SlideShare a Scribd company logo
Shroff S.R. Rotary Institute of Chemical Technology
Principal Supporter & Sponsor- UPL LTD./ Shroff family
Managed By Ankleshwar Rotary Education Society
Approved by AICTE, New Delhi, Govt. of Gujarat & GTU Affiliated
A
PRESENTATION ON
INDUSTRIAL SUMMER TRAINING (IST)
AT
TBEA ENERGY (INDIA) PVT LTD
B. E. Semester – VI
(Branch: ELECTRICAL ENGINEERING)
SUBMITTED BY:
RAVIRAJSINH SOLANKI ( 150990109011 )
Academic year 2018-19
OUTLINE
• Introduction
• Layout of Tbeaenergy (india) pvt ltd
• Basics of transformer
• Information flow diagram
• Transformer manufacturing process
• Testing of transformer
• Main Unit & Trailer Packing Check
• Dispatch
• Conclusion
INTRODUCTION
• TBEA group invested 19.1cr USD in UHV exported job
centre of TBEA energy (india) PVTLTD.
• The investment was allowed to the 265000m uhv main
workshop and r&d is export base of the largest research
and production facility for transformer products.
• The annual gross transformer manufacturing capacity is
200 million KVA, which is third highest in the world.
• It is equipped by over 300 sets of machines including the
most advanced cut to length line and hydraulic roll over
table.
• Tebian electric apparatus (tbea) is a chinese manufacturer
of power transformers and other electrical equipment, and
a developer of transmission projects.
LAYOUT OF TBEA ENERGY PVT. LTD.
BASICS OF TRANSFORMER
• The transformer is a electrostatic device which is used to transfer electrical energy from
one circuit to another by mutual induction of two electric circuits without change in
frequency.
• Each phase of a transformer is composed of two separate coil windings wound on a
common Core.
• The low-voltage winding is placed nearest the core; the high voltage winding is then
Placed around both the low voltage winding and core.
• The core is typically made from very thin Steel laminations, each coated with insulation.
By insulating between individual laminations,
• The steel core provides a low resistance path for magnetic flux. Both high And low
voltage windings are insulated from the core and from each other, and leads are brought
Out through insulating bushings.
• A three-phase transformer typically has a core with three legs and has both high voltage
and Low voltage windings around each leg. Special paper and wood are used for
insulation and Internal structural support.
 INFORMATION FLOW DIAGRAM
CORE ASSEMBLY
Receive And Study Drawings
Incoming Material Inspection
Surface Of Lamination And Pallet
Laying Of Core Table &
Arrangment Of Clamp Assembly
Stacking Of CRGO Lamination
Clamping Of Core
Core Assembly
Welding Of TIE Rods
Upending Of Core Table
Core Inspection Before Storage
TRANSFORMER WINDING
Drawing Study
Acceptance of material
mould insullation
conductor drum loading
insullation of cylinder on the mould
winding manufacturing
LEAD ASSEMBLY
1.Preparation
2. Cabling And
Connection
3.Brazing/
Crimping
4.Surface
Treatment
5.Lead Shielding &
Insulation
Wrapping
6.Pre Assembly Of
Tap Changer
7.Tap Changer
Connection
Sheilding And
Wrapping
8.Cleaning And
Testing
FINAL ASSEMBLY
 TESTING OF TRANSFORMER
Routine tests :
• Measurement of winding resistance
• Measurement of voltage ratio
• Measurement of no-load loss
• Measurement of short-circuit impedance
• Measurement of insulation resistance
• Switching impulse voltage test
• Lightning impulse voltage test
• Temperature rise test
• Determination of capacitances and tan delta between winding to earth and between
windings.
Mechanical Tests :
• Jacking Test
• Vacuum test on transformer tank
• Oil pressure test on completely assembled transformer
MAIN UNIT & TRAILER PACKING CHECK SHEET
POINTS :
(1 ) Trailer Details
 Transporter name.
 Details of the trailer.
 Details of driver.
(2) Transport Dimension Of The Tank
 Ensure that the transport dimension is within the limits as per drawing requirements.
(3) Lashing Of The Job To Trailer
 Lashing should be adequate thickness.
 Lashing should not foul with the Transformer tank at any place.
 Locations of lashing should be proper.
 Lashing should be tight.
 Rubber pads should be put below lashing lug.
(4) Final Dispatch Clearance
 All gate points cleared.
 Job cleared for dispatch by quality.
(5) Loading Of Other Accessories On Trailer
 Packing list of all accessories loaded on trailer.
 Should be placed properly with rubber pad and wrapped with stretchable
plastic cover.
(6) Condition Of Trailer After Loading And To Prior To Movement
 Trailer should be healthy and should not tilt to one side.
 All tyre should be in good condition.
(7) Any Possibility Of Transit Damage
 There should be any sharp and unsupported protections outside the tank
(8) Check Nitrogen/Dry Air
 Nitrogen/dry air pressure should be 5 psi.
 No leak/drop in pressure.
 The pipes should be protected.
 Gauges in working condition.
(9) Rain Protection Cover On Main Unit(If Applicable)
 Main unit shall be covered with rain protection cover from all sides and
cover.
(10) Painting Of Transformer Main Unit And All Blanking Plate
 All temporary blanking plates should be red colour.
(11) The Main Tank Prior To Loading
 Clean and free from dust and air.
 No visible damage to Transformer tank.
 Hardware should be with respective item approved vendor( if applicable).
(12) Loading Of Tank On Trailer
 Ensure that the tank is in centre of trailer with respect to the centre of gravity
of job.
(13) Photographs Prior To Dispatch
 Take photographs from all sides.
 DISPATCH :
• After successful completion of testing,
transformer is handed over to dispatch
sections. At this stage after checking oil
leakage, etc. and covered with the blanking
plates and the tank is fitted with nitrogen gas
and then the transformer is dispatched to the
concerned site.
 There are generally three separate shipments made
• The main tank c/w core and coils
• The accessories that have been removed and
packaged
• The insulating oil.
CONCLUSION
• I would like to say that this summer training is an excellent
opportunity for me to get to the ground level and experience the
things that we would have never gained through going straight into
a job.
• I am grateful to the Shroff S R Rotary Institute of Chemical
Technology for giving me this wonderful opportunity.
• The main objective of the industrial training is to provide an
opportunity to undergraduates to identify, observe and practice
how engineering is applicable in the real industry. It is not only to
get experience on technical practices but also to observe
management practices and to interact with fellow. Workers.
• During 21 days training period, a lot of experience, knowledge and
exposure that I have handy the training was more than hope to me
and also help me to understand about manufacturing of
transformer more.

