§ What is a Baseline?
§ To Baseline or Not to Baseline
§ The Fit within Project Controls
§ Establishing the Baseline
§ What Level of Detail and Control
§ Baseline Elements and Outputs
§ Change Control & Baseline Management
§ Tips, Three Principles and Wrap-up
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo
EVM - APM Guidelines Forward
Good decisions require good informa@on.
To deliver a complex project to @me and cost requires a proper understanding, at regular stages and at an appropriate level of detail, of the rela@onships between: work done, progress against plan, cost incurred against budget, cash spent and cost to come.
Combining this data leads to an understanding of the actual value of what has been achieved and prevents managers from being either too op@mis@c or unduly pessimis@c about the situa@on. It enables them to make appropriate judgements as to what correc@ve ac@ons need to be taken in good @me.
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for...Project Controls Expo
EVM - APM Guidelines Forward
Good decisions require good informa@on.
To deliver a complex project to @me and cost requires a proper understanding, at regular stages and at an appropriate level of detail, of the rela@onships between: work done, progress against plan, cost incurred against budget, cash spent and cost to come.
Combining this data leads to an understanding of the actual value of what has been achieved and prevents managers from being either too op@mis@c or unduly pessimis@c about the situa@on. It enables them to make appropriate judgements as to what correc@ve ac@ons need to be taken in good @me.
Change occurs in almost every project. It may come in the form to increased project scope, decreased budgets, or accelerated timelines. With all of these opportunities for change, project managers must be prepared to adjust the project plan in response to change. Unfortunately, ineffective project change management practices is one of the most common sources of project failure. Project managers must become better equipped at responding to change in order to increase project success. In this presentation the need for project change management is identified and several tools and strategies for effectively dealing with project change are presented.
Portfolio Management Processes Flow in English - 3rd Edition - Simplified Ver...Ricardo Viana Vargas
In this simplified version of the The Standard for Portfolio Management— Third Edition Processes Flow only the processes names are show, without their inputs, tools and techniques and outputs.
A test on the production of pulp and paper from
durian hides has been carried out with cooking temperature of
135 OC for a duration of 1.5 hours in a liquid of 2% : 3% : 4%
NaOH with comparison of durian hide fragment : cooking liquid
1:6. Durian hides possesses grinding level of 180 CSF, cracking
index of 0.6 kPa.m2
/gr and low tension index namely 15 Nm/gr.
The composition of the mixture of durian hide pulp (3% NaOH)
with Old Currugated Carbon (OCC) is (100%:0); (90%:10%);
(80%:20%), (70%:30%). To the grinding level of 300 ml CSF,
starch of 1% and sizing agent (AKD) 1% is added. Physical
characteristics of the paper sheet possesses gramature of 54.5
gr/m2
, thickness 0.321 mm, tensile strength 1.13 kN/m, tearing
strength 253 mN, Porosity (Bensten) 2050 ml/minute and
roughness (Bensten) 1700 ml/minute. The paper grammage had
not fulfilled basic paper specification for plastic laminated
wrapping paper, SNI 14-6519-2001.
Project Management and Change Management - Sean LowPink Elephant
Project Management & Change Management: The Value & Challenges Of Integration & Alignment
Join Sean for a highly interactive discussion about the often challenging relationship between Project Management and Change Management. Come prepared to contribute your questions, insights and opinions to this session which will focus on various aspects of this highly engaging topic.
Sean will answer questions like:
1) Should change managers have the authority to say “NO” to project changes?
2) To what extent should projects be exempt from the Change Management process?
3) At what point in a Project Lifecycle should change managers expect project managers to submit requests for change?
4) What roles are designated in ITIL to coordinate change efforts between Project Management and Change Management?
Project Controls Expo 18th Nov 2014 - Introduction and key note presentation ...Project Controls Expo
I believe that project delivery challenges are driving organisations towards greater integration and changing the way we should approach Project Controls within project delivery organisations.
