TECHNICALLY SPEAKING
4 | PODTalk Newsletter | Q4 2018
Dennis Powers
Vice President of Business
Development & Sales Engineering
The Importance of Reduced and
Predictable Project Timelines
Introduction
Reducing project schedules and completing facility projects on
time has never been more important to our industry than it is
today. It is critical that drug manufacturers have the capability
of and capacity for producing therapies and treatments that
are needed by patients around the world. With the spotlight on
the new cell and gene therapies that are being launched, and
their effectiveness for curing life threatening diseases, the
importance of well-controlled project timelines using
pre-fabricated modular facility solutions continues to grow.
The Impact of Project Timelines
Historically, most drug manufacturers have followed a traditional
facility construction approach with extended project timelines,
high onsite complexity, and risks. Very few of the facilities built
using this approach were completed on time to their planned
schedule and it was not uncommon for a new facility project to
take up to 5 years from start to finish. Because of the duration of
project schedules and the unpredictability of traditional on-site
construction, drug manufacturers have had to make large
capital investments in new facilities long before they required
the capacity for their drug products. This has posed significant
financial risk to the companies under the following scenarios:
• A facility built for a drug product that failed in clinical trials
and/or did not get regulatory approval
• A facility delayed in start-up that could not commercially
manufacture a new drug product upon regulatory approval
• A facility which was oversized and underutilized for producing
a drug product that did not achieve the expected market
acceptance
• A facility which was undersized and not capable of meeting
the market demand for a drug product.
The Problem with Traditional Facility Schedules
There are many reasons for lengthy schedules and why they get
delayed during the design, construction, and commissioning
phases of a project. Because most facilities in our industry have
been stick-built, each one has been a unique or custom design
based on the manufacturers’ requirements, but also on the A&E
firm’s experience, design preferences, and desire to differentiate
their work. This non-standardized approach requires a
significant upfront engineering design effort with multiple stage
gates for design reviews and approvals before moving to the
next phase.
Traditional stick-built facilities require sequential construction
phases where the building shell is first erected, followed by
building core and utilities, and finally the critical cleanroom and
process infrastructure. This requires the continual planning,
coordination, and interaction of multiple sub-contractors and
services at the construction site. Due to the complexity there is
often a domino effect of construction delays if tasks are not
started or completed on time due to permitting issues, material
availability, labor shortages, or weather.
The Benefits of a Pre-Fabricated Modular Solution
PODs represent an innovative pre-fabricated modular
cleanroom solution that can be effective in avoiding the
extended project schedules, delays, and many other issues
experienced with traditional construction. The off-site
fabrication of the PODs allows for parallel construction activities
of both the cleanroom infrastructure and shell building/core
which provides a more compressed project timeline. And
because the PODs are fabricated in a well-controlled factory
environment by an experienced labor force, the risk of schedule
delays as well as the number of on-site contractors, staging
areas, safety issues, and overall project liability can be
significantly reduced.
The end result is a shorter and more predictable project timeline
that can help drug manufacturers produce the required
capacity when they need it. The prefabricated approach also
mitigates manufacturers’ financial risks by allowing them to
delay their capital investment until months before the capacity is
required or until the product is further along in the clinical trial
process and with a higher probability for regulatory approval.
The pre-fabricated modular approach can help companies
prevent the potential loss of millions of dollars in revenue as well
as prevent the wasting of millions of dollars in capital to build a
facility that cannot be used as planned.