More Related Content

What's hot

HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
Shankar Singh
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
Rohit Dave
 
Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substation
Supardi Amaludin
 

What's hot (20)

Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
HT and LT SWITCHGEAR
HT and LT SWITCHGEARHT and LT SWITCHGEAR
HT and LT SWITCHGEAR
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Motor protection
Motor protectionMotor protection
Motor protection
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Internship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission stationInternship Report at a 132/33 KV transmission station
Internship Report at a 132/33 KV transmission station
 
Understanding transformer vector group
Understanding transformer vector groupUnderstanding transformer vector group
Understanding transformer vector group
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
DLW Electrical Engineering industrial training Report
DLW Electrical Engineering industrial training Report DLW Electrical Engineering industrial training Report
DLW Electrical Engineering industrial training Report
 
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
SLD-LINE LENGTH-NAMEPLATE DETAILS OF 765/400/220KV EQUIPMENT DETAILS-TYPES OF...
 
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv JimitPRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
PRESENTATION ON MANUFACTURING OF TRANSFORMER By Dhruv Jimit
 
Motor Protection
Motor ProtectionMotor Protection
Motor Protection
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
 
Transformer & OLTC
Transformer & OLTCTransformer & OLTC
Transformer & OLTC
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
 
Estimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substationEstimation of a_pole_mounted_substation
Estimation of a_pole_mounted_substation
 

Similar to TBEA ENERGY (INDIA) PVT LTD

Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
jksjekmd
 
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
jksjmdmd
 
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
ukejkmd
 
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
jksjdmd
 
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
jkskjdkm
 

Similar to TBEA ENERGY (INDIA) PVT LTD (20)

casing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manualcasing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manual
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Development Of Tipper Unloading Mechanism
Development Of Tipper Unloading MechanismDevelopment Of Tipper Unloading Mechanism
Development Of Tipper Unloading Mechanism
 
Bhel report block 4
Bhel report block 4Bhel report block 4
Bhel report block 4
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
frame manufacture overview
frame manufacture overviewframe manufacture overview
frame manufacture overview
 
DR.VAN
DR.VANDR.VAN
DR.VAN
 
Industrial report presentation
Industrial report presentationIndustrial report presentation
Industrial report presentation
 
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxVIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
 
Report steffones
Report steffonesReport steffones
Report steffones
 
The osterberg cell static loading test
The osterberg cell static loading testThe osterberg cell static loading test
The osterberg cell static loading test
 
Megat Zulkarnain 2016 CV
Megat Zulkarnain 2016 CVMegat Zulkarnain 2016 CV
Megat Zulkarnain 2016 CV
 
ProjectReportL&T
ProjectReportL&TProjectReportL&T
ProjectReportL&T
 
S04503109112
S04503109112S04503109112
S04503109112
 
Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat gp40 kl forklift lift trucks chassis and mast service repair ...
 