This presentation captures my thoughts on a way forward for Project Controls within a Project Delivery organisation discussing:
Scope definition and Work Breakdown techniques driving more effective data integration (Single sources of key data from numerous functions)
Improvements in systems and system integration
Use of Data Warehouses and Management Information systems
Utilisation of BIM incorporating 4th (Time) and 5th (Cost) dimensions
Taking a simpler higher level approach to creation of a control model
Use of an Earned Value Management system and EV Maturity Compass
The need for a wider range of skills to deliver good control
An integrated industry approach to career definition, development, training and qualifications for Project Controls within the Project Management umbrella
My experience tells me that there is no single ‘magic ingredient’ to delivering successful projects; but greater integration of management and team activities, intelligent application of recognised best practices and fit-for-purpose processes, tools and systems would benefit UK construction as a whole in the future.
Here is the PMP Training Project Scope Management Part 2 presented by Skillogic Knowledge Solutions.
Skillogic is one of the top training institute for PMP Certification Course in India. Classroom training available in Bangalore, Hyderabad and Chennai. Classes are conducting during the weekends.
For more details visit our website: http://in.skillogic.com/
Definition
The Construction Industry Institute (CII) defines AWP as “the overall process flow of all the
detailed work packages (construction, engineering, and installation work packages). AWP
is a planned, executable process that encompasses the work on an EPC project, beginning
with the initial planning and continuing through detailed design and construction
execution. AWP provides the framework for productive and progressive construction and
presumes the existence of a construction execution plan.”
Similar to Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What should be the basis?" By David Birch (20)
National Grids Project Controls Journey – past, present and futureProject Controls Expo
National Grids Project Controls Journey – past, present and future By, Tim Fenemore - Head of Project Controls for National Grid, UK
Sanjay Lodhia - Head of Governance & Assurance for National Grid, UK
Tony Abiad - Head of Estimating & Cost for National Grid, UK
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs - Founder and CEO for ShapeDo, Israel" at Project Controls Expo 2017, Arsenal Stadium, London
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
Managing the risk of change by "Simon White - Risk Management Consultant for Trigo White Ltd, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior Consultant for QinetiQ, UK" & "Peter Tart - Senior Consultant for QinetiQ, UK at Project Controls Expo 2017, Arsenal Stadium, London
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston - Director of Project Controls for Costain Group PLC, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Founder for Basis PM, Texas, USA" at Project Controls Expo 2017, Arsenal Stadium, London
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Director for WSP, UK" & "Danny Vaughan - Head of Metrolink for TfGM, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
Governance and the art of decision making on Crossrail by "Walter Macharg - Head of Change Control and Cost Assurance for Crossrail, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partner, UK Head of Programme & Project Controls for Arcadis, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
Governance and Assurance for Nationally Significant Infrastructure Projects by "Terri Harrington"- Sponsorship Director - Complex Infrastructure Programme (CIP) for Highways England, UK at Project Controls Expo 2017, Arsenal Stadium, London
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
A review of whether interdependency exists in effective Project Control Methods and project performance by "Michael Halliday" Director for HKA, UK at Project Controls Expo 2017, Arsenal Stadium, London
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
A Source of Project Cost Integration by "David Hurren - Technical Director for RPCuk, UK Marie Trembacki - Associate Director for Faithful+Gould, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh Bhandari - Technical Principal - Project & Programme Controls for Mott MacDonald, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen - DEO Program Management for LA Metro, Los Angeles" at Project Controls Expo 2017, Arsenal Stadium, London
Have you ever wondered how search works while visiting an e-commerce site, internal website, or searching through other types of online resources? Look no further than this informative session on the ways that taxonomies help end-users navigate the internet! Hear from taxonomists and other information professionals who have first-hand experience creating and working with taxonomies that aid in navigation, search, and discovery across a range of disciplines.
Acorn Recovery: Restore IT infra within minutesIP ServerOne
Introducing Acorn Recovery as a Service, a simple, fast, and secure managed disaster recovery (DRaaS) by IP ServerOne. A DR solution that helps restore your IT infra within minutes.
