Overview Of Project Planning
Introduction
PRINCE 2 is a set of project management
standard.
It is sponsored by Central Computing and
Telecommunications Agency(CCTA)
Step Wise should be comfortable with
PRINCE 2
It covers planning stage of a project, not
monitoring and control the project
07/24/14 2
Stepwise Project Planning
Steps in Project Planning
Step 0 : Select project
Step 1 : Identify project scope and objectives
Step 2 : Identify project infrastructure
Step 3 : Analyze project characteristics
Step 4 : Identify project products and activities
Step 5: Estimate effort for each activity
Step 6 : Identify activity risks
Step 7 : Allocate resources
Step 8: Review / Publicize plan
Step 9 & 10 : Execute plan / lower level of planning07/24/14 3
07/24/14 4
Step 0 : Select Project
07/24/14 5
Step 1: Identify Project Scope and
Objectives
Step 1.1 Identify objectives and measure of
effectiveness
 Get the objectives of a project
 Measuring effectiveness can be in terms of
software quality
 Performance measurement
 Mean time of failure
 Predictive measurement
 Error in code
07/24/14 6
Cont..
Step 1.2 Establish a project authority
 ‘Who is the boss?’
 Identify the authority of the project
Step 1.3 Stakeholders Analysis
Identify all stakeholders in the project
The stockholders who are all having interest in
project
 With the team we want to check
 Not in project team but with in
organization
 External stakeholders
07/24/14 7
Cont..
Step 1.4 Change objectives based on stakeholder
analysis
The stakeholder suggestion is satisfied means
change the objective
 If it’s not satisfied means , don’t change the
original objective of the project
Step 1.5 Establish method of communication with all
parties
We should satisfy the customer requirements
How do we keep in contact with customer
07/24/14 8
Step 2: Establish project infrastructure
Step 2.1: Identify relationship between project and
strategic planning
What are the standard methods going to complete
the project
Step 2.2 : Identify installation standards and procedures
What are the front end and
Back end
Software are going to use in this project
Step 2.3 : Identify project team organization
Order of organizing to the project
Team management07/24/14 9
Step 3:Analyze project characteristics
Step 3.1 : Distinguish project as objective driven or
product driven
Product - It will be given by the user & design by
external person
Objective - Problem is given
We want to find the solution
Get recommendation
Step 3.2 : Analyze other project characteristics
 Including quality –based ones
What are the problems going to solve
07/24/14 10
Cont..
Step 3.3 : Identify high level of project risks
 Identify the level of risk
Step 3.4: Take user requirement concerning
implementation
Confirm with the user requirement
Step 3.5: Select development methodology and life
cycle approach
Step by step process ,what are the methods going
to follow in the project
Step 3.6: Review overall resource estimation
After risk identification, re-estimate effort &
resources of project07/24/14 11
Step 4 : Identify Project Products and
Activities
Step 4.1: Identify and describes project products
Deliverable: Product handover to user
In this step identify each and every phase
Identify the project going to deliver
Each and every stage consider as a product
Product hierarchy
Project Specification
Module specification
System product
Management product07/24/14 12
Cont..
Project Specification
Module System Management
specification procedure products
Design Code Overall Integration Testing
Progress
report
07/24/14 13
Cont..
Step 4.2 : Document generic product flows
 Product flow diagram
 One stage output is given to input of other stage
Eg: Requirements
Design
Coding
Testing
Step 4.3 : Record product instances
For each and every product what are the steps
going to follow
Identifying product instance07/24/14 14
Cont..
Step 4.4 : Produce ideal activity network
 Each and every module having several activity
 After complete individual module combine all the
modules
Step 4.5 : Modify ideal to take stages and
checkpoints
 Project divided into number of product check each
and every stage we do correctly or not
 Check point to check the progress of the project
07/24/14 15
Step 5: Estimate effort for each activity
Step 5.1: Carry out bottom-up estimation
 Estimate
 Staff effort
 How much work in need to complete the
project
 Product elapse time
 How much time taken to complete the
project
 Non-staff resources
 Designing tools
 Software need
07/24/14 16
Cont..
Step 5.2: Revise plan to create controllable activities
 Every phase we need to control
 Need to break a task into a series of manageable
sub-tasks
 Break up very long activities into a series of
smaller ones as we can’t judge the status in long
activities
07/24/14 17
Step 6 : Identify activity risks
Step 6.1 : Identify and quantify activity based risks
Identify risk for each activity
During the design phase identify the risk
Identify damage and likelihood
Identify possibilities of mistakes
07/24/14 18
Cont..
