SlideShare a Scribd company logo
SHUTDOWN
The shutdown is not a routine operation and has potential dangers. A recent analysis of chemical
plants showed that an accident during the shutdown is five times more likely than normal
conditions.
The shutdowns are necessary for different reasons ranging from scheduled events to those in
emergency. So there are three categories of shutdowns:
• normal shutdown: the chemical plant is out of service in a programmed way with the aim to carry
out any maintenance, modification.
• Prolonged shutdown: the shutdown can be caused by damage to the equipment, lack of product
demand or other market reasons. The intent is to restart the system in the future.
• Emergency shutdown: a stop is not planned that can be caused by the deviation of the critical
parameters that exceed the normal limits, by an unexpected failure in equipment / machinery or
lack of utilities
It is clear that it must conduct a safety analysis for all the shutdowns to prevent any accidents.
The scheduled shutdown are determined by any requests for inspections, preventive maintenance,
equipment repair, modification process.
Generally, during a shutdown you may be required interventions such as: removal of inventory,
isolation and decontamination of containers, preparation of equipment, maintenance machines. It
may also be necessary to provide temporary piping for drainage and decontamination, cleaning
and installation of blinds and valves
One way to safely manage the shutdown is to the proper use of the change process (management
of change) .In some chemical processes an important aspect during the stop sequence is to avoid
the flammable range while removing raw products / materials finished.
One example is during the production of acrylic acid when it becomes necessary to stop the
reactor. The reactor operates with a propylene / air mixture above the upper explosive limit. Steam
is added to the reactor to maintain the contents of the reactor outside the flammability limits. The
flammability region is avoided by replacing air with steam until the mixture in the reactor is above
the flash field .Finally the steam can be taken off and the reactor is purged with air.
The decontamination managed by production is an important step in the stop procedure. This step
is operated by the production workers with special work permits, before moving the equipment
maintenance.
Normally in shutdown changes are made that must be handled with appropriate procedure.
The Flixborough accident is an example of how the installation of a temporary pipe without the
adequate support and without a safety analysis can lead to catastrophic events.
In many accidents an analysis showed that a cause basis was correct the deviation from the
application of the security procedures.
A written procedure for the stop must always be used for proper handling of requests sequences.
Below is a checklist that can be an integral part of the procedure.
1. all the lines isolated and closed
2. electrical systems locked and identified
3. Clean valves and purged
4. adequate ventilation
5. proven atmosphere
• flammable limit
• oxygen level
• toxic gas levels
• person in addition
6. scuba
7. A safety belt
8. Grounding
9. physical hazards
10.DPI
11.kit first aid
12.training
13. Fire-fighting equipment
14.comunication
15.signals
16.meeting before work / precautions taken
Reference
guidelines for safe process operations and maintenance-CCPS-Aiche
.

More Related Content

What's hot

Process Safety
Process SafetyProcess Safety
Process Safety
Consultivo
 
Industrial Safety Training by Author Stream
Industrial Safety Training by Author StreamIndustrial Safety Training by Author Stream
Industrial Safety Training by Author StreamAtlantic Training, LLC.
 
Behaviour based safety
Behaviour based safetyBehaviour based safety
Behaviour based safety
Prudhvi raj
 
LOTO Training
LOTO TrainingLOTO Training
LOTO TrainingCM Tiwari
 
Chemical Hazards Training Presentation
Chemical Hazards Training PresentationChemical Hazards Training Presentation
Chemical Hazards Training Presentation
Ahmed Moftah
 
safety training
safety training   safety training
safety training
Jitesh Gaurav
 
National safety week 2023.pptx
National safety week 2023.pptxNational safety week 2023.pptx
National safety week 2023.pptx
Neeraj Kumar Rai
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
Verde Ventures Pvt. Ltd.
 
