SlideShare a Scribd company logo
Zhitomir Solar Park
EXECUTIVE SUMMARY
www.zhitomirsp.weebly.com
September 2016
STRICTLY PRIVATE & CONFIDENTIAL
STRICTLY PRIVATE & CONFIDENTIAL
General Information
The sites is located in Zhitomir region and have size of 135 ha. Based on the latest experience
of visits and technical analysis around 60 MW can be installed with an energy yield in a range
of 1109 kWh/kWp per year. Installation can be finished in 9-13 months with experienced team.
Site is large enough to easily incorporate PV power plant and no major obstacles and issues
are foreseen. The general improvements are more on pre-work on the accessibility in the civil
engineering package. The critical components are the transformers, but with the latest
development of local suppliers and successful completion of the previous projects, the delivery
can be managed on time.
A detail topographical map and a soil analysis are essential for the final layout. The team has to
analyze the best mounting structure for this are with the best interface to the ground and we
assume that localized product range can be integrated into this project.
In addition to this detailed analysis with the local utility needs to be initiated. Power plant has a
significant capacity and this power needs to be transferred to the high voltage grid.
As a result, it could be concluded that this plant can be easily technically installed.
We are looking forward to review with you our EPC concept
to start the design and installation as soon as possible.
Sincerely Yours,
Oleg Gramotenko
2
STRICTLY PRIVATE & CONFIDENTIAL
1. Ukraine Solar Energy information
3
Quantity of RES-electricity production licensees and
RES-electricity generating capacities, 2009-2015
4
The average weighted feed-in tariffs, 2012-2015
5
Actual volume of electricity produced from solar power,
2012-2015
6
Dynamics of actual prices for traditional and renewable
energy, 2014-2015
7
Actual price per MW·h (solar), €ct
8
1.1 About ZHITOMIR SOLAR PARK
• ZHITROMIR SOLAR PARK – including 4 sites http://zhitomirsp.weebly.com for solar energy
plant with all permissions.
1. Bolohyvsky Solar Park 1 LLC is located on 31,89 hectares. The estimated total capacity
around 13,1 MW.
2. Bolohyvsky Solar Park 2 LLC is located on 38,11 hectares. The estimated total capacity
around 15,7 MW.
3. Irshanska SES LCC is located on 35,74 hectares. The estimated total capacity around 17
MW.
4. Ganska SES LLC is located on 30 hectares. The estimated total capacity around 15 MW.
STRICTLY PRIVATE & CONFIDENTIAL
STRICTLY PRIVATE & CONFIDENTIAL
2. Project information
10
STRICTLY PRIVATE & CONFIDENTIAL
2.1 Project background
Project is planned to be installed in Zhitomir region, with
capacity about 60 MW.
Project Zhitomir Solar Park
Total capacity
Solar irradiation
Expected net annual
energy production
Annual energy yield
Feed-in tariff
Land lease agreement
Annual land lease cost
Annual O&M cost
Technology
Panels
Inverters
MS
CNBM
Sungrow
Akcome
n/a
4%
49 years
0.15 EUR/kWh
1 109 MWh/year
65 000 MWh
1 050 kWh/m2
60 MW
11
2.2 Land Lease Agreement
Land plot information
 Land plot is rented (official document – “Certificate”, confirming subsequent land allotment is in place)
 Land lease agreement is signing a Pre-drafting stage of solar power station construction (scheme below)
 Agreement term – 49 years
 Land lease tax tariff – 4% of land value
 The SPV have the right to extend, renew or purchase the land plot at the end of the agreements
STRICTLY PRIVATE & CONFIDENTIAL
12
SPV
• 4 SPV LLC (4 sites) 135
Area, ha
Obtained certificate
Agreement status
STRICTLY PRIVATE & CONFIDENTIAL
2.3 Infrastructure
For O&M and construction needs the access road from
nearest public road to the solar parks will be constructed.
Roads of 4 meters and several parking places will be
constructed for services during maintenance of the solar
parks. All roads will be made from gravel without asphalt
coverage.
Service roads
Service and construction office will consist of 2-floor
masonry building and several garages for machineries,
which will work on site. The building will have independent
boreholes and water treatment facilities
Service and construction office
Site will be protected by fence which consist of panel 2,3 x 2
meters and piles each 2 meters. The land plot will be
surrounded with 0,5 high barbered wire. The access for
trucks will be enabled by the 5 meters gate.
Fence
Security system will consist of passive and active parts:
•Passive part of security system will allow detecting possible
criminals on the land plot, by monitoring current actions. It
presumes installment of radars and self focused cameras,
which will be synchronized in one system that could work
independently with backup batteries.
•Active protection system is portrayed by military security
company, working 24 hours a day on site. With support of
passive system, it will detect and neutralize all possible
criminals.
Security system
13
STRICTLY PRIVATE & CONFIDENTIAL
2.4 Land evaluation
Risk
Obstacles
Power lines
Comments
There are shrubs and trees on the territory of the site
Not ready at the moment and need to be constructed
Geology survey have to be ordered.
There is highway along west border of the site
medium
medium
medium
low
Soil condition
Accessibility
Topography
There is power station 110/35/10 kV at the distance of 2,8 km from
the site.
mediumGrid Connection
low The terrain is flat with slopes up to 1°
-lowEnvironmental concern
-lowHealth and safety
Risk of unauthorized intruders from the nearby village, which will
be covered by the highly efficient security system of nearly
small sized land plot.
low / mediumSecurity
14
Transformer
annex
area
2.5 Site description
Location: Zhytomyr region, Ukraine
Latitude and longitude: 49°56'25“N 27°48'31“E
SPV: Bolohyvsky Solar Park 1 Ltd
Land area: 31,89 ha
Capacity: 13,1 MW*
Irradiation level: 1325,1 kWh/m2
Climate: summer is mostly hot, winter is mild and snowy.
There is quite high solar activity in the region.
Connection point: substation 110/10 kV.
The topography of the surface of the plot
Basic parameters
15
Description of the Site:
•SPV construction site is located west of the village of
Yurovka, outside centres of population.
•Southward slopes up to 1.5° predominate within the site.
• An automobile road is located not far from the northern
boundary of the site.
N
S
* - indicated capacity corresponds to
location of photovoltaic modules only
on unshaded area.
Symbol legend:
- Area shadowed
throughout the year;
- Tile drainage pipes
Bolohyvsky
Solar Park 1
Bolohyvsky
Solar Park 2
Transformer
annex
area
2.5 Site description
Location: Zhytomyr region, Ukraine
Latitude and longitude: 49°56‘2“N 27°48'44"E
SPV: Bolohyvsky Solar Park 2 Ltd
Land area: 38,11 ha
Capacity: 15,7 MW*
Irradiation level: 1325,1 kWh/m2
Climate: summer is mostly hot, winter is mild and snowy.
There is quite high solar activity in the region.
Connection point: substation 110/10 kV.
The topography of the surface of the plot
Basic parameters
16
Description of the Site:
• SPV construction site is located west of the village of
Yurovka, outside centres of population.
• Northward slopes up to 2° predominate within the site.
• An automobile road is located approximately 0.7 km from
the site.
N
S
* - indicated capacity corresponds to
location of photovoltaic modules only
on unshaded area.
Symbol legend:
- Area shadowed
throughout the year;
- Tile drainage pipes
Bolohyvsky
Solar Park 1
Bolohyvsky
Solar Park 2
2.5 Site description
Location: Zhytomyr region, Ukraine
Latitude and longitude: 50°49'34"N 28°48'33"E
SPV: Irshanska SES Ltd
Land area: 35,74 ha
Capacity: 17 MW*
Irradiation level: 1319,8 kWh/m2
Climate: summer is mostly hot, winter is mild and snowy.
There is quite high solar activity in the region.
Connection point: substation 110/10 kV “Meleni”.
The topography of the surface of the plot
Basic parameters
17
Description of the Site:
• SPV construction sites are located west of the village of
Meleni, outside centres of population.
• Southward and south-eastward slopes up to 1° predominate
within the site.
• An automobile road is located 0.35 km north of the site.
N
S
Substation
110/10 kV
“Meleni”
Symbol legend:
- Area shadowed throughout the
year;
- Fenced off area of high-voltage
power line 110 kV
Site №3
Site№2
Site №1
Water drain
Irrigation
channel
* - indicated capacity corresponds to
location of photovoltaic modules only
on unshaded area.
STRICTLY PRIVATE & CONFIDENTIAL
2.5 Site description
Location or picture of land here
Location: Zhitomir region, Ukraine
Latitude and longitude: 49°55'4"N 28°39‘20"E
SPV: Ganska SES Ltd
Land area: 30 ha
Capacity: 15 MW*
Irradiation level: 1349,5 kWh/m2
Climate: summer is mostly hot, winter is mild and snowy.
There is quite high solar activity in the region.
Connection point: substation 110/35/10 kV “Berdichiv”.
The topography of the surface of the plot
Basic parameters
18
Description of the Site:
•The land lot for construction of PhES is located to the east
of the city of Berdichev outside the settlements.
•The area of the land lot has different slopes up to 1°.
•There is a motorway along the western boundary of the site.
N
S
Legend:
- The area shaded throughout a
year
PS 110/35/10 kV
“N. Berdichev”
* - the power value is specified of the
photovoltaic modules are placed only on
the unshaded area.
STRICTLY PRIVATE & CONFIDENTIAL
2.6 Irradiation analysis, energy output
The irradiation levels that the project is going to be exposed to
varies on the monthly basis as illustrated above.
Annual irradiation level is 1349,5 kWh/m2, which enables the
electricity generation of about 1109 kWh/kWp annually.
Expected net annual energy production will be about 14024 MWh.
The solar irradiation levels experienced in Zhytomyr region
of Ukraine are amongst the highest in the country, about
1150-1400 kWh per 𝑚2
. The average temperature may vary
in between -5,1° and +18,5° C and reflects the European
standard range. Even if the values during summer time are
higher than the Standard Test Conditions, no major
reduction in the output due to constant windy conditions is
foreseen.
19
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Average daily electricity production from the given system
(kWh/kWp/day)
STRICTLY PRIVATE & CONFIDENTIAL
Normalized production per installed kWp (12643 kWp): Loss diagram over the whole year
Performance Ratio (PR)
20
2.8 Energy output
STRICTLY PRIVATE & CONFIDENTIAL
3. Key Project Components
21
STRICTLY PRIVATE & CONFIDENTIAL
