SlideShare a Scribd company logo
CONSTRUCTION STATUTE:
CIPAA 2012 and ITS IMPLEMENTATION
YEO DOR EEN
YONG SING YEW
Construction Industry Payment and Adjudication Act 2012
An Act to recover payment which is due and haven’t paid for construction work
done or services rendered.
Enacted in Parliament on 22nd June 2012 and came into operation on 15th April
2014.
Divided into 7 parts.
Has 41 sections.
CIPAA is an Act of Parliament that makes adjudication compulsory via
statutory adjudication, hence, it does not allow parties to contract out of the
provisions of CIPAA and all construction contracts would be bound by this
statutory adjudication.
What is CIPAA?
Main
Objectives
of CIPAA
provide a cheaper and speedy dispute resolution
mechanism of adjudication in the construction
industry.
ensure and promote regular and prompt payment.
remove the conditional 'pay when paid' arrangement.
reduce the issue of cash flow shortage or non-payment
of progress payments which has always been a major
hindrance by obstructing the progress and completion
of many construction projects.
provides remedies for recovery of payment upon the
conclusion of adjudication.
a mandatory statutory process that does not require the
agreement of the parties’ to commence the process and
prevails over any contractual agreements to the
contrary between the parties. Statutory adjudication can
commenced at any time whether during or after the
project completion.
THE
ADJUDICATION
PROCESS
1.0 Application
Section 2
CIPAA applies to
Every construction contract made in
writing relating to construction work
carried out wholly or partly within the
territory of Malaysia including a
construction contract entered into by the
Government.
2.0 Non-application
Section 3
CIPAA does not apply to
Construction contracts entered into by a
natural person for the construction of a
building for his own occupation provided
it is less than 4 storeys high.
3.0 Interpretation
Section 4
CIPAA restricts claims to only claims for
payment for work done or service rendered
under expressed terms of a construction
contract.
4.0 Payment Claim (Step 1)
Section 5
The payment claim served by unpaid party to non-paying party shall be in writing and shall include:
The amount claimed and due date for payment of the amount claimed;
Details to identify the cause of action including the provision in the construction contract to which the
payment relates;
Description of the work or services to which the payment relates;
A statement that it is made under the Act.
5.0 Payment Response (Step 2)
Section 6
Upon receiving payment claim, the non-paying party has the following 3 options:
Admits to the payment claim, serve a payment response, together with the whole amount claimed or
any amount as admitted, to the unpaid party;
Disputes the amount claimed in the payment claim, either wholly or partly stating the amount disputed
and ten reason for the dispute, serve a payment response to the unpaid party;
Choose not to respond to a payment claim in the manner provided under this section. The non-paying
party is then deemed to have disputed the entire payment claims.
Payment response must be served on the unpaid party within 10 working days of the receipt of the
payment claim.
6.0 Commencement of Adjudication (Step 3)
Section 7
CIPAA provides for an unpaid party to refer a dispute arising from a payment claim to adjudication. The right to refer a
dispute to adjudication can only be carried out after the expiry of the period to serve a payment response as specified.
Section 8
A Claimant may initiate adjudication proceedings by serving a written notice of adjudication on the Respondent (non-
paying party) stating the nature and description of the dispute and remedy sought together with any supporting documents.
Section 21
Once the Respondent has received the notice of adjudication, an adjudicator may be appointed in the following manner:
both parties in dispute agree on an adjudicator within 10 working days from the service of the notice of adjudication
by the Claimant;
both parties in dispute cannot agree on an adjudicator within 10 working days from the service of notice of
adjudication by the Claimant, either party can request the Director of the KLRCA to appoint an adjudicator;
both parties in dispute agree to request the Director of KLRCA to appoint an adjudicator.
7.0 Appointment of Adjudicator (Step 4)
When both parties agreed on an adjudicator, the claimant shall notify the adjudicator to be appointed
in writing and provide him with a copy of the notice of adjudication. The adjudicator shall indicate
his acceptance of his appointment within 10 working days from the date he was notified of his
appointment.
When the adjudicator is appointed by the Director of KLRCA, the Director shall appoint an
adjudicator within 5 working days and shall notify the parties and adjudicator in writing. The
adjudicator shall indicate his acceptance of his appointment within 10 working days from the
date he was notified of his appointment.
8.0 Submission of Adjudication Claim (Step 5)
Section 9
Claimant shall serve an Adjudication Claim within 10 working days from the date of receipt of
acceptance of the appointment from the adjudicator on the Respondent with a copy to the adjudicator.
The Adjudication Claim should contain the nature of the claim, description of the dispute and the
remedy sought together with any supporting document.
The Claimant shall also serve a copy of the Adjudication Claim on the Director of KLRCA within 7
working days after served it to the Respondent.
9.0 Adjudication Response (Step 6)
Section 10 of CIPAA
• Respondents serve on the Claimant
• To answer the adjudication claim and be accompanied by any supporting documents
• Within 10 working days from the date of receipt of the Adjudication Claim
• For government construction contract of RM20m or less, the time limit to serve a