Step 6.2 : Plan risk reduction and contingency
measures where appropriate
Review plan and do some steps for reduce risk
Have the alternative plan
Alternative measurement
Otherwise specify a contingency plan
For example:
Contract temporary developer if team
member becomes unavailable through
illness
07/24/14 19
Cont..
Step 6.3 : Adjust overall plans and estimates to take
account of the risks
 Including add new activities - such as training
and practice -if needed
 Add new activities which reduce risk
 associated with other activities
E.g. Training
Pilot trials
Information gathering
07/24/14 20
Step 7 : Allocate resources
Step 7.1 : Identify and allocate resources
Type of staff needed for each activity
Staff availability are identified
Staff are provisionally allocated to task
Step 7.2 : Revise plans and estimates to take into
account resource constraints
Staffing constraints
Staffing issues
07/24/14 21
Step 8 : Review / Publicize Plan
Step 8.1 : Review quality aspects of the project plan
To ensure each activity is completed with a quality
product
Each activity should have “exit requirements”
This ensures the quality of product on each
activity
Check quality of phase before going to next stage
07/24/14 22
Cont..
Step 8.2 : Document plans and obtain agreements
 All parties understand and agree to the
commitments in the plan
 Make sure everyone understands and agree
 Specify this task in a communication plan if
needed
 Develop the documentation
07/24/14 23
Step 9 & 10 :Execute plan / lower level of
planning
During the project draw up plans for activities in
greater detail as they become due
Detail has to wait as more information becomes
available
Especially if you are using an iterative
development approach
Maintain provisional plans for more important
later tasks
Planning in great detail too soon could be a waste
of time
07/24/14 24
References:
Bob Hughes and Mike Cotterell (2004)
“Software Project Management”, McGraw-Hill.
P.Jalote(2000) “Software Project Management
In Practice”, Pearson Education..
https://learning.uonbi.ac.ke/courses/ICS616/doc
ument/Lecture_3_-Project_planning.pdf
http://www.itglitz.in/SPM/stepwise
07/24/14 25
07/24/14 26
07/24/14 27

Software Project Management

  • 1.
    Guided By, Miss R.Indumathi.,MCA (AP/MCA) S.Gomathi(MCA12006) P.Lavanya(MCA12011) P.R.Papitha(MCA12017) K.Revathi(MCA12024) K.Priya(MCA12048) 07/24/14 1
  • 2.
    Overview Of ProjectPlanning Introduction PRINCE 2 is a set of project management standard. It is sponsored by Central Computing and Telecommunications Agency(CCTA) Step Wise should be comfortable with PRINCE 2 It covers planning stage of a project, not monitoring and control the project 07/24/14 2
  • 3.
    Stepwise Project Planning Stepsin Project Planning Step 0 : Select project Step 1 : Identify project scope and objectives Step 2 : Identify project infrastructure Step 3 : Analyze project characteristics Step 4 : Identify project products and activities Step 5: Estimate effort for each activity Step 6 : Identify activity risks Step 7 : Allocate resources Step 8: Review / Publicize plan Step 9 & 10 : Execute plan / lower level of planning07/24/14 3
  • 4.
  • 5.
    Step 0 :Select Project 07/24/14 5
  • 6.
    Step 1: IdentifyProject Scope and Objectives Step 1.1 Identify objectives and measure of effectiveness  Get the objectives of a project  Measuring effectiveness can be in terms of software quality  Performance measurement  Mean time of failure  Predictive measurement  Error in code 07/24/14 6
  • 7.
    Cont.. Step 1.2 Establisha project authority  ‘Who is the boss?’  Identify the authority of the project Step 1.3 Stakeholders Analysis Identify all stakeholders in the project The stockholders who are all having interest in project  With the team we want to check  Not in project team but with in organization  External stakeholders 07/24/14 7
  • 8.
    Cont.. Step 1.4 Changeobjectives based on stakeholder analysis The stakeholder suggestion is satisfied means change the objective  If it’s not satisfied means , don’t change the original objective of the project Step 1.5 Establish method of communication with all parties We should satisfy the customer requirements How do we keep in contact with customer 07/24/14 8
  • 9.
    Step 2: Establishproject infrastructure Step 2.1: Identify relationship between project and strategic planning What are the standard methods going to complete the project Step 2.2 : Identify installation standards and procedures What are the front end and Back end Software are going to use in this project Step 2.3 : Identify project team organization Order of organizing to the project Team management07/24/14 9
  • 10.
