SlideShare a Scribd company logo
Project Integration Management
• Process Groups & Knowledge Areas Mapping
Knowledge Area
Process
Initiating Planning Executing Monitoring & Control Closing
Integration Develop Project
Charter
Develop Project Management Plan Direct and Manage Project
Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project
Scope Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Time Define Activities
Sequence Activities
Estimate Activities Resources
Estimate Activities Duration
Develop Schedule
Control Schedule
Cost Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Perform Quality Assurance Perform Quality Control
Human
Resource
Develop Human Resources Plan Acquire Project Team
Develop Project Team
Manage Project Team
Communication Identify
Stakeholders
Plan Communications Distribute Information
Manage Stakeholders Expectations
Report Performance
Risk Plan Risk Management
Identify Risk
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Monitor and Control Risks
Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurements
Project Integration Management
Knowledge
Area
Process
Initiating Planning Executing Monitoring & Contol Closing
integration
• Develop
Project
Charter
• Develop Project
Management
Plan
• Direct and
Manage Project
Execution
• Monitor and Control
Project Work
• Perform Integrated
Change Control
• Close
Project
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
Execute Plan + Implement approved changes
Direct & Manage Project Execution
Changes (produce and implement)
-Corrective Action: FORMAL documented
direction/activity to bring future work in
line with plan.
-Preventive Action: reduce probability of
negative consequences associated with
Risks
Defect Repair:
- formal document identification of a defect &
recommendation to replace or repair.
Direct & Manage Project Execution
• The process of performing the work defined in the project
management plan to achieve the project’s objectives.
Inputs
1. Project management
plan
2. Approved change
request
3. Enterprise environmental
factors
4. Organizational process
assets
Tools &
Techniques
1. Expert judgment
2. Management
information system
Outputs
1. Deliverables work
2. Performance
information
3. Change requests
4. Project management
plan updates
5. Project document
updates
• Process Groups & Knowledge Areas Mapping
Knowledge Area
Process
Initiating Planning Executing Monitoring & Control Closing
Integration Develop Project
Charter
Develop Project Management Plan Direct and Manage Project
Execution
Monitor and Control Project Work
Perform Integrated Change Control
Close Project
Scope Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Time Define Activities
Sequence Activities
Estimate Activities Resources
Estimate Activities Duration
Develop Schedule
Control Schedule
Cost Estimate Costs
Determine Budget
Control Costs
Quality Plan Quality Perform Quality Assurance Perform Quality Control
Human
Resource
Develop Human Resources Plan Acquire Project Team
Develop Project Team
Manage Project Team
Communication Identify
Stakeholders
Plan Communications Distribute Information
Manage Stakeholders Expectations
Report Performance
Risk Plan Risk Management
Identify Risk
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Monitor and Control Risks
Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurements
Monitor & Control Project Work
1-Comparing actual project performance against
the project management plan.
2 - Assessing performance to determine whether
any corrective or preventive action are indicated.
Analyzing, tracking, and monitoring project risk.
3 - Maintaining an accurate, timely information
base concerning the project’s products. Providing
forecasts to update current cost and schedule
information.
4- Monitoring implementation of approved change
when and as they occur
Monitor & Control Project Work
• The process of tracking, reviewing, and regulating the
progress to meet the performance objectives defined in the
project management plan.
Inputs
1. Project management
plan
2. Performance reports
3. Enterprise environmental
factors
4. Organizational process
assets
Tools &
Techniques
1. Expert judgment
Outputs
1. Change requests
2. Project management
plan updates
3. Project document
updates
Monitor and Control Project Work Data Flow Diagram
Perform Integrated Change Control
• Before push or ask the management for
approval
• Do you know if there’s another alternative?
• Did you evaluate/investigate the effect/impact
of each of the options(on time and cost for
example)?
• What’s the best option?
