The document discusses material requirements planning (MRP) which determines the components and quantities needed to produce items in the master production schedule. MRP explodes bills of material to calculate gross requirements and offsets them based on lead times. It then determines net requirements by subtracting inventory and scheduled receipts. Planned orders are created and either released as real orders if components are available or rescheduled if not. The goal is to keep priorities current and meet product requirements.
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP). It describes the key tasks of MRP including meeting production requirements and capabilities while minimizing inventory and maintaining records. Benefits of MRP include better response to demand, faster market changes, improved utilization, and reduced inventory. MRP uses a bill of materials and master production schedule to calculate dependent demand and determine gross requirements. It then calculates net requirements by factoring inventory levels.
The document provides an overview and example of materials requirement planning (MRP). MRP is a system used to determine the materials, components, and quantities needed to meet production schedules. The example shows how MRP works by using a bill of materials (BOM) and lead times to create a schedule that determines when orders need to be placed to ensure availability of all items when needed for production. Key outputs of MRP include planned order schedules, inventory reports, and exception reports to monitor discrepancies.
The document discusses materials requirements planning (MRP), which determines the materials, parts, and components needed to produce products based on a master production schedule and bill of materials. MRP creates schedules that identify requirements, quantities, and timing of orders based on lead times. It provides primary reports like planned orders and secondary reports for planning and performance. MRP uses inventory and production data to generate net requirements through a process of scheduling gross requirements and projected inventory.
The document provides information on MRP (Material Requirements Planning), including its characteristics, elements, formulas, and lot sizing techniques. It then presents two example problems demonstrating how to construct a product tree, represent level codes, and develop a net material requirements plan. The problems show how to account for changes in demand and calculate planned order quantities using different techniques.
How to activate SAP ATP check for Sales Order, when you place item in sales order. Getting the material's supply and demand information,then meet customer's request delivery date.
1. Material Requirements Planning (MRP) is a computer-based production planning and inventory control system used to determine production and purchasing requirements.
2. MRP takes the master production schedule for end items and translates it into individual time-phased component requirements based on the product structure and lead times.
3. The MRP process involves establishing gross requirements, determining net requirements by subtracting inventory from gross requirements, time-phasing net requirements, and determining planned order releases.
This document provides an overview of materials requirements planning (MRP). It discusses the history and objectives of MRP, which is designed to determine materials needs based on a master production schedule and bill of materials. The key inputs to MRP are outlined, including the master production schedule, bill of materials, and inventory records. An example is provided to demonstrate how MRP works. Safety stocks are also discussed as a way to account for variations in demand and supply.
MRP is a system used in manufacturing to plan production schedules and material requirements. It takes inputs like the master production schedule and bill of materials to calculate net requirements through a process of exploding, netting, and offsetting. This helps control inventory levels and supports forecasted demand. MRP evolved into MRPII, which further integrates capacity planning, production scheduling, and other functions. While MRP improved efficiency, it also has disadvantages like reliance on accurate information and limited capacity planning.
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP). It describes the key tasks of MRP including meeting production requirements and capabilities while minimizing inventory and maintaining records. Benefits of MRP include better response to demand, faster market changes, improved utilization, and reduced inventory. MRP uses a bill of materials and master production schedule to calculate dependent demand and determine gross requirements. It then calculates net requirements by factoring inventory levels.
The document provides an overview and example of materials requirement planning (MRP). MRP is a system used to determine the materials, components, and quantities needed to meet production schedules. The example shows how MRP works by using a bill of materials (BOM) and lead times to create a schedule that determines when orders need to be placed to ensure availability of all items when needed for production. Key outputs of MRP include planned order schedules, inventory reports, and exception reports to monitor discrepancies.
The document discusses materials requirements planning (MRP), which determines the materials, parts, and components needed to produce products based on a master production schedule and bill of materials. MRP creates schedules that identify requirements, quantities, and timing of orders based on lead times. It provides primary reports like planned orders and secondary reports for planning and performance. MRP uses inventory and production data to generate net requirements through a process of scheduling gross requirements and projected inventory.
The document provides information on MRP (Material Requirements Planning), including its characteristics, elements, formulas, and lot sizing techniques. It then presents two example problems demonstrating how to construct a product tree, represent level codes, and develop a net material requirements plan. The problems show how to account for changes in demand and calculate planned order quantities using different techniques.
How to activate SAP ATP check for Sales Order, when you place item in sales order. Getting the material's supply and demand information,then meet customer's request delivery date.
1. Material Requirements Planning (MRP) is a computer-based production planning and inventory control system used to determine production and purchasing requirements.
2. MRP takes the master production schedule for end items and translates it into individual time-phased component requirements based on the product structure and lead times.
3. The MRP process involves establishing gross requirements, determining net requirements by subtracting inventory from gross requirements, time-phasing net requirements, and determining planned order releases.
This document provides an overview of materials requirements planning (MRP). It discusses the history and objectives of MRP, which is designed to determine materials needs based on a master production schedule and bill of materials. The key inputs to MRP are outlined, including the master production schedule, bill of materials, and inventory records. An example is provided to demonstrate how MRP works. Safety stocks are also discussed as a way to account for variations in demand and supply.
MRP is a system used in manufacturing to plan production schedules and material requirements. It takes inputs like the master production schedule and bill of materials to calculate net requirements through a process of exploding, netting, and offsetting. This helps control inventory levels and supports forecasted demand. MRP evolved into MRPII, which further integrates capacity planning, production scheduling, and other functions. While MRP improved efficiency, it also has disadvantages like reliance on accurate information and limited capacity planning.
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP). It provides an overview of MRP concepts like the bill of materials, master production schedule, gross requirements plan, net requirements plan, and lot sizing techniques. MRP is used to plan material needs based on a product structure and production schedule. ERP systems integrate various business functions like planning, manufacturing, sales and more.
