SlideShare a Scribd company logo
1

MATERIALS REQUIREMENT
PLANNING
2

OBJECTIVES


Materials requirement Planning (MRP)



MRP Logic and Product Structure Trees



Time Fences



MRP Example



MRP II and Lot Sizing
3

MATERIALS REQUIREMENT
PLANNING (MRP)


Fundamental Questions in Manufacturing are –

• What are we going to make?
• What does it take to make it?
• What do we have?
• What do we have to get?
Materials Requirement
Planning

•

Materials requirement planning (MRP) is a
means for determining the number of parts,
components, and materials needed to
produce a product

•

MRP provides time scheduling information
specifying when each of the materials, parts,
and components should be ordered or
produced

•
•

Dependent demand drives MRP
MRP is a software system

4
5

Product Hierarchy
End Product

Assembly 2

Assembly 1

Subassembly 1

Component A

Subassembly 2

Component E

Component B

Component C

Raw Material X

Component D

Raw material Y

Component F
6

MRP Example of BOM
Top

Leg

Short Rail

Long Rail

16-6
7

BOM (Product Structure)
Table (End Item)
1 week

Leg Assembly (1)
1 week
Short Rails (2) Long Rails (2)
1 week
1 week

Top (1)
2 weeks
Legs (4)
1 week

16-7
Example of MRP Logic and
Product Structure Tree

Given the product structure tree for “A” and the lead time and
demand information below, provide a materials requirements
plan that defines the number of units of each component and
when they will be needed
Product Structure Tree for Assembly A

A
B(4)
D(2)

C(2)
E(1)

D(3)

F(2)

Lead Times
A
1 day
B
2 days
C
1 day
D
3 days
E
4 days
F
1 day
Total Unit Demand
Day 10 50 A
Day 8
20 B (Spares)
Day 6
15 D (Spares)

8
9

First, the number of units of “A” are scheduled
backwards to allow for their lead time. So, in the
materials requirement plan below, we have to place
an order for 50 units of “A” on the 9th day to receive
them on day 10.
Day:
A Required
Order Placement

1

2

3

4

5

6

7

8

9
50

LT = 1 day

10
50
10

Next, we need to start scheduling the components that make up
“A”. In the case of component “B” we need 4 B’s for each A.
Since we need 50 A’s, that means 200 B’s. And again, we back
the schedule up for the necessary 2 days of lead time.
Day:

1

2

3

4

5

20

LT = 2
A
B(4)
D(2)

D(3)

9
50
200

200

Spares
4x50=200

C(2)
E(1)

7

8

20

A Required
Order Placement
B Required
Order Placement

6

F(2)

10
50
Finally, repeating the process for all components, we have the
final materials requirements plan:
Day:
A
LT=1
B
LT=2
C
LT=1
D
LT=3
E
LT=4
F
LT=1

1

2

4

5

6

20

7

8

9

20

Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement

3

11

10
50

50
200

200
100

55
20

55
20

400

400

100
300

200

300

200
200
200

A
B(4)
D(2)

Part D: Day 6

C(2)
E(1)

D(3)

40 + 15 spares

F(2)
©The McGraw-Hill Companies, Inc., 2001
Master Production Schedule
(MPS)


12

Time-phased plan specifying how
many and when the firm plans to build
each end item

Aggregate Plan
Aggregate Plan
(Product Groups)
(Product Groups)

MPS
(Specific End Items)
13

Types of Time Fences


Frozen
–

No schedule changes allowed within this
window



Moderately Firm
–

Specific changes allowed within product
groups as long as parts are available



Flexible
–

Significant variation allowed as long as overall
capacity requirements remain at the same
levels
14

Example of Time
Fences
Moderately
Firm

Frozen

Flexible

Capacity

Forecast and available
capacity
Firm Customer Orders

8

15
Weeks

26
Materials Requirement
Planning System
Based on a Master Production
Schedule, a Materials Requirement
Planning system:

• Creates schedules identifying the specific

parts and materials required to produce End
Items

• Determines exact unit numbers needed
• Determines the dates when orders for those
materials should be released – based on
Leadtimes

15
16

Aggregate
product
plan

Firm orders
from known
customers

Engineering
design
changes

Master production
Schedule (MPS)

Bill of
material
file

Primary reports
Planned order schedule for
inventory and production
control

Materials
Planning
(MRP
computer
program)