• Do you have the authority to change or do
you have to go to CCB?
Perform Integrated Change Control
• The process of reviewing all change requests, approving changes and
managing changes to deliverables, organizational process assets, project
documents and the project management plan.
Inputs
1. Project management
plan
2. Performance reports
3. Enterprise environmental
factors
4. Organizational process
assets
Tools &
Techniques
1. Expert judgment
Outputs
1. Change requests
2. Project management
plan updates
3. Project document
updates
Perform Integrated Change Control Data Flow Diagram
-Satisfy completion or exit criteria for project or
phase.
-Transfer products, services or results to next phase
or stage
-Verify and document the project deliverables
-Formalize acceptance by customer or sponsor.
- Collect & ARCHIVE PROJECT RECORDS.
- AUDIT success and failure
- Gather & document LESSONS LEARNED.
-Archive project information for future use
Closing Project or Phase
Closing Project or Phase
• The process of of finalizing all activities across all of the Project
Management Process Groups to formally complete the project or phase.
Inputs
1. Project management
plan
2. Accepted deliverables
3. Organizational process
assets
Tools &
Techniques
1. Expert judgment
Outputs
1. Final product, service or
result
2. Organizational process
assets updates
Close Project or Phase Data Flow Diagram
General Principles and Guidelines
• Do the right thing!
• Behave in an honest, open manner
• Solve problems, do not hide them
• Do not violate local laws
• Do not accept bribes or favors
• Disclose potential conflicts of interest
General Principles and Guidelines
• Keep people informed
• Do not change standards or requirements
after the fact
• Attempt to resolve problems at the level they
occur, i.e. do not immediately escalate!
• Make accurate, honest reports
• Make decisions on the basis of facts; not
hearsay, assumptions, or opinions
QUESTIONS?
• 1- a project manager has made a change to
the project what should she do NEXT?
A-Assign resources
B-Revise the project management plan and /or
project documents
C- evaluate impact
D- request change control board involvement
• 2-which of the following best describes the
project managers role as an integrator?
A- help team members become familiar with
the project
B- put all the pieces of a project into a
cohesive whole
C- put all the pieces of a project into a program
D- Get all team members togather into a
cohesive whole
3-in the process of reviewing the status of your team work
assignments, you learn that the project has fallen behind
schedule by one week. The project has high visibility within
the organization and is completely date- driven. The project
finish date is still two months out and you think you can
recover the time over the next month or so. What is the best
course of action for reporting the project status?
A- report the project on schedule . This is not a significant
slippage and there is still time to recover.
B- report the project on schedule. Most project management
plans are not accurate to less than one or two weeks anyway
C- report the project one week behind schedule and include
recommended corrective actions
D- report the project one week behind schedule and then issue
a new report next week showing the problem fixed.
4-a team member notifies you . After the fact , that she has
added extra functionality to the project . There was no
impact on the cost or schedule . What should be done as a
result of this change?
A- inform the customer
B- make sure marketing is aware of the change
C-understand what functionality was added
D- implement change control processes to track the change
• 5- you are in the middle of a new product
development project for your publicly traded
company when you discover that the previous
project manager made 3.000.000 $ payment that
was not approved in accordance with your company
policies. Luckily, the project cost performance index
( CPI) is 1.2 what should you do?
• A- contact your manager
• B- put payment in an escrow account
• C- bury the cost in the larger cost center available
• D- ignore the payment
• 6-your company is in competition to win a
major project for the government of a
country. Your contacts in that country inform
you that you must make a large payment to
the foreign minister to be considered for the
project. What should you do?
A- inform your company's management, and
ask for direction
B- do not make the payment
C- have the local contact make the payment
D- make the payment
Thank you

