SlideShare a Scribd company logo
1 of 16
CONSTRUCTION DISPUTES
• Construction projects are generally complex , for this reason, delays
and disputes are always present
• Involved many parties.
• When a project ends up in a dispute, the project will fail to meet its
original goals and expectation.
• Clients will suffer from high legal fees, delayed completion and
occupation and general dissatisfaction.
• The contractor’s profits will diminish and to these will be added
additional legal fees.
1
CAUSES OF DISPUTES
• May arise on a construction project for a number of reasons:
Late or non-payment for works satisfactorily completed when
payment is due.
Inaccurate valuation of variations and works in progress.
Delays in the supply of general construction information
• Late issue of instruction varying some sections of the works.
• Shortcomings, omissions and errors in contract documentation giving
rise to ambiguities in contract requirements.
• Failure of contractor to construct the works diligently and to
programme.
2
DISPUTE RESOLUTION CLAUSE
A dispute resolution clause is an agreement within a contract which sets
out the mechanism for the resolution of disputes between the Contractual
parties. The scope of that agreement is determined in the drafting of the
clause. ... An increasingly popular alternative for commercial contracts is
arbitration
Arbitration
Arbitration is a legal technique for the resolution of disputes outside the
courts, wherein the parties to a dispute refer it to one or more persons
(the "arbitrators", "arbiters" or "arbitral tribunal"), by whose decision (the
"award") they agree to be bound.
As per the general conditions of contract (GCC) for
CPWD works 2007, the dispute resolution mechanism for
contracts concluded by C.P.W.D. Consists of following:
Reference to Engineer Authorities:
• As per clause 35 pertaining to settlement of disputes in arbitration
in the GCC for CPWD works 2007, all disputes with respect to the
contract shall be referred to the superintending Engineer (SE) in
writing within fifteen days of the cause of action.
• The SE shall give his decision in writing within one month of the
request from contractor.
• The contractor shall appeal to the Chief Engineer within
fifteen days of receipt of SE’s decision. The Chief engineer is
required to give his decision within thirty days of receipt or
contractor’s appeal after giving adequate opportunity to the
contractor to present his case
DISPUTE REDRESSAL COMMITTEE
• In case of dissatisfaction from Chief Engineer’s decision the
contractor can approach the DRC within a time limit of thirty
days. The DRC has to give its decision within ninety days.
• In case, any party is dissatisfied with the decision given by DRC, it
can invoke arbitration within thirty days from the receipt of
decision from DRC. In case, no such reference is made for
invoking arbitration, the DRC decision shall become final and
binding and the parties shall forfeit their right for reference to
arbitration.
• There shall be a standing committee which shall be constituted
for each zone separately for total claims up to twenty five lakh
and more than twenty five lakh. The committees shall comprise of
engineer members of CPWD of the ranks of Chief Engineer, SC
Arbitration:
• The fee to be paid to the arbitrator shall be shared equally by both
the parties before publishing of the award. However, the actual
distribution of the fee and cost of reference may be decided by the
arbitrator in the award.
Working during Arbitration:
• Unless the contract is already terminated, during the entire process
of dispute resolution the contractor shall continue to progress with
the work as per the contract conditions. Thus, there is no embargo
on proceeding with the resolution of disputes during the currency
the contract.
DESIGN, DEVELOPMENT & IMPLEMENTATION OFKNOWLEDGE WEB
PORTAL FOR SUSTAINABLE HABITAT IN INDIA
Settlement of Disputes
• If any dispute of any kind whatsoever shall arise between BMTPC and
Successful Bidder the parties shall seek to resolve any such dispute by
mutual consultation.
• If the parties fail to resolve, within 45 days of its arising, then the
shall be referred by either party by giving notice to the other party. No
