SlideShare a Scribd company logo
The Osterberg Cell Static
Loading Test
Utilizing The Osterberg Cell for Loading test instead of Conventional
Static LoadingTest
12/12/2016 Alaa Mohamed Metwally 1
1. Introduction
• The Osterberg Cell is a Sacrificial jack-like device which the Engineer can have
installed at the tip of a driven pile or on the reinforcement of a bored pile.
• The cell provides the static loading and requires no overhead frame or other
external reaction system.
• Hence, We can now statically test full-sized bored piles (also known as drilled
shafts, drilled piers or caissons) to near their ultimate capacity. Furthermore, we
can do it more conveniently, economically and safely than ever before as no
reaction system required like before.
• O Cell testing and bored pile have a beneficial, cooperative relationship or a
“Symbiosis”.
• Generally high capacity of bored piles, in combination with high cost of top load
system providing more than 10 MN, make conventional top load testing
impractical for routine testing.
12/12/2016 Alaa Mohamed Metwally 2
1. Introduction
• The O Cell static load test method, providing high capacities at affordable costs,
has become an attractive alternative method for testing bored piles.
• At mid 1994 the U.S Federal Highway Administration (FHWA) found that
Engineers and Contractors considered the O Cell “the method of choice” and it’s
use had risen rapidly to about 65% of all bored pile testing, this trend has
continued and usage now exceed 90% not in the U.S only but all over the world.
12/12/2016 Alaa Mohamed Metwally 3
1. Introduction
12/12/2016 Alaa Mohamed Metwally 4
Osterberg
Cell
2. Static load testing using O Cell
12/12/2016 Alaa Mohamed Metwally 5
Fig.
1
Pile
Steel Beam
P=F+Q
F
Q
Pile
F
Q
Expanding
O Cell at the
bottom of
the pile
Ground Level
Ground Level
Reaction System
at the top of pile
Q
2. Static load testing using O Cell
• A Conventional test loads the bored pile in compression, at its tip, using an
overhead reaction system or dead load, side shear F and end bearing Q combine
to resist the top load P and Engineer can only separate this components
approximately by analysis of strain and compression measurements together
with modulus estimates.
• The O Cell also loads the pile in compression, but from its bottom. As the O Cell
expands, the end bearing Q provides reaction for the side shear F. and vice versa.
Until reaching the capacity of one of the two component or the O Cell reaches its
capacity. The vantage point here is that the test separate the side shear and end
bearing components.
• The O Cell test load placed at, or near, the bottom of the pile has twice testing
effectiveness of that same load placed at the top in a conventional test.
12/12/2016 Alaa Mohamed Metwally 6
12/12/2016 Alaa Mohamed Metwally
3. Equipment
7
3. Equipment
• After construction of the shaft, the test operator connects an automatic pump to
the hydraulic lines that provides a pressure conduit to the cell, the load applied
by an O Cell is calibrated versus hydraulic pressure before installation and the
pressure applied to the cell is measured by a pressure transducer.
• Movement measured by electronic gages connected to a computerized
acquisition system.
• The total expansion of the cell is measured by (LVWDTs) Linear vibrating wire
transducers the lower part of which attached to bottom of the cell.
• A steel telltales attached to the bottom of the cell used to measure the upward
movement directly.
• Subtracting the upward movement from total expansion gives the desired
downward movement.
12/12/2016 Alaa Mohamed Metwally 8
12/12/2016 Alaa Mohamed Metwally 9
4. History of Osterberg Cell
• Dr. Jorje Osterberg, professor emeritus at Northwestern university. Developed
and patented test which now carries his name.
• The first experimental test pile was carried out in 1984, after this successful
prototype professorOsterberg works very closely to American Equipment and
Fabrication Corp. to evolve his cell from a bellows type expansion cell to the
current design, very similar to piston type jack used in conventional test, but the
piston extends downward not upward.
• Haley & Aldrich was the first to use O Cell in practical application in 1987, to
driven piles one over a river in Massachusetts and the other on a bridge which
reaches 1.26 and 4 MN respectively.
• Now Osterberg cell has steadily gained popularity all over the world for testing
bored piles.
12/12/2016 Alaa Mohamed Metwally 10
5. Advantages of O Cell
• Economy.
• reduced construction time, saving in outlay capital, no top-of-pile reaction equipment required
and less test design efforts, making the test cost from
