EVM - APM Guidelines Forward
Good decisions require good informa@on.
To deliver a complex project to @me and cost requires a proper understanding, at regular stages and at an appropriate level of detail, of the rela@onships between: work done, progress against plan, cost incurred against budget, cash spent and cost to come.
Combining this data leads to an understanding of the actual value of what has been achieved and prevents managers from being either too op@mis@c or unduly pessimis@c about the situa@on. It enables them to make appropriate judgements as to what correc@ve ac@ons need to be taken in good @me.
Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What sh...Project Controls Expo
§ What is a Baseline?
§ To Baseline or Not to Baseline
§ The Fit within Project Controls
§ Establishing the Baseline
§ What Level of Detail and Control
§ Baseline Elements and Outputs
§ Change Control & Baseline Management
§ Tips, Three Principles and Wrap-up
The document discusses several complex engineering project case studies and failures. It analyzes the root causes of failures including flawed assumptions, incomplete information, technological changes, and improper management of complex interactions within large systems. Traditional project management approaches are shown to be insufficient for complex projects with unknown unknowns. Systems thinking and considering projects as complex adaptive systems is presented as a better framework for managing complexity.
What would you do if government suddenly became a really demanding client? Od...commonsenseLT
The document summarizes a presentation on using Theory of Constraints (TOC) and Critical Chain Project Management (CCPM) approaches to improve project delivery for contractors working with government/public sector clients. It discusses how CCPM introduces several injections including establishing on-time delivery as a key measurement, developing realistic project plans with buffers, and determining the critical chain to better manage resources and uncertainty. Case studies show CCPM achieving over 95% on-time delivery, reduced costs and lead times, and increased capacity and performance.
This document provides an overview of earned value analysis (EVA) concepts and calculations to help make EVA work effectively on projects. It covers key EVA terms like planned value, earned value, and actual cost. It also discusses important metrics like schedule and cost variance, and the schedule and cost performance indices. The document reviews techniques for measuring work progress and calculating earned value. It then presents formulas for estimating costs to complete and the estimate at completion. The goal is to provide project managers with the information needed to successfully implement and use EVA on their projects.
Jon Grunzweig gave a presentation on controlling project costs. He discussed how projects often go over budget and past deadlines due to a lack of accountability and oversight. Grunzweig emphasized the importance of having an accurate project plan, accountable time tracking, and timely status reporting to keep projects on track. He also noted common areas where estimates fall short, such as testing and rework, and stressed measuring success rates to improve estimates over time. The key, according to Grunzweig, is having the right systems and processes in place to monitor costs and catch issues early.
How to reach the highest efficiency on state (country) level. Oded CohencommonsenseLT
This document discusses how to achieve the highest efficiency on a state or country level using the Theory of Constraints (TOC) approach. It provides an example of applying TOC concepts to significantly improve performance at a US Department of Defense maintenance center. Key results included increasing throughput, reducing costs and work in process, cutting repair cycle times, and achieving schedules over 90% of the time. The document argues that using TOC can help systems achieve their full potential within existing budget constraints by continuously improving performance.
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
Introduction
1. Why is forensic delay analysis the ultimate test for project controls?
2. Methods of delay analysis
3. Choice of method of delay analysis
4. Demonstration of methods of delay analysis
5. Project controls, data and records for delay analysis
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance. However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception. Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations to ensure compliance with a number of concerns. Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management challenges. Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project. This article can help you successfully plan, deliver, and control/monitor your large capital program/project.
Project Controls Expo 13th Nov 2013 - "To Baseline or Not to Baseline What sh...Project Controls Expo
§ What is a Baseline?
§ To Baseline or Not to Baseline
§ The Fit within Project Controls
§ Establishing the Baseline
§ What Level of Detail and Control
§ Baseline Elements and Outputs
§ Change Control & Baseline Management
§ Tips, Three Principles and Wrap-up
The document discusses several complex engineering project case studies and failures. It analyzes the root causes of failures including flawed assumptions, incomplete information, technological changes, and improper management of complex interactions within large systems. Traditional project management approaches are shown to be insufficient for complex projects with unknown unknowns. Systems thinking and considering projects as complex adaptive systems is presented as a better framework for managing complexity.
What would you do if government suddenly became a really demanding client? Od...commonsenseLT
The document summarizes a presentation on using Theory of Constraints (TOC) and Critical Chain Project Management (CCPM) approaches to improve project delivery for contractors working with government/public sector clients. It discusses how CCPM introduces several injections including establishing on-time delivery as a key measurement, developing realistic project plans with buffers, and determining the critical chain to better manage resources and uncertainty. Case studies show CCPM achieving over 95% on-time delivery, reduced costs and lead times, and increased capacity and performance.
This document provides an overview of earned value analysis (EVA) concepts and calculations to help make EVA work effectively on projects. It covers key EVA terms like planned value, earned value, and actual cost. It also discusses important metrics like schedule and cost variance, and the schedule and cost performance indices. The document reviews techniques for measuring work progress and calculating earned value. It then presents formulas for estimating costs to complete and the estimate at completion. The goal is to provide project managers with the information needed to successfully implement and use EVA on their projects.
Jon Grunzweig gave a presentation on controlling project costs. He discussed how projects often go over budget and past deadlines due to a lack of accountability and oversight. Grunzweig emphasized the importance of having an accurate project plan, accountable time tracking, and timely status reporting to keep projects on track. He also noted common areas where estimates fall short, such as testing and rework, and stressed measuring success rates to improve estimates over time. The key, according to Grunzweig, is having the right systems and processes in place to monitor costs and catch issues early.
How to reach the highest efficiency on state (country) level. Oded CohencommonsenseLT
This document discusses how to achieve the highest efficiency on a state or country level using the Theory of Constraints (TOC) approach. It provides an example of applying TOC concepts to significantly improve performance at a US Department of Defense maintenance center. Key results included increasing throughput, reducing costs and work in process, cutting repair cycle times, and achieving schedules over 90% of the time. The document argues that using TOC can help systems achieve their full potential within existing budget constraints by continuously improving performance.