arbitration may be commenced unless such notice is given.
In case the Successful Bidder is a Government Department
• the dispute shall be referred for resolution in Permanent Machinery for
Arbitration (PMA) of the Department of Public Enterprise, Government
of India. Such dispute shall be referred for Arbitration to the sole
Arbitrator in the Department of Public Enterprises
• However, any party aggrieved by such award they can further revise
award to the Law Secretary, Department of Legal Affairs, Ministry of
& Justice, Government of India.
• Upon such reference the decision shall be decided by the Law
/ Additional Secretary, that decision shall bind the Parties finally.
• The Parties to the dispute will share equally the cost of arbitration as
intimated by the Arbitrator.
In case the Successful Bidder is not a Government Department.
• In any dispute of any kind whatsoever arising under this contract
shall be referred to the Sole Arbitrator, the ED of BMTPC or to a
person appointed by him for the purpose.
• The arbitration shall be conducted in accordance with the
provision of the Indian Arbitration and Conciliation Act, 1996.
• The Arbitrator may from the time to time, with the agreement of
all parties extend the time in making the award.
• The cost incidental to the arbitration shall be at the discretion of
the Arbitrator.
• Notwithstanding any dispute between the parties Successful
Bidder shall not be entitled to withhold, delay or defer his
obligation under the contract and same shall be carried out
in accordance with the terms & conditions of the contract.
• The arbitrator shall give his reasoned award with respect to the disputes
referred to him by either of the parties.
• If for any reason an arbitrator is unable to perform its function, the
mandate of the Arbitrator shall terminate in accordance with the
provisions of applicable laws as mentioned in GCC Clause
• (Applicable Law) and a substitute shall be appointed in the same
manner as the original arbitrator.
• Arbitration proceedings shall be conducted with The Arbitration and
Conciliation Act, 1996.
• The parties shall continue to perform their respective obligations under
the agreement unless otherwise agreed mutually.
NATIONAL THERMAL POWER
CORPORATION LIMITED (NTPC)
• In the event of any query, dispute or difference whatsoever arising under this contract
or in connection with any question relating to existence, meaning and interpretation of
[his contract or any alleged breach thereof, the same will be referred to the sole
arbitrator of the General Manager of the NTPC or to a person appointed by him for the
purpose. The arbitration shall be conducted in accordance will the provisions of Indian
Arbitration Reconciliation Act, 1996
• It will be no objection that the Arbitrator is an interested person and/or that he had to
deal with the matters to which the contract relates and/or in the course of his duties he
expressed any view on any mutter in dispute. The award of arbitrator shall be final and
binding.
• In the event of Arbitrator dying, neglecting, resigning or being unable to act for any
reason or his award being set aside by the court for any reason, it will lawful for the
General Manager of the NTPC to appoint another Arbitrator in place of the outgoing
Arbitrator.
• It is further terms of this agreement that no person other than
the person shall act as an Arbitrator and that, if for any reason
that is not possible, the matter should not be referred to
arbitration at all.
• The Arbitrator may from time to time, with the consent of nil
parties enlarge the time ill making the award.
• The cost incidental to the arbitration shall be at the discretion
of the Arbitrator; the arbitration shall be conducted in NEW
DELHI or at such other places where arbitrator may decide.
• Not withstanding any dispute between the parties Supplier shall
not be entitled to withhold delay or defer his obligation under
the contract and same shall be carried out strictly in accordance
with terms and condition of contract.
• In the event of dispute or difference arising between parties the
public sector enterprise and Government, the provision of BPE
office memorandum No BPE/GL001/76/MAN/2110-75-BPE
(GML-1) dated 1st January 1976 shall be applicable.

