flow of the charged particle is decided by the vector sum of these forces i.e. Turbulent.  Particle Removal- In dry removal of dust collected on plates, Rapping Mechanism is used. It considers of a geared motor, which moves along shaft paced near the support collector electrode and is provided with cylindrical hammer. On rotating of shaft these hammers, strike the supports causes’ plate to vibrate and dust is removed from plates. Removed dust is collected in the Hoppers below the precipitator. At the time of starting of precipitation of dust from flue gases, the hoppers are at normal temperature but the ash collected is very hot. So there is a chance of ash deposit at the exit of the hopper thus causing problem of removing the ash. To avoid this, heaters are provided which increase the temperature at the exit point of the hopper thus avoiding any undue accumulation of ash at starting. In other method, the water is allowed to flow down the collector electrode and hence dust is collected in hoppers below. 4.1.2) GENERAL DESCRIPTION- The whole ESP is divided into two parts-  Mechanical System  Electrical System Here we will discuss only Mechanical System (i.e. Precipitator Casing, Emitting and Collecting System and Hopper).  Precipitator Casing-Precipitator Casing is made of 6mm mild steel plates with required stiffness. The precipitator casing is all welded construction comprising of pre- fabricated walls and proof-panels. The roof carries the precipitator internals, insulator housing, transformer etc. Both emitting and collecting systems are hung from the top of the casing.  Emitting and Collecting System- Emitting System is the most important part of ESP. Emitting system consists of rigid emitting frame suspended from four points on the top of rigid emitting electrodes in the form of open spiral. The four suspension points are supported on support insulators to give electrical insulation to the emitting frame. The frame is designed to take up the retention forces of the emitting electrode. The emitting electrode consists of hard drawn spiral wires and are fastened with hooks to the discharge frame.
  • 37. 30 Collecting system mainly consists of collecting suspension frame, collection electrodes and shock bars. Collecting electrode are made of 1.6 mm thick Mild Steel sheets formed in ‘G’ Profile of 400mm width. Hook and guide are welded on one end and shock iron on the dipped in rust preventive oil tank. Collecting electrodes bundles are properly bundled in order to avoid any damage to electrode.  Hoppers- Hoppers are seized to hold the ash for 8-hour collection and is provided under the casing of ESP. It is of Pyramidal Shape and is 56 in number. It is preferred to evacuate the hoppers at the earliest as long storage of dust in hopper leads to clogging of hopper. Also at the bottom of hopper, electrical heating is provided to avoid any condensation, which could also lead to clogging of hopper. Baffle plates are provided in each hopper to avoid gas leakage. Fig. 4.1 Electrostatic Precipitation Unit 4.1.3) RAPPING MECAHISM FOR COLLECTING SYSTEM- During electrostatic precipitation a fraction of dust will be collected on the discharge on the discharge electrodes and the corona will be suppressed as the dust layer grows. So rapping is done in order to remove this dust by hammering the electrodes.
  • 38. 31 As the shaft rotates, the hammer tumbles on to the shock bar that transmits the blow to the electrode. The completely rapping mechanism is mounted on a single shaft, which is collection of ash on the collecting electrode. 4.2) ASH HANDLING PLANT (AHP) ESP collects the ash produced on the combustion of coal. This ash is now required to dispose off. Ash Handling Plant (AHP) solves this purpose of ash disposal. There are two types of ash handling process undertaken by AHP.  Dry Ash System  Ash Slurry System 4.2.1) DRY ASH SYSTEM- Dry ash is required in cement factories as it can be directly added to cement. Hence, the dry ash collected in the ESP hopper is directly disposed to silos using pressure pumps. The dry ash from these silos is transported to the required destination. 4.2.2) ASH SLURRY SYSTEM- Ash from boiler is transported to ash dump areas by means of sluicing type hydraulic system, which consists of two types of system-  Bottom Ash System  Ash Water System  BOTTOM ASH SYSTEM- In this system, the ash slag discharged from the furnace is collected in water-impounded scraper installed below bottom ash hopper. The ash collected is transported to clinkers by chain conveyors. The clinker grinders churn ash, which is then mixed with water to form slurry.  ASH WATER SYSTEM-In this system, the ash collected in ESP hopper is passed to flushing system. Here low pressure water is applied through nozzle directing tangentially to the section of pipe to create turbulence and proper mixing of ash with water to form slurry. Slurry formed in above processes is transported to ash slurry sump. Here extra water is added to slurry if required and then is pumped to the dump area. 4.2.3) FLY ASH SYSTEM-Even though ESP is very efficient, there is still some ash, about 0.2%, left in flue gases. It is disposed to the atmosphere along with flue gases through chimney.