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
Introduction
1. Why is forensic delay analysis the ultimate test for project controls?
2. Methods of delay analysis
3. Choice of method of delay analysis
4. Demonstration of methods of delay analysis
5. Project controls, data and records for delay analysis
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
Effective capital program/project delivery is a critical competency for any electric utility to achieve high performance. However, project scope creep, schedule delays, and cost increases have become the rule rather than the exception. Over the past 10 years, the electric utility industry has seen large demands on its projects and construction management organizations to ensure compliance with a number of concerns. Large capital programs/projects come with a variety of complicated planning, implementation, and workforce/vendor management challenges. Using EPU projects as an example, we will provide you with ways to overcome these challenges for any large capital program/project. This article can help you successfully plan, deliver, and control/monitor your large capital program/project.
Whole building design and commissioning takes a holistic approach to ensure proper operation, maintenance and performance of building systems. It involves integrated design of building envelope and mechanical systems using a multi-disciplinary team. Commissioning identifies deficiencies, ensures systems meet design intent, and provides risk management by detecting and correcting problems early. It results in lower operating costs, increased productivity and reduced liability.
This document discusses NASA's Earned Value Management (EVM) capability project. It outlines the overarching EVM requirements for NASA, including compliance with ANSI/EIA-748 guidelines. It describes NASA's development of a common EVM process and its testing on two pilot projects. The rollout plan and available EVM resources are also summarized. Maintaining the integrity of the EVM process through surveillance is highlighted as a key ongoing activity.
JP Morgan Data Center Technology Town Hall 2008John Napier
This document provides an agenda for a Data Center Technologies Townhall meeting on January 30th, 2008. The agenda includes presentations on the 2008 DCT game plan, data center operations, enterprise computing services, regional management for EMEA, architecture/infrastructure technology management, business management/risk and resiliency, and promotions and appointments. Time is allotted for questions and answers at the end.
ScottMadden provides a 6-step capital program assessment to evaluate capital project management effectiveness. The assessment includes: 1) Analyzing the program management office, 2) Evaluating processes, 3) Analyzing project organization, 4) Assessing project execution, 5) Evaluating performance reporting tools, and 6) Issuing a final report with findings and recommendations. Interviews and document reviews are conducted. The assessment identifies strengths and weaknesses, typically taking 4-6 weeks to complete.
EVM is a project management process that integrates scope, schedule, and cost to assess project performance and forecast outcomes. It allows objective measurement of progress against a performance measurement baseline (PMB) which includes a work breakdown structure, schedule, and time-phased budget. EVM helps identify variances so management can take corrective actions to mitigate risks and keep the project on track. NASA requires EVM for projects over $20 million to enhance the likelihood of success through active measurement and management.
The document provides an overview of a presentation on implementing an Earned Value Management System (EVMS) at a federal agency on a low budget. It discusses EVMS concepts and benefits. It then details a case study where a recession-proof EVMS was developed using existing tools and processes to integrate project scheduling, budgeting, reporting, and analysis with minimal costs. The solution standardized processes, automated data collection and linking of schedules and costs. It improved project performance monitoring, accountability, and success rates.
Lean Project Management is a proven method for improving project performance. It focuses on managing variability through planning, execution, and monitoring approaches like identifying essential inputs, aggressive task estimates, critical chain protection, and buffer management. Team support is critical for implementing Lean Project Management successfully.
The document discusses carbon credits and the Clean Development Mechanism (CDM) process under the Kyoto Protocol. It explains key concepts like baselines, additionality, and emission reduction calculations. It also describes the CDM project cycle including developing project design documents, validation by independent entities, approval from host countries, and verification and issuance of carbon credits. Programmes of Activities which allow smaller dispersed projects are also introduced as an alternative to single large projects.
Strategy & Tactics for State Owned Enterprises. Christoph LenhartzcommonsenseLT
The document discusses strategies and tactics for state-owned enterprises (SOEs). It notes that SOEs have financial, strategic, political, and social goals, such as controlling resources/infrastructure or providing essential non-profitable services. SOEs face the challenge of meeting growing demands with limited resources. They also navigate tensions between obligations to stakeholders like generating profits, paying dividends, and achieving strategic goals. The document advocates for SOEs to focus on satisfying stakeholders through excellence in operations, financial performance, and employee/customer satisfaction.
The document discusses the phases of developing an in-house cost estimate (IHCE) for the Space Network Ground Segment Sustainment (SGSS) project. It describes four phases: 1) developing a conceptual estimate using parametric models, 2) refining the estimate using a bottoms-up approach, 3) aligning the cost structure based on matured requirements, and 4) performing a risk analysis to assess confidence levels. Key lessons learned include starting early, using a team approach, adapting to changes, and ensuring confidence through multiple iterations.
This document discusses EVMS certification and provides an overview of earned value management. It contains the following key points:
1) The objectives are to provide perspective on the EVMS certification challenge and identify areas of focus to position an organization for successful certification.
2) EVMS certification evaluates an organization's compliance with 32 ANSI guidelines across stakeholders, processes, baseline development, status and forecasting, metrics and reports, management, and corrective action.
3) Successful certification depends on having a documented EVMS that meets all guidelines, projects executing the documented system, and an adequate surveillance plan to ensure sustainability.
This document discusses the challenges of partnering on major research platforms and facilities. It notes that the high costs and complexity of such projects have driven increased partnering between U.S. agencies and with international entities. However, ensuring alignment between partner processes and practices can be challenging. The document analyzes the practices of three science agencies - DOE, NASA, and NSF - to identify similarities and differences in their approaches to developing and managing large science projects. Understanding these comparative practices is important for facilitating effective interagency and international cooperation on major research infrastructure initiatives.
This document summarizes a presentation on over target baseline (OTB) contracts. It discusses the history and definitions of OTB contracts, the OTB process, and the customer perspective in granting an OTB. Recent studies have found that OTBs do not reliably improve cost performance and formal OTB reprogramming occurs randomly. The customer must carefully assess whether an OTB is warranted by auditing contractor performance and risks, and determining if strategic goals and resources support continuing the contract. Formal OTB processes may provide little tangible benefit and changes are needed for performance to reliably improve.
Calpine Corporation reported third quarter 2008 earnings results. Key highlights included record operating revenues of $3.2 billion, a 37% increase over third quarter 2007. Adjusted EBITDA was a record $593 million, a 17% increase. Cash flow from operations was also a record at $941 million. The company achieved excellent operational performance during the quarter despite hurricanes. Calpine provided guidance for full-year 2008 adjusted EBITDA of $1.65-1.675 billion and discussed near-term strategies around hedging, operations excellence, and growth opportunities.
