QUERY SHEET
JOB
TITLE : INTERNAL AND EXTERNAL FLOOR FINISHES
Q/S NO. : PAGE NO. : 5
TO : FAX NO. :
ATTN. :
NO. OF PAGES (Incl.this
page) :
FROM
: Chiam
Jia E rn
Please provide answer(s) to the following queries by _____________
DATE :
20/6/2015
Item Query Assumptions Answer
1
2
3
4
5
6
7
8
9
10
11
12
13
What is the thickness of ceramic floor tiles?
What is the degree of the ramp of the
handicapped toilet?
What is the door size of handicapped toilet?
Is there any skirting to timber flooring?
Is there any skirting to stage?
What is the size of the staircase?
What is the finishes of stage?
What is the finishes of stage?
What is the grade of timber skirting?
What is the thickness of internal wall?
All dimensions on the plan are measured from
center to center?
What is the entrance door of female and male
toilet?
Is there any drop to left side entrance door?
300mmx300mm x 9mm thick.
Assumed that the ramp is not
exceeding 15 °.
1000mm x 2100mm high.
Yes, 12mm x 100mm high timber
skirting.
Yes, 12mm x100mm high timber
skirting.
900mm x 1000mm high.
Timber flooring.
750mm x 210mmhigh.
Grade B.
115m thick.
Yes, assumed that all the dimensions
are measured from center to center.
Ceramic tiles.
Yes, have 100mm vertical drop.
Prepared by Chiam Jia Ern

More Related Content

What's hot

ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA FormKai Yun Pang
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof coveringEst
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Eca presentation
Eca presentationEca presentation
Eca presentationKailyn Lee
 
M3 EG BQ steel struture
M3 EG BQ steel strutureM3 EG BQ steel struture
M3 EG BQ steel strutureEst
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Measuremeent 2 Assignment
Measuremeent 2 AssignmentMeasuremeent 2 Assignment
Measuremeent 2 AssignmentPang Shuen
 
M3 EG BQ metal frame door
M3 EG BQ metal frame doorM3 EG BQ metal frame door
M3 EG BQ metal frame doorEst
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?Duc Tran Xuan
 
M3 EG BQ timber windows
M3 EG BQ timber windowsM3 EG BQ timber windows
M3 EG BQ timber windowsEst
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bqJeanne Hoo
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows마 이환
 

What's hot (20)

ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
 
ECA form
ECA formECA form
ECA form
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof covering
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
M3 EG BQ steel struture
M3 EG BQ steel strutureM3 EG BQ steel struture
M3 EG BQ steel struture
 
BS Role
BS RoleBS Role
BS Role
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Measuremeent 2 Assignment
Measuremeent 2 AssignmentMeasuremeent 2 Assignment
Measuremeent 2 Assignment
 
M3 EG BQ metal frame door
M3 EG BQ metal frame doorM3 EG BQ metal frame door
M3 EG BQ metal frame door
 
Construction process
Construction processConstruction process
Construction process
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?
 
M3 EG BQ timber windows
M3 EG BQ timber windowsM3 EG BQ timber windows
M3 EG BQ timber windows
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bq
 
Measurement III:Doors & Windows
Measurement III:Doors & WindowsMeasurement III:Doors & Windows
Measurement III:Doors & Windows
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 

Viewers also liked

My presentation slide of Retaining Wall,Cofferdam and Caisson
My presentation slide of Retaining Wall,Cofferdam and CaissonMy presentation slide of Retaining Wall,Cofferdam and Caisson
My presentation slide of Retaining Wall,Cofferdam and Caissonm8main
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and CaissonsRizwan Samor
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewateringShubham Parab
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 

Viewers also liked (15)

My presentation slide of Retaining Wall,Cofferdam and Caisson
My presentation slide of Retaining Wall,Cofferdam and CaissonMy presentation slide of Retaining Wall,Cofferdam and Caisson
My presentation slide of Retaining Wall,Cofferdam and Caisson
 
Soil mechanics
Soil mechanicsSoil mechanics
Soil mechanics
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Types of conract
Types of conractTypes of conract
Types of conract
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Tender
TenderTender
Tender
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

More from Jeanne Hoo

Financial Management - Financial Ratio Formula
Financial Management - Financial Ratio FormulaFinancial Management - Financial Ratio Formula
Financial Management - Financial Ratio FormulaJeanne Hoo
 
Introduction to law assignment
Introduction to law assignmentIntroduction to law assignment
Introduction to law assignmentJeanne Hoo
 