Adjudication Response is within 30 days
• The Respondents shall provide a copy of the Adjudication Response to the adjudicator
• Respondents shall also serve a copy of the Adjudication Response on the KLRCA within
7 working days after serving a written Adjudication Response.
• If fails to serve any adjudication response, the claimant may proceed with the
adjudication
10.0 Adjudication Reply (Step 7)
Section 11 of CIPAA
• The claimant may serve a written reply to the Adjudication Response together with supporting document
on the respondent.
• Within 5 working days from the date of receipt of the Adjudication Response
• For government construction contract of RM20m or less, the time limit to serve a Adjudication
Response is within 30 days
• Same copy of the Adjudication Reply shall be provided to adjudicator
• A copy shall also serve on KLRCA within 7 working days after serving a written Adjudication Reply
11.0 Delivery of Adjudication Decision (Step 8)
Section 12 of CIPAA
Adjudicator shall decide the dispute and deliver the adjudication decision within:
• 45 working days from the service of the adjudication response or reply to the adjudication response,
whichever is later
• 45 working days from the expiry of the period for the service of adjudication response if no
adjudication respond is received
• Any further time as agreed to by the parties
 If there are no any adjudication decision is made within the period specified, then it is null and void.
 The adjudication decision shall made in writing and contain reason for such decision
 It shall determine the adjudicated amount and the time and manner of payment
 A copy of the adjudication decision is to be served on each party and the Director of the KLRCA
Effect of Adjudication Decision
Section 13 of CIPAA
Adjudication decision is binding unless:
• It is set aside by the High Court in any event stated in Section 15
a. the decision was improperly procured through fraud or bribery
b. A denial of natural justice
c. the adjudicator had not acted independently or impartially
d. the adjudicator has acted in excess of his jurisdiction
• The subject matter of the decision is settled by a written agreement between the parties
• The dispute is finally decided by arbitration or the court
Enforcement of Adjudicator Decision
Based on Section 28 to 30 a party may enforce an Adjudicator decision in the following ways:
• Winner can apply to High Court to enforce Decision as a judgment or order of the High
Court (Section 28)
• Winner may suspend performance or reduce the rate of progress of
performance/consultancy services (Section 29)
• Seek direct payment from employer (Section 30)
Suspension or Reduction of the Rate of Progress of Performance
Section 29 of CIPAA
• Party that intending to suspend work or reduce rate of progress shall give written notice to the other party
• The party who exercise his rights to suspend or reduce the rate of progress
a. Is not in breach of contract
b. Is entitle to a fair and reasonable extension of time to complete his obligations under the contract
c. Entitle to recover any loss and expenses
d. Shall resume performance or the rate of progress within 10 working days after having paid by the
other party
Exemption Order 2014
Section 40 of CIPAA
The Minister of Works may, upon considering the recommendation of the KLRCA, to exempt:
a. Any person or class of persons
b. Any contract, matter or transaction or any class thereof,
from all or any of the provision of this act, subject to such terms and conditions as may be prescribed.
 Exemption Order 2014 also exempts two categories of Government construction contracts from the statutory
adjudication regime under the CIPAA.
1. First categories exempts 2 types of Government construction contracts in respect of construction works:
a. that is carried out urgently and without delay due to natural disaster, flood, landslide, ground subsidence, fire
and other emergency and unforeseen circumstances
b. that relates to national security or security related facilities
2. For second categories, it is only a partial exemption in that it gives the parties to Government construction
contracts with a contract sum of RM20 million or less, a longer period for service of certain documents, such as
the payment response, adjudication response and adjudication reply, than the time frames provided under the
CIPAA.
Q & A
1) What are the main objectives of CIPAA?
 To provide a cheaper and speedy dispute resolution.
 To ensure and promote regular and prompt payment.
 To remove the conditional 'pay when paid' arrangement.
 To reduce the issue of cash flow shortage or non-payment of progress payments.
 To provide remedies for recovery of payment upon the conclusion of adjudication.
2) Draw the adjudication process timeline.
10 days
10 days
10 days
10 days
10 days
5 days
45 days
Payment claim (by unpaid party)
Payment response (by non-paying party)
Issuance of notice of adjudication
Appointment of adjudicator
Adjudicator negotiates terms and fees
Adjudication process
Adjudication claim (by claimant)
Adjudication response (by respondent)
Adjudication reply (optional) (by claimant)
Adjudication commences
Adjudication decision
3) State two types of construction works that are exempted entirely from the
operation of CIPAA.
Answer:
1. Construction works that is carried out urgently and without delay due to natural disaster, flood,
landslide, ground subsidence, fire and other emergency and unforeseen circumstances
2. Construction works that is that relates to national security or security related facilities
4) What are the options available to a claimant that is successful in the
adjudication?
Answer:
1. Enforcement of the Adjudication Decision as a Court Order/Judgment (Section 28 of CIPAA
2012)
2. Suspension or Reduction of Rate of Progress of Performance (Section 29 of CIPAA 2012)
3. Direct Payment from Principal (Section 30 of CIPAA 2012)