The document discusses integrating technical performance measures with earned value management. It argues that EVM data is only reliable if technical performance is objectively assessed using the right measures of progress. Standards like CMMI and IEEE 1220 provide guidance on using requirements, product metrics, and success criteria to evaluate technical progress. The document provides examples of how to calculate earned value by linking it to completion of drawings and meeting technical performance targets for weight and diameter. It recommends acquisition best practices like requiring technical performance measurement in proposals and verifying integration at contract award and reviews.
This document discusses the importance of strengthening the connection between technical and financial managers on projects. Traditionally, these managers operate independently with the technical manager focused on requirements and the financial manager on funding. However, this can lead to problems like cost overruns, missed deadlines, and inconsistent information. To overcome these issues, the document recommends that the managers improve communication, develop a trusting relationship, work together on reviews, and share basic knowledge so technical changes are assessed for their budget impacts and funding issues are addressed jointly. Regular communication and cooperation between these critical roles is needed for a project's success.
The document discusses proposed changes to NASA's NPR 7120.7 policy regarding project baselining and rebaselining, and the implementation of a standard Level 2 work breakdown structure (WBS) for IT projects. It outlines draft definitions for project baselining and rebaselining, as well as proposed cost, schedule and scope thresholds for determining when a project rebaseline is warranted. The presentation also discusses benefits of adopting a standard Level 2 WBS, including facilitating project planning, cost/schedule control and identifying performance issues.
John M. Cefola has over 30 years of experience in project management, engineering management, and maintenance management. He has managed global projects up to $100 million and has experience in a wide range of industries including steel production, carbon reactivation, laser optics manufacturing, and algae production. Currently he is the Director of Engineering at Heliae Development where he oversees design, process engineering, project management, and maintenance.
This document discusses the process for developing Joint Confidence Level (JCL) assessments of cost and schedule estimates for programs and projects. It outlines the roles of programs/projects and the independent review board (SRB) in developing probabilistic cost estimates, risk analyses, and JCL assessments to present at key decision points. Both the program/project and SRB will develop their own analyses, then reconcile differences through iterative reviews and updates until agreeing on a final JCL assessment to report out. The goal is for estimates to have a 70% confidence level that costs and schedules will be equal to or less than predicted.
This document discusses the development and validation of an Earned Value Management (EVM) system at the Jet Propulsion Laboratory (JPL). It outlines the key components of developing the EVM system, including establishing the architecture, implementing the necessary tools and processes, and providing education and training. It also describes validating the system through progress assistance visits and a formal validation review. The document shares lessons learned around implementing an effective EVM system.
The document discusses establishing a Project Control Office (PCO) to provide project management practices and oversight. It outlines the changing role of IT from support to strategic enabler of business transformation. A PCO's responsibilities include managing project plans, budgets, schedules and issues. Examples of tools include status reports, scorecards and a master project plan template. Establishing a PCO can help projects complete within 5% of budget and schedule compared to 10-50% over without one. The ROI comes from identifying issues earlier to minimize impacts. Next steps to create an effective PCO include buy-in, dedicated resources, and tools.
Whole building design and commissioning takes a holistic approach to ensure proper operation, maintenance and performance of building systems. It involves integrated design of building envelope and mechanical systems using a multi-disciplinary team. Commissioning identifies deficiencies, ensures systems meet design intent, and provides risk management by detecting and correcting problems early. It results in lower operating costs, increased productivity and reduced liability.
This document discusses NASA's Earned Value Management (EVM) capability project. It outlines the overarching EVM requirements for NASA, including compliance with ANSI/EIA-748 guidelines. It describes NASA's development of a common EVM process and its testing on two pilot projects. The rollout plan and available EVM resources are also summarized. Maintaining the integrity of the EVM process through surveillance is highlighted as a key ongoing activity.
JP Morgan Data Center Technology Town Hall 2008John Napier
This document provides an agenda for a Data Center Technologies Townhall meeting on January 30th, 2008. The agenda includes presentations on the 2008 DCT game plan, data center operations, enterprise computing services, regional management for EMEA, architecture/infrastructure technology management, business management/risk and resiliency, and promotions and appointments. Time is allotted for questions and answers at the end.
ScottMadden provides a 6-step capital program assessment to evaluate capital project management effectiveness. The assessment includes: 1) Analyzing the program management office, 2) Evaluating processes, 3) Analyzing project organization, 4) Assessing project execution, 5) Evaluating performance reporting tools, and 6) Issuing a final report with findings and recommendations. Interviews and document reviews are conducted. The assessment identifies strengths and weaknesses, typically taking 4-6 weeks to complete.
EVM is a project management process that integrates scope, schedule, and cost to assess project performance and forecast outcomes. It allows objective measurement of progress against a performance measurement baseline (PMB) which includes a work breakdown structure, schedule, and time-phased budget. EVM helps identify variances so management can take corrective actions to mitigate risks and keep the project on track. NASA requires EVM for projects over $20 million to enhance the likelihood of success through active measurement and management.
The document provides an overview of a presentation on implementing an Earned Value Management System (EVMS) at a federal agency on a low budget. It discusses EVMS concepts and benefits. It then details a case study where a recession-proof EVMS was developed using existing tools and processes to integrate project scheduling, budgeting, reporting, and analysis with minimal costs. The solution standardized processes, automated data collection and linking of schedules and costs. It improved project performance monitoring, accountability, and success rates.
Lean Project Management is a proven method for improving project performance. It focuses on managing variability through planning, execution, and monitoring approaches like identifying essential inputs, aggressive task estimates, critical chain protection, and buffer management. Team support is critical for implementing Lean Project Management successfully.
The document discusses carbon credits and the Clean Development Mechanism (CDM) process under the Kyoto Protocol. It explains key concepts like baselines, additionality, and emission reduction calculations. It also describes the CDM project cycle including developing project design documents, validation by independent entities, approval from host countries, and verification and issuance of carbon credits. Programmes of Activities which allow smaller dispersed projects are also introduced as an alternative to single large projects.