Presentation hazop introduction
Presentation hazop introductionPresentation hazop introduction
Presentation hazop introduction
Sundararajan Thangavelu
 
HAZOP Basics
HAZOP BasicsHAZOP Basics
HAZOP Basics
hossam hassanein
 
SAFETY TOOLBOX TALK: Seven Common Accident Causes
SAFETY TOOLBOX TALK: Seven Common Accident CausesSAFETY TOOLBOX TALK: Seven Common Accident Causes
SAFETY TOOLBOX TALK: Seven Common Accident Causes
MARLON RAMIREZ
 
Job Safety Analysis
Job Safety AnalysisJob Safety Analysis
Job Safety Analysis
vtsiri
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
TheSafetyGuru
 
Safety orientation urdu
Safety orientation urduSafety orientation urdu
Safety orientation urdu
Rana Irfan Ali
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessment
TechnoSysCon
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
Asif Khan
 
Near miss
Near missNear miss
Near miss
Saeed Hassan
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 

What's hot (20)

Process Safety
Process SafetyProcess Safety
Process Safety
 
Industrial Safety Training by Author Stream
Industrial Safety Training by Author StreamIndustrial Safety Training by Author Stream
Industrial Safety Training by Author Stream
 
Behaviour based safety
Behaviour based safetyBehaviour based safety
Behaviour based safety
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
 
Chemical Hazards Training Presentation
Chemical Hazards Training PresentationChemical Hazards Training Presentation
Chemical Hazards Training Presentation
 
safety training
safety training   safety training
safety training
 
National safety week 2023.pptx
National safety week 2023.pptxNational safety week 2023.pptx
National safety week 2023.pptx
 
14 Tips for Process Safety Management
14 Tips for Process Safety Management14 Tips for Process Safety Management
14 Tips for Process Safety Management
 
Presentation hazop introduction
Presentation hazop introductionPresentation hazop introduction
Presentation hazop introduction
 
HAZOP Basics
HAZOP BasicsHAZOP Basics
HAZOP Basics
 
SAFETY TOOLBOX TALK: Seven Common Accident Causes
SAFETY TOOLBOX TALK: Seven Common Accident CausesSAFETY TOOLBOX TALK: Seven Common Accident Causes
SAFETY TOOLBOX TALK: Seven Common Accident Causes
 
Job Safety Analysis
Job Safety AnalysisJob Safety Analysis
Job Safety Analysis
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 
Safety orientation urdu
Safety orientation urduSafety orientation urdu
Safety orientation urdu
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessment
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
 
Near miss
Near missNear miss
Near miss
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Flixborough disaster
Flixborough disasterFlixborough disaster
Flixborough disaster
 

Viewers also liked

Logiskills Group Presentation 2009
Logiskills Group Presentation 2009Logiskills Group Presentation 2009
Logiskills Group Presentation 2009gcerasi
 
02 competencias del docente del siglo xxi
02 competencias del docente del siglo xxi02 competencias del docente del siglo xxi
02 competencias del docente del siglo xxi
DOCTOR
 
Varghese Chacko Portfolio
Varghese Chacko PortfolioVarghese Chacko Portfolio
Varghese Chacko Portfolio
Varghese Chacko, MBA
 
production and maintenance
production and maintenanceproduction and maintenance
production and maintenancealfredo ruggiero
 
Crouching Seiberg, Hidden Gauge Group.
Crouching Seiberg, Hidden Gauge Group.Crouching Seiberg, Hidden Gauge Group.
Crouching Seiberg, Hidden Gauge Group.
Flip Tanedo
 
минспорт про гто
минспорт про гтоминспорт про гто
минспорт про гто
school184spb
 
Правила приема в 1 класс в 2017-2018
Правила приема в 1 класс в  2017-2018Правила приема в 1 класс в  2017-2018
Правила приема в 1 класс в 2017-2018
school184spb
 
Umanesimo rinascimento (interdisciplinare)
Umanesimo rinascimento (interdisciplinare)Umanesimo rinascimento (interdisciplinare)
Umanesimo rinascimento (interdisciplinare)
Francesco Baldassarre
 
La Clonación
La  ClonaciónLa  Clonación
La ClonaciónAnaiz
 
Плакаты по подготовке к ЕГЭ 2016
Плакаты по подготовке к ЕГЭ 2016Плакаты по подготовке к ЕГЭ 2016
Плакаты по подготовке к ЕГЭ 2016
school184spb
 

Viewers also liked (13)

Logiskills Group Presentation 2009
Logiskills Group Presentation 2009Logiskills Group Presentation 2009
Logiskills Group Presentation 2009
 
02 competencias del docente del siglo xxi
02 competencias del docente del siglo xxi02 competencias del docente del siglo xxi
02 competencias del docente del siglo xxi
 
Av Slideshow
Av SlideshowAv Slideshow
Av Slideshow
 
green chemistry
green chemistrygreen chemistry
green chemistry
 
HAZOP
HAZOPHAZOP
HAZOP
 
Varghese Chacko Portfolio
Varghese Chacko PortfolioVarghese Chacko Portfolio
Varghese Chacko Portfolio
 
production and maintenance
production and maintenanceproduction and maintenance
production and maintenance
 
Crouching Seiberg, Hidden Gauge Group.
Crouching Seiberg, Hidden Gauge Group.Crouching Seiberg, Hidden Gauge Group.
Crouching Seiberg, Hidden Gauge Group.
 