More Related Content

What's hot

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
Kheng Hoe Advocates
 
PP1 report
PP1 reportPP1 report
PP1 report
Doreen Yeo
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
BAYARAN PENDAHULUAN
BAYARAN PENDAHULUANBAYARAN PENDAHULUAN
BAYARAN PENDAHULUANcik Ena
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
Syafiq Zariful
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
Trace96
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
Kai Yun Pang
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
wendyteosy
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
Melvin Lim
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
ahmong4
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
Pang Khai Shuen
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
Arissa Loh
 

What's hot (20)

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
BAYARAN PENDAHULUAN
BAYARAN PENDAHULUANBAYARAN PENDAHULUAN
BAYARAN PENDAHULUAN
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 

Similar to CIPAA presentation

CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
Ir Albert YEU FCIArb MICE
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
Ir Albert YEU FCIArb MICE
 
unit 5& 6.pptx
unit 5& 6.pptxunit 5& 6.pptx
unit 5& 6.pptx
Priyanka Gangwar
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
CIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptxCIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptx
ssuser27bb47
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
Resolution Institute
 
12. appeal and reference, ICAB, KL, Study Manual
12. appeal and reference, ICAB, KL, Study Manual12. appeal and reference, ICAB, KL, Study Manual
12. appeal and reference, ICAB, KL, Study Manual
Sazzad Hossain, ITP, MBA, CSCA™
 
Characteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
Characteristics of Insolvency Act 2063 - Nepal by Prajwal BhattaraiCharacteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
Characteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
Prajwal Bhattarai
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
Jessyca Than
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
MeneerGultom
 
AB 626: What It Means for Public Works Projects and What Public Agencies Need...
AB 626: What It Means for Public Works Projects and What Public Agencies Need...AB 626: What It Means for Public Works Projects and What Public Agencies Need...
AB 626: What It Means for Public Works Projects and What Public Agencies Need...
Meyers Nave
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
ashleyyeap
 