More Related Content

What's hot

Liquidated damages and penalty clause
Liquidated damages and penalty clauseLiquidated damages and penalty clause
Liquidated damages and penalty clauseAdela Perez del Viso
 
Arbitration Law
Arbitration LawArbitration Law
Arbitration LawLeks&Co
 
Arbitration and Conciliation Act
Arbitration and Conciliation ActArbitration and Conciliation Act
Arbitration and Conciliation ActRohit Saraswat
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...SHKLaw
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2A&C Act - CHAPTER III - Kapl Dev Bahl rev 2
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2cmmindia2017
 
Arbitration and conciliation amnedment 2015
Arbitration and conciliation amnedment 2015Arbitration and conciliation amnedment 2015
Arbitration and conciliation amnedment 2015Amitabh Srivastava
 
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREcmmindia2017
 
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India-  an outlook by Rupendra Porwal, RallyMark LegalArbitration in India-  an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India- an outlook by Rupendra Porwal, RallyMark LegalRupendra Porwal
 
Contract for consultancy services lump sum - c special conditions
Contract for consultancy services   lump sum - c special conditionsContract for consultancy services   lump sum - c special conditions
Contract for consultancy services lump sum - c special conditionsJoy Irman
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Chpater 10 The Arbirtation & Conciliation Act
Chpater 10   The Arbirtation & Conciliation ActChpater 10   The Arbirtation & Conciliation Act
Chpater 10 The Arbirtation & Conciliation ActRobin Kapoor
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Arbitration and conciliation act
Arbitration and conciliation actArbitration and conciliation act
Arbitration and conciliation actDr. Arun Mittal
 
Contract lecture Note
 Contract  lecture Note Contract  lecture Note
Contract lecture NoteJifara Chimdi
 
Section 9 of the Arbitration and Conciliation Act, 1996
Section 9 of the Arbitration and Conciliation Act, 1996Section 9 of the Arbitration and Conciliation Act, 1996
Section 9 of the Arbitration and Conciliation Act, 1996Legal
 

What's hot (20)

Liquidated damages and penalty clause
Liquidated damages and penalty clauseLiquidated damages and penalty clause
Liquidated damages and penalty clause
 
CIArb Promotional Talk
CIArb Promotional TalkCIArb Promotional Talk
CIArb Promotional Talk
 
Arbitration Law
Arbitration LawArbitration Law
Arbitration Law
 
Arbitration and Conciliation Act
Arbitration and Conciliation ActArbitration and Conciliation Act
Arbitration and Conciliation Act
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2A&C Act - CHAPTER III - Kapl Dev Bahl rev 2
A&C Act - CHAPTER III - Kapl Dev Bahl rev 2
 
Arbitration and conciliation amnedment 2015
Arbitration and conciliation amnedment 2015Arbitration and conciliation amnedment 2015
Arbitration and conciliation amnedment 2015
 
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
 
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India-  an outlook by Rupendra Porwal, RallyMark LegalArbitration in India-  an outlook by Rupendra Porwal, RallyMark Legal
Arbitration in India- an outlook by Rupendra Porwal, RallyMark Legal
 
Payment terms in construction industry
Payment terms in construction industryPayment terms in construction industry
Payment terms in construction industry
 
Contract for consultancy services lump sum - c special conditions
Contract for consultancy services   lump sum - c special conditionsContract for consultancy services   lump sum - c special conditions
Contract for consultancy services lump sum - c special conditions
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Chpater 10 The Arbirtation & Conciliation Act
Chpater 10   The Arbirtation & Conciliation ActChpater 10   The Arbirtation & Conciliation Act
Chpater 10 The Arbirtation & Conciliation Act
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Arbitration and conciliation act
Arbitration and conciliation actArbitration and conciliation act
Arbitration and conciliation act
 
Retention fund
Retention fundRetention fund
Retention fund
 
Contract lecture Note
 Contract  lecture Note Contract  lecture Note
Contract lecture Note
 
Section 9 of the Arbitration and Conciliation Act, 1996
Section 9 of the Arbitration and Conciliation Act, 1996Section 9 of the Arbitration and Conciliation Act, 1996
Section 9 of the Arbitration and Conciliation Act, 1996
 

Similar to Cc 2

Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfDispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfANKITGUPTA592329
 
Project dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitrationProject dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitration Dr K M SONI
 