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
Caterpillar cat dp40 kl forklift lift trucks chassis and mast service repair ...
 
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
CATERPILLAR CAT GP50K FORKLIFT LIFT TRUCKS CHASSIS AND MAST Service Repair Ma...
 
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat dp40 k forklift lift trucks chassis and mast service repair m...
 
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
Caterpillar cat gp45 k forklift lift trucks chassis and mast service repair m...
 
Space Propulsion Innovation Award
Space Propulsion Innovation AwardSpace Propulsion Innovation Award
Space Propulsion Innovation Award
 

More from Raviraj solanki

More from Raviraj solanki (13)

Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit Breaker
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
Simulation of Boost Converter Using MATLAB SIMULINK.
Simulation of  Boost Converter Using MATLAB SIMULINK.Simulation of  Boost Converter Using MATLAB SIMULINK.
Simulation of Boost Converter Using MATLAB SIMULINK.
 
Inter Connected Power System(Turbine Speed Governing Mechanism )
Inter Connected Power System(Turbine Speed Governing Mechanism)Inter Connected Power System(Turbine Speed Governing Mechanism)
Inter Connected Power System(Turbine Speed Governing Mechanism )
 
Engineering Economics and Management
Engineering Economics and Management Engineering Economics and Management
Engineering Economics and Management
 
FACT devices
FACT devicesFACT devices
FACT devices
 
Switch Gear & Protection (conventional circuit breaker)
Switch Gear & Protection	(conventional circuit breaker)Switch Gear & Protection	(conventional circuit breaker)
Switch Gear & Protection (conventional circuit breaker)
 
continuity equation and relaxation time
continuity equation and relaxation timecontinuity equation and relaxation time
continuity equation and relaxation time
 
time response analysis
time response analysistime response analysis
time response analysis
 
design of chock coil
 design of chock coil design of chock coil
design of chock coil
 
1 phase semiconverter
1 phase semiconverter1 phase semiconverter
1 phase semiconverter
 
Design engineering
Design engineering  Design engineering
Design engineering
 
types of winding dc machine
 types of winding dc machine types of winding dc machine
types of winding dc machine
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
Atif Razi
 

Recently uploaded (20)

Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-4 Notes for II-II Mechanical Engineering
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical SolutionsRS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
RS Khurmi Machine Design Clutch and Brake Exercise Numerical Solutions
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 