3.1 PV modules
Name
Photovoltaic
elements
Maximum Power 260-285Wp
Cell Type 5 - 6 inches
Quantity of cells 60
Weight 19.5 kg
Dimensions min 1638 x 982 x 40
mm (LxWxH)
Maximum Power Voltage 30 – 32V
Maximum Power Current 7,8 - 8A
Open-Circuit Voltage 37 - 38V
Short-Circuit Current 8,5 – 8,8A
Maximum System Voltage 1000 V DC
Maximum Series Fuse Rating 15A
Power Tolerance ±3%
Temperature Coefficients of Pmax -0.4336±0.05% / DC
Temperature Coefficients of Voc -0.4049±0.05% / DC
Temperature Coefficients of Isc 0.0825±0.02%/DC
Nominal Operating Cell
Temperature
45±2°C
Service life 20-25
Module efficiency ratio >15%
Products guarantee 12 years
22
STRICTLY PRIVATE & CONFIDENTIAL
3.1 PV modules
Bankability
All delivered PV modules are produced strictly according to the specifications, datasheets and certificates. The modules are
safely packed for international truck and sea transportation and the appropriate flash-reports are provided in excel format
before each shipment.
CNBM will supply the policrystalline PV modules for the project. These module supplier is established and reputable PV
manufacturer, which provide the PV modules with standard industry product and performance warranties.
Description
The different technologies in the market are mainly crystalline and thin-film products, which work in general with the same
physical effect and can be distinguished in the efficiency, respectively in the power produced per area, where crystalline
modules can reach more than 120 W/m2 and thin-film around 60 W/m2. With a higher production of power per area the user
needs lesser space, which is relevant for leased areas and rented roofs. The thin-film installation costs are lesser per Watt
but need double of the space that crystalline products need.
Technology
The selection of the module type depends on its price, technology, on its availability and mainly on its bankability. The lenders,
banks and insurance companies put their focus on the brand’s value, warranty and track record.
Conclusion
The proposed modules are bankable and have a track record. The selection depends on commercial
and bankability topics and needs to be reviewed together with the banks and investors. Thin-film
modules would need double of the area and Greentech recommends using the crystalline
solution for larger free field power plants.
23
STRICTLY PRIVATE & CONFIDENTIAL
Manufacturer – Sungrow
Combiner box PVS-XM is used for collecting power from
strings by connecting them to the combiner box. PVS-XM
has fuses for short circuit, reverse current defense. PVS-XM
has measurement channels for string monitoring and data
can be transferred by CAN protocol to data logger.
3.2 Combiner boxes
24
Technical data:
Cable requirments:
STRICTLY PRIVATE & CONFIDENTIAL
3.3 PV station
25
SG1000TS-MV PV Station is a 1 MW outdoor PV
station, providing turnkey solution for building PV plant;
designed with 20ft standart sea shipping container,
easy for transportation, high integration for quick
installation and commissioning; consist of:
a) Metallic enclosure;
b) DC cabinet;
c) 2 inverters;
d) LV/MV transformer;
e) MV switchgear;
f) LV auxiliary unit;
g) Communication unit;
h) Safety sensors (temperature&humidity sensors, ip-
camera, extinguishers sensors, door limit switches,
water logging sensors, smog detectors);
i) Heating system
STRICTLY PRIVATE & CONFIDENTIAL
3.3.1 Inverters
Nominal DC power
MPPT Voltage Range
Max. DC voltage
500 PV
500-820
1060A
1000V
Inverter
specifications
Max. DC current
Quantity DC Inputs
Quantity DC Fuses
Input data
Output data
1 MCCB
up to 8 psc (+/-)
The inverters are supplied by Sungrow and provide the
highest efficiency levels across all central and decentral
inverters currently available in the market.
630 PV
500-820
1170A
500-600 kWp 630-693 kWp
26
Operating with 10 kV voltage transformers for energy
transmitting to 10 kV outer grid
•Power capacity 630 kW
•Developed to operate for what 1260 kVA stations
•each PV station includes next equipment:
a) concrete shelter;
b) 2 inverters;
c) copain-mode
d) Data logger;
e) auxiliary board;
f) heater;
g) MV 3-field switchgear;
h) 3-ports transformer 10/0,315/0,315 kV;
i) smoke, door, motion sensors Nominal AC Power
Grid voltage range
Grid frequency
Power factor
EUR ETA after transformer
Max ETA after transformer
500 kVA
~0,9
98,7 %
98,5 %
630 kVA
~0,9
98,7 %
98,5 %
250 ~ 362V 250 ~ 362V
50/60 Hz 50/60 Hz
STRICTLY PRIVATE & CONFIDENTIAL
3.3.1 Inverters
Greentech recommends the supplier of the inverters to offer the best performance in quality and reliability. The chosen
inverter concept from the Sungrow portfolio offers the highest efficiency among central and de-central transformer-less
inverters. The inverter works directly with a medium voltage transformer that ensures less cable losses as well as a
maximized yield. Other suppliers like Sungrow, but also SMA and ABB are internationally orientated and have a very good
access to the European market with local teams and local certifications. The advantage of Sungrow is the local experience in
Ukraine and the track record with similar sized projects in the country.
Description
The selection of the inverter concept mainly depends on the size of the power plant and on the local infrastructure. Central
inverters are often used for larger MW plants with enough space for additional service stations. De-central inverters in the
range of 10-20 kVA are used for roofs or areas with limited space.
Inverter concept
Conclusion
The chosen inverter concept offers the highest efficiency amongst transformer-less inverter. It features an integrated DC
disconnector as well as string monitored fuses. For this larger site with 50 MW we recommend the central versions as a
preferred solution to have an independent system. The combination of 500 kVA and 630 kvA units gives flexibility in the
electrical layout.
27
STRICTLY PRIVATE & CONFIDENTIAL
Technical data:
3.3.2 Voltage transformers
View of 10/0,315/0,315 kV 3 Phase hermetically
sealed transformer transformer:
28
Transformer is used for increasing the voltage to 10 kV
for transferring to the grid.
STRICTLY PRIVATE & CONFIDENTIAL
3.4 Foundation with piles
Standard depth in ground
Material
Specifications
1.2 m – 1.5 m
Steel, hot dip, galvanized
Posts
Type Sigma profile
PV modules in large power plants are usually mounted on
elevated structures to minimize the land occupancy. Due to
the bigger wind aperture of those PV fields, higher loads are
therefore transmitted to the foundations, resulting in a
design of heavy concrete foundations.
The installation of metallic posts or screws is exceptionally
fast and allows a laser cut precise installation. The ramming
is performed with a special vehicle with actuators in order to
press the SIGMA shaped piles into the ground. The length
can be adjusted to the soil conditions’ requirements.
1,8 m – 3 mOverall length
The approach to use concrete foundations is in general not
recommended if metallic ramming piles or equivalent
solutions can be envisaged.
Concrete foundations generally add significantly on
execution time and complexity whereas the products for
metallic ramming piles can be sourced locally.
Conclusion
29
•Suppliers: Fregat, Euroformat
•15 year experience, about 650 000 piles for solar parks
•Local suppliers, good quality of piles
•Piles fixed with mounting system by screws, washers,
clamping plate and nuts
On the picture steel pile is shown:
manufacturer Fregat; coverage - hot dip galvanized with
thickness 120 mkm; tolerances +/– 1 %
STRICTLY PRIVATE & CONFIDENTIAL
3.5 Mounting system
Expected durability
Tilt angle of modules
Single row
15-20 years
&
2x11 & 2x6 [HxV]
MS
specifications
# of modules per
structural element
Orientation of the
modules
Wind loads
Base material
According to euro code 9
T6063/6060
aluminum for
base profiles
SUS304 for
accessories
Hot dip galvanized
steel for plants
T6063/6060 aluminum
for
base profiles
T6063/6060 aluminum
for
base substructure
SUS304 for
accessories
Multiple
rows
4x11 & 4x6 [HxV]
Portrait or
horizontal
Snow loads According to euro code 9
30
Supplier – Akcome
•4 of rows system
•made according European standards
•Support angles are and , height is about 2,8 m
•MS s the basis for the installation of modules at the
required angle. It has special cover -anodized aluminum for
protection from corrosion
Portrait or
horizontal
STRICTLY PRIVATE & CONFIDENTIAL
3.5 Mounting system
Installations with one module mounting system are used for
open areas with differences in the height level of the
topography. It can easily be installed without additional
machinery and is very flexible. No mayor leveling work in
the field is necessary. It can follow the height levels of the
site. A minimum distance of 2m between the rows slightly
decreases the capacity rate per hectare.
The installation with two or more modules in vertical or
horizontal have a slightly higher utilization rate of the field in
MW per hectare. Can be installed in a similar way within the
same time but it is necessary to install the system by teams
of two people. A moveable scaffold is needed to guarantee a
professional and safe installation.
One row system
Multiple row system
Conclusion
When selecting a mount, various options were considered, taking into account dynamic tracking of the sun throughout the
daylight hours. It was found that the optimal solution for flat plot with stable soil is 4 rows system, for plots with complicated
relief and unstable or weak soil is 2 rows or single rows systems on one piles. These structures are optimally priced for the
material consumption per unit modules and savings in bearing piles, have many positive aspect of the series, also increased
distance between the tables which in turn makes it possible to use the standard mechanical engineering. With increasing
design series will have adverse effect on the speed of installation and maintenance during operation as well as the height of
the construction will reach critical levels.
31
STRICTLY PRIVATE & CONFIDENTIAL
The suppliers are Telefonica, SKW, LAPP, Leoni, Prysmian, HELUCABLE
World-known companies with experience more than 40 years
Cables are VDE, IEC, ISO certified
used types – NYY, N2XS(FL)2Y, N2XSEY, solar cable, Li2YCYv, ADQ(ZN)(SR)2Y
3.6 Cables and conduits
MV cables, Solar Cables, DC cables, Data cables
32
N2XS(FL)2Y
N2XSEY
NYY
STRICTLY PRIVATE & CONFIDENTIAL
3.7 Monitoring system
SKYTRON PVGuard Platform was selected as monitoring
system supplier. It is a complete intelligent SCADA solution