1
3
to
2
3
the conventional test.The
comparative cost reduces as the load increases.
• High Load capacity.
• Shear/Bearing Component
• The cell automatically separates the side shear and end bearing components, despite of
conventional test which gives the total capacity at a time
• Improved safety.
• The test energy lies deeply buried and no overhead load at the top of pile.
• Rocket Socket.
• The cell loaded at the bottom of the socket, near its bottom and gives an automated separation
of components
12/12/2016 Alaa Mohamed Metwally 11
5. Advantages of O Cell
• Reduced work area.
• A 65 MN O Cell test, conducted in a 3 meter wide median strip of a busy interstate highway,
which seems impossible when using conventional test as a big area needed for the reaction
system or equipment and kentledge system.
• Over water and battered shafts.
• Static creep and setup effects.
• Because the test is static the test load at any length of time can be estimated, the Engineers
also can obtain separate data about creep behavior for the two components.
• Sequential testing.
• A long term stage tests with minimal efforts can be made for research purposes or other to
obtain “aging” for example, been a unique advantage of O Cell test
12/12/2016 Alaa Mohamed Metwally 12
6. Limitations
• Advance installation required.
• In bored piles and most driven piles, the O Cell must be installed prior construction.
• Balanced component requirement.
• As the cell reaches the ultimate capacity in only one of its components, and shaft capacity limited
to two times the capacity of component reaching ultimate, The Engineer should first analyze the
expected side shear and end bearing components and either attempt to balance the two to get
the most information from both.
• The introduction of multilevel cell mitigates this limitation, and allow calculating ultimate side
shear and end bearing in cases where bearing less than the side shear.
• Equivalent top load curve.
• Although the estimation of equivalent top load curve is conservatism, it remains estimate.
• Sacrificial cell.
• Cell considered expandable and not recovered after the test completed. However, grouting the
tested pile allows using it as a permanent foundation pile.
• Not suitable for certain types of piles.
• H pile and sheet piles.
12/12/2016 Alaa Mohamed Metwally 13
7. Test results
12/12/2016 Alaa Mohamed Metwally 14
Sand and
gravel
shell
8.2
19.2
5.8
2.4
River
18.9
Hydraulic
supply &
telltale casing
35.7 -25
-20
-15
-10
-5
0
5
10
15
20
0 10 20 30
UpwordandDownwordMovement
(mm)
Load (MN)
Osterberg Load-Movement Curve
Purpose: To determine bearing capacity of the drilled shaft supporting a
bridge pier.
Method: Shafts drilled with polymer drilling slurry, 1.9 O.D. casing set on
top of shale and 1.8 m hole drilled 5.8 m into shale 864mm load cell with 1.7
m diameter plate welded to bottom lowered into the hole. Pumped
concrete placed to design top elevation of shaft.
Results: Load reaches capacity of device at 34.56 mm downward and 7.62
mm upward movement, the ultimate capacity was greater than 54 MN.
O-CellTest on a rock socketed bored
pile
-25
-20
-15
-10
-5
0
5
10
15
20
0 5 10 15 20 25 30
UpwordandDownwordMovement(mm)
Load (MN)
Osterberg Load-Movement Curve
8. Interpretation of test results.
12/12/2016 Alaa Mohamed Metwally
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
0 10 20 30 40 50 60
Movement(mm)
Load (MN)
Equivalent Top Load-Movement Curve
8. Interpretation of test results.
• The Osterberg cell loads the test pile in compression similar to a conventional
top load test, and hence the data form o cell is analyzed in much the same way
of conventional test.
• The only significant difference between the two tests is that the o cell provides
two load-movement curves, one for side shear and one for end bearing.
• Combined bearing capacity of the two components obtained as follow:
• Select an arbitrary point on the load movement curve, and determine the side shear.
• Determine the end bearing for the same point.
• From the upper two value we construct a point on “Top Load-Movement curve”.
• Repeat the process for multiple points and construct the curve.
12/12/2016 Alaa Mohamed Metwally 16
9. References
1. John H.Shmertmann & johnA. Hayes “The Osterberg cell and bored pile
testing- a symbiosis".TheThird International Geotechnical Engineering
Conference-Cairo University, 5-8 Jan 1997.
2. https://www.youtube.com/watch?v=fDJVpe37_Qg
3. https://www.youtube.com/watch?v=afKrgdJf2k4&spfreload=10
12/12/2016 Alaa Mohamed Metwally 17
Presented By
Student at Nile Academy for Science and Technology
Code: 130326
Due date: 9-12-2016
12/12/2016 Alaa Mohamed Metwally 18