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATIONengrqasimbutt
 
A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016Mahesh Gupta
 
Ppt on unit 8 Electrical Design Estimate
Ppt on unit 8 Electrical Design EstimatePpt on unit 8 Electrical Design Estimate
Ppt on unit 8 Electrical Design Estimatebiplabskfgi
 
Notes unit 2B for presentation.ppt
Notes unit 2B for presentation.pptNotes unit 2B for presentation.ppt
Notes unit 2B for presentation.pptpiyushbhandari36
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 
Construction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services ContractConstruction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services ContractIr Albert YEU FCIArb MICE
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxMeneerGultom
 
Dispute resolution clause Overview
Dispute resolution clause OverviewDispute resolution clause Overview
Dispute resolution clause OverviewAbdelrahman Eldosh
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsResolution Institute
 

Similar to Cc 2 (20)

Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdfDispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
Dispute 2022-23 - Lecture 4_ACA 1996 (2015+2019+2020 Amendments).pdf
 
Project dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitrationProject dispute avoidance and mitigation through conciliation and arbitration
Project dispute avoidance and mitigation through conciliation and arbitration
 
CCDC 2 Dispute Resolution
CCDC 2 Dispute ResolutionCCDC 2 Dispute Resolution
CCDC 2 Dispute Resolution
 
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION
3- Construction Disputes Lectures COVERING NEGOTIATION AND ARBITRATION
 
A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016A & C (amdt) Act 2015 - Sept 2016
A & C (amdt) Act 2015 - Sept 2016
 
Ppt on unit 8 Electrical Design Estimate
Ppt on unit 8 Electrical Design EstimatePpt on unit 8 Electrical Design Estimate
Ppt on unit 8 Electrical Design Estimate
 
Notes unit 2B for presentation.ppt
Notes unit 2B for presentation.pptNotes unit 2B for presentation.ppt
Notes unit 2B for presentation.ppt
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Seminar
SeminarSeminar
Seminar
 
Performance of contract
Performance of contractPerformance of contract
Performance of contract
 
CIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptxCIAC-ADR_PPT.pptx
CIAC-ADR_PPT.pptx
 
Construction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services ContractConstruction Adjudication for Professional Services Contract
Construction Adjudication for Professional Services Contract
 
CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021CIPAA Conference - 21 August 2021
CIPAA Conference - 21 August 2021
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
 
Dispute resolution clause Overview
Dispute resolution clause OverviewDispute resolution clause Overview
Dispute resolution clause Overview
 
UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution Boards
 

More from AKHIL GEORGE

Sub presentation (1)
Sub presentation (1)Sub presentation (1)
Sub presentation (1)AKHIL GEORGE
 
Essentials of-communication
Essentials of-communicationEssentials of-communication
Essentials of-communicationAKHIL GEORGE
 
HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT AKHIL GEORGE
 
Toxic leadership ppt
Toxic leadership pptToxic leadership ppt
Toxic leadership pptAKHIL GEORGE
 
Wood barn India: Trying to break Concrete Mindset
 Wood barn India: Trying to break Concrete Mindset Wood barn India: Trying to break Concrete Mindset
Wood barn India: Trying to break Concrete MindsetAKHIL GEORGE
 
Waste Disposal and Recycling
Waste Disposal and RecyclingWaste Disposal and Recycling
Waste Disposal and RecyclingAKHIL GEORGE
 

More from AKHIL GEORGE (11)

Sub presentation (1)
Sub presentation (1)Sub presentation (1)
Sub presentation (1)
 
Cbd
CbdCbd
Cbd
 
Essentials of-communication
Essentials of-communicationEssentials of-communication
Essentials of-communication
 
Quality ppt copy
Quality ppt   copyQuality ppt   copy
Quality ppt copy
 
Heathrow airport
Heathrow airportHeathrow airport
Heathrow airport
 
HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT
 
Toxic leadership ppt
Toxic leadership pptToxic leadership ppt
Toxic leadership ppt
 