UK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletterUK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Tendering clauses of contract
Tendering clauses of contractTendering clauses of contract
Tendering clauses of contract
kkganimix
 
Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3
Resolution Institute
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
Seminar
SeminarSeminar
Seminar
kohwenqi
 
Fidic 99 ppt by dr karim
Fidic 99 ppt by dr karimFidic 99 ppt by dr karim
Fidic 99 ppt by dr karim
Salama Shurrab
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Pierrette Khoury BComm/B Laws, GDLP
 

Similar to CIPAA presentation (20)

CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
unit 5& 6.pptx
unit 5& 6.pptxunit 5& 6.pptx
unit 5& 6.pptx
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
CIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptxCIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptx
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
2125.aug 07
2125.aug 072125.aug 07
2125.aug 07
 
12. appeal and reference, ICAB, KL, Study Manual
12. appeal and reference, ICAB, KL, Study Manual12. appeal and reference, ICAB, KL, Study Manual
12. appeal and reference, ICAB, KL, Study Manual
 
Characteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
Characteristics of Insolvency Act 2063 - Nepal by Prajwal BhattaraiCharacteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
Characteristics of Insolvency Act 2063 - Nepal by Prajwal Bhattarai
 
Seminar p8x
Seminar p8xSeminar p8x
Seminar p8x
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
 
AB 626: What It Means for Public Works Projects and What Public Agencies Need...
AB 626: What It Means for Public Works Projects and What Public Agencies Need...AB 626: What It Means for Public Works Projects and What Public Agencies Need...
AB 626: What It Means for Public Works Projects and What Public Agencies Need...
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
UK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletterUK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletter
 
Tendering clauses of contract
Tendering clauses of contractTendering clauses of contract
Tendering clauses of contract
 
Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3Adjudication discussion evening (6 Sep, Sydney) - 2/3
Adjudication discussion evening (6 Sep, Sydney) - 2/3
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Seminar
SeminarSeminar
Seminar
 
Fidic 99 ppt by dr karim
Fidic 99 ppt by dr karimFidic 99 ppt by dr karim
Fidic 99 ppt by dr karim
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 

More from Doreen Yeo

Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slides
Doreen Yeo
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
Doreen Yeo
 
Financial Management Report
Financial Management ReportFinancial Management Report
Financial Management Report
Doreen Yeo
 
CSI Report
CSI ReportCSI Report
CSI Report
Doreen Yeo
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 brief
Doreen Yeo
 
BE Cost Plan
BE Cost Plan BE Cost Plan
BE Cost Plan
Doreen Yeo
 
BE presentation slides
BE presentation slidesBE presentation slides
BE presentation slides
Doreen Yeo
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisal
Doreen Yeo
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answer
Doreen Yeo
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
Doreen Yeo
 
Assignment ceiling finishes
Assignment ceiling finishesAssignment ceiling finishes
Assignment ceiling finishes
Doreen Yeo
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
Doreen Yeo
 
Software Application presentation slides
Software Application presentation slidesSoftware Application presentation slides
Software Application presentation slides
Doreen Yeo
 
Measurement IV assignment presentation slides
Measurement IV assignment presentation slides Measurement IV assignment presentation slides
Measurement IV assignment presentation slides
Doreen Yeo
 
Building Services ll Assignment
Building Services ll AssignmentBuilding Services ll Assignment
Building Services ll Assignment
Doreen Yeo
 
Management Science Report
Management Science ReportManagement Science Report
Management Science Report
Doreen Yeo
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
Doreen Yeo
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
Doreen Yeo
 
Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slides
Doreen Yeo
 
Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)
Doreen Yeo
 

More from Doreen Yeo (20)

Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slides
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
Financial Management Report
Financial Management ReportFinancial Management Report
Financial Management Report
 
CSI Report
CSI ReportCSI Report
CSI Report
 
Pp2 coursework 2 brief
Pp2 coursework 2  briefPp2 coursework 2  brief
Pp2 coursework 2 brief
 