that offers to operator and investors an efficient and real-
time tool for monitoring and maintaining the megawatt-class
PV Park.
It is versatile, flexible and strong instrument that perfectly
interacts with a large part of equipment. The intuitive
graphical user interface represents and confronts
performance and error data consistently making the plant
easily comparable.
Functions
• Real-time visualization of data in high resolution
• Storage and archiving of all measured data
• Alarm management and incident control
• Configurable automatic email notification
• Data exporting
• Single point administration for multiple PV Park
• Compare components across different plants
33
This monitoring system is the fast link between solar
equipment and its owner. It provides a complete plant
monitoring, remote diagnosis, data storage and display.
Access to the system data is available via a web
browser, smartphone and tablet at anytime from
anywhere in the world regardless of the operating
system or browser type.
PVGuard is a vendor-independent PV monitoring, it
support combiner-box, inverters, energy meters and
environment sensors.
STRICTLY PRIVATE & CONFIDENTIAL
3.8 Warranty terms
Mounting system warranties
Sungrow carries out the commissioning and start-up
process of the inverters which is a prerequisite for the
warranty to be valid and effective.
Inverter warranty specification is outlined as follows:
Inverter warranties
Warranties will be provided by supplier (CNBM) that will
provide modules for the project. Both product and
performance warranties will be obtained:
Limited product warranty:
Modules will be replaced or repaired if there are defects in
materials and workmanship.
Guaranteed peak power warranty (performance):
If the modules generate an output rate below:
• 90% in a period of 10 years;
and
• 80% in a period of 25 years,
the loss in power will be compensated through the provision
of additional modules or by repairing the original ones
provided by the suppliers.
PV module warranties
34
The supplier will not be liable for:
Any loss in revenue, profits and reduction as a result of
module defects and damage or injury to persons or property.
Any liability payable by the supplier shall not exceed the
invoice value paid by the SPV for each module.
Validity
period
24 months from the date of commissioning
Costs Transportation costs for repaired inverters or
replacement parts are covered by warranty.
Transportation costs for returning the defective
parts lie with the project.
Warranty term Metallic 10 years
Ultraviolet
resistance or plastic
components
10 years
All other
components
2 years
Warranty commencement date Date of delivery
Limitation of the scope
STRICTLY PRIVATE & CONFIDENTIAL
3.9 Key counterparties
Company
O&M
Modules
Description
High professional and result oriented team with high speed
of execution of the projects
4 SPV
CNBM
Provider
Inverters
Mounting System
Power offtake
Quality assurance
Insurance
Security
Positive experience is solar parks insurance
With obtaining certificates for each parks separately
Sungrow
Akcome
Active insurance
TUVVDE
Positive experience2 local companies
WEM
35
High quality equipment with low quantity of spoilage.
Short terms of delivery, acceptable packages which
allow deliver, unload and storage without significant
losses,
Element supports with full scope of warranty for
required period, manual, recommendations for
assembling and maintenance.
Low price with positive experience on the marked.
STRICTLY PRIVATE & CONFIDENTIAL
4. Project Construction
36
4.1 Stages of solar power stations construction
- Study of the
network status
and substation
capacity
- Selecting
scheme of power
distribution
- Endorsement of
a chosen variant
with the network
Owner
- Topographic
mapping
- Geological
engineering
survey
- Historical
archaeological
survey (if
necessary)
- Permit for
design and
survey work
- Development of
BE Stage
- Development of
P Stage
- Undergoing an
expertise
assessment
- Development of
CD Stage
- The Project
business plan
- Analysis of
suppliers and a
Contractor,
assessment of
opportunities and
risks
- Tendering
- Signing contracts
for services and
supplies
- Declaring of
construction start
- Preparatory and
in-site works
- Pile sinking and
fastening
structure
mounting
- Electric
installation works
(DC/AC)
- Commissioning
works
- Connection of the
constructed SPS to the
network
- Conclusion of
contracts, acquisition of
certificates and
licenses
- Carrying out technical
and financial audit
2-3 months 3-4 months 1 month
up to 1 month up to1 month 2 months 1 month 3 months 1 month6 months
- Listing of plots
for possible
connection
- Selecting of a
land plot
- Visual
inspection of the
plot
- Registration of
a legal entity
- Allotment of
the land plot
6 months
Designing Construction CommissioningPre-drafting stage
Process of solar power station construction
Financial control for all project stages
Land
allotment
FS
Background
data
acquisition
SPS
designing
Supplier
selection
SPS
construction
Commission
37
Currently project is on “SPS designing” and “Supplier selection”
development stages.
5.2 Typical schedule of construction works
38
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Basic engineering
Execution drawings
Equipment delivery
Preparatory works
Roads 5%
Fence installation
Service buildings and facilities
Inverter station + GCB
Ramming piles
Trenches preparation
Cable laying
Mounting of tables
Mounting of modules
0.4 kV electrical works
10 kV electrical works
Commissioning
Lightning protection system
Security & Video Control Systems
100%
100%
100%
100%
95%
100%
100%
100%
100%
100%
100%
Name of works
Weeks
100%
100%
100%
100%
95% 5%
100%
100%
5 Appendix
39
5.3 Compensation of grid connection costs
40
Project documentation development of
external electrical power supply
Works
Funds within tariffs for electricity transmission, and / or through repayable financial
aids provided by the customer to electricity transmission organization
Financing
Construction and installation works and
commissioning of newly constructed or
reconstructed electrical unit; its connection
to the terminal point
• 100% - funds within repayable financial aids provided by the customer to electricity
transmission organization
Source: NERC “Resolution #32 dated 17 January 2013”
PPA Procedure
• Ukrainian legislation does not comply with the European. For "green" tariff in Ukraine the law
provides a certain order. This order is clearly stated in the Decree of 02.11.2012 № 1421 ENERGY
AND UTILITIES the NATIONAL REGULATORY COMMISSION "On approval of the establishment, review
and termination of the" green "tariff for business entities."
• The Law of Ukraine "On elektroenergetku" guarantees by "green" tariff for the whole period of its
validity.
• Article 17.1 (last paragraph) of the Law "On elektroenergetiku."
• The State guarantees the consolidation at the legislative level for the whole period "green" tariff
requirements for procurement in each billing period the electricity produced at the power plants,
including the commissioning phase of construction of power plants (NSC), using alternative sources
energy (except for blast furnace and coking gases, and for hydro-energy - only micro, mini and small
hydroelectric power plants), and not sold directly to consumers under contracts or supply company,
established by the "green" tariff allowances given to him in accordance with established Article 17-3
of the Act, to the extent and manner specified in Article 15 of this Law, as well as the payments for
such electricity in full, on time and in cash.
• Changes in the law may make a Parliament and must be sign by the President of Ukraine.
• Recent changes have been made June 4, 2015 with the aim "to ensure competitive conditions of
production of electricity from alternative energy sources. Law of Ukraine about bringing to log On
amendments to some laws of Ukraine to ensure competitive conditions for the production of
electricity from alternative sources of energy from 04.06.2015. This law was abolished condition of
"local content" for "green" tariff in the construction of energy facilities.
• After the entry into force of the changes for the green tariff is only one limitation, this line of
construction of electric power facilities that generate electricity using alternative energy
development plan incorporated power system of Ukraine for the next ten years the.
• Our facilities are included in the development plan of the united energy system of Ukraine for the
next ten years the, as Technical conditions for connection were issued before 1.7.2015 (Law of
Ukraine "On elektrenergetike")
41
PPA PROCEDURE
Feasibility study on the construction
site and grid connection
Land Lease Agreement
Technical specifications for connection
to the grid
Connection to the grid agreement
after Installation
License NERC http://www.nerc.gov.ua
Signing PPA (sale agreement) with
State Enterprise “Energorynok”
http://www.er.gov.ua
Confirmation of FIT obtaining
Sale of electricity act
PPA PRICE
http://zakon4.rada.gov.ua/laws/show/575/97-вр/print1436274478830553
http://zhitomirsp.weebly.com/ukrainian-law.html
3. Solar tariffs per kWh:
a. Starting feed-in tariff would be for those power plants installed in 2017-2019 – 15 euro
cents + VAT 20%;
5.4 List of required permits / agreements
44
 Permit on development of land
arrangement
 Land arrangement project
 Approval of land arrangement
 Land registry extract
 Land lease agreements
 Other documents
Land lease
 Extract from the Uniform State Register
of Enterprises and Organizations of
Ukraine (USREOU)
 The certificate of state registration of a
legal entity
 Charter
 Other documents
Registration of a legal entity
 General contractor contract
 Design contract
 Equipment supply contracts
 Warranties
 Installation works contracts, designer's
technical supervision
Construction
 Security agreement
 Insurance agreement
 O&M agreement
 Manning table
 Labor contract
 Other documents
Maintenance
 Feasibility Study
 Topographic mapping
 Geological engineering survey
 Pales specification
 Permit for design and survey work
 Corrective action register
 Other documents
Project documentations
 Connection to the grid agreement
 Technical specifications for connection
to the grid
 License NERC
 Membership Agreement with WEM
 Signing power sale agreement with
State Enterprise “Energorynok”
 Confirmation of FIT obtaining
 Sale of electricity act
 Other documents
Sale of electricity

