SlideShare a Scribd company logo
1 of 20
Material Requirements 
Planning 
ISQA 459 Class 4 Mellie Pullman
Materials Requirements 
Planning 
 Material Requirements Planning (MRP) 
 MRP Logic and Product Structure 
Trees 
 MRP Example 
 Lot Sizing in MRP Programs
Material Requirements 
Planning 
 Materials requirements planning (MRP) 
is the logic for determining the number 
of parts, components, and materials 
needed to produce a product. 
 MRP provides time scheduling 
information specifying when each of the 
materials, parts, and components 
should be ordered or produced. 
 Dependent demand drives MRP. 
 MRP is a software system.
Example of MRP Logic and 
Product Structure Tree 
Given the product structure tree for “A” and the lead time and demand 
information below, provide a materials requirements plan that defines 
the number of units of each component and when they will be needed. 
Product Structure Tree for Assembly A 
B(4) 
D(2) E(1) 
C(2) 
A 
D(3) F(2) 
Lead Times 
A 1 day 
B 2 days 
C 1 day 
D 3 days 
E 4 days 
F 1 day 
Demand 
Day 10 50 A 
Day 8 20 B (Spares) 
Day 6 15 D (Spares)
First, the number of units of “A” are scheduled backwards to 
allow for their lead time. So, in the materials requirement plan 
below, we have to place an order for 50 units of “A” in the 9th 
week to receive them in the 10th week. 
Day: 1 2 3 4 5 6 7 8 9 10 
A Required 50 
Order Placement 50 
LT = 1 day
Next, we need to start scheduling the components that make up “A”. In 
the case of component “B” we need 4 B’s for each A. Since we need 50 
A’s, that means 200 B’s. And again, we back the schedule up for the 
necessary 2 days of lead time. 
D a y : 1 2 3 4 5 6 7 8 9 1 0 
A R e q u i re d 5 0 
O rd e r P la c e m e n t 5 0 
B R e q u i re d 2 0 2 0 0 
O rd e r P la c e m e n t 2 0 2 0 0 
Spares 
LT = 2 
B(4) 
D(2) E(1) 
A 4x50=200 
C(2) 
D(3) F(2)
Finally, repeating the process for all components, we have the 
final materials requirements plan: 
Day: 1 2 3 4 5 6 7 8 9 10 
A Required 50 
LT=1 Order Placement 50 
B Required 20 200 
LT=2 Order Placement 20 200 
C Required 100 
LT=1 Order Placement 100 
D Required 55 400 300 
LT=3 Order Placement 55 400 300 
E Required 20 200 
LT=4 Order Placement 20 200 
F Required 200 
LT=1 Order Placement 200 
B(4) 
D(2) E(1) 
C(2) 
A 
D(3) F(2) 
Part D: Day 6 
40 + 15 spares 
7
Material Requirements 
Planning System 
 Based on a master production 
schedule, a material requirements 
planning system: 
 Creates schedules identifying the 
specific parts and materials 
required to produce end items. 
 Determines exact unit numbers 
needed. 
 Determines the dates when 
orders for those materials should 
be released, based on lead times.
Firm orders 
from known 
customers 
Forecasts 
of demand 
from estimates 
Aggregate 
product 
plan 
Master 
production 
schedule 
(MPS) 
Material 
planning 
(MRP) 
Engineering 
design 
changes 
Bill of 
material 
file 
Inventory 
transactions 
Inventory 
record 
file 
Reports 
9
Bill of Materials (BOM) File 
A Complete Product Description 
 Materials 
 Parts 
 Components 
 Production sequence 
 Modular BOM 
 Component or Subassemblies BOM 
 Planning BOM or kits 
 create an artificial parent to the BOM used for 
inexpensive items like washers or pins to group. 
 Explosion: revealing the requirements for each 
component.
Coding 
 If identical items 
exist at various 
levels in the BOM: 
 Item is coded at 
lowest level at which 
it occurs 
 D (Level 2 or Level 
3) 
 This number 
identifies the part at 
the lowest level of 
usage. 
A 
B C 
D E E F 
G D
Inventory Records File 
 Buckets= time units in MRP system 
 Week bucket vs. day bucket 
 Each inventory item carried as a separate 
file 
 Status according to “time buckets”. 
 Pegging 
 Identify each parent item that created demand. 
 Parent vs. child 
 Parent= Items above the current level 
 Child = Items below the current level
Primary MRP Reports 
 Planned orders to be released at a future 
time. 
 Order release notices to execute the 
planned orders. 
 Changes in due dates of open orders due 
to rescheduling. 
 Cancellations or suspensions of open 
orders due to cancellation or suspension of 
orders on the master production schedule. 
 Inventory status data.
Secondary MRP Reports 
 Planning reports, for example, 
forecasting inventory requirements 
over a period of time. 
 Performance reports used to 
determine agreement between actual 
and programmed usage and costs. 
 Exception reports used to point out 
serious discrepancies, such as late or 
overdue orders.
Additional MRP Scheduling 
Terminology 
 Gross Requirements: needed during each period. 
 Scheduled Receipts: Existing orders that arrive at beginning 
of period. 
 On-hand or available balance: 
 (depending on software convention, could be at the beginning 
of each period or end): 
 Book: Inventory balance at end of each period. 
 Net requirements: What is need to meet requirements and 
safety stock. 
 Planned order receipt: arrives at beginning of period. 
 Planned order release: Addresses lead time.
MRP Examples
Closed Loop MRP 
Production Planning 
Master Production Scheduling 
Material Requirements Planning 
Capacity Requirements Planning 
Realistic? 
No 
Feedback 
Yes 
Execute: 
Capacity Plans 
Material Plans 
Feedback
Lot Sizing in MRP 
Programs 
 Lot-for-lot (L4L) 
 Economic order quantity (EOQ) 
 Least total cost (LTC) 
 Least unit cost (LUC) 
 Part Period Balancing-changing lot 
sizes to reflect requirements in the 
future (how many periods should be 
combined to reduce cost)
MRP Game 
Different types of lot sizes
Tinker Toy Lawn Mower

