Mivan Technology
TEJAS C.PATIL
Introduction
• It is the information about AdvanceTechnologies In Building
Construction.
• The construction industry is rapidly changing.With-changing
times, new processes and the materials are being used.
• A lot of research and development is carried out in the
construction industry throughout the globe
• Time, economy and utility of space have become the
important aspects of the construction industry.
MIVAN
(Aluminum Formwork)
• FORMWORK :-
Formwork is the temporary moulds or shutters in
which concrete is placed, so that it will have desired shape or
outline when hardened.This temporary casing is known as
Formwork or Shuttering.
.
History of MIVAN
Mivan is an aluminum formwork system developed by a European
construction company. In 1990, the Mivan Company Ltd. from Malaysia
started manufacturing these formwork systems.Today, more than
30,000sqm of formwork from Mivan Co. Ltd. is used across the world.
There are a number of buildings in Mumbai that are being constructed
with the help of the Mivan system, that has proven economical as well
as satisfactory for the overall Indian construction environment. Mivan
technology is suitable for constructing large number of houses in a
short span of time using room size forms to construct walls and slabs in
one continuous pour on concrete. In this system of formwork
construction, cast–in–situ concrete wall and floor slabs cast monolithic
provides the structural system in one continuous pour. On the removal
of the formwork mold a high quality concrete finish is produced to
accurate tolerances and verticality.The high tolerance of the finish
means that, no further plastering is required.
Uses of Mivan Formwork
• 3S – System of Construction – Speed, Strength, Safety.
• Column and beam construction are eliminated.
• Walls and slabs are cast in one operation.
• Specially designed, easy to handle light weight pre-engineered
aluminum forms.
• Fitting and erecting the portion of shuttering.
• Carrying out concreting of the walls and slabs together.
Advantages of Mivan formwork over
conventional construction
• More seismic resistance: -The box type construction provides more seismic
resistance to the structure.
• Increased durability: -The durability of a complete concrete structure is more
than conventional brick bat masonry.
• Lesser number of joints thereby reducing the leakages and enhancing the
durability.
• Higher carpet area- Due to shear walls the walls are thin thus increasing area.
• Integral and smooth finishing of wall and slab- Smooth finish of aluminum can be
seen vividly on walls.
• Uniform quality of construction – Uniform grade of concrete is
used.
• Negligible maintenance – Strong built up of concrete needs no
maintenance.
• Faster completion – Unsurpassed construction speed can be
achieved due to light weight of forms.
• Lesser manual labour- Less labour is required for carrying
formworks.
• Simplified foundation design due to consistent load distribution.
• The natural density of concrete wall result in better sound
transmission coefficient.
Limitations Of Mivan• Because of small sizes finishing lines are seen on the concrete
surfaces.
• Concealed services become difficult due to small thickness of
components.
• It requires uniform planning as well as uniform elevations to
be cost effective.
• Modifications are not possible as all members are caste in
RCC.
• The formwork requires number of spacer, wall ties etc. which
are create problems such as seepage, leakages during
monsoon.
• Due to box-type construction shrinkage cracks are likely to
appear.
• Heat of Hydration is high due to shear walls.
METHODAND SYSTEMOF CONSTRUCTIONBY MIVAN
FORMWORK
INTRODUCTION
• MIVAN is the brand name from Mivan Far East,
Malaysia. It is Aluminum alloy Form work The
Aluminum formwork system for concreting is
probably the most versatile modern construction
system. Unlike other systems it is equally suited
to both high and low rise construction specifically
designed to allow the rapid construction of
multiple unit projects at optimum productivity.
WALL PANEL:TheWall Panel forms the face of the wall from
the top of the Rocker to the underside of theTop Panel.
ROCKER: The Rocker forms the wall face at the bottom of the wall panels and
helps to facilitate striking.
KICKER:The kicker forms the wall Face at the top of theTop
Panels. It is anchored to the concrete and acts as a ledge for
theWall panels on the next floor to sit on.
BEAM SOFFIT BULKHEAD: The Beam Soffit Bulkhead is used to
form the soffit of the beam. It is used for beams less than 300mm.
DECK COMPONENT: The deck panel rests between pairs of
mid-beams and provides a horizontal surface for casting the
slabs and provides a horizontal surface for casting the slabs.
INTERNAL SOFFIT CORNER: The Internal Soffit Corner forms
the vertical corner between walls and / or beam faces and
horizontal internal corners between wall / beam face and soffit
of slabs.
INTERNAL CORNER:
The Internal Corner connects
2 pieces of vertical formwork
together of their internal
intersection.
PROP LENGTH:
The prop length is
manufactured to a
specific length for each
project. It transmits load
to the previous slab.