    Step 3:Analyze projectcharacteristics Step 3.1 : Distinguish project as objective driven or product driven Product - It will be given by the user & design by external person Objective - Problem is given We want to find the solution Get recommendation Step 3.2 : Analyze other project characteristics  Including quality –based ones What are the problems going to solve 07/24/14 10
  • 11.
    Cont.. Step 3.3 :Identify high level of project risks  Identify the level of risk Step 3.4: Take user requirement concerning implementation Confirm with the user requirement Step 3.5: Select development methodology and life cycle approach Step by step process ,what are the methods going to follow in the project Step 3.6: Review overall resource estimation After risk identification, re-estimate effort & resources of project07/24/14 11
  • 12.
    Step 4 :Identify Project Products and Activities Step 4.1: Identify and describes project products Deliverable: Product handover to user In this step identify each and every phase Identify the project going to deliver Each and every stage consider as a product Product hierarchy Project Specification Module specification System product Management product07/24/14 12
  • 13.
    Cont.. Project Specification Module SystemManagement specification procedure products Design Code Overall Integration Testing Progress report 07/24/14 13
  • 14.
    Cont.. Step 4.2 :Document generic product flows  Product flow diagram  One stage output is given to input of other stage Eg: Requirements Design Coding Testing Step 4.3 : Record product instances For each and every product what are the steps going to follow Identifying product instance07/24/14 14
  • 15.
    Cont.. Step 4.4 :Produce ideal activity network  Each and every module having several activity  After complete individual module combine all the modules Step 4.5 : Modify ideal to take stages and checkpoints  Project divided into number of product check each and every stage we do correctly or not  Check point to check the progress of the project 07/24/14 15
  • 16.
    Step 5: Estimateeffort for each activity Step 5.1: Carry out bottom-up estimation  Estimate  Staff effort  How much work in need to complete the project  Product elapse time  How much time taken to complete the project  Non-staff resources  Designing tools  Software need 07/24/14 16
  • 17.
    Cont.. Step 5.2: Reviseplan to create controllable activities  Every phase we need to control  Need to break a task into a series of manageable sub-tasks  Break up very long activities into a series of smaller ones as we can’t judge the status in long activities 07/24/14 17
  • 18.
    Step 6 :Identify activity risks Step 6.1 : Identify and quantify activity based risks Identify risk for each activity During the design phase identify the risk Identify damage and likelihood Identify possibilities of mistakes 07/24/14 18
  • 19.
    Cont.. Step 6.2 :Plan risk reduction and contingency measures where appropriate Review plan and do some steps for reduce risk Have the alternative plan Alternative measurement Otherwise specify a contingency plan For example: Contract temporary developer if team member becomes unavailable through illness 07/24/14 19
  • 20.
    Cont.. Step 6.3 :Adjust overall plans and estimates to take account of the risks  Including add new activities - such as training and practice -if needed  Add new activities which reduce risk  associated with other activities E.g. Training Pilot trials Information gathering 07/24/14 20
  • 21.
    Step 7 :Allocate resources Step 7.1 : Identify and allocate resources Type of staff needed for each activity Staff availability are identified Staff are provisionally allocated to task Step 7.2 : Revise plans and estimates to take into account resource constraints Staffing constraints Staffing issues 07/24/14 21
  • 22.
    Step 8 :Review / Publicize Plan Step 8.1 : Review quality aspects of the project plan To ensure each activity is completed with a quality product Each activity should have “exit requirements” This ensures the quality of product on each activity Check quality of phase before going to next stage 07/24/14 22
  • 23.
    Cont.. Step 8.2 :Document plans and obtain agreements  All parties understand and agree to the commitments in the plan  Make sure everyone understands and agree  Specify this task in a communication plan if needed  Develop the documentation 07/24/14 23
  • 24.
    Step 9 &10 :Execute plan / lower level of planning During the project draw up plans for activities in greater detail as they become due Detail has to wait as more information becomes available Especially if you are using an iterative development approach Maintain provisional plans for more important later tasks Planning in great detail too soon could be a waste of time 07/24/14 24
  • 25.
    References: Bob Hughes andMike Cotterell (2004) “Software Project Management”, McGraw-Hill. P.Jalote(2000) “Software Project Management In Practice”, Pearson Education.. https://learning.uonbi.ac.ke/courses/ICS616/doc ument/Lecture_3_-Project_planning.pdf http://www.itglitz.in/SPM/stepwise 07/24/14 25