This document provides an overview of material requirements planning (MRP) and enterprise resource planning (ERP) systems. It defines key concepts in MRP like the master production schedule, bills of material, lead times, and how the gross requirements and net requirements plans are developed. It also describes how MRP has been expanded to ERP systems to integrate broader business functions like customers, suppliers, and other business processes. The advantages of ERP systems are integration across the supply chain and common databases, while disadvantages include high costs of implementation and customization.
The document outlines key concepts related to material requirements planning (MRP) and enterprise resource planning (ERP). It discusses MRP concepts like the master production schedule, bills of materials, lead times, and gross and net requirements planning. It also covers extensions of MRP like MRP II and closed-loop MRP. Finally, it introduces enterprise resource planning (ERP) systems and their advantages and disadvantages.
This document provides an overview of material requirements planning (MRP). It discusses how MRP is used to determine material needs by working backwards from a master production schedule based on lead times. An example is provided showing how MRP logic is applied to a sample product structure tree to generate a materials requirements plan specifying material needs and order dates. The document also discusses key aspects of MRP including bill of materials files and inventory records files.
Material Requirements Planning (MRP) is a computer-based inventory management system that helps determine requirements for dependent demand items. MRP uses three primary inputs - the master production schedule, bill of materials, and inventory records - to calculate gross requirements, scheduled receipts, net requirements, planned order receipts, and planned order releases for each time period. This allows companies to plan procurement and production of dependent demand items based on independent demand for end products.
Material requirements planning & erp ppt @ bec domsBabasab Patil
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP) systems. It provides an overview of MRP concepts like the bill of materials, master production schedule, lot sizing techniques, and closed loop MRP. It also discusses extensions of MRP like MRP II/ERP which integrate additional business functions. ERP systems provide advantages like increased customer satisfaction and inventory planning across the entire organization.
The document discusses material requirements planning (MRP) and its use at Collins Industries, a large ambulance manufacturer. Collins requires an MRP system to manage its large inventory of 18,000 item codes and meet production needs. An effective MRP system requires accurate data on the bill of materials, inventory levels, outstanding orders and component lead times. The MRP system then calculates material needs based on the master production schedule to ensure availability of all parts.
MRP System Structure (Input and Output)
Master Production Schedule (MPS)
Bill of Material (BOM)
Inventory Records File
MRP Terminology
MRP Explosion Process
MRP Management
MRP and JIT
- Material Requirements Planning (MRP) is a production planning and inventory control system that determines material requirements based on a master production schedule, bill of materials, and inventory status.
- MRP aims to ensure availability of materials for production while maintaining low inventory levels. It determines gross requirements, nets requirements based on inventory and scheduled receipts, and plans order releases over time.
- MRP can be improved by accounting for capacity constraints, dealing with uncertainty through safety stocks and lead time adjustments, and using different lot sizing rules at different levels.
The document discusses material requirements planning (MRP). It describes the key outputs of MRP as calculating demand for component items, determining requirements for subassemblies and raw materials, determining when they are needed, and generating work orders and purchase orders while considering lead time. The document then provides details on when to use MRP, the major inputs to the MRP process including bills of material and master production schedules, the basic steps of MRP including exploding bills of material and netting inventory, lot sizing rules, and time-phasing requirements. Examples are also provided to illustrate how to use an MRP matrix to determine planned order releases and receipts.
The document describes Materials Requirements Planning (MRP) used by Collins Industries, a large ambulance manufacturer. MRP is a computerized inventory management system that uses a bill of materials, master production schedule, and inventory records to determine time-phased requirements for purchased and manufactured components. It accounts for dependent demand by translating finished good schedule requirements into planned order releases and receipts for subassemblies based on lead times. The example shows how MRP calculates net requirements, planned order receipts, and releases for school supply items like clipboards and desks over multiple periods based on their bills of material and demand forecasts.
The document provides an overview of resource planning systems like MRP and ERP. It describes the types of demand, evolution of material planning systems, and key components and processes of MRP like inputs, outputs, objectives, bills of materials, and lot sizing rules. It also discusses how ERP builds on MRP by integrating additional business functions for a holistic view of the organization. Benefits of ERP implementation include increased information flow and ability to replace disparate systems, though implementation requires significant costs, time, and management commitment.
In this presentation, we will discuss material planning systems and its evolution. Overview on MRP processes, its objectives and types of demands. We will also talk about the various terminologies like bills of material, inventory record, operating logics, MRP explosion process, capacity requirement planning.
To know more about Welingkar School’s Distance Learning Program and courses offered, visit: http://www.welingkaronline.org/distance-learning/online-mba.html
MRP is a computerized inventory control and production planning system that determines what components are needed and when based on orders and capacities. It schedules components, tracks inventory, and helps reduce costs and improve customer service, production, and other business aspects.
The document discusses Material Requirement Planning (MRP), a systematic methodology for production planning and inventory control. MRP answers three key questions: what is needed, how much is needed, and when is it needed. It does this by collecting information from the master production schedule, bill of materials, and inventory data to generate planned order releases and time-phase requirements. MRP aims to reduce inventory levels and costs while maintaining customer service levels.
Material Requirement Planning (MRP) is a computerized inventory control and production planning system that determines what items need to be processed, when, and what needs to be manufactured based on order priorities and capacities. It schedules the production of all items using an MRP matrix to track inventory levels and requirements over time. Implementing MRP at Hubbell Lighting improved on-time order completion from less than 75% to 97% by better coordinating production schedules and requirements.
MRP (Material Requirements Planning) is a computerized inventory control and production planning system that determines what materials and components are needed for production and when, based on orders and forecasts. It schedules the production of all items using an MRP matrix to track inventory levels and help manage other aspects of business like purchasing, production, and shipping. The system inputs include a product structure file, master production schedule, and inventory master file. The outputs are manufacturing orders, purchasing orders, and various reports.
Managing productions across Supply ChainSushovan Bej
This document discusses various production planning and control techniques used across the supply chain. It covers topics such as master scheduling, material requirements planning (MRP), distribution requirements planning (DRP), and Kanban systems. Master scheduling matches production output to customer demand over time. MRP translates the master schedule into planned orders for components by using a bill of materials and backward scheduling. DRP and Kanban help synchronize planning and control between supply chain partners.