0x01 - Newton's Third Law: Static vs. Dynamic AbusersOWASP Beja
f you offer a service on the web, odds are that someone will abuse it. Be it an API, a SaaS, a PaaS, or even a static website, someone somewhere will try to figure out a way to use it to their own needs. In this talk we'll compare measures that are effective against static attackers and how to battle a dynamic attacker who adapts to your counter-measures.
About the Speaker
===============
Diogo Sousa, Engineering Manager @ Canonical
An opinionated individual with an interest in cryptography and its intersection with secure software development.
Sharpen existing tools or get a new toolbox? Contemporary cluster initiatives...Orkestra
UIIN Conference, Madrid, 27-29 May 2024
James Wilson, Orkestra and Deusto Business School
Emily Wise, Lund University
Madeline Smith, The Glasgow School of Art
This presentation by Morris Kleiner (University of Minnesota), was made during the discussion “Competition and Regulation in Professions and Occupations” held at the Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found out at oe.cd/crps.
This presentation was uploaded with the author’s consent.
This presentation, created by Syed Faiz ul Hassan, explores the profound influence of media on public perception and behavior. It delves into the evolution of media from oral traditions to modern digital and social media platforms. Key topics include the role of media in information propagation, socialization, crisis awareness, globalization, and education. The presentation also examines media influence through agenda setting, propaganda, and manipulative techniques used by advertisers and marketers. Furthermore, it highlights the impact of surveillance enabled by media technologies on personal behavior and preferences. Through this comprehensive overview, the presentation aims to shed light on how media shapes collective consciousness and public opinion.
Media as a Mind Controlling Strategy In Old and Modern Era
Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What should be the basis?" By David Birch
1.
Copyright
@
2011.
All
rights
reserved
To
Baseline
or
Not
to
Baseline
What
should
be
the
basis?
Speaker:
David
Birch
Project
Controls
Expo
–
13th
Nov
2013
Twickenham
Stadium,
London
2.
Copyright
@
2011.
All
rights
reserved
David
Birch
Profile
§ 38
years
experience
in
the
delivery
of
high-‐profile
UK
and
internaAonal
project
porColios
for
world
leading
engineering
contractors
§ 28
years
of
Project
Controls
and
OperaAonal
Management
experience
§ Currently
Head
of
Project
Controls
at
NaAonal
Grid
in
the
UK
§ CLM
Programme
Controls
Manager
-‐
London
2012
Olympic
Games
ConstrucAon
for
the
Olympic
Delivery
Authority
(ODA)
§ In
addiAon,
delivered
projects
in
other
industry
sectors
including:
ü UK
&
InternaAonal
projects
in
Oil
and
Gas
ü Nuclear
decommissioning
and
clean-‐up
ü ConvenAonal
and
Nuclear
Energy
ü UAliAes
(including
Eletricity,
Gas,
Water,
Telecoms)
ü Infrastructure,
SporAng
Venues
and
Industrial
3.
Copyright
@
2011.
All
rights
reserved
Contents
§ What
is
a
Baseline?
§ To
Baseline
or
Not
to
Baseline
§ The
Fit
within
Project
Controls
§ Establishing
the
Baseline
§ What
Level
of
Detail
and
Control
§ Baseline
Elements
and
Outputs
§ Change
Control
&
Baseline
Management
§ Tips,
Three
Principles
and
Wrap-‐up
4.
Copyright
@
2011.
All
rights
reserved
What
is
a
Baseline?
APM
DefiniAon:
The
reference
levels
against
which
a
project,
programme
or
porColio
is
monitored
and
controlled.
A
Baseline
should
capture
and
reflect:
AssumpA
ons
and
Exclusion
s
ExecuAon
Strategies
(inc
procurement
&
contracAng
plans)
Budget
(inc
ConAngency
based
on
QRA)
Risk
Register
and
Analysis
(QRA)
Schedule
with
Milestones
Scope
5.