Strategy & Tactics for State Owned Enterprises. Christoph LenhartzcommonsenseLT
The document discusses strategies and tactics for state-owned enterprises (SOEs). It notes that SOEs have financial, strategic, political, and social goals, such as controlling resources/infrastructure or providing essential non-profitable services. SOEs face the challenge of meeting growing demands with limited resources. They also navigate tensions between obligations to stakeholders like generating profits, paying dividends, and achieving strategic goals. The document advocates for SOEs to focus on satisfying stakeholders through excellence in operations, financial performance, and employee/customer satisfaction.
The document discusses the phases of developing an in-house cost estimate (IHCE) for the Space Network Ground Segment Sustainment (SGSS) project. It describes four phases: 1) developing a conceptual estimate using parametric models, 2) refining the estimate using a bottoms-up approach, 3) aligning the cost structure based on matured requirements, and 4) performing a risk analysis to assess confidence levels. Key lessons learned include starting early, using a team approach, adapting to changes, and ensuring confidence through multiple iterations.
This document discusses EVMS certification and provides an overview of earned value management. It contains the following key points:
1) The objectives are to provide perspective on the EVMS certification challenge and identify areas of focus to position an organization for successful certification.
2) EVMS certification evaluates an organization's compliance with 32 ANSI guidelines across stakeholders, processes, baseline development, status and forecasting, metrics and reports, management, and corrective action.
3) Successful certification depends on having a documented EVMS that meets all guidelines, projects executing the documented system, and an adequate surveillance plan to ensure sustainability.
This document discusses the challenges of partnering on major research platforms and facilities. It notes that the high costs and complexity of such projects have driven increased partnering between U.S. agencies and with international entities. However, ensuring alignment between partner processes and practices can be challenging. The document analyzes the practices of three science agencies - DOE, NASA, and NSF - to identify similarities and differences in their approaches to developing and managing large science projects. Understanding these comparative practices is important for facilitating effective interagency and international cooperation on major research infrastructure initiatives.
This document summarizes a presentation on over target baseline (OTB) contracts. It discusses the history and definitions of OTB contracts, the OTB process, and the customer perspective in granting an OTB. Recent studies have found that OTBs do not reliably improve cost performance and formal OTB reprogramming occurs randomly. The customer must carefully assess whether an OTB is warranted by auditing contractor performance and risks, and determining if strategic goals and resources support continuing the contract. Formal OTB processes may provide little tangible benefit and changes are needed for performance to reliably improve.
Calpine Corporation reported third quarter 2008 earnings results. Key highlights included record operating revenues of $3.2 billion, a 37% increase over third quarter 2007. Adjusted EBITDA was a record $593 million, a 17% increase. Cash flow from operations was also a record at $941 million. The company achieved excellent operational performance during the quarter despite hurricanes. Calpine provided guidance for full-year 2008 adjusted EBITDA of $1.65-1.675 billion and discussed near-term strategies around hedging, operations excellence, and growth opportunities.
The document discusses integrating technical performance measures with earned value management. It argues that EVM data is only reliable if technical performance is objectively assessed using the right measures of progress. Standards like CMMI and IEEE 1220 provide guidance on using requirements, product metrics, and success criteria to evaluate technical progress. The document provides examples of how to calculate earned value by linking it to completion of drawings and meeting technical performance targets for weight and diameter. It recommends acquisition best practices like requiring technical performance measurement in proposals and verifying integration at contract award and reviews.
This document discusses the importance of strengthening the connection between technical and financial managers on projects. Traditionally, these managers operate independently with the technical manager focused on requirements and the financial manager on funding. However, this can lead to problems like cost overruns, missed deadlines, and inconsistent information. To overcome these issues, the document recommends that the managers improve communication, develop a trusting relationship, work together on reviews, and share basic knowledge so technical changes are assessed for their budget impacts and funding issues are addressed jointly. Regular communication and cooperation between these critical roles is needed for a project's success.
The document discusses proposed changes to NASA's NPR 7120.7 policy regarding project baselining and rebaselining, and the implementation of a standard Level 2 work breakdown structure (WBS) for IT projects. It outlines draft definitions for project baselining and rebaselining, as well as proposed cost, schedule and scope thresholds for determining when a project rebaseline is warranted. The presentation also discusses benefits of adopting a standard Level 2 WBS, including facilitating project planning, cost/schedule control and identifying performance issues.
John M. Cefola has over 30 years of experience in project management, engineering management, and maintenance management. He has managed global projects up to $100 million and has experience in a wide range of industries including steel production, carbon reactivation, laser optics manufacturing, and algae production. Currently he is the Director of Engineering at Heliae Development where he oversees design, process engineering, project management, and maintenance.
This document discusses the process for developing Joint Confidence Level (JCL) assessments of cost and schedule estimates for programs and projects. It outlines the roles of programs/projects and the independent review board (SRB) in developing probabilistic cost estimates, risk analyses, and JCL assessments to present at key decision points. Both the program/project and SRB will develop their own analyses, then reconcile differences through iterative reviews and updates until agreeing on a final JCL assessment to report out. The goal is for estimates to have a 70% confidence level that costs and schedules will be equal to or less than predicted.
This document discusses the development and validation of an Earned Value Management (EVM) system at the Jet Propulsion Laboratory (JPL). It outlines the key components of developing the EVM system, including establishing the architecture, implementing the necessary tools and processes, and providing education and training. It also describes validating the system through progress assistance visits and a formal validation review. The document shares lessons learned around implementing an effective EVM system.
The document discusses establishing a Project Control Office (PCO) to provide project management practices and oversight. It outlines the changing role of IT from support to strategic enabler of business transformation. A PCO's responsibilities include managing project plans, budgets, schedules and issues. Examples of tools include status reports, scorecards and a master project plan template. Establishing a PCO can help projects complete within 5% of budget and schedule compared to 10-50% over without one. The ROI comes from identifying issues earlier to minimize impacts. Next steps to create an effective PCO include buy-in, dedicated resources, and tools.
Project Controls Expo 18th Nov 2014 - Introduction and key note presentation ...Project Controls Expo
I believe that project delivery challenges are driving organisations towards greater integration and changing the way we should approach Project Controls within project delivery organisations.