Mba ii pmom_unit-2.5 resource planning -mrp aRai University
The document discusses material requirements planning (MRP) systems. It explains that MRP translates a master schedule of finished goods into time-phased requirements for components by exploding bills of materials. MRP takes several inputs like the master production schedule, inventory records, and bills of materials to determine component requirements and planned order releases. The output includes schedules for internal activities, purchase orders, and action notices to trigger replenishment orders when needed. MRP aims to maintain priorities and coordinate production planning across the organization. An example demonstrates how MRP calculates component requirements from a master schedule for building CD cabinets.
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP). It provides an overview of MRP concepts like the bill of materials, master production schedule, gross requirements plan, net requirements plan, and lot sizing techniques. MRP is used to plan material needs based on a product structure and production schedule. ERP systems integrate various business functions like planning, manufacturing, sales and more.
This document provides an overview of material requirements planning (MRP) and enterprise resource planning (ERP) systems. It defines key concepts in MRP like the master production schedule, bills of material, lead times, and how the gross requirements and net requirements plans are developed. It also describes how MRP has been expanded to ERP systems to integrate broader business functions like customers, suppliers, and other business processes. The advantages of ERP systems are integration across the supply chain and common databases, while disadvantages include high costs of implementation and customization.
The document outlines key concepts related to material requirements planning (MRP) and enterprise resource planning (ERP). It discusses MRP concepts like the master production schedule, bills of materials, lead times, and gross and net requirements planning. It also covers extensions of MRP like MRP II and closed-loop MRP. Finally, it introduces enterprise resource planning (ERP) systems and their advantages and disadvantages.
This document provides an overview of material requirements planning (MRP). It discusses how MRP is used to determine material needs by working backwards from a master production schedule based on lead times. An example is provided showing how MRP logic is applied to a sample product structure tree to generate a materials requirements plan specifying material needs and order dates. The document also discusses key aspects of MRP including bill of materials files and inventory records files.
Material Requirements Planning (MRP) is a computer-based inventory management system that helps determine requirements for dependent demand items. MRP uses three primary inputs - the master production schedule, bill of materials, and inventory records - to calculate gross requirements, scheduled receipts, net requirements, planned order receipts, and planned order releases for each time period. This allows companies to plan procurement and production of dependent demand items based on independent demand for end products.
Material requirements planning & erp ppt @ bec domsBabasab Patil
The document discusses material requirements planning (MRP) and enterprise resource planning (ERP) systems. It provides an overview of MRP concepts like the bill of materials, master production schedule, lot sizing techniques, and closed loop MRP. It also discusses extensions of MRP like MRP II/ERP which integrate additional business functions. ERP systems provide advantages like increased customer satisfaction and inventory planning across the entire organization.
The document discusses material requirements planning (MRP) and its use at Collins Industries, a large ambulance manufacturer. Collins requires an MRP system to manage its large inventory of 18,000 item codes and meet production needs. An effective MRP system requires accurate data on the bill of materials, inventory levels, outstanding orders and component lead times. The MRP system then calculates material needs based on the master production schedule to ensure availability of all parts.
MRP System Structure (Input and Output)
Master Production Schedule (MPS)
Bill of Material (BOM)
Inventory Records File
MRP Terminology
MRP Explosion Process
MRP Management
MRP and JIT
- Material Requirements Planning (MRP) is a production planning and inventory control system that determines material requirements based on a master production schedule, bill of materials, and inventory status.
- MRP aims to ensure availability of materials for production while maintaining low inventory levels. It determines gross requirements, nets requirements based on inventory and scheduled receipts, and plans order releases over time.
- MRP can be improved by accounting for capacity constraints, dealing with uncertainty through safety stocks and lead time adjustments, and using different lot sizing rules at different levels.
The document discusses material requirements planning (MRP). It describes the key outputs of MRP as calculating demand for component items, determining requirements for subassemblies and raw materials, determining when they are needed, and generating work orders and purchase orders while considering lead time. The document then provides details on when to use MRP, the major inputs to the MRP process including bills of material and master production schedules, the basic steps of MRP including exploding bills of material and netting inventory, lot sizing rules, and time-phasing requirements. Examples are also provided to illustrate how to use an MRP matrix to determine planned order releases and receipts.
The document describes Materials Requirements Planning (MRP) used by Collins Industries, a large ambulance manufacturer. MRP is a computerized inventory management system that uses a bill of materials, master production schedule, and inventory records to determine time-phased requirements for purchased and manufactured components. It accounts for dependent demand by translating finished good schedule requirements into planned order releases and receipts for subassemblies based on lead times. The example shows how MRP calculates net requirements, planned order receipts, and releases for school supply items like clipboards and desks over multiple periods based on their bills of material and demand forecasts.
The document provides an overview of resource planning systems like MRP and ERP. It describes the types of demand, evolution of material planning systems, and key components and processes of MRP like inputs, outputs, objectives, bills of materials, and lot sizing rules. It also discusses how ERP builds on MRP by integrating additional business functions for a holistic view of the organization. Benefits of ERP implementation include increased information flow and ability to replace disparate systems, though implementation requires significant costs, time, and management commitment.
In this presentation, we will discuss material planning systems and its evolution. Overview on MRP processes, its objectives and types of demands. We will also talk about the various terminologies like bills of material, inventory record, operating logics, MRP explosion process, capacity requirement planning.
To know more about Welingkar School’s Distance Learning Program and courses offered, visit: http://www.welingkaronline.org/distance-learning/online-mba.html
MRP is a computerized inventory control and production planning system that determines what components are needed and when based on orders and capacities. It schedules components, tracks inventory, and helps reduce costs and improve customer service, production, and other business aspects.