More Related Content

What's hot

Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABS
Yousuf Dinar
 
Specification on prestressing strand
Specification on prestressing strandSpecification on prestressing strand
Specification on prestressing strand
NimeshPoddar
 
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
Fawad Najam
 
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
Rahul Leslie
 
Membrane - Plate - Shell
Membrane - Plate - ShellMembrane - Plate - Shell
Membrane - Plate - Shellneikrof
 
problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabs
srinivas cnu
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps design
Nada Zarrak
 
Box culvert
Box culvertBox culvert
Study on the effect of viscous dampers for RCC frame Structure
Study on the effect of viscous dampers for RCC frame StructureStudy on the effect of viscous dampers for RCC frame Structure
Study on the effect of viscous dampers for RCC frame Structure
Puneet Sajjan
 
Concrete testing
Concrete testingConcrete testing
Concrete testing
Avish singh
 
Deep beam
Deep beamDeep beam
Deep beam
Vikas Mehta
 
CE72.52 - Lecture 3a - Section Behavior - Flexure
CE72.52 - Lecture 3a - Section Behavior - FlexureCE72.52 - Lecture 3a - Section Behavior - Flexure
CE72.52 - Lecture 3a - Section Behavior - Flexure
Fawad Najam
 
Laterally Loaded Piles
Laterally Loaded PilesLaterally Loaded Piles
Laterally Loaded Piles
ahmed khalil
 
Progression of Structural Design Approaches by Dr. Naveed Anwar
Progression of Structural Design Approaches by Dr. Naveed AnwarProgression of Structural Design Approaches by Dr. Naveed Anwar
Progression of Structural Design Approaches by Dr. Naveed Anwar
AIT Solutions
 
Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)
Nitesh Singh
 
CE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - IntroductionCE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - Introduction
Fawad Najam
 
Earthquake resistant analysis and design of multistoried building
Earthquake resistant analysis and design of multistoried buildingEarthquake resistant analysis and design of multistoried building
Earthquake resistant analysis and design of multistoried building
Anup Adhikari
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
Fawad Najam
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
Shubham Das
 

What's hot (20)

Book for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABSBook for Beginners, RCC Design by ETABS
Book for Beginners, RCC Design by ETABS
 
Specification on prestressing strand
Specification on prestressing strandSpecification on prestressing strand
Specification on prestressing strand
 
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
CE 72.32 (January 2016 Semester) Lecture 3 - Design Criteria
 
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
Part-I: Seismic Analysis/Design of Multi-storied RC Buildings using STAAD.Pro...
 
Membrane - Plate - Shell
Membrane - Plate - ShellMembrane - Plate - Shell
Membrane - Plate - Shell
 
Bracing connections
Bracing connectionsBracing connections
Bracing connections
 
problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabs
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps design
 
Box culvert
Box culvertBox culvert
Box culvert
 
Study on the effect of viscous dampers for RCC frame Structure
Study on the effect of viscous dampers for RCC frame StructureStudy on the effect of viscous dampers for RCC frame Structure
Study on the effect of viscous dampers for RCC frame Structure
 
Concrete testing
Concrete testingConcrete testing
Concrete testing
 
Deep beam
Deep beamDeep beam
Deep beam
 
CE72.52 - Lecture 3a - Section Behavior - Flexure
CE72.52 - Lecture 3a - Section Behavior - FlexureCE72.52 - Lecture 3a - Section Behavior - Flexure
CE72.52 - Lecture 3a - Section Behavior - Flexure
 
