SCHOOL OF ARCHITECTURE, BUILDING
AND DESIGN
BACHELOR OF QUANTITY SURVEYING
(HONOURS)

QSB1714 – Building Services 1
Site Research Reports (Smart Tunnel)

Name:

YAP ZHI XIN

Student No.: 0314542
Smart Tunnel Report
Introduction
The site visit is held on the Thursday of 10th of October 2013 which organized by
Puan Mariatul Liza who is our Building Services 1 lecturer. This site trip is about
Stormwater Management and Road Tunnel (SMART) also known as “Smart Tunnel” in
Malaysia which located in Imbi, Kuala Lumpur. After that, Mr. Mohd Mustaffi briefs us
about the SMART tunnel.
First of all, SMART is actually storm drainage and road structure which consist of
two component which helps to solve problem of flash floods in Kuala Lumpur and also
reduce traffic jams along Jalan Sungai Besi and Loke Yew flyover at Pudu during rush
hour. SMART is 9.7km long stormwater bypass tunnel
This consists of two components which is stormwater tunnel and motorway
tunnel. Stormwater tunnel consists of 13.2m (43.3ft) of outer diameter and 9.7km long
which begins at Kampung Berembang Lake near Klang River at Ampang and ends at
Taman Desa Lake near Kerayong River at Salak South. Motorway tunnel consists of
double deck structure with 4km long which route from the Southern Gateway of
KualaLumpur–Seremban Highway, Federal Highway and East-West Link entering the
city centre.
The SMART tunnel works in three modes. The first mode which is under normal
conditions where there is no storm or flood water will be diverted into the system. When
the second mode is activated, flood water in lower channel of motorway tunnel will
divert into the bypass tunnel. In this case the motorway section still open to traffic.
When the third mode is in operation, the motorway will be closed to all traffic. After
making sure that all vehicles have exited the motorway, automated water-tight gates will
be opened to allow flood waters to pass through. The motorway will be reopened to
traffic within 48 hours of closure after the maintenance.
Not only that, SMART tunnel also have additional features that are unique over
and above the features seen in a normal motorway tunnel. Automated flood control
gates are used as water tight gates are installed on either ends of the motorway tunnel
within the stormwater section. Similar single flood control steel gates are installed at
both entrances and exits of the motorway tunnel. Cross passage are used between
decks at 250m intervals which act as emergency exits during emergency. Ventilation
and escape shafts are located at 1km intervals which consist of powerful air ventilators
that will constantly renew the air and maintain the air quality within the motorway. Radio
re-broadcasting services available as can receive radio channel, handphone and other
maintenance communication reception without any interference. SCADA monitoring and
surveillance as 212 units of Closed Circuit Television (CCTV), BARCO wall is able to
show 70 CCTV’s screen at one time and automatic detection systems use video image
and laser beams processing to detect unusual events. First responder vehicle (FRV)
which is a custom built fire engine which could shorten mobilization time from a Fire and
Rescue Department. Medical Response Vehicle (MRV) which is a custom built
ambulance which is capable in emergency treatment.
Throughout this visit to SMART tunnel, we gained more knowledge about
stormwater management in Malaysia. We also get to know how a SMART tunnel’s
function in traffic and stormwater management.
Photo and Description

Figure 1: SMART Tunnel Coverage Area

Figure 2: Entry and Exit Points of SMART tunnel
Figure 3: A small model of SMART tunnel

Figure 4: Sectional view of the small model SMART tunnel

Figure 4: Flood operation system in SMART tunnel
Figure 5: Motorway control system

Figure 6: Accident happen in SMART tunnel

Figure 7: Group photo taken after the SMART tunnel visit

More Related Content

What's hot

Building services 2 assignment
Building services 2 assignmentBuilding services 2 assignment
Building services 2 assignment
Shao Xun Sean Thun
 
10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list
Jeanne Hoo
 
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
Aaditya Kashyap
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
Al Hakam Khan
 
Metro presentation
Metro presentationMetro presentation
Metro presentation
Anshuman Tyagi
 
Private Financial Initiative
Private Financial InitiativePrivate Financial Initiative
Private Financial Initiative
Aiman Ismail
 
KLPAC Building Service Report
KLPAC Building Service ReportKLPAC Building Service Report
KLPAC Building Service Report
Yvonne Chin
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
Building Services Project 1 - Summit Mall
Building Services Project 1 - Summit MallBuilding Services Project 1 - Summit Mall
Building Services Project 1 - Summit Mall
Ah Jun
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
Joseph Jincy
 
Building Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah AlamBuilding Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah Alam
Lee Pei Gie
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
hari priya somishetty
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case Study
Bolin Loong
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
Adib Ramli
 
Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)
Shubham Bhargava Slideshares
 
Housing Policies in Malaysia
Housing Policies in Malaysia Housing Policies in Malaysia
Housing Policies in Malaysia
Dhanya Pravin
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
Fakhrul Afifi
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
Adiirfan Che-ani
 

What's hot (20)

Building services 2 assignment
Building services 2 assignmentBuilding services 2 assignment
Building services 2 assignment
 
10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list10) int floor-finishes-1-query-list
10) int floor-finishes-1-query-list
 
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
SUMMER INTERNSHIP REPORT ON NMRC (Noida Metro Rail Corporation Limited) by AA...
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
Metro presentation
Metro presentationMetro presentation
Metro presentation
 
Private Financial Initiative
Private Financial InitiativePrivate Financial Initiative
Private Financial Initiative
 
KLPAC Building Service Report
KLPAC Building Service ReportKLPAC Building Service Report
KLPAC Building Service Report
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Building Services Project 1 - Summit Mall
Building Services Project 1 - Summit MallBuilding Services Project 1 - Summit Mall
Building Services Project 1 - Summit Mall
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Building Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah AlamBuilding Services System in PKNS Complex, Shah Alam
Building Services System in PKNS Complex, Shah Alam
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case Study
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)Delhi metro internship Report (05.05.2018 04.06.2018)
Delhi metro internship Report (05.05.2018 04.06.2018)
 
Housing Policies in Malaysia
Housing Policies in Malaysia Housing Policies in Malaysia
Housing Policies in Malaysia
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 

Viewers also liked

St.kitts tunnel - project references
St.kitts tunnel - project referencesSt.kitts tunnel - project references
St.kitts tunnel - project references
Agata Woźniak
 
Report on study of socail impact due to tunnel construction at sundarijal ou...
Report on study of socail impact due to tunnel construction at sundarijal  ou...Report on study of socail impact due to tunnel construction at sundarijal  ou...
Report on study of socail impact due to tunnel construction at sundarijal ou...
shekharkc
 
Tunnel Project
Tunnel ProjectTunnel Project
Tunnel Project
Briece Newton
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
VISHAL KUMAR SINGH
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
Hitesh Khanna
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
jagadish chintu
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
Adil Shaikh
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpointishict
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
mohammadsalikali
 
Tunnelling
TunnellingTunnelling
Tunnelling
Usama Zia
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
Saurabh Samant
 

Viewers also liked (11)

St.kitts tunnel - project references
St.kitts tunnel - project referencesSt.kitts tunnel - project references
St.kitts tunnel - project references
 
Report on study of socail impact due to tunnel construction at sundarijal ou...
Report on study of socail impact due to tunnel construction at sundarijal  ou...Report on study of socail impact due to tunnel construction at sundarijal  ou...
Report on study of socail impact due to tunnel construction at sundarijal ou...
 
Tunnel Project
Tunnel ProjectTunnel Project
Tunnel Project
 
report for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machinereport for tunnelling by tunnel boring machine
report for tunnelling by tunnel boring machine
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
The tunnel powerpoint
The tunnel powerpointThe tunnel powerpoint
The tunnel powerpoint
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 

Similar to SMART tunnel report

Building Services assignment 1
Building Services assignment 1Building Services assignment 1
Building Services assignment 1
seenyee
 
Arts final project(MOBILE BRIDGE PLATFORM)
Arts final project(MOBILE BRIDGE PLATFORM)Arts final project(MOBILE BRIDGE PLATFORM)
Arts final project(MOBILE BRIDGE PLATFORM)
Thanku Anna Baiju
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
saqib fayyaz
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
saqib fayyaz
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
Ajmal Afzal
 
Design engineering 1 a gaurav
Design engineering 1 a gauravDesign engineering 1 a gaurav
Design engineering 1 a gaurav
gaurav chhatbar
 
SMART (Stormwater Management And Road Tunnel) (1).pptx
SMART (Stormwater Management And Road Tunnel) (1).pptxSMART (Stormwater Management And Road Tunnel) (1).pptx
SMART (Stormwater Management And Road Tunnel) (1).pptx
AngChernXing
 
Automatic railway gate using pic 16f877a
Automatic railway gate using pic 16f877aAutomatic railway gate using pic 16f877a
Automatic railway gate using pic 16f877a
vijay kumar yadav
 
IRJET- Storm Water Management and Road Tunnel
IRJET- Storm Water Management and Road TunnelIRJET- Storm Water Management and Road Tunnel
IRJET- Storm Water Management and Road Tunnel
IRJET Journal
 
Sarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training reportSarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training report
GAURAV KUMAR CHAUBEY
 
automatic railway gate control system
automatic railway gate control system automatic railway gate control system
automatic railway gate control system
GManojkumar11
 
railway gate using servo and arduino uno
railway gate using servo and arduino unorailway gate using servo and arduino uno
railway gate using servo and arduino uno
Hamed Raza
 
Automatic railway gate controller AUP
Automatic railway gate controller AUPAutomatic railway gate controller AUP
Automatic railway gate controller AUP
Masoom Khan
 
IRJET- Automatic Footbridge Platform System on Railway Platform
IRJET- Automatic Footbridge Platform System on Railway PlatformIRJET- Automatic Footbridge Platform System on Railway Platform
IRJET- Automatic Footbridge Platform System on Railway Platform
IRJET Journal
 
railway gate using arduino uno and servo motors
railway gate using arduino uno and servo motorsrailway gate using arduino uno and servo motors
railway gate using arduino uno and servo motors
Hamed Raza
 
A Review on
A Review onA Review on
A Review on
ijsrd.com
 
Kolkata underwater metro project VISHAL PPT.pptx
Kolkata underwater metro project VISHAL PPT.pptxKolkata underwater metro project VISHAL PPT.pptx
Kolkata underwater metro project VISHAL PPT.pptx
imsuraj2309
 
Smart railway crossing embedded with automated platform bridge
Smart railway crossing embedded with automated platform bridgeSmart railway crossing embedded with automated platform bridge
Smart railway crossing embedded with automated platform bridge
eSAT Journals
 
AUTOMATIC RAILWAY GATE CONTROL SYSTEM
AUTOMATIC RAILWAY GATE CONTROL SYSTEMAUTOMATIC RAILWAY GATE CONTROL SYSTEM
AUTOMATIC RAILWAY GATE CONTROL SYSTEM
JOLLUSUDARSHANREDDY
 
IRJET-Solar Operated Automatic Railway Gate Control
IRJET-Solar Operated Automatic Railway Gate ControlIRJET-Solar Operated Automatic Railway Gate Control
IRJET-Solar Operated Automatic Railway Gate Control
IRJET Journal
 

Similar to SMART tunnel report (20)

Building Services assignment 1
Building Services assignment 1Building Services assignment 1
Building Services assignment 1
 
Arts final project(MOBILE BRIDGE PLATFORM)
Arts final project(MOBILE BRIDGE PLATFORM)Arts final project(MOBILE BRIDGE PLATFORM)
Arts final project(MOBILE BRIDGE PLATFORM)
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
Design engineering 1 a gaurav
Design engineering 1 a gauravDesign engineering 1 a gaurav
Design engineering 1 a gaurav
 
SMART (Stormwater Management And Road Tunnel) (1).pptx
SMART (Stormwater Management And Road Tunnel) (1).pptxSMART (Stormwater Management And Road Tunnel) (1).pptx
SMART (Stormwater Management And Road Tunnel) (1).pptx
 
Automatic railway gate using pic 16f877a
Automatic railway gate using pic 16f877aAutomatic railway gate using pic 16f877a
Automatic railway gate using pic 16f877a
 
IRJET- Storm Water Management and Road Tunnel
IRJET- Storm Water Management and Road TunnelIRJET- Storm Water Management and Road Tunnel
IRJET- Storm Water Management and Road Tunnel
 
Sarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training reportSarita Vihar Depot, Dmrc summer training report
Sarita Vihar Depot, Dmrc summer training report
 
automatic railway gate control system
automatic railway gate control system automatic railway gate control system
automatic railway gate control system
 
railway gate using servo and arduino uno
railway gate using servo and arduino unorailway gate using servo and arduino uno
railway gate using servo and arduino uno
 
Automatic railway gate controller AUP
Automatic railway gate controller AUPAutomatic railway gate controller AUP
Automatic railway gate controller AUP
 
IRJET- Automatic Footbridge Platform System on Railway Platform
IRJET- Automatic Footbridge Platform System on Railway PlatformIRJET- Automatic Footbridge Platform System on Railway Platform
IRJET- Automatic Footbridge Platform System on Railway Platform
 
railway gate using arduino uno and servo motors
railway gate using arduino uno and servo motorsrailway gate using arduino uno and servo motors
railway gate using arduino uno and servo motors
 
A Review on
A Review onA Review on
A Review on
 
Kolkata underwater metro project VISHAL PPT.pptx
Kolkata underwater metro project VISHAL PPT.pptxKolkata underwater metro project VISHAL PPT.pptx
Kolkata underwater metro project VISHAL PPT.pptx
 