This presentation captures my thoughts on a way forward for Project Controls within a Project Delivery organisation discussing:
Scope definition and Work Breakdown techniques driving more effective data integration (Single sources of key data from numerous functions)
Improvements in systems and system integration
Use of Data Warehouses and Management Information systems
Utilisation of BIM incorporating 4th (Time) and 5th (Cost) dimensions
Taking a simpler higher level approach to creation of a control model
Use of an Earned Value Management system and EV Maturity Compass
The need for a wider range of skills to deliver good control
An integrated industry approach to career definition, development, training and qualifications for Project Controls within the Project Management umbrella
My experience tells me that there is no single ‘magic ingredient’ to delivering successful projects; but greater integration of management and team activities, intelligent application of recognised best practices and fit-for-purpose processes, tools and systems would benefit UK construction as a whole in the future.
ARES PRISM - Integrating Project & Portfolio Management by Lateef Daly at Pro...Project Controls Expo
ARES PRISM - Integrating Project & Portfolio Management by "Lateef Daly"- Director of Operations, Europe & Middle East for ARES PRISM, UK at Project Controls Expo 2017, Arsenal Stadium, London
This document discusses monitoring and controlling projects, including:
1) Tracking project work against plans using tools like earned value management and identifying changes for integration control.
2) Verifying project scope is completed as planned and controlling scope changes.
3) Monitoring project schedules using tools like tracking Gantt charts and addressing delays.
4) The challenges of schedule control and keeping projects on time.
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...Project Controls Expo
The document discusses the key role of the cost engineer in achieving an integrated work process through a holistic mindset. It describes how cost engineers can add value by moving beyond basic cost estimating and control to engage across the project lifecycle through what-if analysis, regression analysis, and key metrics analysis. The document advocates for continuous improvement by maintaining historical project data to inform future projects. It also discusses the challenges cost engineers face in modern complex projects and the need for an integrated approach rather than working in silos.
Project Controls Expo - 31st Oct 2012 - Extending Earned Value Methodology To...Project Controls Expo
Case Studies:
To illustrate the process, we draw on Supertech’s participation in the development and maintenance of a number of industry projects such as:
Jindal Steel and Power’s (JSPL) 12.5 MTA Steel Plant Project Control System. http://www.jindalsteelpower.com/ facilities/domestic/orissa/angul.aspx We consider this to be a Large Industrial Project (Mega Project).
Debalina Datta has over 10 years of experience as a Technical Delivery Manager, BI Analyst, and Business Analyst. She has worked on projects for clients like British Telecom, Peabody, Toyota Financial Services, and Johnson & Johnson. Her roles have included requirements gathering, system analysis, testing, and project management. She has specialized skills in Oracle BI, PL/SQL, and Agile methodologies.
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo
This document discusses the fundamentals of project cost estimating. It begins by introducing the speaker and discussing the evolution of calculation technology from simple abacuses to modern software. The core of the document then outlines the fundamentals of estimating, including defining estimates, reasons for preparing them, accuracy levels, methodologies, structure, risk/contingency, and other factors. It emphasizes understanding these fundamentals before using software and avoiding a "black box" approach. The document concludes by encouraging companies to train estimators, benchmark software, and capture data from past projects.
Duncan Collins is a project/program manager with over 10 years of experience managing large financial services projects involving system enhancements, workflows, automation, migrations, and regulatory changes. He has a proven track record of leading teams, identifying issues, and implementing solutions that improve efficiency and reduce costs. His expertise includes areas like Pega workflow systems, operational efficiency projects, requirement gathering, and digitalization.
This document provides an overview of project cost management. It discusses estimating, budgeting, and controlling costs so the project can be completed within the approved budget. Key aspects covered include developing cost estimates using various techniques, determining an authorized cost baseline by aggregating estimates, and monitoring costs against the baseline using earned value management. Formulas for calculating important metrics like cost and schedule variance, cost performance index, and estimate at completion are also presented to aid in cost control.
This document provides a summary of Steven Duhig's professional experience and qualifications. He has over 20 years of experience in management roles spanning IT, finance, operations, and customer relations. Some of his key accomplishments include implementing new change management processes, increasing capitalizable labor costs, and managing diverse teams supporting network management systems. He has expertise in areas such as budget control, process management, problem solving, and achieving goals through motivated teams.
A brief introduction tot project management for learners, a simplified lay man introduction thet will give insight into what Project Management is all about.
Derek Swift has over 25 years of experience in project management, construction management, and civil engineering. He has managed projects ranging from $132 million to $5.5 billion. Currently he is a Senior Project Core Team Manager at Turner Construction International in Dubai, where he oversees multiple large-scale projects for EMAAR. Previously he held engineering and management roles in the United States and Middle East.
The document discusses best practices in project controls for driving improved project performance. It covers:
1. Standardizing processes, integrating data, and automating reporting can improve efficiency, accuracy, effectiveness of project controls and provide greater visibility into project cost performance across an organization.
2. Leveraging technology, like an enterprise project controls software, is key to aligning processes, eliminating data silos, adopting best practices standardized across the project lifecycle, and evolving with the business.
3. Adopting and standardizing best practices incrementally, like for estimating, budgeting, progress measurement, and forecasting can improve project controls performance.
The document discusses project scope management and defines it as describing how the project team will define the project scope, verify work, and manage and control scope. It outlines elements that should be included in a project scope management plan such as processes for creating a scope statement, work breakdown structure (WBS), and managing scope changes. An example project scope statement is then provided for an IceScream project to connect its sites through email and an intranet.
Humayun Akhtar has over 15 years of experience managing IT and non-IT projects in financial services, manufacturing, and telecommunications. He has a track record of delivering projects on time and on budget. Akhtar is skilled in coaching teams, applying project management methodologies, and establishing relationships with clients.
The document outlines an M&E training to be held at the Travellers Beach Hotel. The training will cover methods of data collection, organization, analysis, reporting and presentation of M&E results. Key topics will include project control tools like Gantt charts, milestone charts, and earned value analysis which compares planned to actual performance to monitor project progress. The overall goal is to help participants explore best practices for monitoring and evaluating projects.
1. The document proposes a framework for a Strategic Priority Council to prioritize projects, campaigns, and initiatives according to available resources and potential business value.
2. The council would create rules to allocate frontline capacity each month for different activities like change projects, operations, credit, sales and training.
3. It would provide Exco with a holistic view of all projects through tools like a master project list to facilitate transparent decision making about resource allocation.
Thomas Thein is a delivery-focused IT professional with over 15 years of experience in IT project management, application development, and SAP implementations, having managed large distributed teams and budgets across various industries. Most recently, he served as the IT Integration PMO Lead for Graphic Packaging International, where he established and led the PMO through a major corporate merger. He brings expertise in program and project management, budgeting, team leadership, and process optimization.