Laterally Loaded Piles
Laterally Loaded PilesLaterally Loaded Piles
Laterally Loaded Piles
 
Progression of Structural Design Approaches by Dr. Naveed Anwar
Progression of Structural Design Approaches by Dr. Naveed AnwarProgression of Structural Design Approaches by Dr. Naveed Anwar
Progression of Structural Design Approaches by Dr. Naveed Anwar
 
Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)
 
CE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - IntroductionCE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - Introduction
 
Earthquake resistant analysis and design of multistoried building
Earthquake resistant analysis and design of multistoried buildingEarthquake resistant analysis and design of multistoried building
Earthquake resistant analysis and design of multistoried building
 
CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
 
Pre stressed concrete Bridge
Pre stressed concrete BridgePre stressed concrete Bridge
Pre stressed concrete Bridge
 

Viewers also liked

Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook920728035348
 
Bai thuyet trinh nhom 6
Bai thuyet trinh nhom 6Bai thuyet trinh nhom 6
Bai thuyet trinh nhom 6Nhu Nguyen
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENABenoit Latapie
 
Stress Calculation | weyer special
Stress Calculation | weyer specialStress Calculation | weyer special
Stress Calculation | weyer special
weyer gruppe
 
Evaluation of the extreme and fatigue load measurements at alpha ventus
Evaluation of the extreme and fatigue load measurements at alpha ventusEvaluation of the extreme and fatigue load measurements at alpha ventus
Evaluation of the extreme and fatigue load measurements at alpha ventus
Ricardo Faerron Guzmán
 
De cuong tn 17
De cuong tn 17De cuong tn 17
De cuong tn 17
GTVT
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
cfpbolivia
 
72. bien phap thi cong coc khan nhoi
72. bien phap thi cong coc khan nhoi72. bien phap thi cong coc khan nhoi
72. bien phap thi cong coc khan nhoitrunghieu171
 
Cd chap 2 - static loading
Cd   chap 2 - static loadingCd   chap 2 - static loading
Cd chap 2 - static loadingMohamad Sahiedan
 
Giáo Trình thí nghiệm và kiểm định công trình
Giáo Trình thí nghiệm và kiểm định công trìnhGiáo Trình thí nghiệm và kiểm định công trình
Giáo Trình thí nghiệm và kiểm định công trình
Tung Nguyen Xuan
 
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung HiếuBài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
Tung Nguyen Xuan
 
DESIGN AGAINST FLUCTUATING LOAD
DESIGN AGAINST FLUCTUATING LOADDESIGN AGAINST FLUCTUATING LOAD
DESIGN AGAINST FLUCTUATING LOAD
Priyank Gandhi
 
PED 2016 - Design 101 - Week 2 - Handouts
PED 2016 - Design 101 - Week 2 - HandoutsPED 2016 - Design 101 - Week 2 - Handouts
PED 2016 - Design 101 - Week 2 - Handouts
Mohamed Mostafa Ahmed Adam
 
Thi công cọc khoan nhồi
Thi công cọc khoan nhồiThi công cọc khoan nhồi
Thi công cọc khoan nhồi
Nguyễn Phan Thanh Mẫn
 
Design of machine_elements_
Design of machine_elements_Design of machine_elements_
Design of machine_elements_Zainul Abedin
 
Chapter 4 deep foundation ( bi )
Chapter 4 deep foundation ( bi )Chapter 4 deep foundation ( bi )
Chapter 4 deep foundation ( bi )AmiRul AFiq
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
SlideShare
 

Viewers also liked (18)

Loadtestinghandbook
LoadtestinghandbookLoadtestinghandbook
Loadtestinghandbook
 
Bai thuyet trinh nhom 6
Bai thuyet trinh nhom 6Bai thuyet trinh nhom 6
Bai thuyet trinh nhom 6
 
2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA2. Benoit Latapie - Foundations for infrastructure projects in MENA
2. Benoit Latapie - Foundations for infrastructure projects in MENA
 