PANEL PULLER: It is required for removing panels after concreting of wall.
TIE PULLER: It is required for removing wallTies after de shuttering of panels.
BEAM – BAR:
These are used in pairs to
fix the Mid Beam and End
Beams to the deck prop.
The beam_ Bar is removed
when the slab is cast to
allow quick striking of the
deck form work.
CASE STUDY
• Project Name - Amanora ParkTown.
• Location - Hadapsar,Pune.
• Size Of Project - 78,000 m2.
• Project Cost - Rs. 650 million.
• Client - City Development Corp.
• Consultant - P &T, J &W Consultant.
• Cycle - 11 days per floor.
• Storey - 22 Storey.
• System Of Formwork- 6000 sq.mt.
• Year Of Completion - On Going.
CONCLUSION
The task of housing due to the rising population of the country is becoming
increasingly monumental. In terms of technical capabilities to face this
challenge, the potential is enormous; it only needs to be judiciously exploited.
Traditionally, construction firms all over the world have been slow to adopt the
innovation and changes. Contractors are a conservative lot. It is the need of
time to analyze the depth of the problem and find effective solutions. Our aim
is to serves as a cost effective and efficient tool to solve the problems of the
mega housing project all over the world. Our aim is to maximize the use of
modern construction techniques and equipments on its entire project. We
have tried to cover each and every aspect related to conventional and
aluminum form construction. We thus infer that aluminum form construction
is able to provide high quality construction at unbelievable speed and at
reasonable cost.This technology has great potential for application in India to
provide affordable housing to its rising population.Thus it can be concluded
that quality and speed must be given due consideration with regards to
economy. Good quality construction will never deter to projects speed nor will
it be uneconomical. In fact time consuming repairs and modification due to
poor quality work generally delay the job and cause additional financial impact
on the project. Some experts feel that housing alternatives with low
maintenance requirements may be preferred even if at the slightly may
preferred even if at the higher initial cost.
FUTURE SCOPES
This thesis work is restricted to only Mivan formwork and
not other type of aluminum formworks.The future
researchers can continue by working over other type of
formworks construction by analyzing activities like brickwork,
plastering, painting and many more. Furthermore interviews
of different people from construction industry can be taken
based on questionnaire prepared and analysis can be done.
Mivan tech

Mivan tech

  • 1.
  • 2.
    Introduction • It isthe information about AdvanceTechnologies In Building Construction. • The construction industry is rapidly changing.With-changing times, new processes and the materials are being used. • A lot of research and development is carried out in the construction industry throughout the globe • Time, economy and utility of space have become the important aspects of the construction industry.
  • 3.
    MIVAN (Aluminum Formwork) • FORMWORK:- Formwork is the temporary moulds or shutters in which concrete is placed, so that it will have desired shape or outline when hardened.This temporary casing is known as Formwork or Shuttering. .
  • 4.
    History of MIVAN Mivanis an aluminum formwork system developed by a European construction company. In 1990, the Mivan Company Ltd. from Malaysia started manufacturing these formwork systems.Today, more than 30,000sqm of formwork from Mivan Co. Ltd. is used across the world. There are a number of buildings in Mumbai that are being constructed with the help of the Mivan system, that has proven economical as well as satisfactory for the overall Indian construction environment. Mivan technology is suitable for constructing large number of houses in a short span of time using room size forms to construct walls and slabs in one continuous pour on concrete. In this system of formwork construction, cast–in–situ concrete wall and floor slabs cast monolithic provides the structural system in one continuous pour. On the removal of the formwork mold a high quality concrete finish is produced to accurate tolerances and verticality.The high tolerance of the finish means that, no further plastering is required.
  • 5.
    Uses of MivanFormwork • 3S – System of Construction – Speed, Strength, Safety. • Column and beam construction are eliminated. • Walls and slabs are cast in one operation. • Specially designed, easy to handle light weight pre-engineered aluminum forms. • Fitting and erecting the portion of shuttering. • Carrying out concreting of the walls and slabs together.
  • 6.
    Advantages of Mivanformwork over conventional construction • More seismic resistance: -The box type construction provides more seismic resistance to the structure. • Increased durability: -The durability of a complete concrete structure is more than conventional brick bat masonry. • Lesser number of joints thereby reducing the leakages and enhancing the durability. • Higher carpet area- Due to shear walls the walls are thin thus increasing area. • Integral and smooth finishing of wall and slab- Smooth finish of aluminum can be seen vividly on walls.
  • 7.