More Related Content

What's hot

Resume Kevin_Koski_August_2016
Resume Kevin_Koski_August_2016Resume Kevin_Koski_August_2016
Resume Kevin_Koski_August_2016
Kevin Koski
 
Morciglio current resume 2016
Morciglio current resume 2016Morciglio current resume 2016
Morciglio current resume 2016
Chris Morciglio
 
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning LettersHow to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
Greenlight Guru
 
Project Funding Guidelines
Project Funding GuidelinesProject Funding Guidelines
Project Funding Guidelines
Dilip Pandey
 
RESUME-JOSE FALCON
RESUME-JOSE FALCONRESUME-JOSE FALCON
RESUME-JOSE FALCON
Jose Falcon
 

What's hot (20)

G con future flexible facility - mj 03-2015
G con future flexible facility  - mj 03-2015G con future flexible facility  - mj 03-2015
G con future flexible facility - mj 03-2015
 
Helping a Small Biotech Reach a Critical Milestone
Helping a Small Biotech Reach a Critical MilestoneHelping a Small Biotech Reach a Critical Milestone
Helping a Small Biotech Reach a Critical Milestone
 
aaaQA_Dir. SteveCVQ216
aaaQA_Dir. SteveCVQ216aaaQA_Dir. SteveCVQ216
aaaQA_Dir. SteveCVQ216
 
Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.Case Studies in Pharmaceutical Project Management.
Case Studies in Pharmaceutical Project Management.
 
Resume Kevin_Koski_August_2016
Resume Kevin_Koski_August_2016Resume Kevin_Koski_August_2016
Resume Kevin_Koski_August_2016
 
How To Manage and Mitigate Risk in Medical Device New Product Development
How To Manage and Mitigate Risk in Medical Device New Product DevelopmentHow To Manage and Mitigate Risk in Medical Device New Product Development
How To Manage and Mitigate Risk in Medical Device New Product Development
 
Design Controls: Building Objective Evidence and Process Architecture to Mee...
Design Controls: Building Objective Evidence and Process Architecture  to Mee...Design Controls: Building Objective Evidence and Process Architecture  to Mee...
Design Controls: Building Objective Evidence and Process Architecture to Mee...
 
SMi Group's 3rd annual Pre-Filled Syringes West Coast 2018
SMi Group's 3rd annual Pre-Filled Syringes West Coast 2018SMi Group's 3rd annual Pre-Filled Syringes West Coast 2018
SMi Group's 3rd annual Pre-Filled Syringes West Coast 2018
 
Morciglio current resume 2016
Morciglio current resume 2016Morciglio current resume 2016
Morciglio current resume 2016
 
Accelerating Post-approval Change Management with ICH Q12
Accelerating Post-approval Change Management with ICH Q12Accelerating Post-approval Change Management with ICH Q12
Accelerating Post-approval Change Management with ICH Q12
 
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning LettersHow to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
How to Prepare for an FDA Inspection and Respond to FDA 483's / Warning Letters
 
Presentation trvx cdmo-v2
Presentation trvx   cdmo-v2Presentation trvx   cdmo-v2
Presentation trvx cdmo-v2
 
AWR resume
AWR resumeAWR resume
AWR resume
 
CV-Jose - 2015
CV-Jose - 2015CV-Jose - 2015
CV-Jose - 2015
 
FDA Inspections are Different from ISO Audits, So Don't Treat Them the Same -...
FDA Inspections are Different from ISO Audits, So Don't Treat Them the Same -...FDA Inspections are Different from ISO Audits, So Don't Treat Them the Same -...
FDA Inspections are Different from ISO Audits, So Don't Treat Them the Same -...
 
The FDA Early Feasibility Study Pilot and the Innovation Pathway
The FDA Early Feasibility Study Pilot and the Innovation PathwayThe FDA Early Feasibility Study Pilot and the Innovation Pathway
The FDA Early Feasibility Study Pilot and the Innovation Pathway
 
Enabling higher process titers at a manufacturing facility
Enabling higher process titers at a manufacturing facilityEnabling higher process titers at a manufacturing facility
Enabling higher process titers at a manufacturing facility
 
EC Ajawara_Resume_2015MS
EC Ajawara_Resume_2015MSEC Ajawara_Resume_2015MS
EC Ajawara_Resume_2015MS
 
Project Funding Guidelines
Project Funding GuidelinesProject Funding Guidelines
Project Funding Guidelines
 