BE Cost Plan
BE Cost Plan BE Cost Plan
BE Cost Plan
 
BE presentation slides
BE presentation slidesBE presentation slides
BE presentation slides
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisal
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answer
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
Assignment ceiling finishes
Assignment ceiling finishesAssignment ceiling finishes
Assignment ceiling finishes
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
Software Application presentation slides
Software Application presentation slidesSoftware Application presentation slides
Software Application presentation slides
 
Measurement IV assignment presentation slides
Measurement IV assignment presentation slides Measurement IV assignment presentation slides
Measurement IV assignment presentation slides
 
Building Services ll Assignment
Building Services ll AssignmentBuilding Services ll Assignment
Building Services ll Assignment
 
Management Science Report
Management Science ReportManagement Science Report
Management Science Report
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
 
Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slides
 
Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)
 

Recently uploaded

定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
BRELGOSIMAT
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
anvithaav
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
Knowyourright
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
KHURRAMWALI
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
Wendy Couture
 
ALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdfALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdf
46adnanshahzad
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
OmGod1
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Gabe Whitley
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
ssuser0576e4
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
AHRP Law Firm
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
9ib5wiwt
 
How to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the NetherlandsHow to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the Netherlands
BridgeWest.eu
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
Daffodil International University
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
Dr. Oliver Massmann
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
Finlaw Consultancy Pvt Ltd
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
SidharthKashyap5
 

Recently uploaded (20)

定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxNATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptx
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
 
ALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdfALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdf
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
 
Abdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal CourtAbdul Hakim Shabazz Deposition Hearing in Federal Court
Abdul Hakim Shabazz Deposition Hearing in Federal Court
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
 
How to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the NetherlandsHow to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the Netherlands
 
ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.ADR in criminal proceeding in Bangladesh with global perspective.
ADR in criminal proceeding in Bangladesh with global perspective.
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
VIETNAM - DIRECT POWER PURCHASE AGREEMENTS (DPPA) - Latest development - What...
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
 
Cold War - 1, talks about cold water bro
Cold War - 1, talks about cold water broCold War - 1, talks about cold water bro
Cold War - 1, talks about cold water bro
 