Stress Calculation | weyer special
Stress Calculation | weyer specialStress Calculation | weyer special
Stress Calculation | weyer special
 
Evaluation of the extreme and fatigue load measurements at alpha ventus
Evaluation of the extreme and fatigue load measurements at alpha ventusEvaluation of the extreme and fatigue load measurements at alpha ventus
Evaluation of the extreme and fatigue load measurements at alpha ventus
 
De cuong tn 17
De cuong tn 17De cuong tn 17
De cuong tn 17
 
Bullock bidirectional testing
Bullock bidirectional testingBullock bidirectional testing
Bullock bidirectional testing
 
87924560 chuyende detector
87924560 chuyende detector87924560 chuyende detector
87924560 chuyende detector
 
72. bien phap thi cong coc khan nhoi
72. bien phap thi cong coc khan nhoi72. bien phap thi cong coc khan nhoi
72. bien phap thi cong coc khan nhoi
 
Cd chap 2 - static loading
Cd   chap 2 - static loadingCd   chap 2 - static loading
Cd chap 2 - static loading
 
Giáo Trình thí nghiệm và kiểm định công trình
Giáo Trình thí nghiệm và kiểm định công trìnhGiáo Trình thí nghiệm và kiểm định công trình
Giáo Trình thí nghiệm và kiểm định công trình
 
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung HiếuBài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
 
DESIGN AGAINST FLUCTUATING LOAD
DESIGN AGAINST FLUCTUATING LOADDESIGN AGAINST FLUCTUATING LOAD
DESIGN AGAINST FLUCTUATING LOAD
 
PED 2016 - Design 101 - Week 2 - Handouts
PED 2016 - Design 101 - Week 2 - HandoutsPED 2016 - Design 101 - Week 2 - Handouts
PED 2016 - Design 101 - Week 2 - Handouts
 
Thi công cọc khoan nhồi
Thi công cọc khoan nhồiThi công cọc khoan nhồi
Thi công cọc khoan nhồi
 
Design of machine_elements_
Design of machine_elements_Design of machine_elements_
Design of machine_elements_
 
Chapter 4 deep foundation ( bi )
Chapter 4 deep foundation ( bi )Chapter 4 deep foundation ( bi )
Chapter 4 deep foundation ( bi )
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar to The osterberg cell static loading test

Ce6411 som l ab 2013_regulation
Ce6411 som l ab 2013_regulationCe6411 som l ab 2013_regulation
Ce6411 som l ab 2013_regulation
ARUNTHEGEOTECH
 
Swel Presentation
Swel PresentationSwel Presentation
Swel Presentation
Maxim Drozd
 
What if battery would have mind?
What if battery would have mind?What if battery would have mind?
What if battery would have mind?
Salt (market research company)
 
WL 112 Ch06 ch06 presentation
WL 112 Ch06 ch06 presentationWL 112 Ch06 ch06 presentation
WL 112 Ch06 ch06 presentation
BealCollegeOnline
 
TBEA ENERGY (INDIA) PVT LTD
 TBEA   ENERGY (INDIA) PVT LTD TBEA   ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
Raviraj solanki
 
Core plugging
Core plugging Core plugging
Core plugging
SARWAR SALAM
 
My Work
My WorkMy Work
Conference Paper on Multi range load cell
Conference Paper on Multi range load cellConference Paper on Multi range load cell
Conference Paper on Multi range load cell
Shreyas Pandit
 
Creative Pultrusions, Inc. SuperPile Marine Products
Creative Pultrusions, Inc. SuperPile Marine ProductsCreative Pultrusions, Inc. SuperPile Marine Products
Creative Pultrusions, Inc. SuperPile Marine Products
Creative Pultrusions, Inc.
 