More Related Content

Similar to Mrpmep (20)

Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planning
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
 
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planning
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
 
Session 5
Session 5Session 5
Session 5
 
Chapter 5_OM
Chapter 5_OMChapter 5_OM
Chapter 5_OM
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Mrp
MrpMrp
Mrp
 
Mrp
MrpMrp
Mrp
 
Planned order release
Planned order releasePlanned order release
Planned order release
 
5089529.ppt
5089529.ppt5089529.ppt
5089529.ppt
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
Resource Requirement Planning
Resource Requirement PlanningResource Requirement Planning
Resource Requirement Planning
 
MRP MPS.ppt
MRP MPS.pptMRP MPS.ppt
MRP MPS.ppt
 
MRP
MRPMRP
MRP
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 
Mrp
Mrp Mrp
Mrp
 
Material Requirements planning system 01Page to 04 Page
Material Requirements planning system                      01Page to 04 PageMaterial Requirements planning system                      01Page to 04 Page
Material Requirements planning system 01Page to 04 Page
 

Mrpmep

  • 1. Material Requirements Planning ISQA 459 Class 4 Mellie Pullman
  • 2. Materials Requirements Planning  Material Requirements Planning (MRP)  MRP Logic and Product Structure Trees  MRP Example  Lot Sizing in MRP Programs
  • 3. Material Requirements Planning  Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials needed to produce a product.  MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced.  Dependent demand drives MRP.  MRP is a software system.
  • 4. Example of MRP Logic and Product Structure Tree Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed. Product Structure Tree for Assembly A B(4) D(2) E(1) C(2) A D(3) F(2) Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares)
  • 5. First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” in the 9th week to receive them in the 10th week. Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order Placement 50 LT = 1 day
  • 6. Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time. D a y : 1 2 3 4 5 6 7 8 9 1 0 A R e q u i re d 5 0 O rd e r P la c e m e n t 5 0 B R e q u i re d 2 0 2 0 0 O rd e r P la c e m e n t 2 0 2 0 0 Spares LT = 2 B(4) D(2) E(1) A 4x50=200 C(2) D(3) F(2)
  • 7. Finally, repeating the process for all components, we have the final materials requirements plan: Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 LT=1 Order Placement 50 B Required 20 200 LT=2 Order Placement 20 200 C Required 100 LT=1 Order Placement 100 D Required 55 400 300 LT=3 Order Placement 55 400 300 E Required 20 200 LT=4 Order Placement 20 200 F Required 200 LT=1 Order Placement 200 B(4) D(2) E(1) C(2) A D(3) F(2) Part D: Day 6 40 + 15 spares 7
  • 8. Material Requirements Planning System  Based on a master production schedule, a material requirements planning system:  Creates schedules identifying the specific parts and materials required to produce end items.  Determines exact unit numbers needed.  Determines the dates when orders for those materials should be released, based on lead times.
  • 9. Firm orders from known customers Forecasts of demand from estimates Aggregate product plan Master production schedule (MPS) Material planning (MRP) Engineering design changes Bill of material file Inventory transactions Inventory record file Reports 9
  • 10. Bill of Materials (BOM) File A Complete Product Description  Materials  Parts  Components  Production sequence  Modular BOM  Component or Subassemblies BOM  Planning BOM or kits  create an artificial parent to the BOM used for inexpensive items like washers or pins to group.  Explosion: revealing the requirements for each component.
  • 11. Coding  If identical items exist at various levels in the BOM:  Item is coded at lowest level at which it occurs  D (Level 2 or Level 3)  This number identifies the part at the lowest level of usage. A B C D E E F G D
  • 12. Inventory Records File  Buckets= time units in MRP system  Week bucket vs. day bucket  Each inventory item carried as a separate file  Status according to “time buckets”.  Pegging  Identify each parent item that created demand.  Parent vs. child  Parent= Items above the current level  Child = Items below the current level
  • 13. Primary MRP Reports  Planned orders to be released at a future time.  Order release notices to execute the planned orders.  Changes in due dates of open orders due to rescheduling.  Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule.  Inventory status data.
  • 14. Secondary MRP Reports  Planning reports, for example, forecasting inventory requirements over a period of time.  Performance reports used to determine agreement between actual and programmed usage and costs.  Exception reports used to point out serious discrepancies, such as late or overdue orders.
  • 15. Additional MRP Scheduling Terminology  Gross Requirements: needed during each period.  Scheduled Receipts: Existing orders that arrive at beginning of period.  On-hand or available balance:  (depending on software convention, could be at the beginning of each period or end):  Book: Inventory balance at end of each period.  Net requirements: What is need to meet requirements and safety stock.  Planned order receipt: arrives at beginning of period.  Planned order release: Addresses lead time.
  • 17. Closed Loop MRP Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning Realistic? No Feedback Yes Execute: Capacity Plans Material Plans Feedback
  • 18. Lot Sizing in MRP Programs  Lot-for-lot (L4L)  Economic order quantity (EOQ)  Least total cost (LTC)  Least unit cost (LUC)  Part Period Balancing-changing lot sizes to reflect requirements in the future (how many periods should be combined to reduce cost)
  • 19. MRP Game Different types of lot sizes