CIPAA presentation

  • 1. CONSTRUCTION STATUTE: CIPAA 2012 and ITS IMPLEMENTATION YEO DOR EEN YONG SING YEW
  • 2. Construction Industry Payment and Adjudication Act 2012 An Act to recover payment which is due and haven’t paid for construction work done or services rendered. Enacted in Parliament on 22nd June 2012 and came into operation on 15th April 2014. Divided into 7 parts. Has 41 sections. CIPAA is an Act of Parliament that makes adjudication compulsory via statutory adjudication, hence, it does not allow parties to contract out of the provisions of CIPAA and all construction contracts would be bound by this statutory adjudication. What is CIPAA?
  • 3. Main Objectives of CIPAA provide a cheaper and speedy dispute resolution mechanism of adjudication in the construction industry. ensure and promote regular and prompt payment. remove the conditional 'pay when paid' arrangement. reduce the issue of cash flow shortage or non-payment of progress payments which has always been a major hindrance by obstructing the progress and completion of many construction projects. provides remedies for recovery of payment upon the conclusion of adjudication. a mandatory statutory process that does not require the agreement of the parties’ to commence the process and prevails over any contractual agreements to the contrary between the parties. Statutory adjudication can commenced at any time whether during or after the project completion.
  • 5. 1.0 Application Section 2 CIPAA applies to Every construction contract made in writing relating to construction work carried out wholly or partly within the territory of Malaysia including a construction contract entered into by the Government. 2.0 Non-application Section 3 CIPAA does not apply to Construction contracts entered into by a natural person for the construction of a building for his own occupation provided it is less than 4 storeys high. 3.0 Interpretation Section 4 CIPAA restricts claims to only claims for payment for work done or service rendered under expressed terms of a construction contract.
  • 6. 4.0 Payment Claim (Step 1) Section 5 The payment claim served by unpaid party to non-paying party shall be in writing and shall include: The amount claimed and due date for payment of the amount claimed; Details to identify the cause of action including the provision in the construction contract to which the payment relates; Description of the work or services to which the payment relates; A statement that it is made under the Act.
  • 7. 5.0 Payment Response (Step 2) Section 6 Upon receiving payment claim, the non-paying party has the following 3 options: Admits to the payment claim, serve a payment response, together with the whole amount claimed or any amount as admitted, to the unpaid party; Disputes the amount claimed in the payment claim, either wholly or partly stating the amount disputed and ten reason for the dispute, serve a payment response to the unpaid party; Choose not to respond to a payment claim in the manner provided under this section. The non-paying party is then deemed to have disputed the entire payment claims. Payment response must be served on the unpaid party within 10 working days of the receipt of the payment claim.
  • 8. 6.0 Commencement of Adjudication (Step 3) Section 7 CIPAA provides for an unpaid party to refer a dispute arising from a payment claim to adjudication. The right to refer a dispute to adjudication can only be carried out after the expiry of the period to serve a payment response as specified. Section 8 A Claimant may initiate adjudication proceedings by serving a written notice of adjudication on the Respondent (non- paying party) stating the nature and description of the dispute and remedy sought together with any supporting documents. Section 21 Once the Respondent has received the notice of adjudication, an adjudicator may be appointed in the following manner: both parties in dispute agree on an adjudicator within 10 working days from the service of the notice of adjudication by the Claimant; both parties in dispute cannot agree on an adjudicator within 10 working days from the service of notice of adjudication by the Claimant, either party can request the Director of the KLRCA to appoint an adjudicator; both parties in dispute agree to request the Director of KLRCA to appoint an adjudicator.
  • 9. 7.0 Appointment of Adjudicator (Step 4) When both parties agreed on an adjudicator, the claimant shall notify the adjudicator to be appointed in writing and provide him with a copy of the notice of adjudication. The adjudicator shall indicate his acceptance of his appointment within 10 working days from the date he was notified of his appointment. When the adjudicator is appointed by the Director of KLRCA, the Director shall appoint an adjudicator within 5 working days and shall notify the parties and adjudicator in writing. The adjudicator shall indicate his acceptance of his appointment within 10 working days from the date he was notified of his appointment.
  • 10. 8.0 Submission of Adjudication Claim (Step 5) Section 9 Claimant shall serve an Adjudication Claim within 10 working days from the date of receipt of acceptance of the appointment from the adjudicator on the Respondent with a copy to the adjudicator. The Adjudication Claim should contain the nature of the claim, description of the dispute and the remedy sought together with any supporting document. The Claimant shall also serve a copy of the Adjudication Claim on the Director of KLRCA within 7 working days after served it to the Respondent.
  • 11. 9.0 Adjudication Response (Step 6) Section 10 of CIPAA • Respondents serve on the Claimant • To answer the adjudication claim and be accompanied by any supporting documents • Within 10 working days from the date of receipt of the Adjudication Claim • For government construction contract of RM20m or less, the time limit to serve a Adjudication Response is within 30 days • The Respondents shall provide a copy of the Adjudication Response to the adjudicator • Respondents shall also serve a copy of the Adjudication Response on the KLRCA within 7 working days after serving a written Adjudication Response. • If fails to serve any adjudication response, the claimant may proceed with the adjudication