Forecasts
of demand
from random
customers

Inventory
transactions

Inventory
record file

Secondary reports
Exception reports
Planning reports
Reports for performance
control
©The McGraw-Hill Companies, Inc., 2004
17

Bill of Materials (BOM) File
A Complete Product Description

• Materials
• Parts
• Components
• Production sequence
• Modular BOM
• Subassemblies

• Super BOM

• Fractional options
18

Inventory Records File

• Each inventory item carried as a
separate file

• Status according to “time buckets”

• Pegging each parent item that created
Identify
• demand
19

Primary MRP Reports

• Planned orders to be released at a future time
• Order release notices to execute the planned
•
•

orders
Changes in due dates of open orders due to
rescheduling
Cancellations or suspensions of open orders
due to cancellation or suspension of orders on
the master production schedule

• Inventory status data
20

Secondary MRP Reports

• Planning reports, for example, forecasting
•
•

inventory requirements over a period of
time
Performance reports used to determine
agreement between actual and
programmed usage and costs
Exception reports used to point out
serious discrepancies, such as late or
overdue orders
21

Additional MRP Scheduling
Terminology

• Gross Requirements
• Scheduled receipts
• Projected available balance
• Net requirements
• Planned order receipt
• Planned order release
22

MRP Example
Item
X
A
B
C
D

X
A(2)
C(3)

B(1)
C(2)

On-Hand Lead Time (Weeks)
50
2
75
3
25
1
10
2
20
2

D(5)

Requirements include 95 units (80 firm orders and 15 forecast) of X
Requirements include 95 units (80 firm orders and 15 forecast) of X
in week 10
in week 10
23
Day:

X

A(2)

It takes
It takes
2 A’s for
2 A’s for
each X
each X

X
LT=2
Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

1

2

3

4

5

6

7

8

9

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

20
40

45
10 10

10

10

35

25

10
35
35
40

40
40
100

20 20

20

20

20

80

20

20
80
80

25
20
20
24
Day:
X
LT=2

X

A(2)

B(1)

It takes
It takes
1 B for
1 B for
each X
each X

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

1

2

3

4

5

6

7

8

9

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

20
40

45
10 10

10

10

35

25

10
35
35
40

40
40
100

20 20

20

20

20

80

20

20
80
80

25
20
20
25
Day:
X
LT=2

X

A(2)

C(3)

It takes 3
It takes 3
C’s for
C’s for
each A
each A

B(1)

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

1

2

3

4

5

6

7

8

9

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

20
40

45
10 10

10

10

35

25

10
35
35
40

40
40
100

20 20

20

20

20

80

20

20
80
80

25
20
20
26
Day:
X
LT=2

X

A(2)

C(3)

B(1)

C(2)

It takes 2
It takes 2
C’s for
C’s for
each B
each B

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

1

2

3

4

5

6

7

8

9

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

20
40

45
10 10

10

10

35

25

10
35
35
40

40
40
100

20 20

20

20

20

80

20

20
80
80

25
20
20
27
Day:
X
LT=2

X

A(2)

C(3)

B(1)

C(2)

It takes 5
It takes 5
D’s for
D’s for
each B
each B

D(5)

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

1

2

3

4

5

6

7

8

9

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

20
40

45
10 10

10

10

35

25

10
35
35
40

40
40
100

20 20

20

20

20

80

20

20
80
80

25
20
20
28

Closed Loop MRP
Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning

No
Feedback

Realistic?

Yes
Execute:
Capacity Plans
Material Plans

Feedback
29

EVOLUTION OF MRP - II

MRP
MPS
PPC
IC
ENG
CC

-

Materials Requirement Planning
Master Production Schedule
Production Planning and Control
Inventory Control
Engineering Data
Cost Control
30

Manufacturing Resource Planning
(MRP II)


Goal: Plan and monitor all resources of
a manufacturing firm (closed loop):
–
–

marketing

–

finance

–



manufacturing

engineering

Simulate the manufacturing system
31

Question Bowl
Which type of industry has only “medium”
expected benefits from the use of MRP?
a.

Assemble-to-stock

b.

Fabricate-to-stock

c.

Assemble-to-order

d.

Fabricate-to-order

e.

Process

Answer: e. Process
32

Question Bowl
a.
b.
c.
d.
e.

To ensure good master scheduling, a master
scheduler must do which of the following?
Never lose sight of the aggregate plan
Identify and communicate all problems
Be involved with customer order promising
Be visible to all levels of management
All of the above

Answer: e. All of the above (Correct answer can also
include objectively trade off manufacturing, marketing,
and engineering conflicts and include all demands from
product sales, warehouse replenishment, spares, and
interplant requirements.)
33

Question Bowl
The purpose of a “time fence” is which of the
following?
a.