Copyright
@
2011.
All
rights
reserved
To
Baseline
or
Not
to
Baseline?
To
Baseline
§ Drives
good
scope
definiAon
and
assumpAons
§ Allows
performance
to
be
measured
§ Enables
change
to
be
defined
and
controlled
§ Facilitates
early
warnings
on
compromised
project
outcomes
(when
used
with
forecasAng)
Not
to
Baseline
–
the
common
complaints
§ The
scope
isn’t
well
defined
yet
§ There’ll
be
a
lot
of
change
-‐
it’ll
be
out
of
date
as
soon
as
it’s
set
§ You
can’t
change
a
Baseline,
we
need
a
flexible
plan
here
§ It
takes
far
too
much
effort
to
run
a
Baseline
with
full
change
control
§ This
project
isn’t
big
enough
to
need
it
Baselining is great
of course, but it’s
not quite right for
my project
6.
Copyright
@
2011.
All
rights
reserved
The
fit
within
Project
Controls
-‐
1
Baseline
Correct
Analyse
Measure
Project
Controls Cycle
7.
Copyright
@
2011.
All
rights
reserved
A.1
OrganisaAon
(1-‐5)
A.2
Planning,
Scheduling
and
BudgeAng
(6-‐15)
-‐
THE
BASELINE
A.3
Actual
Costs
(16-‐21)
A.4
Analysis
and
ReporAng
(22-‐27)
A.5
Change
Management
(28-‐32)
The
fit
within
Project
Controls
-‐
2
EVM
System
(32
Criteria)
Geing
the
system
right
leads
to:
Informed,
effec-ve
management
and
decision
making
by
knowing:
§ What
has
been
achieved
of
the
plan
§ What
it
has
cost
to
achieve
the
planned
work
§ If
the
work
achieved
is
cosAng
more
or
less
than
was
planned
§ If
the
project
is
ahead
of
or
behind
the
planned
schedule
8.
Copyright
@
2011.
All
rights
reserved
Establishing
the
Baseline
§ Original
Baseline
Budget
(OBB)
should
be
formally
agreed
§ OBB
includes
distributed
project
budget
and
conAngency
§ Baseline
should
be
a
simplified
high-‐level
version
of
a
detailed
model
which
becomes
the
forecast
dataset
§ Level
of
detail
determined
by
complexity
of
the
project,
planned
to
the
level
where
there
is
sufficient
informaAon/knowledge
to
manage
§ The
BASELINE
is
the
basis
for
performance
measurement
during
execuAon
and
should
be
formally
approved
and
published
9.
Copyright
@
2011.
All
rights
reserved
What
level
of
Detail
&
Control?
Complex
Projects
–
Large
And
Small
§ Detail
WBS
(minimum
Level
4)
§ Milestones
and
fully
cost
loaded
schedule
§ Project
ExecuAon
Plan
§ Full
project
controls
system
(including
Earned
Value)
Large
Simple
Projects
§ WBS
to
Level
2
or
3
§ Milestones
with
cost
loaded
schedule
on
high
level
acAviAes
§ Simple
budget
breakdown
§ Basic
project
controls
(monitoring
of
milestones
&
actual
cost
against
plan)
Small
Simple
Projects
§ One
line
WBS
§ One
line
cost
profile
and
milestones
§ Simple
budget
breakdown
§ Basic
project
controls
(monitoring
of
milestones
&
actual
cost
against
plan)
10.
Copyright
@
2011.
All
rights
reserved
Elements
that
make
up
a
Baseline
§ Work
Breakdown
Structure
(WBS)
derived
from
Scope
definiAon
§ WBS
DicAonary
§ Project
Milestones
and
Schedule
with
costs
loaded
at
WBS
level
§ Project
EsAmate
broken
down
by
WBS
(Cost
breakdown
may
be
at
lower
levels
under
each
WBS
element)
§ Project
ExecuAon
Plan
(PEP)
§ Risk
Register
that
underpins
ConAngency
value
in
EsAmate
§ Documented
AssumpAons
and
Exclusions
§ Basis
for
establishing
Earned
Value
by
acAvity
type
(EV
Technique)
12.
