Call Girls Bapu Nagar 7397865700 Ridhima Hire Me Full Night
404128086-mivan-ppt-0-pptx.pptx.................
1. 1
Submitted By:
Akash Suresh K
4VP14CV402
8th Sem Civil Engg.
VCET Puttur.
Guided By:
Prof. Divya Swaroopa
Asst Professor
Dept. of Civil Engg.
VCET Puttur.
2. Introduction
Uses of Mivan Formwork
Advantages and limitations of Mivan formwork
Comparison of Mivan formwork with Conventional formwork
Working cycle of Mivan formwork
Case study
Summary
Reference
2
CONTENTS
3. Mivan technology is a fast-paced construction
technique by using aluminium formworks.
Mivan is an aluminum formwork system
developed by a European construction company.
In 1990, the Mivan Company Ltd. from
Malaysia started manufacturing these formwork
systems.
To facilitate fast construction, early removal
of forms.
3
INTRODUCTION
Mivan Formwork
4. 4
3S – System of Construction – Speed, Strength, Safety.
Column and beam construction are eliminated.
Walls and slabs are cast in one operation.
Specially designed, easy to handle light weight pre-engineered aluminium
forms.
Fitting and erecting the portion of shuttering.
Carrying out concreting of the walls and slabs together.
USES OF MIVAN FORMWORK
5. Fast construction is assured and is particularly suitable for large magnitude
construction of respective nature at one project site.
Construction carried out by this system has exceptionally good quality with accurate
dimensions for all openings i.e., doors & windows.
.Concrete surface finishes are good to receive painting directly without plaster.
System components are durable and can be used several times without sacrificing the
quality or correctness of dimensions and surface.
As all the walls are cast monolithic and simultaneously with floor slabs requiring no
further plasters finish. Therefore the time required in the conventional method for
construction of walls and plastering is saved. 5
ADVANTAGES OF MIVAN FORMWORK
6. It requires uniform planning as well as uniform elevations to be cost effective.
Due to box-type construction, contraction cracks are likely to appear.
Heat of hydration is high due to shear walls.
It is rigid in design once placed, as any alteration becomes tough later.
The formwork requires number of spacer, wall ties etc. which are placed @ 2ft c/c;
these produce problems such as seepage, leakages during monsoon.
Services after completing become slightly difficult.
6
LIMITATIONS OF MIVAN FORMWORK
7. 7
COMPARSION OF MIVAN FORMWORK WITH
CONVENTIONAL FORMWORK
SL
NO
CHARACTERISTICS MIVAN
FORMWORK
CONVENTIONAL
FORMWORK
1. Speed of construction Four days cycle per
floor
Ten days cycle per
floor
2. Quality of surface finish Excellent plastering is
not required
Plastering is required
3. Pre-planning of formwork system Required Not required
4. Wastage of formwork material Very less In great amount
5. Accuracy in construction Accurate construction Less than Aluminium
formwork
6. Resistance to earthquake Good resistance Less than Aluminium
formwork
8. 8
WORKING CYCLE OF MIVAN FORMWORK
Positioning of brackets & platforms
Lifting & fixing of panels
Fixing kicker & external shutters
Erection of wall
Pouring concrete
Setting up the wall reinforcement
Dismantling
9. COST COMPARISON OF MIVAN TECHOLOGY WITH COVENTIONAL
CONSTRUCTION TECHNOLOGY
Study site: Blue Ridge Tower HA-1, Pune.
It is a part of Paranjpe scheme’s “Blue Ridge” a 138 acre integrated township Hinjewadi
, Pune. They had acquired the data of Tower HA-1 (25 Floors).
9
CASE STUDY 1
“Blue Ridge” Tower HA-1 Hinjewadi, Pune.
10. 10
DETAILS ABOUT THE STRUCTURE:
1. Grade of concrete M 35
2. Slump 180 -200mm
3. Wall thickness External wall : 200mm
Internal wall : 100 mm
4. Steel Partition wall : 10mm dia
Structural : 12mm dia
Shear wall : 16mm dia
5. Slab thickness Hall : 175mm
Bed room : 150mm
Kitchen : 125mm
6. Finishing External : Textural paint
Internal : Paint over gypsum
7. Number of floors 25 floors
8. Area 3 BHK : 184 Sq.m
2 BHK : 125.4 Sq.m
11. 11
COST COMPARSION:
Sl
no
Parameter Cost by conventional
technology
Cost by Mivan
technology
Cost saving
1. Shuttering after
repitation
Wooden materials =
Rs.88.50/sq.m
M.S. materials=Rs.100/sq.m
Rs.83.8/sq.m Rs.104.63/sq.m
2. Concreting Rs.1400/sq.m Rs.1505/sq.m Rs.105/sq.m
3. Reinforcement 1,480.00 2,115.20 Rs.635.2/sq.m
4. Brickwork 484.00 0.00 Rs.480/sq.m
5. Plaster 700.00 0.00 Rs.700/sq.m
Total cost saving = RS.548.43/sq.m
12. It’s well known that the Mivan Technology reduces the cost of construction from
above analysis, hence the technology is useful to the construction company and
builder.
MIVAN formwork played a vital role in the construction of the project. The project
was completed not only on stipulated period of time but also paid off with its
attributes. Speedy & quality dwelling units were provided to the people of low
income groups at very reasonable costs. MIVAN is a definitely future of this ever
growing construction industry with lots of project still awaiting its touch of
excellence.
12
CONCULSION OF CASESTUDY
13. Civil engineers not only build but also enhance the quality of life. Their creativity and
technical skill help to plan, design, construct and operate the facilities essential to life.
It is important for civil engineers to gain and harness the potent and versatile
construction tools.
MIVAN serves as a cost effective and efficient tool to solve the problems of the mega
housing project all over the world. MIVAN aims to maximize the use of modern
construction techniques and equipments on its entire project.
Thus it can be concluded that quality and speed must be given due consideration with
regards to economy. Good quality construction will never deter to projects speed nor
will it be uneconomical.
13
SUMMARY
14. 14
REFERENCES
Ketan Shah., (2005),“Modular formwork for faster, economical and quality
Construction”, Indian Concrete Journal, Vol-79, pg. 6-23.
Kushal Patil., Ajitkumar Jadhav., Nikhil Shingat.,(2015),“Mivan Technology”,
International Journal of Engineering and Technical Research (IJETR) ISSN: 2321-0869,
Volume-3, Issue-6.
Mr. Shankar Bimal Banerjee., Mr. Pawan Dilip Barhate., Mr. Vipul Pradip Jaiswal.,
(2015),“Mivan Technology”, Novateu Publications International Journals Of Innovation In
Engineering Research And Technology [IJIERT], Volume 2, Issue 3.
Patil R.S., Pawale D.B., Tambe H. D. and Pawar P.D., Wakchuare A.V., (2016),“Mivan
Technology Using Aluminium Formwork”, International Journals Of Engineering
Sciences & Management, ISSN 2277 – 5528, Impact Factor- 3.145.