    • Uniform qualityof construction – Uniform grade of concrete is used. • Negligible maintenance – Strong built up of concrete needs no maintenance. • Faster completion – Unsurpassed construction speed can be achieved due to light weight of forms. • Lesser manual labour- Less labour is required for carrying formworks. • Simplified foundation design due to consistent load distribution. • The natural density of concrete wall result in better sound transmission coefficient.
  • 8.
    Limitations Of Mivan•Because of small sizes finishing lines are seen on the concrete surfaces. • Concealed services become difficult due to small thickness of components. • It requires uniform planning as well as uniform elevations to be cost effective. • Modifications are not possible as all members are caste in RCC. • The formwork requires number of spacer, wall ties etc. which are create problems such as seepage, leakages during monsoon. • Due to box-type construction shrinkage cracks are likely to appear. • Heat of Hydration is high due to shear walls.
  • 9.
    METHODAND SYSTEMOF CONSTRUCTIONBYMIVAN FORMWORK INTRODUCTION • MIVAN is the brand name from Mivan Far East, Malaysia. It is Aluminum alloy Form work The Aluminum formwork system for concreting is probably the most versatile modern construction system. Unlike other systems it is equally suited to both high and low rise construction specifically designed to allow the rapid construction of multiple unit projects at optimum productivity.
  • 11.
    WALL PANEL:TheWall Panelforms the face of the wall from the top of the Rocker to the underside of theTop Panel.
  • 12.
    ROCKER: The Rockerforms the wall face at the bottom of the wall panels and helps to facilitate striking.
  • 13.
    KICKER:The kicker formsthe wall Face at the top of theTop Panels. It is anchored to the concrete and acts as a ledge for theWall panels on the next floor to sit on.
  • 14.
    BEAM SOFFIT BULKHEAD:The Beam Soffit Bulkhead is used to form the soffit of the beam. It is used for beams less than 300mm.
  • 15.
    DECK COMPONENT: Thedeck panel rests between pairs of mid-beams and provides a horizontal surface for casting the slabs and provides a horizontal surface for casting the slabs.
  • 16.
    INTERNAL SOFFIT CORNER:The Internal Soffit Corner forms the vertical corner between walls and / or beam faces and horizontal internal corners between wall / beam face and soffit of slabs.
  • 17.
    INTERNAL CORNER: The InternalCorner connects 2 pieces of vertical formwork together of their internal intersection.
  • 18.
    PROP LENGTH: The proplength is manufactured to a specific length for each project. It transmits load to the previous slab.
  • 19.
    PANEL PULLER: Itis required for removing panels after concreting of wall.
  • 20.
    TIE PULLER: Itis required for removing wallTies after de shuttering of panels.
  • 21.
    BEAM – BAR: Theseare used in pairs to fix the Mid Beam and End Beams to the deck prop. The beam_ Bar is removed when the slab is cast to allow quick striking of the deck form work.
  • 22.
    CASE STUDY • ProjectName - Amanora ParkTown. • Location - Hadapsar,Pune. • Size Of Project - 78,000 m2. • Project Cost - Rs. 650 million. • Client - City Development Corp. • Consultant - P &T, J &W Consultant. • Cycle - 11 days per floor. • Storey - 22 Storey. • System Of Formwork- 6000 sq.mt. • Year Of Completion - On Going.
  • 34.
    CONCLUSION The task ofhousing due to the rising population of the country is becoming increasingly monumental. In terms of technical capabilities to face this challenge, the potential is enormous; it only needs to be judiciously exploited. Traditionally, construction firms all over the world have been slow to adopt the innovation and changes. Contractors are a conservative lot. It is the need of time to analyze the depth of the problem and find effective solutions. Our aim is to serves as a cost effective and efficient tool to solve the problems of the mega housing project all over the world. Our aim is to maximize the use of modern construction techniques and equipments on its entire project. We have tried to cover each and every aspect related to conventional and aluminum form construction. We thus infer that aluminum form construction is able to provide high quality construction at unbelievable speed and at reasonable cost.This technology has great potential for application in India to provide affordable housing to its rising population.Thus it can be concluded that quality and speed must be given due consideration with regards to economy. Good quality construction will never deter to projects speed nor will it be uneconomical. In fact time consuming repairs and modification due to poor quality work generally delay the job and cause additional financial impact on the project. Some experts feel that housing alternatives with low maintenance requirements may be preferred even if at the slightly may preferred even if at the higher initial cost.
  • 35.
    FUTURE SCOPES This thesiswork is restricted to only Mivan formwork and not other type of aluminum formworks.The future researchers can continue by working over other type of formworks construction by analyzing activities like brickwork, plastering, painting and many more. Furthermore interviews of different people from construction industry can be taken based on questionnaire prepared and analysis can be done.