Copyright
@
2011.
All
rights
reserved
Measuring
Performance
against
the
Baseline
§ The
Performance
Measurement
Baseline
is
used
to
establish
Earned
Value
measurements
§ DefiniAon:
Performance
Measurement
Baseline
(PMB).
The
Ame-‐phased
budget
plan
against
which
contract
performance
is
measured.
It
is
formed
by
the
budgets
assigned
to
scheduled
cost
accounts
and
the
applicable
indirect
budgets.
For
future
effort,
not
planned
to
the
cost
account
level,
the
Performance
Measurement
Baseline
also
includes
budgets
assigned
to
higher
level
CWBS
elements,
and
undistributed
budgets.
It
equals
the
total
allocated
budget
less
management
reserve
or
conSngency.
13.
Copyright
@
2011.
All
rights
reserved
13
Performance
Basis
Anticipated Final Cost (AFC)
(AFC = cost to date + estimate for remaining work)
AFC = Actual Costs + (Budget at Completion – Earned Value)
CPI
Variances (favourable is positive, unfavourable is negative)
Cost Variance (CV) = Earned Value – Actual Costs
Schedule Variance (SV) = Earned – Planned Costs
Variance at Completion (VAC) = Budget at Completion (BAC) – Anticipated
Final Cost (AFC)
Performance Indices (favourable is >1.0, unfavourable is <1.0)
Cost Performance Index (CPI) = Earned Value / Actual Cost
Schedule Performance Index (SPI) = Earned Value / Planned Value (Baseline)
% Scheduled / Complete / Spent
% scheduled = Baseline Value (planned costs)
BAC
% complete = Earned Value
BAC
% spent = Actual Costs
BAC
X 100
X 100
X 100
14.
Copyright
@
2011.
All
rights
reserved
and
one
of
the
certainAes
of
project
life
is
that
things
will
…change
Once
approved
the
Baseline
forms
the
basis
for
CHANGE
15.
Copyright
@
2011.
All
rights
reserved
Change
Management
Process
BASELINE- Change Control Process Flow
Week4Week1Week2Week3Week5
Weekofmonthend
Project Sponsor & Project
Manager initial consultation
determine categories of
Change Baseline Scope
Cost /Budget Work
Breakdown Structure
Schedule & funding
CLM Programme Controls
Change Manager
establishes a Baseline
Change Proposal number
and logs item in Change
Control Log
Adequate
documentation for
formal change
Project Team prepare
draft Change Control
Form and supporting
documentation
Change Identified
Risk
Procurement
Design
Project
Stakeholders
Others (Early Warnings Etc)
CLM executive approval
to proceed to Internal
Change Board
Project Team finalise Change
Control Form and supporting
documentation
Last date for
issue of draft
changes to
Change Control
Internal Review Board
Programme Controls review
and comment for QA/QC and
process compliance
CLM Project Manager
notifies ODA Project Sponsor
and solicits support and
feedback
Obtain Project Sponsors approval
Change Control review of
changes with ODA SROs
Change Control review
agenda with ODA Director
of Construction
Financial Review with ODA
Financial Director, DCMS
and Treasury
Programme Controls distribute to board members,Project
Sponsors, Programme Assurance Office /Schedule
Programme Change Control Board Meeting
Programme Change Control Board
approves the Change &
determines approval authority
Approved
within boards
remit
Programme Controls implement
Change
OPRG / ODA Change Review
Meeting
Funders Change Review Meeting
Final authorisation
required
Change Control
meet with
Programme
Assurance Office,
LOCOG, LDA &
Town Planning
For approval
outside OPRG
remit
For approval
outside Change
Control Board
remit
Date for issue of complete
change packs to Change
Control
FeedbackFeedback Feedback
CLM-D0501-PRO-CC-v1.2
Feedback
Obtain signature from CLM Head
of Programme Controls provide
notification of Change and update
the Programme Assurance Office
Potential Change Notification
Reporting Process
Proposed or Potential Changes
Pending Change Summary
Change summary
Inform Programme Assurance Office
Inform Project Sponsor & Manager
ImperaAve
to
establish
a
Change
Management
process
that
is
part
of
the
monthly
update
cycle
16.