Smart railway crossing embedded with automated platform bridge
Smart railway crossing embedded with automated platform bridgeSmart railway crossing embedded with automated platform bridge
Smart railway crossing embedded with automated platform bridge
 
AUTOMATIC RAILWAY GATE CONTROL SYSTEM
AUTOMATIC RAILWAY GATE CONTROL SYSTEMAUTOMATIC RAILWAY GATE CONTROL SYSTEM
AUTOMATIC RAILWAY GATE CONTROL SYSTEM
 
IRJET-Solar Operated Automatic Railway Gate Control
IRJET-Solar Operated Automatic Railway Gate ControlIRJET-Solar Operated Automatic Railway Gate Control
IRJET-Solar Operated Automatic Railway Gate Control
 

More from Yap Xin

Building services report subang parade
Building services report  subang paradeBuilding services report  subang parade
Building services report subang parade
Yap Xin
 
Building services presentation subang parade
Building services presentation subang paradeBuilding services presentation subang parade
Building services presentation subang parade
Yap Xin
 
Compile version communication in consruction
Compile version communication in consructionCompile version communication in consruction
Compile version communication in consruction
Yap Xin
 
Site Surveying Fieldwork 2
Site Surveying Fieldwork 2Site Surveying Fieldwork 2
Site Surveying Fieldwork 2
Yap Xin
 
BS Stormwater management assignment
BS Stormwater management assignmentBS Stormwater management assignment
BS Stormwater management assignment
Yap Xin
 
Site Surveying Fieldwork 1
Site Surveying Fieldwork 1Site Surveying Fieldwork 1
Site Surveying Fieldwork 1
Yap Xin
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
Yap Xin
 
CT Part 2
CT Part 2CT Part 2
CT Part 2
Yap Xin
 
Rubber presentation slide
Rubber presentation slideRubber presentation slide
Rubber presentation slide
Yap Xin
 
CT Presentation (KLCC)
CT Presentation (KLCC)CT Presentation (KLCC)
CT Presentation (KLCC)
Yap Xin
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
Yap Xin
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
Yap Xin
 
Site research report bm (steel) corrected
Site research report bm (steel) correctedSite research report bm (steel) corrected
Site research report bm (steel) corrected
Yap Xin
 

More from Yap Xin (13)

Building services report subang parade
Building services report  subang paradeBuilding services report  subang parade
Building services report subang parade
 
Building services presentation subang parade
Building services presentation subang paradeBuilding services presentation subang parade
Building services presentation subang parade
 
Compile version communication in consruction
Compile version communication in consructionCompile version communication in consruction
Compile version communication in consruction
 
Site Surveying Fieldwork 2
Site Surveying Fieldwork 2Site Surveying Fieldwork 2
Site Surveying Fieldwork 2
 
BS Stormwater management assignment
BS Stormwater management assignmentBS Stormwater management assignment
BS Stormwater management assignment
 
Site Surveying Fieldwork 1
Site Surveying Fieldwork 1Site Surveying Fieldwork 1
Site Surveying Fieldwork 1
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
CT Part 2
CT Part 2CT Part 2
CT Part 2
 
Rubber presentation slide
Rubber presentation slideRubber presentation slide
Rubber presentation slide
 
CT Presentation (KLCC)
CT Presentation (KLCC)CT Presentation (KLCC)
CT Presentation (KLCC)
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
 
Site research report bm (steel) corrected
Site research report bm (steel) correctedSite research report bm (steel) corrected
Site research report bm (steel) corrected
 

Recently uploaded

JavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green MasterplanJavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green Masterplan
Miro Wengner
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
Zilliz
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
saastr
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
saastr
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
Chart Kalyan
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
Jason Packer
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
Zilliz
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
ScyllaDB
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Alpen-Adria-Universität
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
Dinusha Kumarasiri
 
SAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloudSAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloud
maazsz111
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
HarisZaheer8
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Tatiana Kojar
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Precisely
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
Data Hops
 
A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
Intelisync
 

Recently uploaded (20)

JavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green MasterplanJavaLand 2024: Application Development Green Masterplan
JavaLand 2024: Application Development Green Masterplan
 
Fueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte WebinarFueling AI with Great Data with Airbyte Webinar
Fueling AI with Great Data with Airbyte Webinar
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
Overcoming the PLG Trap: Lessons from Canva's Head of Sales & Head of EMEA Da...
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdfHow to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
How to Interpret Trends in the Kalyan Rajdhani Mix Chart.pdf
 
Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024Columbus Data & Analytics Wednesdays - June 2024
Columbus Data & Analytics Wednesdays - June 2024
 