RESUME-JOSE FALCON
RESUME-JOSE FALCONRESUME-JOSE FALCON
RESUME-JOSE FALCON
 

Similar to The Importance of Reduced and Predictable Project Timelines, By: Dennis Powers - G-CON Manufacturing

Nancy K Johnson PMP_resume
Nancy K Johnson PMP_resumeNancy K Johnson PMP_resume
Nancy K Johnson PMP_resume
Nancy Johnson
 
Contract manufacturing, By Anubhav Singh, M.pharm
Contract manufacturing, By Anubhav Singh, M.pharmContract manufacturing, By Anubhav Singh, M.pharm
Contract manufacturing, By Anubhav Singh, M.pharm
Anubhav Singh
 
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
mwright1
 
Customerlogo hereProject Name Project CharterCompany
Customerlogo hereProject Name Project CharterCompanyCustomerlogo hereProject Name Project CharterCompany
Customerlogo hereProject Name Project CharterCompany
OllieShoresna
 
Does Innovation Pay DIA 2006
Does Innovation Pay DIA 2006Does Innovation Pay DIA 2006
Does Innovation Pay DIA 2006
Neil Patel
 

Similar to The Importance of Reduced and Predictable Project Timelines, By: Dennis Powers - G-CON Manufacturing (20)

Nancy K Johnson PMP_resume
Nancy K Johnson PMP_resumeNancy K Johnson PMP_resume
Nancy K Johnson PMP_resume
 
Contract manufacturing, By Anubhav Singh, M.pharm
Contract manufacturing, By Anubhav Singh, M.pharmContract manufacturing, By Anubhav Singh, M.pharm
Contract manufacturing, By Anubhav Singh, M.pharm
 
It's easy to turn money into technology...
It's easy to turn money into technology...It's easy to turn money into technology...
It's easy to turn money into technology...
 
Product definition starting point for medical device manufacturing
Product definition starting point for medical device manufacturingProduct definition starting point for medical device manufacturing
Product definition starting point for medical device manufacturing
 
The Medical Device Milestone Map
The Medical Device Milestone MapThe Medical Device Milestone Map
The Medical Device Milestone Map
 
industrial microbial culture (1).pdf
industrial microbial culture (1).pdfindustrial microbial culture (1).pdf
industrial microbial culture (1).pdf
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Technology Absorption & Management, Concurrent Engineering, Project Management
Technology Absorption & Management, Concurrent Engineering, Project ManagementTechnology Absorption & Management, Concurrent Engineering, Project Management
Technology Absorption & Management, Concurrent Engineering, Project Management
 
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
Having a Prosperous New Year with Your CRO: The Gift of a Great Contract!
 
Customerlogo hereProject Name Project CharterCompany
Customerlogo hereProject Name Project CharterCompanyCustomerlogo hereProject Name Project CharterCompany
Customerlogo hereProject Name Project CharterCompany
 
Future flexible facility needs - mj 06-2016
Future flexible facility needs - mj 06-2016Future flexible facility needs - mj 06-2016
Future flexible facility needs - mj 06-2016
 
6 Tips to Accelerate MedTech Time To Clinical Data
6 Tips to Accelerate MedTech Time To Clinical Data6 Tips to Accelerate MedTech Time To Clinical Data
6 Tips to Accelerate MedTech Time To Clinical Data
 
IJSRED-V2I2P1
IJSRED-V2I2P1IJSRED-V2I2P1
IJSRED-V2I2P1
 
Does Innovation Pay DIA 2006
Does Innovation Pay DIA 2006Does Innovation Pay DIA 2006
Does Innovation Pay DIA 2006
 
Qualty Competence in Outsourced Formulations Labs - Making the Grade
Qualty Competence in Outsourced Formulations Labs - Making the GradeQualty Competence in Outsourced Formulations Labs - Making the Grade
Qualty Competence in Outsourced Formulations Labs - Making the Grade
 
UNIT 1
UNIT 1UNIT 1
UNIT 1
 
project management
project managementproject management
project management
 
Building the Right Product vs. The Product Right
Building the Right Product vs. The Product RightBuilding the Right Product vs. The Product Right
Building the Right Product vs. The Product Right
 
Reconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and StartupReconsidering the Potential of Commissioning and Startup
Reconsidering the Potential of Commissioning and Startup
 
Project management risks.pptx for college
Project management risks.pptx for collegeProject management risks.pptx for college
Project management risks.pptx for college
 

More from Brittany Berryman

More from Brittany Berryman (9)

Standardized Cleanrooms Give Biopharma the Speed it Needs
Standardized Cleanrooms Give Biopharma the Speed it NeedsStandardized Cleanrooms Give Biopharma the Speed it Needs
Standardized Cleanrooms Give Biopharma the Speed it Needs
 
White paper 2020: G-CON's Transmissible Disease Defense Units
White paper 2020: G-CON's Transmissible Disease Defense UnitsWhite paper 2020: G-CON's Transmissible Disease Defense Units
White paper 2020: G-CON's Transmissible Disease Defense Units
 
Delivery of the First POD to Europe... Achieved with Flying Colors
Delivery of the First POD to Europe... Achieved with Flying ColorsDelivery of the First POD to Europe... Achieved with Flying Colors
Delivery of the First POD to Europe... Achieved with Flying Colors
 
How to Get iCON Ready
How to Get iCON ReadyHow to Get iCON Ready
How to Get iCON Ready
 
iCON: The Turnkey Facility of the Future Here Today
iCON: The Turnkey Facility of the Future Here TodayiCON: The Turnkey Facility of the Future Here Today
iCON: The Turnkey Facility of the Future Here Today
 
Deployable Facilities Offer Pay As-You-Go Biomanufacturing Says Just
Deployable Facilities Offer Pay As-You-Go Biomanufacturing Says JustDeployable Facilities Offer Pay As-You-Go Biomanufacturing Says Just
Deployable Facilities Offer Pay As-You-Go Biomanufacturing Says Just
 
Cleanroom PODs with LifeAire Systems
Cleanroom PODs with LifeAire SystemsCleanroom PODs with LifeAire Systems
Cleanroom PODs with LifeAire Systems
 
Trends of Modular Mobile Cleanroom Facilities
Trends of Modular Mobile Cleanroom FacilitiesTrends of Modular Mobile Cleanroom Facilities
Trends of Modular Mobile Cleanroom Facilities
 
Cost Comparison of Cleanroom Designs
Cost Comparison of Cleanroom DesignsCost Comparison of Cleanroom Designs
Cost Comparison of Cleanroom Designs
 

Recently uploaded

Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose AcademicsCytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
MedicoseAcademics
 
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose AcademicsConnective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
MedicoseAcademics
 

Recently uploaded (20)

Quality control tests of suppository ...
Quality control tests  of suppository ...Quality control tests  of suppository ...
Quality control tests of suppository ...
 
Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose AcademicsCytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
Cytoskeleton and Cell Inclusions - Dr Muhammad Ali Rabbani - Medicose Academics
 
Unveiling Alcohol Withdrawal Syndrome: exploring it's hidden depths
Unveiling Alcohol Withdrawal Syndrome: exploring it's hidden depthsUnveiling Alcohol Withdrawal Syndrome: exploring it's hidden depths
Unveiling Alcohol Withdrawal Syndrome: exploring it's hidden depths
 
Bhimrad + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x...
Bhimrad + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x...Bhimrad + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x...
Bhimrad + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x...
 