The document discusses Material Requirement Planning (MRP), a systematic methodology for production planning and inventory control. MRP answers three key questions: what is needed, how much is needed, and when is it needed. It does this by collecting information from the master production schedule, bill of materials, and inventory data to generate planned order releases and time-phase requirements. MRP aims to reduce inventory levels and costs while maintaining customer service levels.
Material Requirement Planning (MRP) is a computerized inventory control and production planning system that determines what items need to be processed, when, and what needs to be manufactured based on order priorities and capacities. It schedules the production of all items using an MRP matrix to track inventory levels and requirements over time. Implementing MRP at Hubbell Lighting improved on-time order completion from less than 75% to 97% by better coordinating production schedules and requirements.
MRP (Material Requirements Planning) is a computerized inventory control and production planning system that determines what materials and components are needed for production and when, based on orders and forecasts. It schedules the production of all items using an MRP matrix to track inventory levels and help manage other aspects of business like purchasing, production, and shipping. The system inputs include a product structure file, master production schedule, and inventory master file. The outputs are manufacturing orders, purchasing orders, and various reports.
Managing productions across Supply ChainSushovan Bej
This document discusses various production planning and control techniques used across the supply chain. It covers topics such as master scheduling, material requirements planning (MRP), distribution requirements planning (DRP), and Kanban systems. Master scheduling matches production output to customer demand over time. MRP translates the master schedule into planned orders for components by using a bill of materials and backward scheduling. DRP and Kanban help synchronize planning and control between supply chain partners.
Mba ii pmom_unit-2.5 resource planning -mrp aRai University
The document discusses material requirements planning (MRP) systems. It explains that MRP translates a master schedule of finished goods into time-phased requirements for components by exploding bills of materials. MRP takes several inputs like the master production schedule, inventory records, and bills of materials to determine component requirements and planned order releases. The output includes schedules for internal activities, purchase orders, and action notices to trigger replenishment orders when needed. MRP aims to maintain priorities and coordinate production planning across the organization. An example demonstrates how MRP calculates component requirements from a master schedule for building CD cabinets.
Similar to Scps -materials_requirements_planning (20)
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
Climate Change All over the World .pptxsairaanwer024
Climate change refers to significant and lasting changes in the average weather patterns over periods ranging from decades to millions of years. It encompasses both global warming driven by human emissions of greenhouse gases and the resulting large-scale shifts in weather patterns. While climate change is a natural phenomenon, human activities, particularly since the Industrial Revolution, have accelerated its pace and intensity
ENVIRONMENT~ Renewable Energy Sources and their future prospects.tiwarimanvi3129
This presentation is for us to know that how our Environment need Attention for protection of our natural resources which are depleted day by day that's why we need to take time and shift our attention to renewable energy sources instead of non-renewable sources which are better and Eco-friendly for our environment. these renewable energy sources are so helpful for our planet and for every living organism which depends on environment.
Microbial characterisation and identification, and potability of River Kuywa ...Open Access Research Paper
Water contamination is one of the major causes of water borne diseases worldwide. In Kenya, approximately 43% of people lack access to potable water due to human contamination. River Kuywa water is currently experiencing contamination due to human activities. Its water is widely used for domestic, agricultural, industrial and recreational purposes. This study aimed at characterizing bacteria and fungi in river Kuywa water. Water samples were randomly collected from four sites of the river: site A (Matisi), site B (Ngwelo), site C (Nzoia water pump) and site D (Chalicha), during the dry season (January-March 2018) and wet season (April-July 2018) and were transported to Maseno University Microbiology and plant pathology laboratory for analysis. The characterization and identification of bacteria and fungi were carried out using standard microbiological techniques. Nine bacterial genera and three fungi were identified from Kuywa river water. Clostridium spp., Staphylococcus spp., Enterobacter spp., Streptococcus spp., E. coli, Klebsiella spp., Shigella spp., Proteus spp. and Salmonella spp. Fungi were Fusarium oxysporum, Aspergillus flavus complex and Penicillium species. Wet season recorded highest bacterial and fungal counts (6.61-7.66 and 3.83-6.75cfu/ml) respectively. The results indicated that the river Kuywa water is polluted and therefore unsafe for human consumption before treatment. It is therefore recommended that the communities to ensure that they boil water especially for drinking.
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Joshua Orris
Results of geophysics and pneumatic injection pilot tests during 2003 – 2007 yielded significant positive results for injection delivery design and contaminant mass treatment, resulting in permanent shut-down of an existing groundwater Pump & Treat system.
Accessible source areas were subsequently removed (2011) by soil excavation and treated with the placement of Emulsified Vegetable Oil EVO and zero-valent iron ZVI to accelerate treatment of impacted groundwater in overburden and weathered fractured bedrock. Post pilot test and post remediation groundwater monitoring has included analyses of CVOCs, organic fatty acids, dissolved gases and QuantArray® -Chlor to quantify key microorganisms (e.g., Dehalococcoides, Dehalobacter, etc.) and functional genes (e.g., vinyl chloride reductase, methane monooxygenase, etc.) to assess potential for reductive dechlorination and aerobic cometabolism of CVOCs.
In 2022, the first commercial application of MetaArray™ was performed at the site. MetaArray™ utilizes statistical analysis, such as principal component analysis and multivariate analysis to provide evidence that reductive dechlorination is active or even that it is slowing. This creates actionable data allowing users to save money by making important site management decisions earlier.
The results of the MetaArray™ analysis’ support vector machine (SVM) identified groundwater monitoring wells with a 80% confidence that were characterized as either Limited for Reductive Decholorination or had a High Reductive Reduction Dechlorination potential. The results of MetaArray™ will be used to further optimize the site’s post remediation monitoring program for monitored natural attenuation.
Recycling and Disposal on SWM Raymond Einyu pptxRayLetai1
Increasing urbanization, rural–urban migration, rising standards of living, and rapid development associated with population growth have resulted in increased solid waste generation by industrial, domestic and other activities in Nairobi City. It has been noted in other contexts too that increasing population, changing consumption patterns, economic development, changing income, urbanization and industrialization all contribute to the increased generation of waste.