More Related Content

What's hot

6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Kateri Manglicmot
 
Cost management
Cost managementCost management
Cost management
Abhi Kalyan
 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMC Mentor
 
project cost management
project cost managementproject cost management
project cost management
jay mitkari
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
Ahmed Elshaboury,PMP,LEED GA
 
PMP Training - 12 project procurement management
PMP Training - 12 project procurement managementPMP Training - 12 project procurement management
PMP Training - 12 project procurement managementejlp12
 
Project cost management
Project cost management Project cost management
Project cost management
PALLA NARASIMHUDU
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
Hossam Maghrabi
 
Project cost management
Project cost managementProject cost management
Project cost management
ProjectManager247
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
12 projectprocurementmanagement
12 projectprocurementmanagement12 projectprocurementmanagement
12 projectprocurementmanagement
Dhamo daran
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 

What's hot (20)

07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
Session 16 4th edition
Session 16 4th editionSession 16 4th edition
Session 16 4th edition
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Cost management
Cost managementCost management
Cost management
 
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & SkillsPMP TKS GUIDE:  Closing Process Group; Tasks, Knowledge & Skills
PMP TKS GUIDE: Closing Process Group; Tasks, Knowledge & Skills
 
project cost management
project cost managementproject cost management
project cost management
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
PMP Training - 12 project procurement management
PMP Training - 12 project procurement managementPMP Training - 12 project procurement management
PMP Training - 12 project procurement management
 
Project cost management
Project cost management Project cost management
Project cost management
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
12 projectprocurementmanagement
12 projectprocurementmanagement12 projectprocurementmanagement
12 projectprocurementmanagement
 
Project management
Project managementProject management
Project management
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 

Viewers also liked

PMP Exam Prep - Communications Management
PMP Exam Prep - Communications ManagementPMP Exam Prep - Communications Management
PMP Exam Prep - Communications Management
tkrikau
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
Cybrary
 
Business architecture design choices
Business architecture design choicesBusiness architecture design choices
Business architecture design choices
CapabilitiesRich
 
Project management professional (PMP)
Project management professional (PMP)Project management professional (PMP)
Project management professional (PMP)
Saad Al Jabri
 

Viewers also liked (20)

Session 14 4th edition PMP
Session  14 4th edition PMPSession  14 4th edition PMP
Session 14 4th edition PMP
 
PMP Exam Prep - Communications Management
PMP Exam Prep - Communications ManagementPMP Exam Prep - Communications Management
PMP Exam Prep - Communications Management
 
Session 4 4th edition PMP
Session   4 4th edition PMPSession   4 4th edition PMP
Session 4 4th edition PMP
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
 
Session 1 PMP 4th edition
Session 1 PMP 4th editionSession 1 PMP 4th edition
Session 1 PMP 4th edition
 
Business architecture design choices
Business architecture design choicesBusiness architecture design choices
Business architecture design choices
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
Session 15 4th edition PMP
Session 15 4th edition PMPSession 15 4th edition PMP
Session 15 4th edition PMP
 
Session 19 4th edition PMP
Session  19 4th edition PMPSession  19 4th edition PMP
Session 19 4th edition PMP
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Session 2 PMP 4TH edition
Session 2 PMP 4TH editionSession 2 PMP 4TH edition
Session 2 PMP 4TH edition
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
Project management professional (PMP)
Project management professional (PMP)Project management professional (PMP)
Project management professional (PMP)
 
Session 3 4th edition
Session   3 4th editionSession   3 4th edition
Session 3 4th edition
 
Session 20 4th edition PMP
Session 20 4th edition PMPSession 20 4th edition PMP
Session 20 4th edition PMP
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 

Similar to Session 22 4th edition PMP

Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen657394
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
UjalaBatool7
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
Project Management Solutions
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
Dhamo daran
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
BhuWan Khadka
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
Project Management Solutions
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
Jacobs Engineering
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
GeorgeKabongah2
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
Rasan Samarasinghe
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
PhocasSebastian1
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
ARIV4
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
stilliegeorgiana
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
Joshua Render
 
PROJECT MANAGEMENT_Framework.pdf
PROJECT MANAGEMENT_Framework.pdfPROJECT MANAGEMENT_Framework.pdf
PROJECT MANAGEMENT_Framework.pdf
LeonardoFlixPortilla
 