  • 39. 32 Fig. 4.2 Working of Ash Handling Plant Fig. 4.3 Ash Handling Plant at KaTPP
  • 40. 33 CHAPTER-5 CONTROL ROOM 5.1) CONTROL AND INSTRUMENTATION SYSTEM Control and Instrumentation (C & I) systems are provided to enable the power station to be operated in a safe and efficient manner while responding to the demands of the national grid system. These demands have to be met without violating the safety or operational constraints of the plants. For example, metallurgical limitations are important as they set limits on the maximum permissible boiler metal temperature and the chemical constituents of the Feed water. The control and Instrumentation system provides the means of the manual and automatic control of plant operating conditions to maintain an adequate margin from the safety and operational constraints. Monitor these margins and the plant conditions, and provide immediate indications and permanent records. Draw the attention of the operator by an alarm system to any unacceptable reduction in the margins. Shut down the plant if the operating constraints are violated. Most of the power plant operational controls are automatic. However, at times, manual intervention may be required. Thus, the plant is provided with monitors and alarm systems that alert the plant operators when certain operating parameters are seriously deviating from their normal range. .
  • 41. 34 Fig. 5.1 Control & Instrumentation System
  • 42. 35 CHAPTER-6 SWITCHING AND TRANSMISSION 6.1) INTRODUCTION The electricity is usually produced in the stator winding of the large modern generators at about 22,000 volts and is fed through terminal connections to one side of a generator transformer that steps up the voltage 132000, 220000 or 400000 volts. From here conductors carry it to a series of three switches comprising an insulator, a circuit breaker and another isolator. The circuit breaker, which is a heavy-duty switch capable of operating in a fraction of a second, is used to switch off the current flowing to the transmission lines. Once the current has been interrupted, the isolators can be opened. These isolate the circuit breaker from all outside electrical sources. From the circuit breaker, the current is taken to the bus bars-conductors, which run the length of the switching compound and then to another circuit breaker with its associated isolates before feeding to the grid. Three wires are used in a ‘three=phase’ system for large power transmission. The centre of the power station is the control room. Here engineers monitor the output of electricity, supervising and controlling the operation of the generation plant and high voltage switchgear and directing power to the grid system as required. 6.2) BUS BARS Bus Bars are the common electrical component through which a large no. of feeders operating at same voltage have to be connected. If the bus bars are of rigid type (Aluminium types), the structure heights are low and minimum clearance is required. While in case of strain type of bus bars suitable ACSR conductors are strung / tensioned by tension insulator discs according to system voltages. In the widely used strain type bus bars, stringing tension is about 500 - 900 kg depending upon the size of conductor used.
  • 43. 36 Fig. 6.1 Switchyard of KaTPP 6.2.1) BUS BAR ARRANGEMENT MAY BE OF FOLLOWING TYPES, WHICH ARE BEING USED IN KaTPP 1.) Single bus bar arrangement. 2.) Double bus bar arrangement. a) Main bus with transformer bus. b.) Main bus-I with Main bus-II. 3.) Double bus bar arrangement with auxiliary bus. 6.3) ISOLATORS Isolators which are also called disconnect switches or air break switches after the assembly as per drawings on the leveled structures the adjustment of connecting pipes, moving and fixed contacts is done so that all the three phase of the isolator close and open simultaneously and there is a full surface contact between moving and fixed contacts. Such switches are generally used on both sides of equipment in order that repairs and replacement