Make sure the cows don’t get out of the barn

b.

Control flow through the production system

c.

Maximize sales to retailers

d.

All of the above

e.

None of the above

Answer: b. Control flow through the
production system
34

Question Bowl
Which of the following is an objective under an
MRP system?
a.

To improve customer service

b.

Minimize inventory investment

c.

Maximize production operating efficiency

d.

All of the above

e.

None of the above

Answer: d. All of the above
35

Question Bowl

a.
b.
c.
d.
e.

Which of the following is one of the three
main inputs into an MRP system?
BOM file
Exception report
Planning report
All of the above
None of the above
Answer: a. BOM file (Correct answer can
also include Master Schedule and Inventory
Records File.)
36

Question Bowl
An MRP program accesses the status of a job
according to specific time periods called which
of the following?
a.

Peg record

b.

Time fence

c.

Time bucket

d.

Time clock

e.

None of the above

Answer: c. Time bucket
37

Question Bowl
In MRP, workload per work center can be
determined. When the work capacity is
exceeded, which of the following options can be
implemented to correct the imbalance of
workload?
a.
Work overtime
b.
Renegotiate the due date and reschedule
c.
Subcontract to an outside shop
d.
All of the above
e.
None of the above
Answer: d. All of the above (Correct answer can also
include selecting an alternative work center and
rescheduling the work at a different time.)
38

Question Bowl
Which of the following are reasons why a Lot-ForLot (L4L) method of lot sizing can be used in an
MRP application?
a.

Minimizes carrying costs

b.

Sets planned orders to exactly match the net
requirements

c.

Produces exactly what is needed

d.

Does not carry any units over into future periods

e.

All of the above

Answer: e. All of the above

More Related Content

What's hot

Abc analysis
Abc analysisAbc analysis
Abc analysis
Sachin Tiwari
 
Classification of materials
Classification of materialsClassification of materials
Classification of materials
Akshata Bodke
 
Vendor managed inventory
Vendor managed inventoryVendor managed inventory
Vendor managed inventory
Hammaduddin
 
Inventory management
Inventory managementInventory management
Inventory management
kahogan62
 
Inventory control
Inventory controlInventory control
Inventory control
shaikhsaif
 
Warehouse Automation- Complete guide.pdf
Warehouse Automation- Complete guide.pdfWarehouse Automation- Complete guide.pdf
Warehouse Automation- Complete guide.pdf
philipthomas428223
 
Inventory Management Presentation
Inventory Management  Presentation Inventory Management  Presentation
Inventory Management Presentation
KattareeyaPrompreing
 
Inventory management
Inventory managementInventory management
Inventory management
RajThakuri
 
Materials management
Materials managementMaterials management
Materials management
DR .PALLAVI PATHANIA
 
Material Management
Material Management Material Management
Material Management
Fozia Khanzada
 
Effective Inventory Management
Effective Inventory ManagementEffective Inventory Management
Effective Inventory Management
Tata Power Delhi Distribution Limited
 
Purchase and procurement
Purchase and procurementPurchase and procurement
Purchase and procurement
Dr.Tamasmita Basu
 
Material management control power point presentation
Material management control power point presentationMaterial management control power point presentation
Material management control power point presentation
Muhammad Asif Khan Awan
 
Methods of Stock Verification
Methods of Stock VerificationMethods of Stock Verification
Methods of Stock Verification
Samiran Halder
 
Master Scheduling
Master SchedulingMaster Scheduling
Master Scheduling
pilly_leon
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
Zamri Yahya
 
Pengelolaan persediaan - Pert. 5.pptx
Pengelolaan persediaan - Pert. 5.pptxPengelolaan persediaan - Pert. 5.pptx
Pengelolaan persediaan - Pert. 5.pptx
BeritaDunia3
 
Material management
Material managementMaterial management
Material management
orion_06
 
Manufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemManufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) system
Yash Dave
 
Forecasting and Methods of Forecasting in Production Planning
Forecasting and Methods of Forecasting in Production PlanningForecasting and Methods of Forecasting in Production Planning
Forecasting and Methods of Forecasting in Production Planning
Bhanu Arora
 

What's hot (20)

Abc analysis
Abc analysisAbc analysis
Abc analysis
 
Classification of materials
Classification of materialsClassification of materials
Classification of materials
 