Project life cycle_management by Subbu
Project life cycle_management by SubbuProject life cycle_management by Subbu
Project life cycle_management by SubbuTechGigDotCom
 

Similar to Session 22 4th edition PMP (20)

Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Project Management Ch 14.ppt
Project Management Ch 14.pptProject Management Ch 14.ppt
Project Management Ch 14.ppt
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
07. Project Integration Management
07. Project Integration Management07. Project Integration Management
07. Project Integration Management
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
PROJECT MANAGEMENT_Framework.pdf
PROJECT MANAGEMENT_Framework.pdfPROJECT MANAGEMENT_Framework.pdf
PROJECT MANAGEMENT_Framework.pdf
 
Project life cycle_management by Subbu
Project life cycle_management by SubbuProject life cycle_management by Subbu
Project life cycle_management by Subbu
 

Recently uploaded

RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
PaulBryant58
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
YourLegal Accounting
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 

Recently uploaded (20)

RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
Accpac to QuickBooks Conversion Navigating the Transition with Online Account...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Filing Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed GuideFiling Your Delaware Franchise Tax A Detailed Guide
Filing Your Delaware Franchise Tax A Detailed Guide
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 

Session 22 4th edition PMP

  • 2. • Process Groups & Knowledge Areas Mapping Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Perform Integrated Change Control Close Project Scope Collect Requirements Define Scope Create WBS Verify Scope Control Scope Time Define Activities Sequence Activities Estimate Activities Resources Estimate Activities Duration Develop Schedule Control Schedule Cost Estimate Costs Determine Budget Control Costs Quality Plan Quality Perform Quality Assurance Perform Quality Control Human Resource Develop Human Resources Plan Acquire Project Team Develop Project Team Manage Project Team Communication Identify Stakeholders Plan Communications Distribute Information Manage Stakeholders Expectations Report Performance Risk Plan Risk Management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Monitor and Control Risks Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurements
  • 3. Project Integration Management Knowledge Area Process Initiating Planning Executing Monitoring & Contol Closing integration • Develop Project Charter • Develop Project Management Plan • Direct and Manage Project Execution • Monitor and Control Project Work • Perform Integrated Change Control • Close Project Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes
  • 4. Execute Plan + Implement approved changes Direct & Manage Project Execution Changes (produce and implement) -Corrective Action: FORMAL documented direction/activity to bring future work in line with plan. -Preventive Action: reduce probability of negative consequences associated with Risks Defect Repair: - formal document identification of a defect & recommendation to replace or repair.
  • 5. Direct & Manage Project Execution • The process of performing the work defined in the project management plan to achieve the project’s objectives. Inputs 1. Project management plan 2. Approved change request 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment 2. Management information system Outputs 1. Deliverables work 2. Performance information 3. Change requests 4. Project management plan updates 5. Project document updates
  • 6.
  • 7. • Process Groups & Knowledge Areas Mapping Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Integration Develop Project Charter Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Perform Integrated Change Control Close Project Scope Collect Requirements Define Scope Create WBS Verify Scope Control Scope Time Define Activities Sequence Activities Estimate Activities Resources Estimate Activities Duration Develop Schedule Control Schedule Cost Estimate Costs Determine Budget Control Costs Quality Plan Quality Perform Quality Assurance Perform Quality Control Human Resource Develop Human Resources Plan Acquire Project Team Develop Project Team Manage Project Team Communication Identify Stakeholders Plan Communications Distribute Information Manage Stakeholders Expectations Report Performance Risk Plan Risk Management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Response Monitor and Control Risks Procurement Plan Procurements Conduct Procurements Administer Procurements Close Procurements
  • 8. Monitor & Control Project Work 1-Comparing actual project performance against the project management plan. 2 - Assessing performance to determine whether any corrective or preventive action are indicated. Analyzing, tracking, and monitoring project risk. 3 - Maintaining an accurate, timely information base concerning the project’s products. Providing forecasts to update current cost and schedule information. 4- Monitoring implementation of approved change when and as they occur