  • 44. 37 of the equipment can be made without any danger. They should never be opened until the equipment in the same circuit has been turned off and should always be closed before the equipment is turned on. The adjustment of the tendon pipes levelling of post insulator, stop holts in the fixed contacts etc. is done for smooth operation of insulator. Following type of insulator are being used in KaTPP- a) Isolator without earth blades. b) Isolator with earth blade. c) Tendon isolator. Table 6.1 Isolator Ratings Type VB Manufacturing by GR-power switchgear ltd Hyderabad Rated voltage 420/245 KV Rating 400/200A Impulse voltage 1050KVp Total weight 1300/950kg Short time current 40KA for 3 sec Control voltage 220V DC 6.4) INSULATORS The insulators for the overhead lines provide insulation to the power conductors from the ground so that currents from conductors do not flow to earth through supports. The insulators are connected to the cross arm of supporting structure and the power conductors passes through the clamp of the insulator. The insulators provide necessary insulation between line conductors and supports and thus prevent any leakage current from conductors to earth. In general, the insulators should have the following desirable properties:
  • 45. 38 1 High mechanical strength in order to withstand conductor load, wind load etc. 2 High electrical resistance of insulator material in order to avoid leakage currents to earth. 3 High relative permittivity of insulator material in order that dielectric strength is high. 4 The insulator material should be non-porous; free from impurities and cracks otherwise the permittivity will be lowered. 5 High ratio of puncture strength to flash over. 6.4.1) TYPE OF INSULATORS There are three types of insulators used for overhead lines:  Pin Type  Strain Type  Suspension Type 6.5) PROTECTIVE RELAYS A Protective relay is a device that detects the fault and initiates the operation of the circuit breaker to isolate the defective element from the rest of the system. The relays detect the abnormal condition in the electrical circuits by constantly measuring the electrical quantities i.e. voltage, current, frequency, phase angle which are different under normal and fault conditions. Having detected the fault, the relay operates to close the trip circuit of the breaker, which results in opening of the breaker and disconnection of the faulty circuit. Relay circuit connections can be divided in three parts: 1.) Primary winding of a C.T. that is connected in series with the line to be protected. 2.) Secondary winding of C.T. and the relay operating coil. 3.) Third part is the tripping circuit, which may be either a.c. or d.c... It consists of a source of a supply, the trip coil of a circuit breaker and the relays stationary contacts. When a short circuit occurs at point F on the transmission line the current increases to enormous value. This results in a heavy current flow through the relay coil, causing the relay to operate by closing its contacts. This in turn closes the trip circuit of the breaker, making the C.B. open and isolating the family section from the rest of the system. In this way, the relay ensures the safety of the circuit equipment from damage and normal working of the healthy portion of the system.
  • 46. 39 Fig. 6.2 Basic Relay Circuit Basic qualities that a protective relay must possess are: 1.) Selectivity 2.) Speed 3.) Sensitivity 4.) Reliability 5.) Simplicity 6.) Economy 6.5.1) BUCHHOLZ RELAY It is a gas-actuated relay installed in oil-immersed transformers for protection against all kinds of faults. It is used to give an alarm in case of incipient (i.e. slow developing) faults in the transformer and to disconnect the transformer from the supply in the event of severe
  • 47. 40 internal faults. It is usually installed in the pipe connecting the conservator to the main tank. It is a universal practice to use BUCHHOLZ relay on all such oil-immersed transformers having ratings in excess of 750kVA. Fig. 6.3 Buchholz Relay 6.6) CIRCUIT BREAKER Circuit breakers are used for switching & protection of various parts of power system. Circuit breaker is a piece of equipment, which can 1) Make or break a circuit manually or automatically under normal condition. 2) Break a circuit automatically under fault condition. 3) Make a circuit either manually or by remote control under fault conditions. 6.6.1) CLASSIFICATION OF CIRCUIT BREAKERS They are generally classified based on the medium used for arc elimination (i) Oil circuit breakers, which employ some insulating oil for arc extinction. (ii) Air-blast circuit breakers in which high-pressure air blast is used for extinguishing the arc. (iii) Sulphur hexa fluoride C.B. in which SF6 gas is used for arc extinction. (iv) Vacuum C.B. in which vacuum is used for arc extinction.  Here in KaTPP 3AP1FI/3AP2FI type CB are used for 400KV &220KV Switchyard.