Design and development of horizontal tensile testing machine (5kN)
Design and development of horizontal tensile testing machine (5kN)Design and development of horizontal tensile testing machine (5kN)
Design and development of horizontal tensile testing machine (5kN)
Sajeed Mahaboob
 
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docxSheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
bjohn46
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
Independent Geoscience
 
Load banks
Load banksLoad banks
Load banks
Maryam Sanaei- PMP
 
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
IRJET Journal
 
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
"Fatigue testing of reinforced concrete beam instrumented with distributed op..."Fatigue testing of reinforced concrete beam instrumented with distributed op...
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
TRUSS ITN
 
31456536-MIT - Masters Thesis, Edward Snow
31456536-MIT - Masters Thesis, Edward Snow31456536-MIT - Masters Thesis, Edward Snow
31456536-MIT - Masters Thesis, Edward SnowEdward Snow
 
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
FEA  AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTUREFEA  AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
Vishal Mudka
 
Space Propulsion Innovation Award
Space Propulsion Innovation AwardSpace Propulsion Innovation Award
Space Propulsion Innovation Award
A. Rocketeer
 
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxVIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
norzilanoh1
 

Similar to The osterberg cell static loading test (20)

Ce6411 som l ab 2013_regulation
Ce6411 som l ab 2013_regulationCe6411 som l ab 2013_regulation
Ce6411 som l ab 2013_regulation
 
Swel Presentation
Swel PresentationSwel Presentation
Swel Presentation
 
What if battery would have mind?
What if battery would have mind?What if battery would have mind?
What if battery would have mind?
 
WL 112 Ch06 ch06 presentation
WL 112 Ch06 ch06 presentationWL 112 Ch06 ch06 presentation
WL 112 Ch06 ch06 presentation
 
TBEA ENERGY (INDIA) PVT LTD
 TBEA   ENERGY (INDIA) PVT LTD TBEA   ENERGY (INDIA) PVT LTD
TBEA ENERGY (INDIA) PVT LTD
 
Core plugging
Core plugging Core plugging
Core plugging
 
My Work
My WorkMy Work
My Work
 
Conference Paper on Multi range load cell
Conference Paper on Multi range load cellConference Paper on Multi range load cell
Conference Paper on Multi range load cell
 
Creative Pultrusions, Inc. SuperPile Marine Products
Creative Pultrusions, Inc. SuperPile Marine ProductsCreative Pultrusions, Inc. SuperPile Marine Products
Creative Pultrusions, Inc. SuperPile Marine Products
 
Design and development of horizontal tensile testing machine (5kN)
Design and development of horizontal tensile testing machine (5kN)Design and development of horizontal tensile testing machine (5kN)
Design and development of horizontal tensile testing machine (5kN)
 
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docxSheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
 
High strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty LtdHigh strain dynamic pile testing - Independent Geoscience Pty Ltd
High strain dynamic pile testing - Independent Geoscience Pty Ltd
 
Load banks
Load banksLoad banks
Load banks
 
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
 
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
"Fatigue testing of reinforced concrete beam instrumented with distributed op..."Fatigue testing of reinforced concrete beam instrumented with distributed op...
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
 
31456536-MIT - Masters Thesis, Edward Snow
31456536-MIT - Masters Thesis, Edward Snow31456536-MIT - Masters Thesis, Edward Snow
31456536-MIT - Masters Thesis, Edward Snow
 
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
FEA  AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTUREFEA  AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
 
URC Poster
URC PosterURC Poster
URC Poster
 
Space Propulsion Innovation Award
Space Propulsion Innovation AwardSpace Propulsion Innovation Award
Space Propulsion Innovation Award
 
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptxVIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
VIVA VOCE NORZILA NOH 0008908 - 10122021.pptx
 