Vendor managed inventory
Vendor managed inventoryVendor managed inventory
Vendor managed inventory
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory control
Inventory controlInventory control
Inventory control
 
Warehouse Automation- Complete guide.pdf
Warehouse Automation- Complete guide.pdfWarehouse Automation- Complete guide.pdf
Warehouse Automation- Complete guide.pdf
 
Inventory Management Presentation
Inventory Management  Presentation Inventory Management  Presentation
Inventory Management Presentation
 
Inventory management
Inventory managementInventory management
Inventory management
 
Materials management
Materials managementMaterials management
Materials management
 
Material Management
Material Management Material Management
Material Management
 
Effective Inventory Management
Effective Inventory ManagementEffective Inventory Management
Effective Inventory Management
 
Purchase and procurement
Purchase and procurementPurchase and procurement
Purchase and procurement
 
Material management control power point presentation
Material management control power point presentationMaterial management control power point presentation
Material management control power point presentation
 
Methods of Stock Verification
Methods of Stock VerificationMethods of Stock Verification
Methods of Stock Verification
 
Master Scheduling
Master SchedulingMaster Scheduling
Master Scheduling
 
INVENTORY MANAGEMENT
INVENTORY MANAGEMENT INVENTORY MANAGEMENT
INVENTORY MANAGEMENT
 
Pengelolaan persediaan - Pert. 5.pptx
Pengelolaan persediaan - Pert. 5.pptxPengelolaan persediaan - Pert. 5.pptx
Pengelolaan persediaan - Pert. 5.pptx
 
Material management
Material managementMaterial management
Material management
 
Manufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) systemManufacturing planning & control (mpc) system
Manufacturing planning & control (mpc) system
 
Forecasting and Methods of Forecasting in Production Planning
Forecasting and Methods of Forecasting in Production PlanningForecasting and Methods of Forecasting in Production Planning
Forecasting and Methods of Forecasting in Production Planning
 

Similar to Ch16 mrp

Mrpmep
MrpmepMrpmep
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planning
Daniel Romero
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planning
ajithsrc
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
JOHN PAUL ROBERTO
 
MRP and ERP
MRP and ERPMRP and ERP
MRP and ERP
Musab Cannon
 
5089529.ppt
5089529.ppt5089529.ppt
MRP
MRP MRP
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
Dipesh Pandey
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
Shree Bhargava and Associate
 
Session 5
Session 5Session 5
Session 5
thangv
 
Chapter 5_OM
Chapter 5_OMChapter 5_OM
Chapter 5_OM
guest537689
 
MRP in English
MRP in EnglishMRP in English
MRP in English
Yesica Adicondro
 
Mrp
MrpMrp
Mrp
MrpMrp
Heizer 14
Heizer 14Heizer 14
Heizer 14
ajithsrc
 
Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009
Akash Maurya
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
Mostafa Ewees
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
Babasab Patil
 
08. 444444444444444444444444444444MRP.ppt
08. 444444444444444444444444444444MRP.ppt08. 444444444444444444444444444444MRP.ppt
08. 444444444444444444444444444444MRP.ppt
DarrajBrahim1
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
YashMorwal
 

Similar to Ch16 mrp (20)

Mrpmep
MrpmepMrpmep
Mrpmep
 
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planning
 
Material Requisite Planning
Material Requisite PlanningMaterial Requisite Planning
Material Requisite Planning
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
 
MRP and ERP
MRP and ERPMRP and ERP
MRP and ERP
 
5089529.ppt
5089529.ppt5089529.ppt
5089529.ppt
 
MRP
MRP MRP
MRP
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
Session 5
Session 5Session 5
Session 5
 
Chapter 5_OM
Chapter 5_OMChapter 5_OM
Chapter 5_OM
 
MRP in English
MRP in EnglishMRP in English
MRP in English
 
Mrp
MrpMrp
Mrp
 
Mrp
MrpMrp
Mrp
 
Heizer 14
Heizer 14Heizer 14
Heizer 14
 
Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009Mrp 1 deepak 12mt07ind009
Mrp 1 deepak 12mt07ind009
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
08. 444444444444444444444444444444MRP.ppt
08. 444444444444444444444444444444MRP.ppt08. 444444444444444444444444444444MRP.ppt
08. 444444444444444444444444444444MRP.ppt
 
5 MRP.ppt
5 MRP.ppt5 MRP.ppt
5 MRP.ppt
 

More from videoaakash15

Articlesof association
Articlesof associationArticlesof association
Articlesof association
videoaakash15
 