  • 48. 41 Table 6.2 Parameter of CB Parameters 400KV yard For 220KV yard Type 3AP2FI 3AP1FI Rated voltage 420KV 245KV Rated lighting impulse withstand voltage 1425KVp 1050KVp Rated power frequency withstand voltage 610KV 460KV Frequency 50Hz 50Hz Rated nominal current 3150A 3150A Rated short circuit breaking current 50KA 40KA Rated short circuit time duration 3 sec 3 sec Rated out of phase breaking current 12.5A 10KA First pole to clear factor 1.3 1.3 Rated single capacitor bank break current 400A 125A Rated line charging break current 600A 400A DC component 46% 25% Rated operation sequence o-.3s-co- 0-.3S-CO-3M-CO Weight of SF6 6.0 bar rel 6.0bar rel
  • 49. 42 Total weight 39kg 22kg Control voltage 5400kg 3000kg Operation mechanism/heating voltage 220V DC 240V AC 220V DC 240V AC 6.7) LIGHTENING ARRESTORS An electric discharge between cloud and earth, between clouds or between the charge of the same cloud is known is as Lightening. A Lightening Arrester or a surge diverter is a protective device, which conducts the high voltage surges on the power system to the ground. Table 6.3 Parameters of LA Type A Maximum Voltage 245KV MAX Current 2000A RELAY Maximum Current 40A Rating 165KW Total weight 215kg 6.8) CURRENT TRANSFORMER Fig. 6.4 Current Transformer
  • 50. 43 Current transformer is used for monitoring the current for the purpose of measuring and protection. The dead tank current transformer accommodate the secondary cores inside the tank, which is at ground potential. CT used current ratio 1000:1 and range is 1A-5A.CT connected in series while PT in parallel. 6.9) POTENTIAL TRANSFORMER These transformers are extremely accurate ratio step down transformers and are used in conjunction with standard low range voltmeter (usually 150 volt) whose deflection when divided by voltage transformation ratio, gives the true voltage on the high voltage side. In general, they are of the shell type and do not differ much from the ordinary two winding transformer, except that their power rating is extremely small. Fig. 6.5 Potential Transformer Up to voltage of 5000 potential transformers are usually of dry type, between 5000 and 13800 volts, they may be either dry type or oil immersed type, although for voltage above 13800 they are oil type. Since their secondary windings are required to operate instruments, relays or pilot lights, their ratings are usually 42 to 100 watts. 6.10) CAPACITIVE VOLTAGE TRANSFORMER Capacitive voltage transformers are special kind of power transformers using capacitors to step down the voltage.
  • 51. 44 APPLICATION 1. Capacitive voltage transformers can be effectively as potential sources for measuring, metering, protection, carrier communication and other vital functions of an electrical network. 2. CVT are constructed in single or multi-unit porcelain housing with their associated magnetic units. For EHV system cuts are always supplied in multi-unit construction. 3. In case of EHV cuts, the multi-unit system has many advantage easy to transport and storing, convenience in handling. Table 6.4 CVT Specification Type 10SK-245/460/1050 Rated voltage 245KV Frequency 50Hz Current 40KA for 3 sec Rated primary current 2000A Continues current 2400A Insulation class A Secondary terminal rating 2A Oil weight 210kg Total weight 850 kg 6.11) SINGLE LINE DIAGRAM
  • 52. 45 Fig. 6.6 Single Line Diagram of KaTPP Switchyard
  • 53. 46 CHAPTER-7 EFFICIENCY 7.1) EFFICIENCY Efficiency is defined as the ratio of output to input. Efficiency of any thermal power plant can be divided into four parts- 1) Cycle Efficiency 2) Boiler Efficiency 3) Generator Efficiency 4) Turbine Efficiency Efficiency of thermal power plant is defined as in the term of overall efficiency i.e. Overall efficiency = cycle × boiler × generator × turbine efficiency 7.2) CYCLE EFFICIENCY- Cycle efficiency is defined as the ration of energy available for conversion in work to the heat supplied to the boiler. 7.3) BOILER EFFICIENCY- Efficiency of boiler depends upon the following factors: a) Dry flue gas loss: Increase by excess air in boiler. b) Wet flue gas loss: Moisture in coal. c) Moisture in combustion loss: Hydrogen loss. 7.4) GENERATOR EFFICIENCY- Efficiency of generator is about 98% also its efficiency depends upon: a) Copper and iron loss b) Windage losses 7.5) TURBINE EFFICIENCY-It means the efficiency of steam turbine in converting the heat energy made available in the cycle into actual mechanical work.
  • 54. 47 CONCLUSION This is my first practical training in which I learned lot of things and seen lot of huge machine like Turbine, Boiler, Generator, cooling tower and many other things. The architecture of the power plant, the way various units are linked and the way working of whole plant is controlled make the student realize that engineering is not just learning the structure description and working of various machine but the great part is of planning proper and management. I think training has essential for any student. It has allowed an opportunity to get an exposure of the practical implementation to theoretical fundamentals.
  • 55. 48 REFERENCE  www.rvunl.com  www.googleindia.com  Generation of electrical power By B. R. Gupta, S CHAND PUBLICATION  Steam and Gas Turbine By R. Yadav, CPH  Engineering Thermodynamics By P. K. Nag, TMH