With the increasing urban population in Kenya, which is estimated to be growing at a rate higher than that of the country’s general population, waste generation and management is already a major challenge. The industrialization and urbanization process in the country, dominated by one major city – Nairobi, which has around four times the population of the next largest urban centre (Mombasa) – has witnessed an exponential increase in the generation of solid waste. It is projected that by 2030, about 50 per cent of the Kenyan population will be urban.
Aim:
A healthy, safe, secure and sustainable solid waste management system fit for a world – class city.
Improve and protect the public health of Nairobi residents and visitors.
Ecological health, diversity and productivity and maximize resource recovery through the participatory approach.
Goals:
Build awareness and capacity for source separation as essential components of sustainable waste management.
Build new environmentally sound infrastructure and systems for safe disposal of residual waste and replacing current dumpsites which should be commissioned.
Current solid waste management situation:
The status.
Solid waste generation rate is at 2240 tones / day
collection efficiently is at about 50%.
Actors i.e. city authorities, CBO’s , private firms and self-disposal
Current SWM Situation in Nairobi City:
Solid waste generation – collection – dumping
Good Practices:
• Separation – recycling – marketing.
• Open dumpsite dandora dump site through public education on source separation of waste, of which the situation can be reversed.
• Nairobi is one of the C40 cities in this respect , various actors in the solid waste management space have adopted a variety of technologies to reduce short lived climate pollutants including source separation , recycling , marketing of the recycled products.
• Through the network, it should expect to benefit from expertise of the different actors in the network in terms of applicable technologies and practices in reducing the short-lived climate pollutants.
Good practices:
Despite the dismal collection of solid waste in Nairobi city, there are practices and activities of informal actors (CBOs, CBO-SACCOs and yard shop operators) and other formal industrial actors on solid waste collection, recycling and waste reduction.
Practices and activities of these actor groups are viewed as innovations with the potential to change the way solid waste is handled.
CHALLENGES:
• Resource Allocation.
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Open Access Research Paper
Water polluted by dyestuffs compounds is a global threat to health and the environment; accordingly, we prepared a green novel sorbent chemical and Physical system from an algae, chitosan and chitosan nanoparticle and impregnated with algae with chitosan nanocomposite for the sorption of Malachite green dye from water. The algae with chitosan nanocomposite by a simple method and used as a recyclable and effective adsorbent for the removal of malachite green dye from aqueous solutions. Algae, chitosan, chitosan nanoparticle and algae with chitosan nanocomposite were characterized using different physicochemical methods. The functional groups and chemical compounds found in algae, chitosan, chitosan algae, chitosan nanoparticle, and chitosan nanoparticle with algae were identified using FTIR, SEM, and TGADTA/DTG techniques. The optimal adsorption conditions, different dosages, pH and Temperature the amount of algae with chitosan nanocomposite were determined. At optimized conditions and the batch equilibrium studies more than 99% of the dye was removed. The adsorption process data matched well kinetics showed that the reaction order for dye varied with pseudo-first order and pseudo-second order. Furthermore, the maximum adsorption capacity of the algae with chitosan nanocomposite toward malachite green dye reached as high as 15.5mg/g, respectively. Finally, multiple times reusing of algae with chitosan nanocomposite and removing dye from a real wastewater has made it a promising and attractive option for further practical applications.
Epcon is One of the World's leading Manufacturing Companies.EpconLP
Epcon is One of the World's leading Manufacturing Companies. With over 4000 installations worldwide, EPCON has been pioneering new techniques since 1977 that have become industry standards now. Founded in 1977, Epcon has grown from a one-man operation to a global leader in developing and manufacturing innovative air pollution control technology and industrial heating equipment.
Presented by The Global Peatlands Assessment: Mapping, Policy, and Action at GLF Peatlands 2024 - The Global Peatlands Assessment: Mapping, Policy, and Action
Evolving Lifecycles with High Resolution Site Characterization (HRSC) and 3-D...Joshua Orris
The incorporation of a 3DCSM and completion of HRSC provided a tool for enhanced, data-driven, decisions to support a change in remediation closure strategies. Currently, an approved pilot study has been obtained to shut-down the remediation systems (ISCO, P&T) and conduct a hydraulic study under non-pumping conditions. A separate micro-biological bench scale treatability study was competed that yielded positive results for an emerging innovative technology. As a result, a field pilot study has commenced with results expected in nine-twelve months. With the results of the hydraulic study, field pilot studies and an updated risk assessment leading site monitoring optimization cost lifecycle savings upwards of $15MM towards an alternatively evolved best available technology remediation closure strategy.
