HINDUSTAN INSTITUTE OF
TECHNOLOGY AND MANAGEMENT
NAME _VIVEK KUMAR SINGH
ROLL NUMBER_1300300058
PROJECT TITLE_
RAMP CONSTRUCTION
<DETAILS>
<Calculation of slope of ramp>
<Construction of ramp>
<CONTENTS>
• Comparison b/w ramp & stairs
• Theory
• About
<Comparison>
Stairs Ramp
<theory>
• The maximum recommended slope of ramps
is 1:20.
• Steeper slopes may be allowed in special cases
depending on the length to be covered.
• Simple mathematics is used for calculation of
slope.......
Meaning of 1:20
<recommended standards>
<About >
• OPD BLOCK & OTHER ASSOCIATED SERVICES
• Project:-OPD Block & other Associated Services
• Client:-The Director AIIMS C/O M/S HSCC (India) Ltd.
• Location:-AIIMS Campus, Ansari Nagar, New Delhi
• Architect:-The Genral Manager (CIVIL), HSCC (India) Ltd.E-6
(A), Sector-1, Noida-201301
• Project Highlights:-Rcc Frame structure building (3B+G+8)
Cilvil, Plumbing, Electrical, HVAC, Lift, Fire Alram, external
development, drainage etc..
<AHLUWALIA CONTRACTS LTD.>
• Project cost -251 crore
• Project duration-09 months
• My training duration-25 days
<Memories>
<Notes>
• Circular and round slope can not be construct.

Summer training (civil engineering)-Ramp construction