  • 12. 10.0 Adjudication Reply (Step 7) Section 11 of CIPAA • The claimant may serve a written reply to the Adjudication Response together with supporting document on the respondent. • Within 5 working days from the date of receipt of the Adjudication Response • For government construction contract of RM20m or less, the time limit to serve a Adjudication Response is within 30 days • Same copy of the Adjudication Reply shall be provided to adjudicator • A copy shall also serve on KLRCA within 7 working days after serving a written Adjudication Reply
  • 13. 11.0 Delivery of Adjudication Decision (Step 8) Section 12 of CIPAA Adjudicator shall decide the dispute and deliver the adjudication decision within: • 45 working days from the service of the adjudication response or reply to the adjudication response, whichever is later • 45 working days from the expiry of the period for the service of adjudication response if no adjudication respond is received • Any further time as agreed to by the parties  If there are no any adjudication decision is made within the period specified, then it is null and void.  The adjudication decision shall made in writing and contain reason for such decision  It shall determine the adjudicated amount and the time and manner of payment  A copy of the adjudication decision is to be served on each party and the Director of the KLRCA
  • 14. Effect of Adjudication Decision Section 13 of CIPAA Adjudication decision is binding unless: • It is set aside by the High Court in any event stated in Section 15 a. the decision was improperly procured through fraud or bribery b. A denial of natural justice c. the adjudicator had not acted independently or impartially d. the adjudicator has acted in excess of his jurisdiction • The subject matter of the decision is settled by a written agreement between the parties • The dispute is finally decided by arbitration or the court
  • 15. Enforcement of Adjudicator Decision Based on Section 28 to 30 a party may enforce an Adjudicator decision in the following ways: • Winner can apply to High Court to enforce Decision as a judgment or order of the High Court (Section 28) • Winner may suspend performance or reduce the rate of progress of performance/consultancy services (Section 29) • Seek direct payment from employer (Section 30)
  • 16. Suspension or Reduction of the Rate of Progress of Performance Section 29 of CIPAA • Party that intending to suspend work or reduce rate of progress shall give written notice to the other party • The party who exercise his rights to suspend or reduce the rate of progress a. Is not in breach of contract b. Is entitle to a fair and reasonable extension of time to complete his obligations under the contract c. Entitle to recover any loss and expenses d. Shall resume performance or the rate of progress within 10 working days after having paid by the other party
  • 17. Exemption Order 2014 Section 40 of CIPAA The Minister of Works may, upon considering the recommendation of the KLRCA, to exempt: a. Any person or class of persons b. Any contract, matter or transaction or any class thereof, from all or any of the provision of this act, subject to such terms and conditions as may be prescribed.
  • 18.  Exemption Order 2014 also exempts two categories of Government construction contracts from the statutory adjudication regime under the CIPAA. 1. First categories exempts 2 types of Government construction contracts in respect of construction works: a. that is carried out urgently and without delay due to natural disaster, flood, landslide, ground subsidence, fire and other emergency and unforeseen circumstances b. that relates to national security or security related facilities 2. For second categories, it is only a partial exemption in that it gives the parties to Government construction contracts with a contract sum of RM20 million or less, a longer period for service of certain documents, such as the payment response, adjudication response and adjudication reply, than the time frames provided under the CIPAA.
  • 19. Q & A
  • 20. 1) What are the main objectives of CIPAA?  To provide a cheaper and speedy dispute resolution.  To ensure and promote regular and prompt payment.  To remove the conditional 'pay when paid' arrangement.  To reduce the issue of cash flow shortage or non-payment of progress payments.  To provide remedies for recovery of payment upon the conclusion of adjudication.
  • 21. 2) Draw the adjudication process timeline. 10 days 10 days 10 days 10 days 10 days 5 days 45 days Payment claim (by unpaid party) Payment response (by non-paying party) Issuance of notice of adjudication Appointment of adjudicator Adjudicator negotiates terms and fees Adjudication process Adjudication claim (by claimant) Adjudication response (by respondent) Adjudication reply (optional) (by claimant) Adjudication commences Adjudication decision
  • 22. 3) State two types of construction works that are exempted entirely from the operation of CIPAA. Answer: 1. Construction works that is carried out urgently and without delay due to natural disaster, flood, landslide, ground subsidence, fire and other emergency and unforeseen circumstances 2. Construction works that is that relates to national security or security related facilities
  • 23. 4) What are the options available to a claimant that is successful in the adjudication? Answer: 1. Enforcement of the Adjudication Decision as a Court Order/Judgment (Section 28 of CIPAA 2012) 2. Suspension or Reduction of Rate of Progress of Performance (Section 29 of CIPAA 2012) 3. Direct Payment from Principal (Section 30 of CIPAA 2012)