Global Peatlands Map and Hotspot Explanation Atlas
Scps -materials_requirements_planning
1. Materials Requirement Planning
Supply Chain Planning and
Scheduling 1
Supply Chain
Planning and
Scheduling
Material Requirements
Planning
The MPS states the
definitive schedule for
end items… we still
need to plan the
components required to
produce the end items
2. Materials Requirement Planning
Supply Chain Planning and
Scheduling 2
Material
Requirements
Planning
Planning and Control Hierarchy
Material
Requirements
Planning
(MRP)
Master
Production
Schedule
(MPS)
Production
Activity
Control
(PAC)
Sales and
Operations
Planning
(S&OP)
Strategic
Business
Plan
TimeScope
Level of Detail
Low High
Short
Long
Master Plan
Planning Phase
Implementation
phase
3. Materials Requirement Planning
Supply Chain Planning and
Scheduling 3
Links To Other MPC Functions
Major Objectives of MRP
Determine Requirements from Purchasing and
Production
Calculated to meet product requirements defined in
the MPS
What to order
How much to order
When to order
When to schedule delivery
Keep Priorities Current
Adjustment to changing situations
4. Materials Requirement Planning
Supply Chain Planning and
Scheduling 4
Inputs to MRP
Master Production Schedule quantities and times
Inventory records of all items to be planned
Planning factors such as lead times, order quantities, and
safety stock
Current status such as availability, allocation, and availability
for future demand
Bills of material for MPS items
MPS
MRP
Inventory
Records
Bill of
Materials
At the MRP level there is
a key difference from the
previous steps in the
planning process… it is
the way in which demand
requirements are
calculated
5. Materials Requirement Planning
Supply Chain Planning and
Scheduling 5
Nature of demand at the MRP level
Independent Demand
Not related to demand for other
assemblies or products, instead from
outside sources
Generally forecasted demand
Dependent Demand
Generally related to production of an
end product (as defined on the MPS)
Can be calculated instead of forecasted
ProductionProduction
PlanPlan
MPSMPS
MRPMRP
The key instrument
used at the MRP level
is the Bill of Materials
6. Materials Requirement Planning
Supply Chain Planning and
Scheduling 6
The Bill of Material (BOM)
The BOM shows all the parts required to make one item
Each part has one, and only one, part number
A part is defined by form, fit, and function – any change requires a
new part number
Product Tree
The product tree is graphic representation of the bill of
materials
Key concepts: Parent and Component
7. Materials Requirement Planning
Supply Chain Planning and
Scheduling 7
Multilevel bill
Breaks down the BOM into more detail
Single-level bill
Single-level
bill
Multiple bills
Often, two or more products use the same components
5
3In this example we have a
table with a different finishing
(e.g. top with rounded edges)
5
8. Materials Requirement Planning
Supply Chain Planning and
Scheduling 8
Exercise
Given the following parents and components, construct a
product tree. The numbers in brackets show the
quantities required per item.
How many G’s are required to make one A item?
Which components are purchased?
Construct the appropriate single level trees
A B C E
B(2) E(2) G(2) G(4)
C(4) F(1) F(3)
D(3) H(2)
Exercise (cont.)
Construct a product tree. The numbers in brackets show
the quantities required per item.
How many G’s are required to make one A item?
9. Materials Requirement Planning
Supply Chain Planning and
Scheduling 9
Exercise (cont.)
Which components are purchased?
Construct the appropriate single level trees
There are other
representations of
the bill of materials
10. Materials Requirement Planning
Supply Chain Planning and
Scheduling 10
Summarized parts list
Lists all the parts required to make one complete
assembly, but does not contain information about the
way the product should be made or assembled
Indented BOM
The indentation is used to show parent-component
relationships
11. Materials Requirement Planning
Supply Chain Planning and
Scheduling 11
Planning Bill of Material
Artificial grouping of components for Planning
Purposes
Used to simplify
Forecasting
Planning
Master Scheduling
Represent an average, not buildable product
Planning Bill of Material
12. Materials Requirement Planning
Supply Chain Planning and
Scheduling 12
The Bill of Material (BOM)
The BOM shows all parts to make one item
Each part has one, and only one, part number
A part is defined by form, fit, and function – any change requires
a new part number
Product tree
Parent - component
Single / Multiple level bill
Other presentations of the BOM
Indented BOM
Summarized part list
Planning BOM
“Where-used” and “Pegging” data
Where-used report
It is the reverse of the BOM, it lists all the parents for
a given component
Pegging report
It is like the where-used report, but it shows only the
parents creating the current demand for the
components, the quantities needed and when they
are needed
13. Materials Requirement Planning
Supply Chain Planning and
Scheduling 13
Pegged report
A
C B
C D
Pegged Requirements
Item
number
Week
1 2 3 4 5
C 50 125 25 50 150
Demand for part C comes from
product A and part B
MPS
Week 1 2 3 4 5
A 50 25 25 50 50
Source of requirements (Where Used)
A 50 25 25 50 50
B 100 100
(Fixed Order Policy for part B)
How do we prepare
the Material
Requirements Plan?
14. Materials Requirement Planning
Supply Chain Planning and
Scheduling 14
The MRP Planning Process
Determines
Components needed
Quantities
Due dates
Involves
Exploding and offsetting
Gross and Net requirements
Releasing orders
Capacity Requirements Planning
Low-level coding and netting
Multiple Bill of Materials
MPS
MRP
Inventory
Records
Bill of
Materials
Exploding and Offsetting
Exploding: The process of multiplying the requirements
by the usage quantity for all items throughout the product
tree
Offsetting: The process of placing the exploded
requirements in their proper period based on lead time
A
B C
D E
LT: 1 week
LT: 1 weekLT: 1 week
LT: 1 weekLT: 2 weeks
LT: Lead Time
15. Materials Requirement Planning
Supply Chain Planning and
Scheduling 15
Exploding and Offsetting
Planned order:Planned order: A suggested order quantity, release date, and due date created by the system’s
logic. Planned orders are created by the computer, and exist only within the computer, therefore
they can be changed or deleted if conditions change
A
B C
D E
LT: 1 week
LT: 1 weekLT: 1 week
LT: 1 weekLT: 2 weeks
Part number
Week
1 2 3 4 5
A
Planned order receipt 50
Planned order release
B
Planned order receipt
Planned order release
C
Planned order receipt
Planned order release
D
Planned order receipt
Planned order release
E
Planned order receipt
Planned order release
Exercise
Using the product tree and lead times above complete the table to determine planned order
receipts and releases. There are 200 Ls required in week 5
M
N O(2)
P Q
LT: 1 week
LT: 1 weekLT: 1 week
LT: 2 weekLT: 1 weeks
Part number
Week
1 2 3 4 5
M
Planned order receipt 200
Planned order release
N
Planned order receipt
Planned order release
O
Planned order receipt
Planned order release
P
Planned order receipt
Planned order release
Q
Planned order receipt
Planned order release
16. Materials Requirement Planning
Supply Chain Planning and
Scheduling 16
Gross and Net requirements