Copyright
@
2011.
All
rights
reserved
Baseline
Management
Dynamics
Baseline
• Fixed
• Controlled through Change Management
• Reflected current delivery strategies
• Aligned with contract s
• High Level – Project Milestones and
summarised Cost Loaded activities
Forecast
• Dynamic
• Reflects contractor current status &
progress
• Includes mitigation strategies and trends
• Takes account of integration impacts
• Forecasts outturn
Change Control
Fed from Trending
process
Trending Process
Fed from forecast
data and enabler for
Risk mitigation
Compare Inform
Change
Drive
17.
Copyright
@
2011.
All
rights
reserved
Rules
§ ImperaAve
to
measure
against
a
plan
which
reflects
reality
(i.e.
is
current)
ü Evolve
toward
a
‘bonom
up’
basis
which
reflects
accepted
contractor’s
plans
ü All
changes
require
approved
Change
Control
no
maner
how
small
or
insignificant
(using
delegated
levels
of
Authority
for
lower
value
changes)
ü Current
Budget
Baseline
(CBB)
=
OBB
+
approved
changes
Achieved
through
§ Focused
Re-‐planning
ü Knowledge
based
updates
as
more
informaAon
is
available
to
inform
the
plan
ü Series
of
anAcipated
changes
aligned
to
design
&
build
life-‐cycle
ü By
Project
or
Sub-‐Project
Level
§ Rigorous
Change
Control
Managing
the
Baseline
(using
Change
Control)
18.
Copyright
@
2011.
All
rights
reserved
Tips
for
successful
creaAon
and
use
of
a
Baseline
§ Spend
the
Ame
and
resources
to
get
your
Baseline
right
(and
minimise
heartache
down
the
road)
§ Keep
Baseline
high
level
and
ensure
Forecast
is
dynamic
and
integrated
§ Everyone
must
work
within
the
WBS
structure
ü
Cost
collecAon
system
fully
keyed
in
by
coding
ü
Contractors
keyed
in
at
lower
levels
§ Provide
right
level
of
alignment,
training
and
assurance
to
include:
ü
Customer’s
and
stakeholder’s
organisaAons
ü
Early
engagement
with
Contractors
teams
§ Keep
checking
fitness-‐for-‐purpose
-‐
Does
the
Baseline
reflect
current
Delivery
strategy
and
objecAves?
19.
Copyright
@
2011.
All
rights
reserved
Three
principles
to
remember
1. CreaAng
a
Baseline
and
keeping
it
current
is
essenAal
for
effecAve
management
decision
making
2. Updates
must
be
rigorously
controlled
through
the
Change
process
3. Ensure
a
comprehensive
Risk
process
is
integrated
with
the
Controls
processes
that
create
the
Baseline
20.
Copyright
@
2011.
All
rights
reserved
Wrapping
Up
§ Likely
outcomes
with
a
Baseline
§ Encourages
structured
approach
to
managing
a
project
§ There
is
a
controlled
plan
to
measure
performance
against
§ Facilitates
early
idenAficaAon
of
issues
§ Early
warnings
enable
miAgaAon
strategies
to
be
employed
to
minimise
impact
of
change
§ Successful
project
delivery
(on
or
before
-me
&
under
budget)
§ Likely
outcomes
without
a
Baseline
§ Encourages
unstructured
&
disjointed
approach
to
managing
a
project
§ Plan
keeps
moving
§ Unsure
of
project
issues
and
change
idenAfied
aqer
occurance
leaving
no
chance
to
miAgate
§ Unsuccessful
project
delivery
(late
delivery
&
over
budget)