Recently uploaded

Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

The osterberg cell static loading test

  • 1. The Osterberg Cell Static Loading Test Utilizing The Osterberg Cell for Loading test instead of Conventional Static LoadingTest 12/12/2016 Alaa Mohamed Metwally 1
  • 2. 1. Introduction • The Osterberg Cell is a Sacrificial jack-like device which the Engineer can have installed at the tip of a driven pile or on the reinforcement of a bored pile. • The cell provides the static loading and requires no overhead frame or other external reaction system. • Hence, We can now statically test full-sized bored piles (also known as drilled shafts, drilled piers or caissons) to near their ultimate capacity. Furthermore, we can do it more conveniently, economically and safely than ever before as no reaction system required like before. • O Cell testing and bored pile have a beneficial, cooperative relationship or a “Symbiosis”. • Generally high capacity of bored piles, in combination with high cost of top load system providing more than 10 MN, make conventional top load testing impractical for routine testing. 12/12/2016 Alaa Mohamed Metwally 2
  • 3. 1. Introduction • The O Cell static load test method, providing high capacities at affordable costs, has become an attractive alternative method for testing bored piles. • At mid 1994 the U.S Federal Highway Administration (FHWA) found that Engineers and Contractors considered the O Cell “the method of choice” and it’s use had risen rapidly to about 65% of all bored pile testing, this trend has continued and usage now exceed 90% not in the U.S only but all over the world. 12/12/2016 Alaa Mohamed Metwally 3
  • 4. 1. Introduction 12/12/2016 Alaa Mohamed Metwally 4 Osterberg Cell
  • 5. 2. Static load testing using O Cell 12/12/2016 Alaa Mohamed Metwally 5 Fig. 1 Pile Steel Beam P=F+Q F Q Pile F Q Expanding O Cell at the bottom of the pile Ground Level Ground Level Reaction System at the top of pile Q
  • 6. 2. Static load testing using O Cell • A Conventional test loads the bored pile in compression, at its tip, using an overhead reaction system or dead load, side shear F and end bearing Q combine to resist the top load P and Engineer can only separate this components approximately by analysis of strain and compression measurements together with modulus estimates. • The O Cell also loads the pile in compression, but from its bottom. As the O Cell expands, the end bearing Q provides reaction for the side shear F. and vice versa. Until reaching the capacity of one of the two component or the O Cell reaches its capacity. The vantage point here is that the test separate the side shear and end bearing components. • The O Cell test load placed at, or near, the bottom of the pile has twice testing effectiveness of that same load placed at the top in a conventional test. 12/12/2016 Alaa Mohamed Metwally 6
  • 7. 12/12/2016 Alaa Mohamed Metwally 3. Equipment 7
  • 8. 3. Equipment • After construction of the shaft, the test operator connects an automatic pump to the hydraulic lines that provides a pressure conduit to the cell, the load applied by an O Cell is calibrated versus hydraulic pressure before installation and the pressure applied to the cell is measured by a pressure transducer. • Movement measured by electronic gages connected to a computerized acquisition system. • The total expansion of the cell is measured by (LVWDTs) Linear vibrating wire transducers the lower part of which attached to bottom of the cell. • A steel telltales attached to the bottom of the cell used to measure the upward movement directly. • Subtracting the upward movement from total expansion gives the desired downward movement. 12/12/2016 Alaa Mohamed Metwally 8
  • 10. 4. History of Osterberg Cell • Dr. Jorje Osterberg, professor emeritus at Northwestern university. Developed and patented test which now carries his name. • The first experimental test pile was carried out in 1984, after this successful prototype professorOsterberg works very closely to American Equipment and Fabrication Corp. to evolve his cell from a bellows type expansion cell to the current design, very similar to piston type jack used in conventional test, but the piston extends downward not upward. • Haley & Aldrich was the first to use O Cell in practical application in 1987, to driven piles one over a river in Massachusetts and the other on a bridge which reaches 1.26 and 4 MN respectively. • Now Osterberg cell has steadily gained popularity all over the world for testing bored piles. 12/12/2016 Alaa Mohamed Metwally 10