Gross requirement: Total independent and dependent
demand for an item or assembly
Net requirement: Requirements after discounting
available inventory, scheduled receipts and safety stock
The planned order release of the parent becomes the
gross requirement of the component
Net requirement = Gross
requirement
Available
inventory
-
Gross and Net requirements
Complete the table: Lead time for the part is two weeks
and the lot size is 100 units
Week 1 2 3 4
Gross requirements
Projected available 75
Net requirements
Planned order receipt
Planned order release
75
100
50
25
45
80
20
100
20
60
17. Materials Requirement Planning
Supply Chain Planning and
Scheduling 17
Gross and Net requirements
A
B C
D E
LT: 1 wk
LT: 1 wkLT: 1 wk
LT: 1 wkLT: 2 wks
Part number
Week
1 2 3 4 5
A
Gross requirements
Projected available 20
Net requirements
Planned order receipt
Planned order release
20 20 20 20
30
50
0
30
30
B
Gross requirements
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10
20
10
30
0
20
20
C
Gross requirements
Projected available
Net requirements
Planned order receipt
Planned order release
0 0 0
30
30
0
30
30
D
Gross requirements
Projected available
Net requirements
Planned order receipt
Planned order release
0
20
20
0
20
20
E
Gross requirements
Projected available
Net requirements
Planned order receipt
Planned order release
0
20
20
0
20
20
In this example we are
using a L4L policy
Releasing Orders
Releasing an order means that authorization is
given to buy or make an item
Planned orders are not real orders yet, they still
have to be released
Placing orders is the material planner’s
responsibility
Orders are released only when the release date
arrives, that usually the current week (week 1)
18. Materials Requirement Planning
Supply Chain Planning and
Scheduling 18
Key points about the basic MRP record
Part number
Week
1 2 3 4 5
A
Gross requirements
Scheduled receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10 10
10
20
30
50
0
30
30
Time bucket
Planning horizon
Today
Considered available
at the beginning of
the time bucket
Projected on-hand
balance at the end of
the period
Action bucket
The releasing orders process
Check availability of components
If available, allocate necessary quantity to work
order
If not available,
release authorization for purchase or manufacturing,
create scheduled receipt,
cancel planned order receipt, and
Allocate required quantities of a parents components
to that order
19. Materials Requirement Planning
Supply Chain Planning and
Scheduling 19
The releasing orders process
Part
number
Week
1 2 3 4 5
D
Gross requirements
Scheduled receipts
Projected available
Net requirements
Planned order receipt
Planned order release
0
20
20
20
0
20
20
E
Gross requirements
Scheduled receipts
Projected available
Net requirements
Planned order receipt
Planned order release
0
20
20
20
0
20
20
Here, planned orders are released by the planner and
scheduled receipts are created
The releasing orders process
Scheduled receipt: Open orders released for
processing (production or purchase) scheduled to be
received at a defined time
Open order: A released manufacturing or purchase
order. When goods are available for use the order is
closed and the scheduled receipt disappears
Net requirement calculation: Now it is possible to
consider scheduled receipts
Net requirement = Gross
requirement
Available
inventory
Scheduled
receipt
- -
20. Materials Requirement Planning
Supply Chain Planning and
Scheduling 20
Exercise
Complete the table: Lead time for the item is two weeks
and the lot size is 200 units.
What action should be taken?
Week 1 2 3 4
Gross requirements
Scheduled receipts
Projected available 150
Net requirements
Planned order receipt
Planned order release
50 250
200
100 50
Exercise
Complete the table: Lead time for the item is two weeks
and the lot size is 100 units.
What is the projected available at the end of week 3?
When is it planned to release an order?
Week 1 2 3 4
Gross requirements
Scheduled receipts
Projected available 40
Net requirements
Planned order receipt
Planned order release
20 65
100
35 25
21. Materials Requirement Planning
Supply Chain Planning and
Scheduling 21
Low-Level Coding and Netting
A part may reside at more than one level in a Bill of
Material
The process of collecting gross requirements and netting
can be simplified by using low-level codes
Low-level code: Lowest level on which a part resides
on the Bill of Materials
A
B C
C D
Level
0
1
2
Low-Level Coding
Low-level codes are determined by starting at the lowest
level of a bill of material and working up, recording the
level against the part.
Part C is found at both levels 2 and 1, we assign the
lowest one
This is to make sure we have accounted for all its
sources of demand before exploding it.
A
B C
C D
Level
0
1
2
Part Low-level code
D 2
C 2
B 1
A 0
22. Materials Requirement Planning
Supply Chain Planning and
Scheduling 22
Low-level Coding and Netting
Start at level zero
Look for all low-level zero
parts and record their
gross requirements.
Net their requirements
With all low-level 0
identified it is possible to
start netting and
exploding the
requirements for the
components at the next
level
For this exercise:
Requirements are for 1 unit
All lead times are 1 week
Part
number
Week
1 2 3 4 5
A
Level 0
Gross requirements
Scheduled Receipts
Projected available 20
Net requirements
Planned order receipt
Planned order release
20 20 20 20
30
50
0
30
30
B
Level 1
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
30
Low-level Coding and Netting
Continue at level 1
Repeat the routine
followed in the first step
Notice that B is low-level
code 1, therefore it can be
netted and exploded
However, part C has low-
level code 2, which
means there may be
further requirements.
Therefore, it is not netted
at this point
For this exercise:
Requirements are for 1 unit
All lead times are 1 week
Part
number
Week
1 2 3 4 5
B
Level 1
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10 10
20
30
0
20
20
C
Level 2
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
20 30
D
Level 2
Gross requirements
Scheduled Receipts
Projected available
Net requirements
Planned order receipt
Planned order release
20
23. Materials Requirement Planning
Supply Chain Planning and
Scheduling 23
Low-level Coding and Netting
Continue at low-level 2
Repeat the routine as
before
Now it is found that part C
has low-level 2, there are
no additional
requirements and it can
be netted at this point
The bill of material has
been reached and there is
no need for further
explosion
For this exercise:
Requirements are for 1 unit
All lead times are 1 week
Part
number
Week
1 2 3 4 5
A
Gross requirements
Scheduled Receipts
Projected available 20
Net requirements
Planned order receipt
Planned order release
20 20 20 20
30
50
0
30
30
B
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10 10
20
30
0
20
20
C
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10
10
20
0
10
10
30
30
0
30
30
D
Gross requirements
Scheduled Receipts
Projected available
Net requirements
Planned order receipt
Planned order release
0 0
20
20
0
20
20
Multiple Bills of Material
A part or component may be used in more than one product. The
same procedure that is used for a single bill of material can be used
for multiple products. All bills must be netted and exploded level by
level as in the previous example.