More Related Content

What's hot

Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Asian Paint Bangladesh Ltd
 
Effects on transmission line
Effects on transmission lineEffects on transmission line
Effects on transmission line
Ajaj Shaikh
 
Kurram garhi Dam
Kurram garhi DamKurram garhi Dam
Kurram garhi Dam
Aamir Shahzad
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
Vaishnavee Patel
 
Electric power transmission full explanation and presentation
Electric power transmission full explanation and presentationElectric power transmission full explanation and presentation
Electric power transmission full explanation and presentation
Rakesh Gurjar
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systems
anish_hercules
 
132 kv seminar ppt
132 kv seminar ppt132 kv seminar ppt
132 kv seminar ppt
Sourabh Bhattacharya
 
Vfd technology in hvac system
Vfd technology in hvac systemVfd technology in hvac system
Vfd technology in hvac system
Gaurav Gupta
 
A report on solar power plant visit
A report on solar power plant visitA report on solar power plant visit
A report on solar power plant visit
MahipalSoni4
 
Solar pv systems
Solar pv systemsSolar pv systems
Solar pv systems
Stephen Jones
 
Solar on grid application ppt
Solar on grid application pptSolar on grid application ppt
Solar on grid application ppt
swati malla
 
Difference of a solar cell a solar panel
Difference of a solar cell a solar panelDifference of a solar cell a solar panel
Difference of a solar cell a solar panelBartolata Romeo
 
Off grid pv system for indonesia
Off grid pv system for indonesiaOff grid pv system for indonesia
Off grid pv system for indonesiaNany Wardhani
 
PV system design for house
PV system design for housePV system design for house
PV system design for houseKeshar Rawal
 
Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system - Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system -
mme
 
132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur
kishankky
 
The Many Uses of PV Systems
The Many Uses of PV SystemsThe Many Uses of PV Systems
The Many Uses of PV Systems
Sunworks
 
synchronous generators
synchronous generatorssynchronous generators
synchronous generators
Souvik Dutta
 
Rooftop PV System Shubham Gaurav
Rooftop PV System Shubham GauravRooftop PV System Shubham Gaurav
Rooftop PV System Shubham Gaurav
Shubham Gaurav
 

What's hot (20)

Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
Solar energy presentation(sayef amin 01924122222/01614122222/04475122222)
 
Effects on transmission line
Effects on transmission lineEffects on transmission line
Effects on transmission line
 
Kurram garhi Dam
Kurram garhi DamKurram garhi Dam
Kurram garhi Dam
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
 
Electric power transmission full explanation and presentation
Electric power transmission full explanation and presentationElectric power transmission full explanation and presentation
Electric power transmission full explanation and presentation
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systems
 
132 kv seminar ppt
132 kv seminar ppt132 kv seminar ppt
132 kv seminar ppt
 
Solar Power
Solar PowerSolar Power
Solar Power
 
Vfd technology in hvac system
Vfd technology in hvac systemVfd technology in hvac system
Vfd technology in hvac system
 
A report on solar power plant visit
A report on solar power plant visitA report on solar power plant visit
A report on solar power plant visit
 
Solar pv systems
Solar pv systemsSolar pv systems
Solar pv systems
 
Solar on grid application ppt
Solar on grid application pptSolar on grid application ppt
Solar on grid application ppt
 
Difference of a solar cell a solar panel
Difference of a solar cell a solar panelDifference of a solar cell a solar panel
Difference of a solar cell a solar panel
 
Off grid pv system for indonesia
Off grid pv system for indonesiaOff grid pv system for indonesia
Off grid pv system for indonesia
 
PV system design for house
PV system design for housePV system design for house
PV system design for house
 
Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system - Mme solar off grid &on grid solar system -
Mme solar off grid &on grid solar system -
 
132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur132kv Gss report of sitapura jaipur
132kv Gss report of sitapura jaipur
 
The Many Uses of PV Systems
The Many Uses of PV SystemsThe Many Uses of PV Systems
The Many Uses of PV Systems
 
synchronous generators
synchronous generatorssynchronous generators
synchronous generators
 
Rooftop PV System Shubham Gaurav
Rooftop PV System Shubham GauravRooftop PV System Shubham Gaurav
Rooftop PV System Shubham Gaurav
 

Viewers also liked

Solar Projects
Solar ProjectsSolar Projects
Solar Projectsrzampa
 
Dst localisation presentation
Dst localisation presentationDst localisation presentation
Dst localisation presentationUNIDO SA
 
Dti solar park cob pillay 2010
Dti solar park cob pillay 2010Dti solar park cob pillay 2010
Dti solar park cob pillay 2010UNIDO SA
 
Draft Energy Strategy by 2035 (reference materials)
Draft Energy Strategy by 2035 (reference materials)Draft Energy Strategy by 2035 (reference materials)
Draft Energy Strategy by 2035 (reference materials)
Oleg Gramotenko
 
UOxJS_FinalGroupProject
UOxJS_FinalGroupProjectUOxJS_FinalGroupProject
UOxJS_FinalGroupProjectLogan Thomas
 
Autorizados contratar propaganda_electoral
Autorizados contratar propaganda_electoralAutorizados contratar propaganda_electoral
Autorizados contratar propaganda_electoral
Freddy Mejia
 
Ignite MC and IT partners
Ignite MC and IT partnersIgnite MC and IT partners
Ignite MC and IT partners
Ignite Magazine
 
Kosenconf in fukui2
Kosenconf in fukui2Kosenconf in fukui2
Kosenconf in fukui2
syobon0xff
 
GLASS, Ian (Mar15)
GLASS, Ian (Mar15)GLASS, Ian (Mar15)
GLASS, Ian (Mar15)ian glass
 
Energy security v02_vv
Energy security v02_vvEnergy security v02_vv
Energy security v02_vv
Alexey Yankovski
 
Wwics ppt for the immigration
Wwics ppt for the immigrationWwics ppt for the immigration
Wwics ppt for the immigration
WWICS
 
Кваліфікаційні характеристики для ІТ-провесій
Кваліфікаційні характеристики  для ІТ-провесійКваліфікаційні характеристики  для ІТ-провесій
Кваліфікаційні характеристики для ІТ-провесій
Alexey Yankovski
 
Funeral Prayers sefardic - hebrew version
Funeral Prayers sefardic - hebrew versionFuneral Prayers sefardic - hebrew version
Funeral Prayers sefardic - hebrew version
Masada Memorial Chapels
 

Viewers also liked (20)

Solar Projects
Solar ProjectsSolar Projects
Solar Projects
 
Dst localisation presentation
Dst localisation presentationDst localisation presentation
Dst localisation presentation
 
Dti solar park cob pillay 2010
Dti solar park cob pillay 2010Dti solar park cob pillay 2010
Dti solar park cob pillay 2010
 
Draft Energy Strategy by 2035 (reference materials)
Draft Energy Strategy by 2035 (reference materials)Draft Energy Strategy by 2035 (reference materials)
Draft Energy Strategy by 2035 (reference materials)
 