  • 9. Monitor & Control Project Work • The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan. Inputs 1. Project management plan 2. Performance reports 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment Outputs 1. Change requests 2. Project management plan updates 3. Project document updates
  • 10. Monitor and Control Project Work Data Flow Diagram
  • 11. Perform Integrated Change Control • Before push or ask the management for approval • Do you know if there’s another alternative? • Did you evaluate/investigate the effect/impact of each of the options(on time and cost for example)? • What’s the best option? • Do you have the authority to change or do you have to go to CCB?
  • 12. Perform Integrated Change Control • The process of reviewing all change requests, approving changes and managing changes to deliverables, organizational process assets, project documents and the project management plan. Inputs 1. Project management plan 2. Performance reports 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Expert judgment Outputs 1. Change requests 2. Project management plan updates 3. Project document updates
  • 13. Perform Integrated Change Control Data Flow Diagram
  • 14. -Satisfy completion or exit criteria for project or phase. -Transfer products, services or results to next phase or stage -Verify and document the project deliverables -Formalize acceptance by customer or sponsor. - Collect & ARCHIVE PROJECT RECORDS. - AUDIT success and failure - Gather & document LESSONS LEARNED. -Archive project information for future use Closing Project or Phase
  • 15. Closing Project or Phase • The process of of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase. Inputs 1. Project management plan 2. Accepted deliverables 3. Organizational process assets Tools & Techniques 1. Expert judgment Outputs 1. Final product, service or result 2. Organizational process assets updates
  • 16. Close Project or Phase Data Flow Diagram
  • 17. General Principles and Guidelines • Do the right thing! • Behave in an honest, open manner • Solve problems, do not hide them • Do not violate local laws • Do not accept bribes or favors • Disclose potential conflicts of interest
  • 18. General Principles and Guidelines • Keep people informed • Do not change standards or requirements after the fact • Attempt to resolve problems at the level they occur, i.e. do not immediately escalate! • Make accurate, honest reports • Make decisions on the basis of facts; not hearsay, assumptions, or opinions
  • 20. • 1- a project manager has made a change to the project what should she do NEXT? A-Assign resources B-Revise the project management plan and /or project documents C- evaluate impact D- request change control board involvement
  • 21. • 2-which of the following best describes the project managers role as an integrator? A- help team members become familiar with the project B- put all the pieces of a project into a cohesive whole C- put all the pieces of a project into a program D- Get all team members togather into a cohesive whole
  • 22. 3-in the process of reviewing the status of your team work assignments, you learn that the project has fallen behind schedule by one week. The project has high visibility within the organization and is completely date- driven. The project finish date is still two months out and you think you can recover the time over the next month or so. What is the best course of action for reporting the project status? A- report the project on schedule . This is not a significant slippage and there is still time to recover. B- report the project on schedule. Most project management plans are not accurate to less than one or two weeks anyway C- report the project one week behind schedule and include recommended corrective actions D- report the project one week behind schedule and then issue a new report next week showing the problem fixed.
  • 23. 4-a team member notifies you . After the fact , that she has added extra functionality to the project . There was no impact on the cost or schedule . What should be done as a result of this change? A- inform the customer B- make sure marketing is aware of the change C-understand what functionality was added D- implement change control processes to track the change
  • 24. • 5- you are in the middle of a new product development project for your publicly traded company when you discover that the previous project manager made 3.000.000 $ payment that was not approved in accordance with your company policies. Luckily, the project cost performance index ( CPI) is 1.2 what should you do? • A- contact your manager • B- put payment in an escrow account • C- bury the cost in the larger cost center available • D- ignore the payment
  • 25. • 6-your company is in competition to win a major project for the government of a country. Your contacts in that country inform you that you must make a large payment to the foreign minister to be considered for the project. What should you do? A- inform your company's management, and ask for direction B- do not make the payment C- have the local contact make the payment D- make the payment