минспорт про гто
минспорт про гтоминспорт про гто
минспорт про гто
 
Правила приема в 1 класс в 2017-2018
Правила приема в 1 класс в  2017-2018Правила приема в 1 класс в  2017-2018
Правила приема в 1 класс в 2017-2018
 
Umanesimo rinascimento (interdisciplinare)
Umanesimo rinascimento (interdisciplinare)Umanesimo rinascimento (interdisciplinare)
Umanesimo rinascimento (interdisciplinare)
 
La Clonación
La  ClonaciónLa  Clonación
La Clonación
 
Плакаты по подготовке к ЕГЭ 2016
Плакаты по подготовке к ЕГЭ 2016Плакаты по подготовке к ЕГЭ 2016
Плакаты по подготовке к ЕГЭ 2016
 

Similar to SHUTDOWN

Safety in maintenance process, By B C Das
Safety in maintenance process, By B C DasSafety in maintenance process, By B C Das
Safety in maintenance process, By B C Das
Bimal Chandra Das
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
SAJJAD KHUDHUR ABBAS
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
SAJJAD KHUDHUR ABBAS
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptx
TYPPEOnlineLecture
 
Oil & Gas Maintenance Guide
Oil & Gas Maintenance GuideOil & Gas Maintenance Guide
Oil & Gas Maintenance Guide
Josiah Igoni (B. Eng., DiPM)
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Design World
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)
Rohini Haridas
 
An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...
MARIO524285
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
vikramparuthi1
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
Dr. Munthear Alqaderi
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
vijay oak
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
vijay oak
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
vijay oak
 
Rams 2007 paper pdf
Rams 2007 paper pdfRams 2007 paper pdf
Rams 2007 paper pdf
Sharad Vishwasrao
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Nylex Water Solutions Ingleburn - Main Body
Nylex Water Solutions Ingleburn - Main BodyNylex Water Solutions Ingleburn - Main Body
Nylex Water Solutions Ingleburn - Main BodyTom Evans
 
Leak Detection And Repair
Leak Detection And RepairLeak Detection And Repair
Leak Detection And RepairAshutosh Soni
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationEwart Cox
 
1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx
ZerayacobTeklearegay
 
G0366046050
G0366046050G0366046050
G0366046050
theijes
 

Similar to SHUTDOWN (20)

Safety in maintenance process, By B C Das
Safety in maintenance process, By B C DasSafety in maintenance process, By B C Das
Safety in maintenance process, By B C Das
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptx
 
Oil & Gas Maintenance Guide
Oil & Gas Maintenance GuideOil & Gas Maintenance Guide
Oil & Gas Maintenance Guide
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
 
Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)Ppt maintenance cb(encrypted)
Ppt maintenance cb(encrypted)
 
An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...An appropriate methodology to achieve a clear vision of the valves and proper...
An appropriate methodology to achieve a clear vision of the valves and proper...
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Rams 2007 paper pdf
Rams 2007 paper pdfRams 2007 paper pdf
Rams 2007 paper pdf
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 
Nylex Water Solutions Ingleburn - Main Body
Nylex Water Solutions Ingleburn - Main BodyNylex Water Solutions Ingleburn - Main Body
Nylex Water Solutions Ingleburn - Main Body
 
Leak Detection And Repair
Leak Detection And RepairLeak Detection And Repair
Leak Detection And Repair
 
STM_Autumn2015 Article Publication
STM_Autumn2015 Article PublicationSTM_Autumn2015 Article Publication
STM_Autumn2015 Article Publication
 
1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx
 
G0366046050
G0366046050G0366046050
G0366046050
 

More from alfredo ruggiero

2.5 valutazione rischio esplosione impianto frigo
2.5 valutazione rischio esplosione impianto frigo2.5 valutazione rischio esplosione impianto frigo
2.5 valutazione rischio esplosione impianto frigoalfredo ruggiero
 