UOxJS_FinalGroupProject
UOxJS_FinalGroupProjectUOxJS_FinalGroupProject
UOxJS_FinalGroupProject
 
2014AR
2014AR2014AR
2014AR
 
CV_4__new
CV_4__newCV_4__new
CV_4__new
 
Autorizados contratar propaganda_electoral
Autorizados contratar propaganda_electoralAutorizados contratar propaganda_electoral
Autorizados contratar propaganda_electoral
 
Ignite MC and IT partners
Ignite MC and IT partnersIgnite MC and IT partners
Ignite MC and IT partners
 
ODC Projects
ODC ProjectsODC Projects
ODC Projects
 
Kosenconf in fukui2
Kosenconf in fukui2Kosenconf in fukui2
Kosenconf in fukui2
 
Summary Statement
Summary StatementSummary Statement
Summary Statement
 
Biometric Products Catalogue
Biometric Products CatalogueBiometric Products Catalogue
Biometric Products Catalogue
 
GLASS, Ian (Mar15)
GLASS, Ian (Mar15)GLASS, Ian (Mar15)
GLASS, Ian (Mar15)
 
Energy security v02_vv
Energy security v02_vvEnergy security v02_vv
Energy security v02_vv
 
Wwics ppt for the immigration
Wwics ppt for the immigrationWwics ppt for the immigration
Wwics ppt for the immigration
 
Кваліфікаційні характеристики для ІТ-провесій
Кваліфікаційні характеристики  для ІТ-провесійКваліфікаційні характеристики  для ІТ-провесій
Кваліфікаційні характеристики для ІТ-провесій
 
RESUME
RESUMERESUME
RESUME
 
Funeral Prayers sefardic - hebrew version
Funeral Prayers sefardic - hebrew versionFuneral Prayers sefardic - hebrew version
Funeral Prayers sefardic - hebrew version
 
SCG Presentation Formal
SCG Presentation FormalSCG Presentation Formal
SCG Presentation Formal
 

Similar to Solar Park Executive summary

Wind Farm 42 MW Deleni November 2014
Wind Farm 42 MW Deleni November 2014Wind Farm 42 MW Deleni November 2014
Wind Farm 42 MW Deleni November 2014Bassam Gorgis, Ph.D.
 
Detailed project report.pptx
Detailed project report.pptxDetailed project report.pptx
Detailed project report.pptx
GYANENDRASATAPATHY
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
Saurabh Biswas
 
Pet Mogili Solar Project
Pet Mogili Solar ProjectPet Mogili Solar Project
Pet Mogili Solar ProjectIvSatinLtd
 
Substation
Substation Substation
Substation
SanjayMk11
 
Wireless power trans mission via solar satelite
Wireless power trans mission via solar sateliteWireless power trans mission via solar satelite
Wireless power trans mission via solar satelite
Saumya Mahapatra
 
Dhanush Varma.pptx
Dhanush Varma.pptxDhanush Varma.pptx
Dhanush Varma.pptx
Arunkumar Tulasi
 
IRJET- Delineation of Ground Water Potential Zones at Moodbidri by Electr...
IRJET-  	  Delineation of Ground Water Potential Zones at Moodbidri by Electr...IRJET-  	  Delineation of Ground Water Potential Zones at Moodbidri by Electr...
IRJET- Delineation of Ground Water Potential Zones at Moodbidri by Electr...
IRJET Journal
 
Chornobyl Solar
Chornobyl SolarChornobyl Solar
Chornobyl Solar
EasyBusiness
 
Pollo solar power plant
Pollo solar power plantPollo solar power plant
Pollo solar power plant
A. D.
 
RPVF PR10
RPVF PR10RPVF PR10
RPVF PR10
Paul Keisch
 
Aboalazaim s cv f-2-1-2020
Aboalazaim s cv  f-2-1-2020Aboalazaim s cv  f-2-1-2020
Aboalazaim s cv f-2-1-2020
AboalazaimMaghraby
 
Potential for wind farm development
Potential for wind farm developmentPotential for wind farm development
Potential for wind farm development
Pia Sorokou
 
Solar Roadways PPT
Solar Roadways PPT Solar Roadways PPT
Solar Roadways PPT
Aseena Latheef
 
VISHAL INGALE.pptx
VISHAL INGALE.pptxVISHAL INGALE.pptx
VISHAL INGALE.pptx
SumitSabale4
 
Solar roadways technology in the world
Solar roadways technology in the worldSolar roadways technology in the world
Solar roadways technology in the world
swetha samv
 
200238.pptx
200238.pptx200238.pptx
200238.pptx
MahmudHasanShuvo1
 
Solar roadways
Solar roadwaysSolar roadways
Solar roadways
Nilesh Bhagare
 
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
НАЕК «Енергоатом»
 

Similar to Solar Park Executive summary (20)

Wind Farm 42 MW Deleni November 2014
Wind Farm 42 MW Deleni November 2014Wind Farm 42 MW Deleni November 2014
Wind Farm 42 MW Deleni November 2014
 
Detailed project report.pptx
Detailed project report.pptxDetailed project report.pptx
Detailed project report.pptx
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
Pet Mogili Solar Project
Pet Mogili Solar ProjectPet Mogili Solar Project
Pet Mogili Solar Project
 
Substation
Substation Substation
Substation
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
Wireless power trans mission via solar satelite
Wireless power trans mission via solar sateliteWireless power trans mission via solar satelite
Wireless power trans mission via solar satelite
 
Dhanush Varma.pptx
Dhanush Varma.pptxDhanush Varma.pptx
Dhanush Varma.pptx
 
IRJET- Delineation of Ground Water Potential Zones at Moodbidri by Electr...
IRJET-  	  Delineation of Ground Water Potential Zones at Moodbidri by Electr...IRJET-  	  Delineation of Ground Water Potential Zones at Moodbidri by Electr...
IRJET- Delineation of Ground Water Potential Zones at Moodbidri by Electr...
 
Chornobyl Solar
Chornobyl SolarChornobyl Solar
Chornobyl Solar
 
Pollo solar power plant
Pollo solar power plantPollo solar power plant
Pollo solar power plant
 
RPVF PR10
RPVF PR10RPVF PR10
RPVF PR10
 
Aboalazaim s cv f-2-1-2020
Aboalazaim s cv  f-2-1-2020Aboalazaim s cv  f-2-1-2020
Aboalazaim s cv f-2-1-2020
 
Potential for wind farm development
Potential for wind farm developmentPotential for wind farm development
Potential for wind farm development
 
Solar Roadways PPT
Solar Roadways PPT Solar Roadways PPT
Solar Roadways PPT
 
VISHAL INGALE.pptx
VISHAL INGALE.pptxVISHAL INGALE.pptx
VISHAL INGALE.pptx
 
Solar roadways technology in the world
Solar roadways technology in the worldSolar roadways technology in the world
Solar roadways technology in the world
 
200238.pptx
200238.pptx200238.pptx
200238.pptx
 
Solar roadways
Solar roadwaysSolar roadways
Solar roadways
 
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
Presentation to the speech President SE NNEGC “Energoatom” Yuriy Nedashkovsky...
 

Recently uploaded

ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
yasmindemoraes1
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
zm9ajxup
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
How about Huawei mobile phone-www.cfye-commerce.shop
How about Huawei mobile phone-www.cfye-commerce.shopHow about Huawei mobile phone-www.cfye-commerce.shop
How about Huawei mobile phone-www.cfye-commerce.shop
laozhuseo02
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
CECOS University Peshawar, Pakistan
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
World Resources Institute (WRI)
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
Piermenotti Mauro
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 

Recently uploaded (20)

ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
How about Huawei mobile phone-www.cfye-commerce.shop
How about Huawei mobile phone-www.cfye-commerce.shopHow about Huawei mobile phone-www.cfye-commerce.shop
How about Huawei mobile phone-www.cfye-commerce.shop
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
Q&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service PlaybookQ&A with the Experts: The Food Service Playbook
Q&A with the Experts: The Food Service Playbook
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
Navigating the complex landscape of AI governance
Navigating the complex landscape of AI governanceNavigating the complex landscape of AI governance
Navigating the complex landscape of AI governance
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 

