SlideShare a Scribd company logo
1 of 8
1- Half way through the executing processes of your
project, a team member alerts you to a potential cost
overrun for a specific deliverable. What do you do first?
A ) Determine the projected actual cost.
B ) Implement a change control process to track the
change
C ) Inform the customer.
D ) Determine the cause of the overage
2- Which of the following represents the value of
work we have actually completed?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
3- While completing your project, you realized that you
need to decrease the project costs. After researching
your options, you came up with the following choices.
Which choice would DECREASE project costs?
A ) Change to component A from component B. component A
costs more to purchase, but has a lower life cycle cost than B.
B ) Change activity A to be completed by resource B instead of
resource c. resource B is more experienced worker.
C ) Move activities B and H to occur concurrently, and accept a
30 percent increase in the risk that five more resources will be
needed later.
D ) Remove a test from the project management plan.
4- If earned value (EV) is U.S.$300000, actual
cost (AC) is U.S.$350000, and planned value (PV)
is U.S. $375000, what does the schedule
performance index (SPI) indicate?
A ) You are progressing at 86% of the rate originally
planned.
B ) You are progressing at 125% of the rate originally
planned.
C ) You are progressing at 116% of the rate originally
planned.
D ) You are progressing at 80% of the rate originally
planned.
5- The formula, EAC = BAC/CPI, assumes that:
A ) All subsequent work will be completed at the planned
expenditures.
B ) All subsequent work will be completed at the planned
expenditures, excluding the work packages currently
under way
C ) All subsequent work will be completed based upon the
cost performance to-date
D ) The cost performance cannot change during the project
6- What tool must project managers rely upon
to accurately identify the costs associated with
the project?
A ) A bill of materials
B ) A Gantt chart
C ) A precedence diagram network
D ) A work breakdown structure
7- If the Earned Value is equal to Actual Cost, it
means:
A-Project is on budget and on schedule
B-Schedule Variance Index is 1
C-There is no schedule variance
D-There is no cost variance
8-Suppose you have a budgeted cost of a project at
$900,000. The project is to be completed in 9 months.
After a month, you have completed 10% of the project
at a total expense of $100,000. The planned
completion should have been 15%. At the current
progress rate, how much more money is required to
complete the project?
A) $ 800,000
B) $ 900,000
C) $ 1,000,000
D) $ 1,100,000

More Related Content

What's hot

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosPraveen Malik, PMP
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasPraveen Malik, PMP
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementPraveen Malik, PMP
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management Praveen Malik, PMP
 
Long Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingLong Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingTerry Jackson
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsAnatoly Ryabukha
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)Maintenance Connection
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...Helmut F Giesa HFG2404@gmail.com
 
SSRS BI Project
SSRS BI ProjectSSRS BI Project
SSRS BI Projectpencarver
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for AgileBrett Ansley
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revisedleif2016
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningPraveen Malik, PMP
 

What's hot (19)

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project Management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Long Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingLong Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical Programming
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costs
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
 
SSRS BI Project
SSRS BI ProjectSSRS BI Project
SSRS BI Project
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for Agile
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revised
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost Planning
 

Viewers also liked (16)

Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Session 15 4th edition PMP
Session 15 4th edition PMPSession 15 4th edition PMP
Session 15 4th edition PMP
 
Session 16 4th edition
Session 16 4th editionSession 16 4th edition
Session 16 4th edition
 
Session 19 4th edition PMP
Session  19 4th edition PMPSession  19 4th edition PMP
Session 19 4th edition PMP
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Session 2 PMP 4TH edition
Session 2 PMP 4TH editionSession 2 PMP 4TH edition
Session 2 PMP 4TH edition
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
Session 20 4th edition PMP
Session 20 4th edition PMPSession 20 4th edition PMP
Session 20 4th edition PMP
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Session 14 4th edition PMP
Session  14 4th edition PMPSession  14 4th edition PMP
Session 14 4th edition PMP
 
Kanban (1)
Kanban (1)Kanban (1)
Kanban (1)
 

Similar to Session 10 4th edition PMP

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docxdorishigh
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name InstructionBetseyCalderon89
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docxkarlhennesey
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newuopassignment
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 

Similar to Session 10 4th edition PMP (20)

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name Instruction
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 

Recently uploaded

internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 

Recently uploaded (20)

internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 

Session 10 4th edition PMP

  • 1. 1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first? A ) Determine the projected actual cost. B ) Implement a change control process to track the change C ) Inform the customer. D ) Determine the cause of the overage
  • 2. 2- Which of the following represents the value of work we have actually completed? A ) Earned value B ) Planned value C ) Actual cost D ) Estimate to complete
  • 3. 3- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs? A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B. B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker. C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later. D ) Remove a test from the project management plan.
  • 4. 4- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate? A ) You are progressing at 86% of the rate originally planned. B ) You are progressing at 125% of the rate originally planned. C ) You are progressing at 116% of the rate originally planned. D ) You are progressing at 80% of the rate originally planned.
  • 5. 5- The formula, EAC = BAC/CPI, assumes that: A ) All subsequent work will be completed at the planned expenditures. B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way C ) All subsequent work will be completed based upon the cost performance to-date D ) The cost performance cannot change during the project
  • 6. 6- What tool must project managers rely upon to accurately identify the costs associated with the project? A ) A bill of materials B ) A Gantt chart C ) A precedence diagram network D ) A work breakdown structure
  • 7. 7- If the Earned Value is equal to Actual Cost, it means: A-Project is on budget and on schedule B-Schedule Variance Index is 1 C-There is no schedule variance D-There is no cost variance
  • 8. 8-Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9 months. After a month, you have completed 10% of the project at a total expense of $100,000. The planned completion should have been 15%. At the current progress rate, how much more money is required to complete the project? A) $ 800,000 B) $ 900,000 C) $ 1,000,000 D) $ 1,100,000