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICOalfredo ruggiero
 
THE ROLE OF HUMAN ERROR IN ACCIDENTS
THE ROLE OF HUMAN ERROR IN ACCIDENTSTHE ROLE OF HUMAN ERROR IN ACCIDENTS
THE ROLE OF HUMAN ERROR IN ACCIDENTSalfredo ruggiero
 
alfredo ruggiero engtech ticheme
alfredo ruggiero engtech tichemealfredo ruggiero engtech ticheme
alfredo ruggiero engtech tichemealfredo ruggiero
 
4.4 MANUTENZIONE E PROCEDURE
4.4 MANUTENZIONE E PROCEDURE4.4 MANUTENZIONE E PROCEDURE
4.4 MANUTENZIONE E PROCEDUREalfredo ruggiero
 
Chemtura_Sustainabilty_2016_FINAL_low_27May2016
Chemtura_Sustainabilty_2016_FINAL_low_27May2016Chemtura_Sustainabilty_2016_FINAL_low_27May2016
Chemtura_Sustainabilty_2016_FINAL_low_27May2016alfredo ruggiero
 
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTORE
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTOREPROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTORE
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTOREalfredo ruggiero
 
1.2Il ruolo della Produzione e della Manutenzione
1.2Il ruolo della Produzione e della Manutenzione1.2Il ruolo della Produzione e della Manutenzione
1.2Il ruolo della Produzione e della Manutenzionealfredo ruggiero
 
4.2 GESTIONE DELLE MODICHE
4.2 GESTIONE DELLE MODICHE4.2 GESTIONE DELLE MODICHE
4.2 GESTIONE DELLE MODICHEalfredo ruggiero
 
7.1 SIX SIGMA E PROCESSI CHIMICI
7.1  SIX SIGMA E PROCESSI CHIMICI7.1  SIX SIGMA E PROCESSI CHIMICI
7.1 SIX SIGMA E PROCESSI CHIMICIalfredo ruggiero
 
8.1 MINIMIZZAZIONE DEI RIFIUTI
8.1 MINIMIZZAZIONE DEI RIFIUTI8.1 MINIMIZZAZIONE DEI RIFIUTI
8.1 MINIMIZZAZIONE DEI RIFIUTIalfredo ruggiero
 
chemical reactor runaway case study
chemical reactor runaway case studychemical reactor runaway case study
chemical reactor runaway case studyalfredo ruggiero
 
1.1La sicurezza in uno stabilimento chimico
1.1La sicurezza in uno stabilimento chimico1.1La sicurezza in uno stabilimento chimico
1.1La sicurezza in uno stabilimento chimicoalfredo ruggiero
 
Company Presentation_Short Version
Company Presentation_Short VersionCompany Presentation_Short Version
Company Presentation_Short Versionalfredo ruggiero
 

More from alfredo ruggiero (20)

foto
fotofoto
foto
 
Annual_report_2014
Annual_report_2014Annual_report_2014
Annual_report_2014
 
2.5 valutazione rischio esplosione impianto frigo
2.5 valutazione rischio esplosione impianto frigo2.5 valutazione rischio esplosione impianto frigo
2.5 valutazione rischio esplosione impianto frigo
 
automation
automationautomation
automation
 
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO
6.1 AUTOMAZIONE SICURA DI PROCESSO CHIMICO
 
THE ROLE OF HUMAN ERROR IN ACCIDENTS
THE ROLE OF HUMAN ERROR IN ACCIDENTSTHE ROLE OF HUMAN ERROR IN ACCIDENTS
THE ROLE OF HUMAN ERROR IN ACCIDENTS
 
WASTE MINIMIZATION
WASTE MINIMIZATIONWASTE MINIMIZATION
WASTE MINIMIZATION
 
alfredo ruggiero engtech ticheme
alfredo ruggiero engtech tichemealfredo ruggiero engtech ticheme
alfredo ruggiero engtech ticheme
 
4.4 MANUTENZIONE E PROCEDURE
4.4 MANUTENZIONE E PROCEDURE4.4 MANUTENZIONE E PROCEDURE
4.4 MANUTENZIONE E PROCEDURE
 
Chemtura_Sustainabilty_2016_FINAL_low_27May2016
Chemtura_Sustainabilty_2016_FINAL_low_27May2016Chemtura_Sustainabilty_2016_FINAL_low_27May2016
Chemtura_Sustainabilty_2016_FINAL_low_27May2016
 
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTORE
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTOREPROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTORE
PROGETTAZIONE DI UN PROCESSO CHIMICO IN UN REATTORE
 