Solar Park Executive summary

  • 1. Zhitomir Solar Park EXECUTIVE SUMMARY www.zhitomirsp.weebly.com September 2016 STRICTLY PRIVATE & CONFIDENTIAL
  • 2. STRICTLY PRIVATE & CONFIDENTIAL General Information The sites is located in Zhitomir region and have size of 135 ha. Based on the latest experience of visits and technical analysis around 60 MW can be installed with an energy yield in a range of 1109 kWh/kWp per year. Installation can be finished in 9-13 months with experienced team. Site is large enough to easily incorporate PV power plant and no major obstacles and issues are foreseen. The general improvements are more on pre-work on the accessibility in the civil engineering package. The critical components are the transformers, but with the latest development of local suppliers and successful completion of the previous projects, the delivery can be managed on time. A detail topographical map and a soil analysis are essential for the final layout. The team has to analyze the best mounting structure for this are with the best interface to the ground and we assume that localized product range can be integrated into this project. In addition to this detailed analysis with the local utility needs to be initiated. Power plant has a significant capacity and this power needs to be transferred to the high voltage grid. As a result, it could be concluded that this plant can be easily technically installed. We are looking forward to review with you our EPC concept to start the design and installation as soon as possible. Sincerely Yours, Oleg Gramotenko 2
  • 3. STRICTLY PRIVATE & CONFIDENTIAL 1. Ukraine Solar Energy information 3
  • 4. Quantity of RES-electricity production licensees and RES-electricity generating capacities, 2009-2015 4
  • 5. The average weighted feed-in tariffs, 2012-2015 5
  • 6. Actual volume of electricity produced from solar power, 2012-2015 6
  • 7. Dynamics of actual prices for traditional and renewable energy, 2014-2015 7
  • 8. Actual price per MW·h (solar), €ct 8
  • 9. 1.1 About ZHITOMIR SOLAR PARK • ZHITROMIR SOLAR PARK – including 4 sites http://zhitomirsp.weebly.com for solar energy plant with all permissions. 1. Bolohyvsky Solar Park 1 LLC is located on 31,89 hectares. The estimated total capacity around 13,1 MW. 2. Bolohyvsky Solar Park 2 LLC is located on 38,11 hectares. The estimated total capacity around 15,7 MW. 3. Irshanska SES LCC is located on 35,74 hectares. The estimated total capacity around 17 MW. 4. Ganska SES LLC is located on 30 hectares. The estimated total capacity around 15 MW. STRICTLY PRIVATE & CONFIDENTIAL
  • 10. STRICTLY PRIVATE & CONFIDENTIAL 2. Project information 10
  • 11. STRICTLY PRIVATE & CONFIDENTIAL 2.1 Project background Project is planned to be installed in Zhitomir region, with capacity about 60 MW. Project Zhitomir Solar Park Total capacity Solar irradiation Expected net annual energy production Annual energy yield Feed-in tariff Land lease agreement Annual land lease cost Annual O&M cost Technology Panels Inverters MS CNBM Sungrow Akcome n/a 4% 49 years 0.15 EUR/kWh 1 109 MWh/year 65 000 MWh 1 050 kWh/m2 60 MW 11
  • 12. 2.2 Land Lease Agreement Land plot information  Land plot is rented (official document – “Certificate”, confirming subsequent land allotment is in place)  Land lease agreement is signing a Pre-drafting stage of solar power station construction (scheme below)  Agreement term – 49 years  Land lease tax tariff – 4% of land value  The SPV have the right to extend, renew or purchase the land plot at the end of the agreements STRICTLY PRIVATE & CONFIDENTIAL 12 SPV • 4 SPV LLC (4 sites) 135 Area, ha Obtained certificate Agreement status
  • 13. STRICTLY PRIVATE & CONFIDENTIAL 2.3 Infrastructure For O&M and construction needs the access road from nearest public road to the solar parks will be constructed. Roads of 4 meters and several parking places will be constructed for services during maintenance of the solar parks. All roads will be made from gravel without asphalt coverage. Service roads Service and construction office will consist of 2-floor masonry building and several garages for machineries, which will work on site. The building will have independent boreholes and water treatment facilities Service and construction office Site will be protected by fence which consist of panel 2,3 x 2 meters and piles each 2 meters. The land plot will be surrounded with 0,5 high barbered wire. The access for trucks will be enabled by the 5 meters gate. Fence Security system will consist of passive and active parts: •Passive part of security system will allow detecting possible criminals on the land plot, by monitoring current actions. It presumes installment of radars and self focused cameras, which will be synchronized in one system that could work independently with backup batteries. •Active protection system is portrayed by military security company, working 24 hours a day on site. With support of passive system, it will detect and neutralize all possible criminals. Security system 13
  • 14. STRICTLY PRIVATE & CONFIDENTIAL 2.4 Land evaluation Risk Obstacles Power lines Comments There are shrubs and trees on the territory of the site Not ready at the moment and need to be constructed Geology survey have to be ordered. There is highway along west border of the site medium medium medium low Soil condition Accessibility Topography There is power station 110/35/10 kV at the distance of 2,8 km from the site. mediumGrid Connection low The terrain is flat with slopes up to 1° -lowEnvironmental concern -lowHealth and safety Risk of unauthorized intruders from the nearby village, which will be covered by the highly efficient security system of nearly small sized land plot. low / mediumSecurity 14
  • 15. Transformer annex area 2.5 Site description Location: Zhytomyr region, Ukraine Latitude and longitude: 49°56'25“N 27°48'31“E SPV: Bolohyvsky Solar Park 1 Ltd Land area: 31,89 ha Capacity: 13,1 MW* Irradiation level: 1325,1 kWh/m2 Climate: summer is mostly hot, winter is mild and snowy. There is quite high solar activity in the region. Connection point: substation 110/10 kV. The topography of the surface of the plot Basic parameters 15 Description of the Site: •SPV construction site is located west of the village of Yurovka, outside centres of population. •Southward slopes up to 1.5° predominate within the site. • An automobile road is located not far from the northern boundary of the site. N S * - indicated capacity corresponds to location of photovoltaic modules only on unshaded area. Symbol legend: - Area shadowed throughout the year; - Tile drainage pipes Bolohyvsky Solar Park 1 Bolohyvsky Solar Park 2
  • 16. Transformer annex area 2.5 Site description Location: Zhytomyr region, Ukraine Latitude and longitude: 49°56‘2“N 27°48'44"E SPV: Bolohyvsky Solar Park 2 Ltd Land area: 38,11 ha Capacity: 15,7 MW* Irradiation level: 1325,1 kWh/m2 Climate: summer is mostly hot, winter is mild and snowy. There is quite high solar activity in the region. Connection point: substation 110/10 kV. The topography of the surface of the plot Basic parameters 16 Description of the Site: • SPV construction site is located west of the village of Yurovka, outside centres of population. • Northward slopes up to 2° predominate within the site. • An automobile road is located approximately 0.7 km from the site. N S * - indicated capacity corresponds to location of photovoltaic modules only on unshaded area. Symbol legend: - Area shadowed throughout the year; - Tile drainage pipes Bolohyvsky Solar Park 1 Bolohyvsky Solar Park 2
  • 17. 2.5 Site description Location: Zhytomyr region, Ukraine Latitude and longitude: 50°49'34"N 28°48'33"E SPV: Irshanska SES Ltd Land area: 35,74 ha Capacity: 17 MW* Irradiation level: 1319,8 kWh/m2 Climate: summer is mostly hot, winter is mild and snowy. There is quite high solar activity in the region. Connection point: substation 110/10 kV “Meleni”. The topography of the surface of the plot Basic parameters 17 Description of the Site: • SPV construction sites are located west of the village of Meleni, outside centres of population. • Southward and south-eastward slopes up to 1° predominate within the site. • An automobile road is located 0.35 km north of the site. N S Substation 110/10 kV “Meleni” Symbol legend: - Area shadowed throughout the year; - Fenced off area of high-voltage power line 110 kV Site №3 Site№2 Site №1 Water drain Irrigation channel * - indicated capacity corresponds to location of photovoltaic modules only on unshaded area.
  • 18. STRICTLY PRIVATE & CONFIDENTIAL 2.5 Site description Location or picture of land here Location: Zhitomir region, Ukraine Latitude and longitude: 49°55'4"N 28°39‘20"E SPV: Ganska SES Ltd Land area: 30 ha Capacity: 15 MW* Irradiation level: 1349,5 kWh/m2 Climate: summer is mostly hot, winter is mild and snowy. There is quite high solar activity in the region. Connection point: substation 110/35/10 kV “Berdichiv”. The topography of the surface of the plot Basic parameters 18 Description of the Site: •The land lot for construction of PhES is located to the east of the city of Berdichev outside the settlements. •The area of the land lot has different slopes up to 1°. •There is a motorway along the western boundary of the site. N S Legend: - The area shaded throughout a year PS 110/35/10 kV “N. Berdichev” * - the power value is specified of the photovoltaic modules are placed only on the unshaded area.
  • 19. STRICTLY PRIVATE & CONFIDENTIAL 2.6 Irradiation analysis, energy output The irradiation levels that the project is going to be exposed to varies on the monthly basis as illustrated above. Annual irradiation level is 1349,5 kWh/m2, which enables the electricity generation of about 1109 kWh/kWp annually. Expected net annual energy production will be about 14024 MWh. The solar irradiation levels experienced in Zhytomyr region of Ukraine are amongst the highest in the country, about 1150-1400 kWh per 𝑚2 . The average temperature may vary in between -5,1° and +18,5° C and reflects the European standard range. Even if the values during summer time are higher than the Standard Test Conditions, no major reduction in the output due to constant windy conditions is foreseen. 19 0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average daily electricity production from the given system (kWh/kWp/day)
  • 20. STRICTLY PRIVATE & CONFIDENTIAL Normalized production per installed kWp (12643 kWp): Loss diagram over the whole year Performance Ratio (PR) 20 2.8 Energy output
  • 21. STRICTLY PRIVATE & CONFIDENTIAL 3. Key Project Components 21