Wood barn India: Trying to break Concrete Mindset
 Wood barn India: Trying to break Concrete Mindset Wood barn India: Trying to break Concrete Mindset
Wood barn India: Trying to break Concrete Mindset
 
Jackma
JackmaJackma
Jackma
 
Law presentation
Law presentationLaw presentation
Law presentation
 
Waste Disposal and Recycling
Waste Disposal and RecyclingWaste Disposal and Recycling
Waste Disposal and Recycling
 

Recently uploaded

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

Cc 2

  • 1. CONSTRUCTION DISPUTES • Construction projects are generally complex , for this reason, delays and disputes are always present • Involved many parties. • When a project ends up in a dispute, the project will fail to meet its original goals and expectation. • Clients will suffer from high legal fees, delayed completion and occupation and general dissatisfaction. • The contractor’s profits will diminish and to these will be added additional legal fees. 1
  • 2. CAUSES OF DISPUTES • May arise on a construction project for a number of reasons: Late or non-payment for works satisfactorily completed when payment is due. Inaccurate valuation of variations and works in progress. Delays in the supply of general construction information • Late issue of instruction varying some sections of the works. • Shortcomings, omissions and errors in contract documentation giving rise to ambiguities in contract requirements. • Failure of contractor to construct the works diligently and to programme. 2
  • 3. DISPUTE RESOLUTION CLAUSE A dispute resolution clause is an agreement within a contract which sets out the mechanism for the resolution of disputes between the Contractual parties. The scope of that agreement is determined in the drafting of the clause. ... An increasingly popular alternative for commercial contracts is arbitration Arbitration Arbitration is a legal technique for the resolution of disputes outside the courts, wherein the parties to a dispute refer it to one or more persons (the "arbitrators", "arbiters" or "arbitral tribunal"), by whose decision (the "award") they agree to be bound.
  • 4. As per the general conditions of contract (GCC) for CPWD works 2007, the dispute resolution mechanism for contracts concluded by C.P.W.D. Consists of following: Reference to Engineer Authorities: • As per clause 35 pertaining to settlement of disputes in arbitration in the GCC for CPWD works 2007, all disputes with respect to the contract shall be referred to the superintending Engineer (SE) in writing within fifteen days of the cause of action.
  • 5. • The SE shall give his decision in writing within one month of the request from contractor. • The contractor shall appeal to the Chief Engineer within fifteen days of receipt of SE’s decision. The Chief engineer is required to give his decision within thirty days of receipt or contractor’s appeal after giving adequate opportunity to the contractor to present his case
  • 6. DISPUTE REDRESSAL COMMITTEE • In case of dissatisfaction from Chief Engineer’s decision the contractor can approach the DRC within a time limit of thirty days. The DRC has to give its decision within ninety days. • In case, any party is dissatisfied with the decision given by DRC, it can invoke arbitration within thirty days from the receipt of decision from DRC. In case, no such reference is made for invoking arbitration, the DRC decision shall become final and binding and the parties shall forfeit their right for reference to arbitration. • There shall be a standing committee which shall be constituted for each zone separately for total claims up to twenty five lakh and more than twenty five lakh. The committees shall comprise of engineer members of CPWD of the ranks of Chief Engineer, SC
  • 7. Arbitration: • The fee to be paid to the arbitrator shall be shared equally by both the parties before publishing of the award. However, the actual distribution of the fee and cost of reference may be decided by the arbitrator in the award. Working during Arbitration: • Unless the contract is already terminated, during the entire process of dispute resolution the contractor shall continue to progress with the work as per the contract conditions. Thus, there is no embargo on proceeding with the resolution of disputes during the currency the contract.
  • 8.