Gross Anatomy and Histology of Tongue by Dr. Rabia Inam Gandapore.pptx
Gross Anatomy and Histology of Tongue by Dr. Rabia Inam Gandapore.pptxGross Anatomy and Histology of Tongue by Dr. Rabia Inam Gandapore.pptx
Gross Anatomy and Histology of Tongue by Dr. Rabia Inam Gandapore.pptx
 
Overview on the Automatic pill identifier
Overview on the Automatic pill identifierOverview on the Automatic pill identifier
Overview on the Automatic pill identifier
 
ANAPHYLAXIS BY DR.SOHAN BISWAS,MBBS,DNB(INTERNAL MEDICINE) RESIDENT.pptx
ANAPHYLAXIS BY DR.SOHAN BISWAS,MBBS,DNB(INTERNAL MEDICINE) RESIDENT.pptxANAPHYLAXIS BY DR.SOHAN BISWAS,MBBS,DNB(INTERNAL MEDICINE) RESIDENT.pptx
ANAPHYLAXIS BY DR.SOHAN BISWAS,MBBS,DNB(INTERNAL MEDICINE) RESIDENT.pptx
 
Hemodialysis: Chapter 1, Physiological Principles of Hemodialysis - Dr.Gawad
Hemodialysis: Chapter 1, Physiological Principles of Hemodialysis - Dr.GawadHemodialysis: Chapter 1, Physiological Principles of Hemodialysis - Dr.Gawad
Hemodialysis: Chapter 1, Physiological Principles of Hemodialysis - Dr.Gawad
 
Video capsule endoscopy (VCE ) in children
Video capsule endoscopy (VCE ) in childrenVideo capsule endoscopy (VCE ) in children
Video capsule endoscopy (VCE ) in children
 
Young & Hot ℂall Girls Patna 8250077686 WhatsApp Number Best Rates of Patna ℂ...
Young & Hot ℂall Girls Patna 8250077686 WhatsApp Number Best Rates of Patna ℂ...Young & Hot ℂall Girls Patna 8250077686 WhatsApp Number Best Rates of Patna ℂ...
Young & Hot ℂall Girls Patna 8250077686 WhatsApp Number Best Rates of Patna ℂ...
 
Young & Hot ℂall Girls Salem 8250077686 WhatsApp Number Best Rates of Surat ℂ...
Young & Hot ℂall Girls Salem 8250077686 WhatsApp Number Best Rates of Surat ℂ...Young & Hot ℂall Girls Salem 8250077686 WhatsApp Number Best Rates of Surat ℂ...
Young & Hot ℂall Girls Salem 8250077686 WhatsApp Number Best Rates of Surat ℂ...
 
The Clean Living Project Episode 24 - Subconscious
The Clean Living Project Episode 24 - SubconsciousThe Clean Living Project Episode 24 - Subconscious
The Clean Living Project Episode 24 - Subconscious
 
VIP ℂall Girls Kandivali west Mumbai 8250077686 WhatsApp: Me All Time Serviℂe...
VIP ℂall Girls Kandivali west Mumbai 8250077686 WhatsApp: Me All Time Serviℂe...VIP ℂall Girls Kandivali west Mumbai 8250077686 WhatsApp: Me All Time Serviℂe...
VIP ℂall Girls Kandivali west Mumbai 8250077686 WhatsApp: Me All Time Serviℂe...
 
Drug development life cycle indepth overview.pptx
Drug development life cycle indepth overview.pptxDrug development life cycle indepth overview.pptx
Drug development life cycle indepth overview.pptx
 
Unlocking Holistic Wellness: Addressing Depression, Mental Well-Being, and St...
Unlocking Holistic Wellness: Addressing Depression, Mental Well-Being, and St...Unlocking Holistic Wellness: Addressing Depression, Mental Well-Being, and St...
Unlocking Holistic Wellness: Addressing Depression, Mental Well-Being, and St...
 
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose AcademicsConnective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
Connective Tissue II - Dr Muhammad Ali Rabbani - Medicose Academics
 
TEST BANK For Huether and McCance's Understanding Pathophysiology, Canadian 2...
TEST BANK For Huether and McCance's Understanding Pathophysiology, Canadian 2...TEST BANK For Huether and McCance's Understanding Pathophysiology, Canadian 2...
TEST BANK For Huether and McCance's Understanding Pathophysiology, Canadian 2...
 