  • 22. STRICTLY PRIVATE & CONFIDENTIAL 3.1 PV modules Name Photovoltaic elements Maximum Power 260-285Wp Cell Type 5 - 6 inches Quantity of cells 60 Weight 19.5 kg Dimensions min 1638 x 982 x 40 mm (LxWxH) Maximum Power Voltage 30 – 32V Maximum Power Current 7,8 - 8A Open-Circuit Voltage 37 - 38V Short-Circuit Current 8,5 – 8,8A Maximum System Voltage 1000 V DC Maximum Series Fuse Rating 15A Power Tolerance ±3% Temperature Coefficients of Pmax -0.4336±0.05% / DC Temperature Coefficients of Voc -0.4049±0.05% / DC Temperature Coefficients of Isc 0.0825±0.02%/DC Nominal Operating Cell Temperature 45±2°C Service life 20-25 Module efficiency ratio >15% Products guarantee 12 years 22
  • 23. STRICTLY PRIVATE & CONFIDENTIAL 3.1 PV modules Bankability All delivered PV modules are produced strictly according to the specifications, datasheets and certificates. The modules are safely packed for international truck and sea transportation and the appropriate flash-reports are provided in excel format before each shipment. CNBM will supply the policrystalline PV modules for the project. These module supplier is established and reputable PV manufacturer, which provide the PV modules with standard industry product and performance warranties. Description The different technologies in the market are mainly crystalline and thin-film products, which work in general with the same physical effect and can be distinguished in the efficiency, respectively in the power produced per area, where crystalline modules can reach more than 120 W/m2 and thin-film around 60 W/m2. With a higher production of power per area the user needs lesser space, which is relevant for leased areas and rented roofs. The thin-film installation costs are lesser per Watt but need double of the space that crystalline products need. Technology The selection of the module type depends on its price, technology, on its availability and mainly on its bankability. The lenders, banks and insurance companies put their focus on the brand’s value, warranty and track record. Conclusion The proposed modules are bankable and have a track record. The selection depends on commercial and bankability topics and needs to be reviewed together with the banks and investors. Thin-film modules would need double of the area and Greentech recommends using the crystalline solution for larger free field power plants. 23
  • 24. STRICTLY PRIVATE & CONFIDENTIAL Manufacturer – Sungrow Combiner box PVS-XM is used for collecting power from strings by connecting them to the combiner box. PVS-XM has fuses for short circuit, reverse current defense. PVS-XM has measurement channels for string monitoring and data can be transferred by CAN protocol to data logger. 3.2 Combiner boxes 24 Technical data: Cable requirments:
  • 25. STRICTLY PRIVATE & CONFIDENTIAL 3.3 PV station 25 SG1000TS-MV PV Station is a 1 MW outdoor PV station, providing turnkey solution for building PV plant; designed with 20ft standart sea shipping container, easy for transportation, high integration for quick installation and commissioning; consist of: a) Metallic enclosure; b) DC cabinet; c) 2 inverters; d) LV/MV transformer; e) MV switchgear; f) LV auxiliary unit; g) Communication unit; h) Safety sensors (temperature&humidity sensors, ip- camera, extinguishers sensors, door limit switches, water logging sensors, smog detectors); i) Heating system
  • 26. STRICTLY PRIVATE & CONFIDENTIAL 3.3.1 Inverters Nominal DC power MPPT Voltage Range Max. DC voltage 500 PV 500-820 1060A 1000V Inverter specifications Max. DC current Quantity DC Inputs Quantity DC Fuses Input data Output data 1 MCCB up to 8 psc (+/-) The inverters are supplied by Sungrow and provide the highest efficiency levels across all central and decentral inverters currently available in the market. 630 PV 500-820 1170A 500-600 kWp 630-693 kWp 26 Operating with 10 kV voltage transformers for energy transmitting to 10 kV outer grid •Power capacity 630 kW •Developed to operate for what 1260 kVA stations •each PV station includes next equipment: a) concrete shelter; b) 2 inverters; c) copain-mode d) Data logger; e) auxiliary board; f) heater; g) MV 3-field switchgear; h) 3-ports transformer 10/0,315/0,315 kV; i) smoke, door, motion sensors Nominal AC Power Grid voltage range Grid frequency Power factor EUR ETA after transformer Max ETA after transformer 500 kVA ~0,9 98,7 % 98,5 % 630 kVA ~0,9 98,7 % 98,5 % 250 ~ 362V 250 ~ 362V 50/60 Hz 50/60 Hz
  • 27. STRICTLY PRIVATE & CONFIDENTIAL 3.3.1 Inverters Greentech recommends the supplier of the inverters to offer the best performance in quality and reliability. The chosen inverter concept from the Sungrow portfolio offers the highest efficiency among central and de-central transformer-less inverters. The inverter works directly with a medium voltage transformer that ensures less cable losses as well as a maximized yield. Other suppliers like Sungrow, but also SMA and ABB are internationally orientated and have a very good access to the European market with local teams and local certifications. The advantage of Sungrow is the local experience in Ukraine and the track record with similar sized projects in the country. Description The selection of the inverter concept mainly depends on the size of the power plant and on the local infrastructure. Central inverters are often used for larger MW plants with enough space for additional service stations. De-central inverters in the range of 10-20 kVA are used for roofs or areas with limited space. Inverter concept Conclusion The chosen inverter concept offers the highest efficiency amongst transformer-less inverter. It features an integrated DC disconnector as well as string monitored fuses. For this larger site with 50 MW we recommend the central versions as a preferred solution to have an independent system. The combination of 500 kVA and 630 kvA units gives flexibility in the electrical layout. 27
  • 28. STRICTLY PRIVATE & CONFIDENTIAL Technical data: 3.3.2 Voltage transformers View of 10/0,315/0,315 kV 3 Phase hermetically sealed transformer transformer: 28 Transformer is used for increasing the voltage to 10 kV for transferring to the grid.
  • 29. STRICTLY PRIVATE & CONFIDENTIAL 3.4 Foundation with piles Standard depth in ground Material Specifications 1.2 m – 1.5 m Steel, hot dip, galvanized Posts Type Sigma profile PV modules in large power plants are usually mounted on elevated structures to minimize the land occupancy. Due to the bigger wind aperture of those PV fields, higher loads are therefore transmitted to the foundations, resulting in a design of heavy concrete foundations. The installation of metallic posts or screws is exceptionally fast and allows a laser cut precise installation. The ramming is performed with a special vehicle with actuators in order to press the SIGMA shaped piles into the ground. The length can be adjusted to the soil conditions’ requirements. 1,8 m – 3 mOverall length The approach to use concrete foundations is in general not recommended if metallic ramming piles or equivalent solutions can be envisaged. Concrete foundations generally add significantly on execution time and complexity whereas the products for metallic ramming piles can be sourced locally. Conclusion 29 •Suppliers: Fregat, Euroformat •15 year experience, about 650 000 piles for solar parks •Local suppliers, good quality of piles •Piles fixed with mounting system by screws, washers, clamping plate and nuts On the picture steel pile is shown: manufacturer Fregat; coverage - hot dip galvanized with thickness 120 mkm; tolerances +/– 1 %
  • 30. STRICTLY PRIVATE & CONFIDENTIAL 3.5 Mounting system Expected durability Tilt angle of modules Single row 15-20 years & 2x11 & 2x6 [HxV] MS specifications # of modules per structural element Orientation of the modules Wind loads Base material According to euro code 9 T6063/6060 aluminum for base profiles SUS304 for accessories Hot dip galvanized steel for plants T6063/6060 aluminum for base profiles T6063/6060 aluminum for base substructure SUS304 for accessories Multiple rows 4x11 & 4x6 [HxV] Portrait or horizontal Snow loads According to euro code 9 30 Supplier – Akcome •4 of rows system •made according European standards •Support angles are and , height is about 2,8 m •MS s the basis for the installation of modules at the required angle. It has special cover -anodized aluminum for protection from corrosion Portrait or horizontal
  • 31. STRICTLY PRIVATE & CONFIDENTIAL 3.5 Mounting system Installations with one module mounting system are used for open areas with differences in the height level of the topography. It can easily be installed without additional machinery and is very flexible. No mayor leveling work in the field is necessary. It can follow the height levels of the site. A minimum distance of 2m between the rows slightly decreases the capacity rate per hectare. The installation with two or more modules in vertical or horizontal have a slightly higher utilization rate of the field in MW per hectare. Can be installed in a similar way within the same time but it is necessary to install the system by teams of two people. A moveable scaffold is needed to guarantee a professional and safe installation. One row system Multiple row system Conclusion When selecting a mount, various options were considered, taking into account dynamic tracking of the sun throughout the daylight hours. It was found that the optimal solution for flat plot with stable soil is 4 rows system, for plots with complicated relief and unstable or weak soil is 2 rows or single rows systems on one piles. These structures are optimally priced for the material consumption per unit modules and savings in bearing piles, have many positive aspect of the series, also increased distance between the tables which in turn makes it possible to use the standard mechanical engineering. With increasing design series will have adverse effect on the speed of installation and maintenance during operation as well as the height of the construction will reach critical levels. 31
  • 32. STRICTLY PRIVATE & CONFIDENTIAL The suppliers are Telefonica, SKW, LAPP, Leoni, Prysmian, HELUCABLE World-known companies with experience more than 40 years Cables are VDE, IEC, ISO certified used types – NYY, N2XS(FL)2Y, N2XSEY, solar cable, Li2YCYv, ADQ(ZN)(SR)2Y 3.6 Cables and conduits MV cables, Solar Cables, DC cables, Data cables 32 N2XS(FL)2Y N2XSEY NYY