  • 11. 5. Advantages of O Cell • Economy. • reduced construction time, saving in outlay capital, no top-of-pile reaction equipment required and less test design efforts, making the test cost from 1 3 to 2 3 the conventional test.The comparative cost reduces as the load increases. • High Load capacity. • Shear/Bearing Component • The cell automatically separates the side shear and end bearing components, despite of conventional test which gives the total capacity at a time • Improved safety. • The test energy lies deeply buried and no overhead load at the top of pile. • Rocket Socket. • The cell loaded at the bottom of the socket, near its bottom and gives an automated separation of components 12/12/2016 Alaa Mohamed Metwally 11
  • 12. 5. Advantages of O Cell • Reduced work area. • A 65 MN O Cell test, conducted in a 3 meter wide median strip of a busy interstate highway, which seems impossible when using conventional test as a big area needed for the reaction system or equipment and kentledge system. • Over water and battered shafts. • Static creep and setup effects. • Because the test is static the test load at any length of time can be estimated, the Engineers also can obtain separate data about creep behavior for the two components. • Sequential testing. • A long term stage tests with minimal efforts can be made for research purposes or other to obtain “aging” for example, been a unique advantage of O Cell test 12/12/2016 Alaa Mohamed Metwally 12
  • 13. 6. Limitations • Advance installation required. • In bored piles and most driven piles, the O Cell must be installed prior construction. • Balanced component requirement. • As the cell reaches the ultimate capacity in only one of its components, and shaft capacity limited to two times the capacity of component reaching ultimate, The Engineer should first analyze the expected side shear and end bearing components and either attempt to balance the two to get the most information from both. • The introduction of multilevel cell mitigates this limitation, and allow calculating ultimate side shear and end bearing in cases where bearing less than the side shear. • Equivalent top load curve. • Although the estimation of equivalent top load curve is conservatism, it remains estimate. • Sacrificial cell. • Cell considered expandable and not recovered after the test completed. However, grouting the tested pile allows using it as a permanent foundation pile. • Not suitable for certain types of piles. • H pile and sheet piles. 12/12/2016 Alaa Mohamed Metwally 13
  • 14. 7. Test results 12/12/2016 Alaa Mohamed Metwally 14 Sand and gravel shell 8.2 19.2 5.8 2.4 River 18.9 Hydraulic supply & telltale casing 35.7 -25 -20 -15 -10 -5 0 5 10 15 20 0 10 20 30 UpwordandDownwordMovement (mm) Load (MN) Osterberg Load-Movement Curve Purpose: To determine bearing capacity of the drilled shaft supporting a bridge pier. Method: Shafts drilled with polymer drilling slurry, 1.9 O.D. casing set on top of shale and 1.8 m hole drilled 5.8 m into shale 864mm load cell with 1.7 m diameter plate welded to bottom lowered into the hole. Pumped concrete placed to design top elevation of shaft. Results: Load reaches capacity of device at 34.56 mm downward and 7.62 mm upward movement, the ultimate capacity was greater than 54 MN. O-CellTest on a rock socketed bored pile
  • 15. -25 -20 -15 -10 -5 0 5 10 15 20 0 5 10 15 20 25 30 UpwordandDownwordMovement(mm) Load (MN) Osterberg Load-Movement Curve 8. Interpretation of test results. 12/12/2016 Alaa Mohamed Metwally -18 -16 -14 -12 -10 -8 -6 -4 -2 0 0 10 20 30 40 50 60 Movement(mm) Load (MN) Equivalent Top Load-Movement Curve
  • 16. 8. Interpretation of test results. • The Osterberg cell loads the test pile in compression similar to a conventional top load test, and hence the data form o cell is analyzed in much the same way of conventional test. • The only significant difference between the two tests is that the o cell provides two load-movement curves, one for side shear and one for end bearing. • Combined bearing capacity of the two components obtained as follow: • Select an arbitrary point on the load movement curve, and determine the side shear. • Determine the end bearing for the same point. • From the upper two value we construct a point on “Top Load-Movement curve”. • Repeat the process for multiple points and construct the curve. 12/12/2016 Alaa Mohamed Metwally 16
  • 17. 9. References 1. John H.Shmertmann & johnA. Hayes “The Osterberg cell and bored pile testing- a symbiosis".TheThird International Geotechnical Engineering Conference-Cairo University, 5-8 Jan 1997. 2. https://www.youtube.com/watch?v=fDJVpe37_Qg 3. https://www.youtube.com/watch?v=afKrgdJf2k4&spfreload=10 12/12/2016 Alaa Mohamed Metwally 17
  • 18. Presented By Student at Nile Academy for Science and Technology Code: 130326 Due date: 9-12-2016 12/12/2016 Alaa Mohamed Metwally 18