  • 9. DESIGN, DEVELOPMENT & IMPLEMENTATION OFKNOWLEDGE WEB PORTAL FOR SUSTAINABLE HABITAT IN INDIA Settlement of Disputes • If any dispute of any kind whatsoever shall arise between BMTPC and Successful Bidder the parties shall seek to resolve any such dispute by mutual consultation. • If the parties fail to resolve, within 45 days of its arising, then the shall be referred by either party by giving notice to the other party. No arbitration may be commenced unless such notice is given.
  • 10. In case the Successful Bidder is a Government Department • the dispute shall be referred for resolution in Permanent Machinery for Arbitration (PMA) of the Department of Public Enterprise, Government of India. Such dispute shall be referred for Arbitration to the sole Arbitrator in the Department of Public Enterprises • However, any party aggrieved by such award they can further revise award to the Law Secretary, Department of Legal Affairs, Ministry of & Justice, Government of India. • Upon such reference the decision shall be decided by the Law / Additional Secretary, that decision shall bind the Parties finally. • The Parties to the dispute will share equally the cost of arbitration as intimated by the Arbitrator.
  • 11. In case the Successful Bidder is not a Government Department. • In any dispute of any kind whatsoever arising under this contract shall be referred to the Sole Arbitrator, the ED of BMTPC or to a person appointed by him for the purpose. • The arbitration shall be conducted in accordance with the provision of the Indian Arbitration and Conciliation Act, 1996. • The Arbitrator may from the time to time, with the agreement of all parties extend the time in making the award. • The cost incidental to the arbitration shall be at the discretion of the Arbitrator. • Notwithstanding any dispute between the parties Successful Bidder shall not be entitled to withhold, delay or defer his obligation under the contract and same shall be carried out in accordance with the terms & conditions of the contract.
  • 12. • The arbitrator shall give his reasoned award with respect to the disputes referred to him by either of the parties. • If for any reason an arbitrator is unable to perform its function, the mandate of the Arbitrator shall terminate in accordance with the provisions of applicable laws as mentioned in GCC Clause • (Applicable Law) and a substitute shall be appointed in the same manner as the original arbitrator. • Arbitration proceedings shall be conducted with The Arbitration and Conciliation Act, 1996. • The parties shall continue to perform their respective obligations under the agreement unless otherwise agreed mutually.
  • 13. NATIONAL THERMAL POWER CORPORATION LIMITED (NTPC) • In the event of any query, dispute or difference whatsoever arising under this contract or in connection with any question relating to existence, meaning and interpretation of [his contract or any alleged breach thereof, the same will be referred to the sole arbitrator of the General Manager of the NTPC or to a person appointed by him for the purpose. The arbitration shall be conducted in accordance will the provisions of Indian Arbitration Reconciliation Act, 1996
  • 14. • It will be no objection that the Arbitrator is an interested person and/or that he had to deal with the matters to which the contract relates and/or in the course of his duties he expressed any view on any mutter in dispute. The award of arbitrator shall be final and binding. • In the event of Arbitrator dying, neglecting, resigning or being unable to act for any reason or his award being set aside by the court for any reason, it will lawful for the General Manager of the NTPC to appoint another Arbitrator in place of the outgoing Arbitrator.
  • 15. • It is further terms of this agreement that no person other than the person shall act as an Arbitrator and that, if for any reason that is not possible, the matter should not be referred to arbitration at all. • The Arbitrator may from time to time, with the consent of nil parties enlarge the time ill making the award. • The cost incidental to the arbitration shall be at the discretion of the Arbitrator; the arbitration shall be conducted in NEW DELHI or at such other places where arbitrator may decide.
  • 16. • Not withstanding any dispute between the parties Supplier shall not be entitled to withhold delay or defer his obligation under the contract and same shall be carried out strictly in accordance with terms and condition of contract. • In the event of dispute or difference arising between parties the public sector enterprise and Government, the provision of BPE office memorandum No BPE/GL001/76/MAN/2110-75-BPE (GML-1) dated 1st January 1976 shall be applicable.