  • 33. STRICTLY PRIVATE & CONFIDENTIAL 3.7 Monitoring system SKYTRON PVGuard Platform was selected as monitoring system supplier. It is a complete intelligent SCADA solution that offers to operator and investors an efficient and real- time tool for monitoring and maintaining the megawatt-class PV Park. It is versatile, flexible and strong instrument that perfectly interacts with a large part of equipment. The intuitive graphical user interface represents and confronts performance and error data consistently making the plant easily comparable. Functions • Real-time visualization of data in high resolution • Storage and archiving of all measured data • Alarm management and incident control • Configurable automatic email notification • Data exporting • Single point administration for multiple PV Park • Compare components across different plants 33 This monitoring system is the fast link between solar equipment and its owner. It provides a complete plant monitoring, remote diagnosis, data storage and display. Access to the system data is available via a web browser, smartphone and tablet at anytime from anywhere in the world regardless of the operating system or browser type. PVGuard is a vendor-independent PV monitoring, it support combiner-box, inverters, energy meters and environment sensors.
  • 34. STRICTLY PRIVATE & CONFIDENTIAL 3.8 Warranty terms Mounting system warranties Sungrow carries out the commissioning and start-up process of the inverters which is a prerequisite for the warranty to be valid and effective. Inverter warranty specification is outlined as follows: Inverter warranties Warranties will be provided by supplier (CNBM) that will provide modules for the project. Both product and performance warranties will be obtained: Limited product warranty: Modules will be replaced or repaired if there are defects in materials and workmanship. Guaranteed peak power warranty (performance): If the modules generate an output rate below: • 90% in a period of 10 years; and • 80% in a period of 25 years, the loss in power will be compensated through the provision of additional modules or by repairing the original ones provided by the suppliers. PV module warranties 34 The supplier will not be liable for: Any loss in revenue, profits and reduction as a result of module defects and damage or injury to persons or property. Any liability payable by the supplier shall not exceed the invoice value paid by the SPV for each module. Validity period 24 months from the date of commissioning Costs Transportation costs for repaired inverters or replacement parts are covered by warranty. Transportation costs for returning the defective parts lie with the project. Warranty term Metallic 10 years Ultraviolet resistance or plastic components 10 years All other components 2 years Warranty commencement date Date of delivery Limitation of the scope
  • 35. STRICTLY PRIVATE & CONFIDENTIAL 3.9 Key counterparties Company O&M Modules Description High professional and result oriented team with high speed of execution of the projects 4 SPV CNBM Provider Inverters Mounting System Power offtake Quality assurance Insurance Security Positive experience is solar parks insurance With obtaining certificates for each parks separately Sungrow Akcome Active insurance TUVVDE Positive experience2 local companies WEM 35 High quality equipment with low quantity of spoilage. Short terms of delivery, acceptable packages which allow deliver, unload and storage without significant losses, Element supports with full scope of warranty for required period, manual, recommendations for assembling and maintenance. Low price with positive experience on the marked.
  • 36. STRICTLY PRIVATE & CONFIDENTIAL 4. Project Construction 36
  • 37. 4.1 Stages of solar power stations construction - Study of the network status and substation capacity - Selecting scheme of power distribution - Endorsement of a chosen variant with the network Owner - Topographic mapping - Geological engineering survey - Historical archaeological survey (if necessary) - Permit for design and survey work - Development of BE Stage - Development of P Stage - Undergoing an expertise assessment - Development of CD Stage - The Project business plan - Analysis of suppliers and a Contractor, assessment of opportunities and risks - Tendering - Signing contracts for services and supplies - Declaring of construction start - Preparatory and in-site works - Pile sinking and fastening structure mounting - Electric installation works (DC/AC) - Commissioning works - Connection of the constructed SPS to the network - Conclusion of contracts, acquisition of certificates and licenses - Carrying out technical and financial audit 2-3 months 3-4 months 1 month up to 1 month up to1 month 2 months 1 month 3 months 1 month6 months - Listing of plots for possible connection - Selecting of a land plot - Visual inspection of the plot - Registration of a legal entity - Allotment of the land plot 6 months Designing Construction CommissioningPre-drafting stage Process of solar power station construction Financial control for all project stages Land allotment FS Background data acquisition SPS designing Supplier selection SPS construction Commission 37 Currently project is on “SPS designing” and “Supplier selection” development stages.
  • 38. 5.2 Typical schedule of construction works 38 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Basic engineering Execution drawings Equipment delivery Preparatory works Roads 5% Fence installation Service buildings and facilities Inverter station + GCB Ramming piles Trenches preparation Cable laying Mounting of tables Mounting of modules 0.4 kV electrical works 10 kV electrical works Commissioning Lightning protection system Security & Video Control Systems 100% 100% 100% 100% 95% 100% 100% 100% 100% 100% 100% Name of works Weeks 100% 100% 100% 100% 95% 5% 100% 100%
  • 40. 5.3 Compensation of grid connection costs 40 Project documentation development of external electrical power supply Works Funds within tariffs for electricity transmission, and / or through repayable financial aids provided by the customer to electricity transmission organization Financing Construction and installation works and commissioning of newly constructed or reconstructed electrical unit; its connection to the terminal point • 100% - funds within repayable financial aids provided by the customer to electricity transmission organization Source: NERC “Resolution #32 dated 17 January 2013”
  • 41. PPA Procedure • Ukrainian legislation does not comply with the European. For "green" tariff in Ukraine the law provides a certain order. This order is clearly stated in the Decree of 02.11.2012 № 1421 ENERGY AND UTILITIES the NATIONAL REGULATORY COMMISSION "On approval of the establishment, review and termination of the" green "tariff for business entities." • The Law of Ukraine "On elektroenergetku" guarantees by "green" tariff for the whole period of its validity. • Article 17.1 (last paragraph) of the Law "On elektroenergetiku." • The State guarantees the consolidation at the legislative level for the whole period "green" tariff requirements for procurement in each billing period the electricity produced at the power plants, including the commissioning phase of construction of power plants (NSC), using alternative sources energy (except for blast furnace and coking gases, and for hydro-energy - only micro, mini and small hydroelectric power plants), and not sold directly to consumers under contracts or supply company, established by the "green" tariff allowances given to him in accordance with established Article 17-3 of the Act, to the extent and manner specified in Article 15 of this Law, as well as the payments for such electricity in full, on time and in cash. • Changes in the law may make a Parliament and must be sign by the President of Ukraine. • Recent changes have been made June 4, 2015 with the aim "to ensure competitive conditions of production of electricity from alternative energy sources. Law of Ukraine about bringing to log On amendments to some laws of Ukraine to ensure competitive conditions for the production of electricity from alternative sources of energy from 04.06.2015. This law was abolished condition of "local content" for "green" tariff in the construction of energy facilities. • After the entry into force of the changes for the green tariff is only one limitation, this line of construction of electric power facilities that generate electricity using alternative energy development plan incorporated power system of Ukraine for the next ten years the. • Our facilities are included in the development plan of the united energy system of Ukraine for the next ten years the, as Technical conditions for connection were issued before 1.7.2015 (Law of Ukraine "On elektrenergetike") 41
  • 42. PPA PROCEDURE Feasibility study on the construction site and grid connection Land Lease Agreement Technical specifications for connection to the grid Connection to the grid agreement after Installation License NERC http://www.nerc.gov.ua Signing PPA (sale agreement) with State Enterprise “Energorynok” http://www.er.gov.ua Confirmation of FIT obtaining Sale of electricity act
  • 43. PPA PRICE http://zakon4.rada.gov.ua/laws/show/575/97-вр/print1436274478830553 http://zhitomirsp.weebly.com/ukrainian-law.html 3. Solar tariffs per kWh: a. Starting feed-in tariff would be for those power plants installed in 2017-2019 – 15 euro cents + VAT 20%;
  • 44. 5.4 List of required permits / agreements 44  Permit on development of land arrangement  Land arrangement project  Approval of land arrangement  Land registry extract  Land lease agreements  Other documents Land lease  Extract from the Uniform State Register of Enterprises and Organizations of Ukraine (USREOU)  The certificate of state registration of a legal entity  Charter  Other documents Registration of a legal entity  General contractor contract  Design contract  Equipment supply contracts  Warranties  Installation works contracts, designer's technical supervision Construction  Security agreement  Insurance agreement  O&M agreement  Manning table  Labor contract  Other documents Maintenance  Feasibility Study  Topographic mapping  Geological engineering survey  Pales specification  Permit for design and survey work  Corrective action register  Other documents Project documentations  Connection to the grid agreement  Technical specifications for connection to the grid  License NERC  Membership Agreement with WEM  Signing power sale agreement with State Enterprise “Energorynok”  Confirmation of FIT obtaining  Sale of electricity act  Other documents Sale of electricity