1.2Il ruolo della Produzione e della Manutenzione
1.2Il ruolo della Produzione e della Manutenzione1.2Il ruolo della Produzione e della Manutenzione
1.2Il ruolo della Produzione e della Manutenzione
 
4.2 GESTIONE DELLE MODICHE
4.2 GESTIONE DELLE MODICHE4.2 GESTIONE DELLE MODICHE
4.2 GESTIONE DELLE MODICHE
 
2.2 HAZOP
2.2 HAZOP2.2 HAZOP
2.2 HAZOP
 
3.1 PRODUZIONE
3.1 PRODUZIONE3.1 PRODUZIONE
3.1 PRODUZIONE
 
7.1 SIX SIGMA E PROCESSI CHIMICI
7.1  SIX SIGMA E PROCESSI CHIMICI7.1  SIX SIGMA E PROCESSI CHIMICI
7.1 SIX SIGMA E PROCESSI CHIMICI
 
8.1 MINIMIZZAZIONE DEI RIFIUTI
8.1 MINIMIZZAZIONE DEI RIFIUTI8.1 MINIMIZZAZIONE DEI RIFIUTI
8.1 MINIMIZZAZIONE DEI RIFIUTI
 
chemical reactor runaway case study
chemical reactor runaway case studychemical reactor runaway case study
chemical reactor runaway case study
 
1.1La sicurezza in uno stabilimento chimico
1.1La sicurezza in uno stabilimento chimico1.1La sicurezza in uno stabilimento chimico
1.1La sicurezza in uno stabilimento chimico
 
Company Presentation_Short Version
Company Presentation_Short VersionCompany Presentation_Short Version
Company Presentation_Short Version
 

SHUTDOWN

  • 1. SHUTDOWN The shutdown is not a routine operation and has potential dangers. A recent analysis of chemical plants showed that an accident during the shutdown is five times more likely than normal conditions. The shutdowns are necessary for different reasons ranging from scheduled events to those in emergency. So there are three categories of shutdowns: • normal shutdown: the chemical plant is out of service in a programmed way with the aim to carry out any maintenance, modification. • Prolonged shutdown: the shutdown can be caused by damage to the equipment, lack of product demand or other market reasons. The intent is to restart the system in the future. • Emergency shutdown: a stop is not planned that can be caused by the deviation of the critical parameters that exceed the normal limits, by an unexpected failure in equipment / machinery or lack of utilities It is clear that it must conduct a safety analysis for all the shutdowns to prevent any accidents. The scheduled shutdown are determined by any requests for inspections, preventive maintenance, equipment repair, modification process. Generally, during a shutdown you may be required interventions such as: removal of inventory, isolation and decontamination of containers, preparation of equipment, maintenance machines. It may also be necessary to provide temporary piping for drainage and decontamination, cleaning and installation of blinds and valves One way to safely manage the shutdown is to the proper use of the change process (management of change) .In some chemical processes an important aspect during the stop sequence is to avoid the flammable range while removing raw products / materials finished. One example is during the production of acrylic acid when it becomes necessary to stop the reactor. The reactor operates with a propylene / air mixture above the upper explosive limit. Steam is added to the reactor to maintain the contents of the reactor outside the flammability limits. The flammability region is avoided by replacing air with steam until the mixture in the reactor is above the flash field .Finally the steam can be taken off and the reactor is purged with air. The decontamination managed by production is an important step in the stop procedure. This step is operated by the production workers with special work permits, before moving the equipment maintenance. Normally in shutdown changes are made that must be handled with appropriate procedure. The Flixborough accident is an example of how the installation of a temporary pipe without the adequate support and without a safety analysis can lead to catastrophic events. In many accidents an analysis showed that a cause basis was correct the deviation from the application of the security procedures. A written procedure for the stop must always be used for proper handling of requests sequences. Below is a checklist that can be an integral part of the procedure. 1. all the lines isolated and closed 2. electrical systems locked and identified 3. Clean valves and purged 4. adequate ventilation 5. proven atmosphere • flammable limit • oxygen level
  • 2. • toxic gas levels • person in addition 6. scuba 7. A safety belt 8. Grounding 9. physical hazards 10.DPI 11.kit first aid 12.training 13. Fire-fighting equipment 14.comunication 15.signals 16.meeting before work / precautions taken Reference guidelines for safe process operations and maintenance-CCPS-Aiche .