Generating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and MilvusGenerating privacy-protected synthetic data using Secludy and Milvus
Generating privacy-protected synthetic data using Secludy and Milvus
 
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-EfficiencyFreshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
Freshworks Rethinks NoSQL for Rapid Scaling & Cost-Efficiency
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
 
Azure API Management to expose backend services securely
Azure API Management to expose backend services securelyAzure API Management to expose backend services securely
Azure API Management to expose backend services securely
 
SAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloudSAP S/4 HANA sourcing and procurement to Public cloud
SAP S/4 HANA sourcing and procurement to Public cloud
 
AWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptxAWS Cloud Cost Optimization Presentation.pptx
AWS Cloud Cost Optimization Presentation.pptx
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
Skybuffer AI: Advanced Conversational and Generative AI Solution on SAP Busin...
 
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their MainframeDigital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
Digital Banking in the Cloud: How Citizens Bank Unlocked Their Mainframe
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3FREE A4 Cyber Security Awareness  Posters-Social Engineering part 3
FREE A4 Cyber Security Awareness Posters-Social Engineering part 3
 
A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024A Comprehensive Guide to DeFi Development Services in 2024
A Comprehensive Guide to DeFi Development Services in 2024
 

SMART tunnel report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) QSB1714 – Building Services 1 Site Research Reports (Smart Tunnel) Name: YAP ZHI XIN Student No.: 0314542
  • 2. Smart Tunnel Report Introduction The site visit is held on the Thursday of 10th of October 2013 which organized by Puan Mariatul Liza who is our Building Services 1 lecturer. This site trip is about Stormwater Management and Road Tunnel (SMART) also known as “Smart Tunnel” in Malaysia which located in Imbi, Kuala Lumpur. After that, Mr. Mohd Mustaffi briefs us about the SMART tunnel. First of all, SMART is actually storm drainage and road structure which consist of two component which helps to solve problem of flash floods in Kuala Lumpur and also reduce traffic jams along Jalan Sungai Besi and Loke Yew flyover at Pudu during rush hour. SMART is 9.7km long stormwater bypass tunnel This consists of two components which is stormwater tunnel and motorway tunnel. Stormwater tunnel consists of 13.2m (43.3ft) of outer diameter and 9.7km long which begins at Kampung Berembang Lake near Klang River at Ampang and ends at Taman Desa Lake near Kerayong River at Salak South. Motorway tunnel consists of double deck structure with 4km long which route from the Southern Gateway of KualaLumpur–Seremban Highway, Federal Highway and East-West Link entering the city centre. The SMART tunnel works in three modes. The first mode which is under normal conditions where there is no storm or flood water will be diverted into the system. When the second mode is activated, flood water in lower channel of motorway tunnel will divert into the bypass tunnel. In this case the motorway section still open to traffic. When the third mode is in operation, the motorway will be closed to all traffic. After making sure that all vehicles have exited the motorway, automated water-tight gates will be opened to allow flood waters to pass through. The motorway will be reopened to traffic within 48 hours of closure after the maintenance. Not only that, SMART tunnel also have additional features that are unique over and above the features seen in a normal motorway tunnel. Automated flood control gates are used as water tight gates are installed on either ends of the motorway tunnel within the stormwater section. Similar single flood control steel gates are installed at both entrances and exits of the motorway tunnel. Cross passage are used between decks at 250m intervals which act as emergency exits during emergency. Ventilation and escape shafts are located at 1km intervals which consist of powerful air ventilators that will constantly renew the air and maintain the air quality within the motorway. Radio re-broadcasting services available as can receive radio channel, handphone and other
  • 3. maintenance communication reception without any interference. SCADA monitoring and surveillance as 212 units of Closed Circuit Television (CCTV), BARCO wall is able to show 70 CCTV’s screen at one time and automatic detection systems use video image and laser beams processing to detect unusual events. First responder vehicle (FRV) which is a custom built fire engine which could shorten mobilization time from a Fire and Rescue Department. Medical Response Vehicle (MRV) which is a custom built ambulance which is capable in emergency treatment. Throughout this visit to SMART tunnel, we gained more knowledge about stormwater management in Malaysia. We also get to know how a SMART tunnel’s function in traffic and stormwater management.
  • 4. Photo and Description Figure 1: SMART Tunnel Coverage Area Figure 2: Entry and Exit Points of SMART tunnel
  • 5. Figure 3: A small model of SMART tunnel Figure 4: Sectional view of the small model SMART tunnel Figure 4: Flood operation system in SMART tunnel
  • 6. Figure 5: Motorway control system Figure 6: Accident happen in SMART tunnel Figure 7: Group photo taken after the SMART tunnel visit