Similar to Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch (20)
National Grids Project Controls Journey – past, present and futureProject Controls Expo
National Grids Project Controls Journey – past, present and future By, Tim Fenemore - Head of Project Controls for National Grid, UK
Sanjay Lodhia - Head of Governance & Assurance for National Grid, UK
Tony Abiad - Head of Estimating & Cost for National Grid, UK
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
Tata Steel UK recognized that their application of project controls was inadequate for successfully delivering their capital program on time and budget. They partnered with Faithful + Gould to implement industry best practices. Through an initial assessment, transition phase, implementation phase, and deployment phase, Tata Steel improved their project controls capabilities across areas like planning, cost management, and reporting. This transformation helped Tata Steel better optimize their budget and deliver reporting and oversight through standardized monthly project reporting.
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
This document discusses balancing burdens of proof in construction projects. It defines key terms like burden of proof and balance. Maintaining balance is challenging due to complex environments with multiple stakeholders and uncertainties. Contracts aim to balance costs, claimed rights, unclaimed rights, and margins. Disruptions off the critical path are broadly unaccounted for and represent risks. To control more activities, owners should engage contractors, implement robust program controls, maintain design documentation, and work collaboratively. Digging deep into designs and proactively engaging stakeholders helps maintain balance during projects.
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director for LogiKal Projects, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
This document summarizes a presentation on navigating building information modeling (BIM) given by Natacha Redon. It defines BIM as a process, not just software, to create and manage digital representations of physical and functional characteristics of buildings. It discusses the role of project managers in leading BIM implementation given their oversight of information flow. It also outlines challenges to successful BIM adoption like varying client and industry knowledge and capabilities and potential misunderstandings.
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
Managing the risk of change by "Simon White - Risk Management Consultant for Trigo White Ltd, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior Consultant for QinetiQ, UK" & "Peter Tart - Senior Consultant for QinetiQ, UK at Project Controls Expo 2017, Arsenal Stadium, London
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston - Director of Project Controls for Costain Group PLC, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Founder for Basis PM, Texas, USA" at Project Controls Expo 2017, Arsenal Stadium, London
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
The document discusses Mike Laws' presentation on attracting, retaining, and developing skilled project controls professionals. It provides background on Mike Laws and his experience in program management. It also gives overviews of several large infrastructure projects that CH2M has worked on, including Crossrail, High Speed 2, Team2100, Lower Thames Crossing, and the Panama Canal expansion. These case studies highlight CH2M's roles in providing program controls, cost estimation, and risk management services. The final sections discuss a systems model of program communication and the breadth of skills needed in program and project controls roles.
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Director for WSP, UK" & "Danny Vaughan - Head of Metrolink for TfGM, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
Governance and the art of decision making on Crossrail by "Walter Macharg - Head of Change Control and Cost Assurance for Crossrail, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partner, UK Head of Programme & Project Controls for Arcadis, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
Governance and Assurance for Nationally Significant Infrastructure Projects by "Terri Harrington"- Sponsorship Director - Complex Infrastructure Programme (CIP) for Highways England, UK at Project Controls Expo 2017, Arsenal Stadium, London
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
A review of whether interdependency exists in effective Project Control Methods and project performance by "Michael Halliday" Director for HKA, UK at Project Controls Expo 2017, Arsenal Stadium, London
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
A Source of Project Cost Integration by "David Hurren - Technical Director for RPCuk, UK Marie Trembacki - Associate Director for Faithful+Gould, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh Bhandari - Technical Principal - Project & Programme Controls for Mott MacDonald, UK" at Project Controls Expo 2017, Arsenal Stadium, London
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen - DEO Program Management for LA Metro, Los Angeles" at Project Controls Expo 2017, Arsenal Stadium, London
Collapsing Narratives: Exploring Non-Linearity • a micro report by Rosie WellsRosie Wells
Insight: In a landscape where traditional narrative structures are giving way to fragmented and non-linear forms of storytelling, there lies immense potential for creativity and exploration.
'Collapsing Narratives: Exploring Non-Linearity' is a micro report from Rosie Wells.
Rosie Wells is an Arts & Cultural Strategist uniquely positioned at the intersection of grassroots and mainstream storytelling.
Their work is focused on developing meaningful and lasting connections that can drive social change.
Please download this presentation to enjoy the hyperlinks!
Mastering the Concepts Tested in the Databricks Certified Data Engineer Assoc...SkillCertProExams
• For a full set of 760+ questions. Go to
https://skillcertpro.com/product/databricks-certified-data-engineer-associate-exam-questions/
• SkillCertPro offers detailed explanations to each question which helps to understand the concepts better.
• It is recommended to score above 85% in SkillCertPro exams before attempting a real exam.
• SkillCertPro updates exam questions every 2 weeks.
• You will get life time access and life time free updates
• SkillCertPro assures 100% pass guarantee in first attempt.
This presentation by OECD, OECD Secretariat, was made during the discussion “Competition and Regulation in Professions and Occupations” held at the 77th meeting of the OECD Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found at oe.cd/crps.
This presentation was uploaded with the author’s consent.
This presentation, created by Syed Faiz ul Hassan, explores the profound influence of media on public perception and behavior. It delves into the evolution of media from oral traditions to modern digital and social media platforms. Key topics include the role of media in information propagation, socialization, crisis awareness, globalization, and education. The presentation also examines media influence through agenda setting, propaganda, and manipulative techniques used by advertisers and marketers. Furthermore, it highlights the impact of surveillance enabled by media technologies on personal behavior and preferences. Through this comprehensive overview, the presentation aims to shed light on how media shapes collective consciousness and public opinion.
XP 2024 presentation: A New Look to Leadershipsamililja
Presentation slides from XP2024 conference, Bolzano IT. The slides describe a new view to leadership and combines it with anthro-complexity (aka cynefin).
This presentation by Professor Alex Robson, Deputy Chair of Australia’s Productivity Commission, was made during the discussion “Competition and Regulation in Professions and Occupations” held at the 77th meeting of the OECD Working Party No. 2 on Competition and Regulation on 10 June 2024. More papers and presentations on the topic can be found at oe.cd/crps.
This presentation was uploaded with the author’s consent.