Management Science
Management Science Management Science
Management Science Jeanne Hoo
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2 Jeanne Hoo
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2 Jeanne Hoo
 
Measurement 2 assignment cover pages
Measurement 2 assignment cover pagesMeasurement 2 assignment cover pages
Measurement 2 assignment cover pagesJeanne Hoo
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list Jeanne Hoo
 
Int walls element to list
Int walls element   to listInt walls element   to list
Int walls element to listJeanne Hoo
 
Ext walls-to-list
Ext walls-to-listExt walls-to-list
Ext walls-to-listJeanne Hoo
 
Ext wall-finishes-1-to
Ext wall-finishes-1-toExt wall-finishes-1-to
Ext wall-finishes-1-toJeanne Hoo
 
7) ext wall-finishes-1-bq
7) ext wall-finishes-1-bq7) ext wall-finishes-1-bq
7) ext wall-finishes-1-bqJeanne Hoo
 
6) int walls finishes query
6) int walls finishes query6) int walls finishes query
6) int walls finishes queryJeanne Hoo
 
4) ext walls-element-revised-query
4) ext walls-element-revised-query4) ext walls-element-revised-query
4) ext walls-element-revised-queryJeanne Hoo
 
3) ext walls-bq
3) ext walls-bq3) ext walls-bq
3) ext walls-bqJeanne Hoo
 
1) int walls element bq
1) int walls element   bq1) int walls element   bq
1) int walls element bqJeanne Hoo
 
Building services-power-point
Building services-power-pointBuilding services-power-point
Building services-power-pointJeanne Hoo
 

More from Jeanne Hoo (16)

Financial Management - Financial Ratio Formula
Financial Management - Financial Ratio FormulaFinancial Management - Financial Ratio Formula
Financial Management - Financial Ratio Formula
 
Introduction to law assignment
Introduction to law assignmentIntroduction to law assignment
Introduction to law assignment
 
Management Science
Management Science Management Science
Management Science
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2
 
Building Services 2
Building Services 2 Building Services 2
Building Services 2
 
Measurement 2 assignment cover pages
Measurement 2 assignment cover pagesMeasurement 2 assignment cover pages
Measurement 2 assignment cover pages
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list
 
Int walls element to list
Int walls element   to listInt walls element   to list
Int walls element to list
 
Ext walls-to-list
Ext walls-to-listExt walls-to-list
Ext walls-to-list
 
Ext wall-finishes-1-to
Ext wall-finishes-1-toExt wall-finishes-1-to
Ext wall-finishes-1-to
 
7) ext wall-finishes-1-bq
7) ext wall-finishes-1-bq7) ext wall-finishes-1-bq
7) ext wall-finishes-1-bq
 
6) int walls finishes query
6) int walls finishes query6) int walls finishes query
6) int walls finishes query
 
4) ext walls-element-revised-query
4) ext walls-element-revised-query4) ext walls-element-revised-query
4) ext walls-element-revised-query
 
3) ext walls-bq
3) ext walls-bq3) ext walls-bq
3) ext walls-bq
 
1) int walls element bq
1) int walls element   bq1) int walls element   bq
1) int walls element bq
 
Building services-power-point
Building services-power-pointBuilding services-power-point
Building services-power-point
 

10) int floor-finishes-1-query-list

  • 1. QUERY SHEET JOB TITLE : INTERNAL AND EXTERNAL FLOOR FINISHES Q/S NO. : PAGE NO. : 5 TO : FAX NO. : ATTN. : NO. OF PAGES (Incl.this page) : FROM : Chiam Jia E rn Please provide answer(s) to the following queries by _____________ DATE : 20/6/2015 Item Query Assumptions Answer 1 2 3 4 5 6 7 8 9 10 11 12 13 What is the thickness of ceramic floor tiles? What is the degree of the ramp of the handicapped toilet? What is the door size of handicapped toilet? Is there any skirting to timber flooring? Is there any skirting to stage? What is the size of the staircase? What is the finishes of stage? What is the finishes of stage? What is the grade of timber skirting? What is the thickness of internal wall? All dimensions on the plan are measured from center to center? What is the entrance door of female and male toilet? Is there any drop to left side entrance door? 300mmx300mm x 9mm thick. Assumed that the ramp is not exceeding 15 °. 1000mm x 2100mm high. Yes, 12mm x 100mm high timber skirting. Yes, 12mm x100mm high timber skirting. 900mm x 1000mm high. Timber flooring. 750mm x 210mmhigh. Grade B. 115m thick. Yes, assumed that all the dimensions are measured from center to center. Ceramic tiles. Yes, have 100mm vertical drop.