DR. Neha Mehta Best Psychologist.in India
DR. Neha Mehta Best Psychologist.in IndiaDR. Neha Mehta Best Psychologist.in India
DR. Neha Mehta Best Psychologist.in India
 
Vesu + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x7 C...
Vesu + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x7 C...Vesu + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x7 C...
Vesu + ℂall Girls Serviℂe Surat (Adult Only) 8849756361 Esℂort Serviℂe 24x7 C...
 
Renal Replacement Therapy in Acute Kidney Injury -time modality -Dr Ayman Se...
Renal Replacement Therapy in Acute Kidney Injury -time  modality -Dr Ayman Se...Renal Replacement Therapy in Acute Kidney Injury -time  modality -Dr Ayman Se...
Renal Replacement Therapy in Acute Kidney Injury -time modality -Dr Ayman Se...
 

The Importance of Reduced and Predictable Project Timelines, By: Dennis Powers - G-CON Manufacturing

  • 1. TECHNICALLY SPEAKING 4 | PODTalk Newsletter | Q4 2018 Dennis Powers Vice President of Business Development & Sales Engineering The Importance of Reduced and Predictable Project Timelines Introduction Reducing project schedules and completing facility projects on time has never been more important to our industry than it is today. It is critical that drug manufacturers have the capability of and capacity for producing therapies and treatments that are needed by patients around the world. With the spotlight on the new cell and gene therapies that are being launched, and their effectiveness for curing life threatening diseases, the importance of well-controlled project timelines using pre-fabricated modular facility solutions continues to grow. The Impact of Project Timelines Historically, most drug manufacturers have followed a traditional facility construction approach with extended project timelines, high onsite complexity, and risks. Very few of the facilities built using this approach were completed on time to their planned schedule and it was not uncommon for a new facility project to take up to 5 years from start to finish. Because of the duration of project schedules and the unpredictability of traditional on-site construction, drug manufacturers have had to make large capital investments in new facilities long before they required the capacity for their drug products. This has posed significant financial risk to the companies under the following scenarios: • A facility built for a drug product that failed in clinical trials and/or did not get regulatory approval • A facility delayed in start-up that could not commercially manufacture a new drug product upon regulatory approval • A facility which was oversized and underutilized for producing a drug product that did not achieve the expected market acceptance • A facility which was undersized and not capable of meeting the market demand for a drug product. The Problem with Traditional Facility Schedules There are many reasons for lengthy schedules and why they get delayed during the design, construction, and commissioning phases of a project. Because most facilities in our industry have been stick-built, each one has been a unique or custom design based on the manufacturers’ requirements, but also on the A&E firm’s experience, design preferences, and desire to differentiate their work. This non-standardized approach requires a significant upfront engineering design effort with multiple stage gates for design reviews and approvals before moving to the next phase. Traditional stick-built facilities require sequential construction phases where the building shell is first erected, followed by building core and utilities, and finally the critical cleanroom and process infrastructure. This requires the continual planning, coordination, and interaction of multiple sub-contractors and services at the construction site. Due to the complexity there is often a domino effect of construction delays if tasks are not started or completed on time due to permitting issues, material availability, labor shortages, or weather. The Benefits of a Pre-Fabricated Modular Solution PODs represent an innovative pre-fabricated modular cleanroom solution that can be effective in avoiding the extended project schedules, delays, and many other issues experienced with traditional construction. The off-site fabrication of the PODs allows for parallel construction activities of both the cleanroom infrastructure and shell building/core which provides a more compressed project timeline. And because the PODs are fabricated in a well-controlled factory environment by an experienced labor force, the risk of schedule delays as well as the number of on-site contractors, staging areas, safety issues, and overall project liability can be significantly reduced. The end result is a shorter and more predictable project timeline that can help drug manufacturers produce the required capacity when they need it. The prefabricated approach also mitigates manufacturers’ financial risks by allowing them to delay their capital investment until months before the capacity is required or until the product is further along in the clinical trial process and with a higher probability for regulatory approval. The pre-fabricated modular approach can help companies prevent the potential loss of millions of dollars in revenue as well as prevent the wasting of millions of dollars in capital to build a facility that cannot be used as planned.