TBEA ENERGY (INDIA) PVT LTD

  • 1. Shroff S.R. Rotary Institute of Chemical Technology Principal Supporter & Sponsor- UPL LTD./ Shroff family Managed By Ankleshwar Rotary Education Society Approved by AICTE, New Delhi, Govt. of Gujarat & GTU Affiliated A PRESENTATION ON INDUSTRIAL SUMMER TRAINING (IST) AT TBEA ENERGY (INDIA) PVT LTD B. E. Semester – VI (Branch: ELECTRICAL ENGINEERING) SUBMITTED BY: RAVIRAJSINH SOLANKI ( 150990109011 ) Academic year 2018-19
  • 2.
  • 3.
  • 4. OUTLINE • Introduction • Layout of Tbeaenergy (india) pvt ltd • Basics of transformer • Information flow diagram • Transformer manufacturing process • Testing of transformer • Main Unit & Trailer Packing Check • Dispatch • Conclusion
  • 5. INTRODUCTION • TBEA group invested 19.1cr USD in UHV exported job centre of TBEA energy (india) PVTLTD. • The investment was allowed to the 265000m uhv main workshop and r&d is export base of the largest research and production facility for transformer products. • The annual gross transformer manufacturing capacity is 200 million KVA, which is third highest in the world. • It is equipped by over 300 sets of machines including the most advanced cut to length line and hydraulic roll over table. • Tebian electric apparatus (tbea) is a chinese manufacturer of power transformers and other electrical equipment, and a developer of transmission projects.
  • 6. LAYOUT OF TBEA ENERGY PVT. LTD.
  • 7. BASICS OF TRANSFORMER • The transformer is a electrostatic device which is used to transfer electrical energy from one circuit to another by mutual induction of two electric circuits without change in frequency. • Each phase of a transformer is composed of two separate coil windings wound on a common Core. • The low-voltage winding is placed nearest the core; the high voltage winding is then Placed around both the low voltage winding and core. • The core is typically made from very thin Steel laminations, each coated with insulation. By insulating between individual laminations, • The steel core provides a low resistance path for magnetic flux. Both high And low voltage windings are insulated from the core and from each other, and leads are brought Out through insulating bushings. • A three-phase transformer typically has a core with three legs and has both high voltage and Low voltage windings around each leg. Special paper and wood are used for insulation and Internal structural support.
  • 9. CORE ASSEMBLY Receive And Study Drawings Incoming Material Inspection Surface Of Lamination And Pallet Laying Of Core Table & Arrangment Of Clamp Assembly Stacking Of CRGO Lamination Clamping Of Core Core Assembly Welding Of TIE Rods Upending Of Core Table Core Inspection Before Storage
  • 10.
  • 11. TRANSFORMER WINDING Drawing Study Acceptance of material mould insullation conductor drum loading insullation of cylinder on the mould winding manufacturing
  • 12. LEAD ASSEMBLY 1.Preparation 2. Cabling And Connection 3.Brazing/ Crimping 4.Surface Treatment 5.Lead Shielding & Insulation Wrapping 6.Pre Assembly Of Tap Changer 7.Tap Changer Connection Sheilding And Wrapping 8.Cleaning And Testing
  • 13.
  • 15.  TESTING OF TRANSFORMER Routine tests : • Measurement of winding resistance • Measurement of voltage ratio • Measurement of no-load loss • Measurement of short-circuit impedance • Measurement of insulation resistance • Switching impulse voltage test • Lightning impulse voltage test • Temperature rise test • Determination of capacitances and tan delta between winding to earth and between windings. Mechanical Tests : • Jacking Test • Vacuum test on transformer tank • Oil pressure test on completely assembled transformer
  • 16. MAIN UNIT & TRAILER PACKING CHECK SHEET POINTS : (1 ) Trailer Details  Transporter name.  Details of the trailer.  Details of driver. (2) Transport Dimension Of The Tank  Ensure that the transport dimension is within the limits as per drawing requirements. (3) Lashing Of The Job To Trailer  Lashing should be adequate thickness.  Lashing should not foul with the Transformer tank at any place.  Locations of lashing should be proper.  Lashing should be tight.  Rubber pads should be put below lashing lug. (4) Final Dispatch Clearance  All gate points cleared.  Job cleared for dispatch by quality.
  • 17. (5) Loading Of Other Accessories On Trailer  Packing list of all accessories loaded on trailer.  Should be placed properly with rubber pad and wrapped with stretchable plastic cover. (6) Condition Of Trailer After Loading And To Prior To Movement  Trailer should be healthy and should not tilt to one side.  All tyre should be in good condition. (7) Any Possibility Of Transit Damage  There should be any sharp and unsupported protections outside the tank (8) Check Nitrogen/Dry Air  Nitrogen/dry air pressure should be 5 psi.  No leak/drop in pressure.  The pipes should be protected.  Gauges in working condition.
  • 18. (9) Rain Protection Cover On Main Unit(If Applicable)  Main unit shall be covered with rain protection cover from all sides and cover. (10) Painting Of Transformer Main Unit And All Blanking Plate  All temporary blanking plates should be red colour.
  • 19. (11) The Main Tank Prior To Loading  Clean and free from dust and air.  No visible damage to Transformer tank.  Hardware should be with respective item approved vendor( if applicable). (12) Loading Of Tank On Trailer  Ensure that the tank is in centre of trailer with respect to the centre of gravity of job. (13) Photographs Prior To Dispatch  Take photographs from all sides.
  • 20.  DISPATCH : • After successful completion of testing, transformer is handed over to dispatch sections. At this stage after checking oil leakage, etc. and covered with the blanking plates and the tank is fitted with nitrogen gas and then the transformer is dispatched to the concerned site.
  • 21.  There are generally three separate shipments made • The main tank c/w core and coils
  • 22. • The accessories that have been removed and packaged
  • 24.
  • 25. CONCLUSION • I would like to say that this summer training is an excellent opportunity for me to get to the ground level and experience the things that we would have never gained through going straight into a job. • I am grateful to the Shroff S R Rotary Institute of Chemical Technology for giving me this wonderful opportunity. • The main objective of the industrial training is to provide an opportunity to undergraduates to identify, observe and practice how engineering is applicable in the real industry. It is not only to get experience on technical practices but also to observe management practices and to interact with fellow. Workers. • During 21 days training period, a lot of experience, knowledge and exposure that I have handy the training was more than hope to me and also help me to understand about manufacturing of transformer more.