20(1) + 30(2) = 80
Part B Part C
24. Materials Requirement Planning
Supply Chain Planning and
Scheduling 24
Multiple Bills of Material
Example
A
C(2)
F(2)
B
F(1)
Multiproduct
What if part F is present,
but at different levels?
Apply low-level coding
Multiple Bills of Material
Example
All lead-times are
1 week
Order policy is
L4L
A
C(2)
F(2)
B
F(1)
Low-level
code
Part number
Week
1 2 3 4 5
0 A
Gross requirements
Scheduled Receipts
Projected available 20
Net requirements
Planned order receipt
Planned order release
20 20 20 20
30
50
0
30
30
0 B
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10
20
30
0
20
20
1 C
Gross requirements
Scheduled Receipts
Projected available 10
Net requirements
Planned order receipt
Planned order release
10 10 10
50
60
0
50
50
2 F
Gross requirements
Scheduled Receipts
Projected available
Net requirements
Planned order receipt
Planned order release
0
20
20
0
20
20
100
100
0
100
100
25. Materials Requirement Planning
Supply Chain Planning and
Scheduling 25
Well, that’s the MRP
logic, but it is applied
by a software…
What’s the role of
people at the MRP
level of planning?
Planner’s responsibilities for MRP
Release Orders – Production or Purchasing
Reschedule open orders as required
Reconcile errors and search for causes
Solve critical material shortages
Replan
Expedite
Coordinate with other functions to resolve
problems
26. Materials Requirement Planning
Supply Chain Planning and
Scheduling 26
Types of orders used by planners
Planned orders: Planned orders are
automatically scheduled and controlled by the
computer
Released orders: Open orders launched by the
planner. These are substituted in the MRP file as
scheduled receipts.
Firm Planned orders: Orders not yet released,
but “frozen” in quantity and time to reduce
system “nervousness”
%
Messages issued by the MRP software
The software
Nets, explodes requirements offsets, and creates planned
orders.
It does not release orders or reschedules open orders
But it issues messages suggesting the planner to take action
Exception messages
(suggestions for release, possible problems)
(Actions taken by the planner affecting MRP)
Transaction messages
27. Materials Requirement Planning
Supply Chain Planning and
Scheduling 27
Managing the MRP
The planner receives feedback
Suppliers actions
Changes to orders in the factory
Management actions
The planner must evaluate the feedback and
take corrective action considering the following:
Priority: correct amounts and dates
Bottom-up replanning: corrective actions should occur
as low in the product structure as possible
Reducing system nervousness: smoothing reaction
to variability
Example
As the MRP planner, you arrive at work Monday morning and look at the
MRP record for part 2876.
There is an exception message to release planned order of 30 in week 1
The following transactions take place
Only 25 units of the scheduled receipt are received into inventory, the balance is
scrapped
The gross requirement for week 3 is changed to 10
The gross requirement for week 4 is increased to 50
The requirement for week 7 is 15
An inventory count reveals there are 10 more in inventory than the record shows
The 35 gross requirement for week 1 is issued from inventory
The planned order release for 30 in week 1 is released and becomes a scheduled
receipt in week 3
Week 1 2 3 4 5 6 7
Gross requirements
Scheduled receipts
Projected available 20
Net requirements
Planned order receipt
Planned order release
35
30
15
30
10
5
30
15
20
10
30
30
20
10
30
30
15
5
20
15
15
30
Order quantity:
30 units
Lead time:
2 weeks
28. Materials Requirement Planning
Supply Chain Planning and
Scheduling 28
Exercise
Its Monday morning and you have arrived at work.
Complete the following MRP record as it would appear Monday
morning.
During the week the following events occur. Enter them in the MRP
record
The planned order for 100 in week 1 is released
Thirty of the scheduled receipts from week 1 are scrapped
An order for 20 is received for delivery in week 3
An order for 40 is received for delivery in week 6
The gross requirements of 70 in week 1 are issued
Week 1 2 3 4 5
Gross requirements
Scheduled receipts
Projected available 50
Net requirements
Planned order receipt
Planned order release
70
100
40 80 50 40
Order quantity= 100 units
Lead time= 2 weeks
MRP v. MRP II
MRP is a computer based application designed
to manage the large amounts of data and
calculations required to schedule requirements
MRP II deals with other factors influencing
production scheduling
Helps verify and ensure the feasibility of priority plans
by considering capacity
Its objective is to help collect and distribute
information used to coordinate and harmonize the
different functions that have an effect on
manufacturing
29. Materials Requirement Planning
Supply Chain Planning and
Scheduling 29
MRP v. MRP II
Areas outside manufacturing that are included
by using MRP II:
Maintenance management
Cost accounting
Stock management
Sales orders
Procurement
Personnel levels
MRP II requires considerable computing power
due to all the activities connected by it
From MRP II to ERP
Organizations require increasing levels of integration of
information and decision making
This decision making goes beyond that required for
manufacturing to encompass that of the company as a
whole
IT systems have been developed with the purpose of
satisfying these needs
The resulting software solutions are called Enterprise
Resource Planning (ERP)
30. Materials Requirement Planning
Supply Chain Planning and
Scheduling 30
Capacity Requirements Planning
Check against available capacity
Units of output
Standard time
Available time
Utilization
Rated capacity
Calculation of capacity required
Load
Work center load report
Supply Chain
Planning and
Scheduling
Material Requirements
Planning