Suzanne Lagerweij - Influence Without Power - Why Empathy is Your Best Friend...Suzanne Lagerweij
This is a workshop about communication and collaboration. We will experience how we can analyze the reasons for resistance to change (exercise 1) and practice how to improve our conversation style and be more in control and effective in the way we communicate (exercise 2).
This session will use Dave Gray’s Empathy Mapping, Argyris’ Ladder of Inference and The Four Rs from Agile Conversations (Squirrel and Fredrick).
Abstract:
Let’s talk about powerful conversations! We all know how to lead a constructive conversation, right? Then why is it so difficult to have those conversations with people at work, especially those in powerful positions that show resistance to change?
Learning to control and direct conversations takes understanding and practice.
We can combine our innate empathy with our analytical skills to gain a deeper understanding of complex situations at work. Join this session to learn how to prepare for difficult conversations and how to improve our agile conversations in order to be more influential without power. We will use Dave Gray’s Empathy Mapping, Argyris’ Ladder of Inference and The Four Rs from Agile Conversations (Squirrel and Fredrick).
In the session you will experience how preparing and reflecting on your conversation can help you be more influential at work. You will learn how to communicate more effectively with the people needed to achieve positive change. You will leave with a self-revised version of a difficult conversation and a practical model to use when you get back to work.
Come learn more on how to become a real influencer!
Carrer goals.pptx and their importance in real lifeartemacademy2
Career goals serve as a roadmap for individuals, guiding them toward achieving long-term professional aspirations and personal fulfillment. Establishing clear career goals enables professionals to focus their efforts on developing specific skills, gaining relevant experience, and making strategic decisions that align with their desired career trajectory. By setting both short-term and long-term objectives, individuals can systematically track their progress, make necessary adjustments, and stay motivated. Short-term goals often include acquiring new qualifications, mastering particular competencies, or securing a specific role, while long-term goals might encompass reaching executive positions, becoming industry experts, or launching entrepreneurial ventures.
Moreover, having well-defined career goals fosters a sense of purpose and direction, enhancing job satisfaction and overall productivity. It encourages continuous learning and adaptation, as professionals remain attuned to industry trends and evolving job market demands. Career goals also facilitate better time management and resource allocation, as individuals prioritize tasks and opportunities that advance their professional growth. In addition, articulating career goals can aid in networking and mentorship, as it allows individuals to communicate their aspirations clearly to potential mentors, colleagues, and employers, thereby opening doors to valuable guidance and support. Ultimately, career goals are integral to personal and professional development, driving individuals toward sustained success and fulfillment in their chosen fields.
Mẫu PPT kế hoạch làm việc sáng tạo cho nửa cuối năm PowerPoint
Project Controls Expo - 31st Oct 2012 - The Practical use of Earned Value for real-time forecast and control By David Birch
1.
Copyright
@
2011.
All
rights
reserved
Session
B2
The
Prac0cal
use
of
Earned
Value
for
real-‐0me
forecast
and
control
Project
Controls
Expo
-‐
31st
Oct
2012
Twickenham
Stadium,
London
Speaker
–
David
Birch
2.
Copyright
@
2011.
All
rights
reserved
About
the
Speaker
§ David
Birch
-‐
35
years
experience
in
the
delivery
of
high
profile
UK
and
interna@onal
projects
and
Programmes
for
world
leading
Engineering/Construc@on
contractors.
§ 25
years
of
Project
Controls
and
Opera@onal
Management
experience
§ Since
2008
responsible
for
the
London
2012
Programme
Controls
group
for
CLM,
the
delivery
partner
to
the
Olympic
Delivery
Authority
(ODA).
§ Previously,
delivered
projects
numerous
industry
sectors
including:
ü UK
&
Interna@onal
Oil
and
Gas
ü UK
Nuclear
decommissioning
and
clean-‐up
ü Conven@onal
and
Nuclear
Energy
ü Water
ü Telecoms
ü Industrial
and
Infrastructure
3.
Copyright
@
2011.
All
rights
reserved
Good
decisions
require
good
informa@on.
To
deliver
a
complex
project
to
@me
and
cost
requires
a
proper
understanding,
at
regular
stages
and
at
an
appropriate
level
of
detail,
of
the
rela@onships
between:
work
done,
progress
against
plan,
cost
incurred
against
budget,
cash
spent
and
cost
to
come.
Combining
this
data
leads
to
an
understanding
of
the
actual
value
of
what
has
been
achieved
and
prevents
managers
from
being
either
too
op@mis@c
or
unduly
pessimis@c
about
the
situa@on.
It
enables
them
to
make
appropriate
judgements
as
to
what
correc@ve
ac@ons
need
to
be
taken
in
good
@me.
Sir
John
Armi+
Chairman
-‐
Olympic
Delivery
Authority
EVM
-‐
APM
Guidelines
Forward
4.
Copyright
@
2011.
All
rights
reserved
Baseline
Correct
Analyse
Measure
Project
Controls Cycle
Where are we?
Where are we
going to end
up?
How do we get
on track again?
Classic
Project
Control
Cycle
5.
Copyright
@
2011.
All
rights
reserved
1. Organisa@on
(1-‐5)
2. Planning,
Scheduling
and
Budge@ng
(6-‐15)
3. Actual
Costs
(16-‐21)
4. Analysis
and
Repor@ng
(22-‐27)
5. Change
Management
(28-‐32)
EVM
System
(32
Criteria)
Geang
the
system
right
leads
to:
Informed,
effec>ve
management
and
decision
making
by
knowing:
• What
has
been
achieved
of
the
plan
• What
it
has
cost
to
achieve
the
planned
work
• If
the
work
achieved
is
cos@ng
more
or
less
than
was
planned
• If
the
project
is
ahead
of
or
behind
the
planned
schedule
6.
Copyright
@
2011.
All
rights
reserved
1
-‐
Organisa0on
• Essen@al
to
understand
scope
and
how
it
will
be
broken
down
and
delivered
(Work
Element
Defini@on)
• Key
is
then
to
create
the
Work
Breakdown
Structure
(WBS)
and
progressively
develop
the
Contract
Work
Breakdown
Structure
(CWBS)
• Who
will
deliver
and
be
responsible
for
delivery
Organisa>onal
Breakdown
Structure
(OBS)
• Ensure
that
the
systems
(WBS,
CWBS
and
OBS)
will
support
each
other
and
are
integrated
(via
coding)
7.
Copyright
@
2011.
All
rights
reserved
WBS
Example
8.
Copyright
@
2011.
All
rights
reserved
2
–
Planning,
Scheduling
and
Budge0ng
• Essen@al
to
Schedule
all
the
work
logically
• Iden@fy
the
Project
Milestone
set
and
the
Key
Milestones
within
that
set
• Cost
Loaded
Schedule
ac@vi@es
should
be
aligned
with
Cost
Accounts
within
the
WBS
elements
• Establish
how
the
progress
will
be
measured
• Iden@fy
Level
of
Effort
(LOE)
ac@vi@es
(management,
management
reserves,
prelim’s/overheads,
etc.)
• Create
the
Project
Es@mates
and
fix
the
Budgets
• Baseline
and
implement
Change
Control
11.
Copyright
@
2011.
All
rights
reserved
2
–
Objec0ve
Measures
of
Progress
• Milestones
• Percentage
Complete
ü Agreed
steps
ü Evaluated
ü Once
at
100%
• Quan@@es
• Appor@oned
Level
of
Effort
• Level
of
Effort
12.
Copyright
@
2011.
All
rights
reserved
2
–
Original
Budget
Summary
13.
Copyright
@
2011.
All
rights
reserved
3
–
Actual
Costs
• Essen@al
that
Actual
Costs
(cost
accounts)
are
mapped
to
WBS
• Ensure
that
cost
collec@on
systems
and
contractor
invoices
are
broken
down
into
at
least
the
level
of
the
WBS
elements
• Understand
the
material
accoun@ng
system
and
ensure
plan
aligns
with
when
material
costs
will
be
recorded
(either
invoiced
or
accrued)
• Keep
the
mapping
up
to
date
at
each
update
(normally
monthly)
14. London 2012
06/11/2012
100k 100k 100k 100k
50k 50k 75k 75k
50k 50k 50k 50k
BAC
Status - Performance To Date
Mar 08 Apr 08 May 08 Jun 08 Jul 08 Aug 08 Sep 08 Oct 08 Nov 08 Dec 08
200k
850k
400k
250k
200k
100k 100k 150k 150k 100k 100k 75k 75k
Performance Measurement
BASELINE
BV
Time Now
CLM Accepted Programme
CURRENT
- - 150k 50k 50k 50k
50k 50k 75k 75k
50k 50k 50k 50k
120k 119k
100k
989k
300k
250k
200k
239k
120k 119k 100k 100k 125k 125k 50k 50k 50k 50kEV
EAC
AC
Compare
Cumulative To Date At Completion
BV EV AC SV CV BAC EAC VAC
200k 100k 239k -100k -139k 850k 989k -139k
15.
Copyright
@
2011.
All
rights
reserved
4
–
Analysis
and
Repor0ng
• Collect
progress
data
and
record
%
complete
of
each
ac@vity
(using
the
rules
established
at
planning
phase)
• Compare
Baseline
Plan
with
Progress
and
Actual
Costs
establishing
Schedule
Variance
(SV)
and
Cost
Variance
(CV)
• Forecast
Dura%ons
to
complete
• Forecast
Costs
to
complete
• Review
Milestone
comple@on
forecasts
against
Plan
• Review
An@cipated
Final
Cost
to
Budget
• Project
Team
determine
project
issues/mi@ga@ons/plan
adjustments
• Project
Team
Report
the
outcome
of
analysis
and
plans
to
complete
16.
Copyright
@
2011.
All
rights
reserved
4
–
Quan00es
17.
Copyright
@
2011.
All
rights
reserved
4
–
Progress
18.
Copyright
@
2011.
All
rights
reserved
4
–
Performance
19.
Copyright
@
2011.
All
rights
reserved
4
–
Analysis
20.
Copyright
@
2011.
All
rights
reserved
4
–
Forecas0ng
21.
Copyright
@
2011.
All
rights
reserved
4
–
Project
Manager
Summary
22.
Copyright
@
2011.
All
rights
reserved
5
–
Change
Management
Once
the
Baseline
is
agreed,
published
and
fixed
• The
Original
Budget
should
be
FROZEN
• Change
Control
should
start
and
formal
monthly
change
reviews
should
be
held
and
recorded
• Approved
Changes
should
be
incorporated
into
the
Current
Baseline
(ONLY
APPROVED
CHANGES
–
need
strong
Governance)
• Retrospec@ve
Changes
should
be
strongly
discouraged
• Con@ngency
and
Risk
Management
essen@al
processes
• Current
Baseline
should
reflect
realis0cally
achievable
targets
When
status
and
forecasts
show
significant
variance
to
Baseline
raise
a
change
for
Management
approval.
23.
Copyright
@
2011.
All
rights
reserved
5
–
Change
Process
within
Monthly
Cycle
24.
Copyright
@
2011.
All
rights
reserved
Crea0ng
a
Control
Culture
• Do
not
under
es@mate
the
effort
required
to
set
up
an
effec@ve
control
system
• Once
set
up
the
team
and
contractors
need
to
understand
how
it
will
work
•
Training
is
essen@al
(team,
contractor
and
execu@ve)
• Establishing
a
culture
will
take
@me,
start
early.....
• The
0me
and
effort
will
be
worth
it
25. 2006 2007 2008 2009 2010 2011
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Controls Building Blocks in Place
Baseline developed & Yellow Book Published
Culture & Trust Established
Systems Maturing
Change Control implemented
Monthly & Quarterly Reviews
Trending Process
AFC process
Monthly Trend Reviews
Monthly Trend & AFC Reviews
Simplify Baseline
Schedule Integration maturing
Support & Training
Assurance, Support & Intervention (where necessary)
Align Reporting
London 2012 - Maturity Timeline
Big Build; CompletionBig Build; StructuresBig Build; FoundationsDesign, Dig, Demolish
Controls
mature and
fully functional
26.
Copyright
@
2011.
All
rights
reserved
Integrated
Project
Controls
The Plan &
Physical
Progress
Design,
Procurement and
Construction
Commercial
Position
Budget,
Commitments &
Outturn Costs
Financial
Position
Invoiced and
Accrued Liabilities
In
summary
With
Earned
Value
at
it’s
heart
27.
Copyright
@
2011.
All
rights
reserved
Ques0ons
Thank
You