Allotment shares
Allotment sharesAllotment shares
Allotment shares
videoaakash15
 
Ca
CaCa
Allotment of shares vamsi
Allotment of shares vamsiAllotment of shares vamsi
Allotment of shares vamsi
videoaakash15
 
Allotment of shares total
Allotment of shares totalAllotment of shares total
Allotment of shares total
videoaakash15
 
2448661 issue-of-shares
2448661 issue-of-shares2448661 issue-of-shares
2448661 issue-of-shares
videoaakash15
 
87099 19849-book bulding process
87099 19849-book bulding process87099 19849-book bulding process
87099 19849-book bulding process
videoaakash15
 
Ultravires. cons.notice & indoor
Ultravires. cons.notice & indoorUltravires. cons.notice & indoor
Ultravires. cons.notice & indoor
videoaakash15
 
The contract act
The contract actThe contract act
The contract act
videoaakash15
 
Procedure for incorporating a public limited company
Procedure for incorporating a public limited companyProcedure for incorporating a public limited company
Procedure for incorporating a public limited company
videoaakash15
 
Notes on wto etc
Notes on wto etcNotes on wto etc
Notes on wto etc
videoaakash15
 
Mms la12corsout
Mms la12corsoutMms la12corsout
Mms la12corsout
videoaakash15
 
Minor as a member of a limited company
Minor as a member of a limited companyMinor as a member of a limited company
Minor as a member of a limited company
videoaakash15
 
Mergers and amalgamations
Mergers and amalgamationsMergers and amalgamations
Mergers and amalgamations
videoaakash15
 
Legal environment of business
Legal environment of businessLegal environment of business
Legal environment of business
videoaakash15
 
Law of special contracts
Law of special contractsLaw of special contracts
Law of special contracts
videoaakash15
 
It act,2000 note
It act,2000 noteIt act,2000 note
It act,2000 note
videoaakash15
 
Ipr notes
Ipr notesIpr notes
Ipr notes
videoaakash15
 
Introduction to legal frame work
Introduction to legal frame workIntroduction to legal frame work
Introduction to legal frame work
videoaakash15
 
Exhaus comp old form
Exhaus comp old formExhaus comp old form
Exhaus comp old form
videoaakash15
 

More from videoaakash15 (20)

Articlesof association
Articlesof associationArticlesof association
Articlesof association
 
Allotment shares
Allotment sharesAllotment shares
Allotment shares
 
Ca
CaCa
Ca
 
Allotment of shares vamsi
Allotment of shares vamsiAllotment of shares vamsi
Allotment of shares vamsi
 
Allotment of shares total
Allotment of shares totalAllotment of shares total
Allotment of shares total
 
2448661 issue-of-shares
2448661 issue-of-shares2448661 issue-of-shares
2448661 issue-of-shares
 
87099 19849-book bulding process
87099 19849-book bulding process87099 19849-book bulding process
87099 19849-book bulding process
 
Ultravires. cons.notice & indoor
Ultravires. cons.notice & indoorUltravires. cons.notice & indoor
Ultravires. cons.notice & indoor
 
The contract act
The contract actThe contract act
The contract act
 
Procedure for incorporating a public limited company
Procedure for incorporating a public limited companyProcedure for incorporating a public limited company
Procedure for incorporating a public limited company
 
Notes on wto etc
Notes on wto etcNotes on wto etc
Notes on wto etc
 
Mms la12corsout
Mms la12corsoutMms la12corsout
Mms la12corsout
 
Minor as a member of a limited company
Minor as a member of a limited companyMinor as a member of a limited company
Minor as a member of a limited company
 
Mergers and amalgamations
Mergers and amalgamationsMergers and amalgamations
Mergers and amalgamations
 
Legal environment of business
Legal environment of businessLegal environment of business
Legal environment of business
 
Law of special contracts
Law of special contractsLaw of special contracts
Law of special contracts
 
It act,2000 note
It act,2000 noteIt act,2000 note
It act,2000 note
 
Ipr notes
Ipr notesIpr notes
Ipr notes
 
Introduction to legal frame work
Introduction to legal frame workIntroduction to legal frame work
Introduction to legal frame work
 
Exhaus comp old form
Exhaus comp old formExhaus comp old form
Exhaus comp old form
 

Recently uploaded

How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
Zilliz
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
Mariano Tinti
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
Claudio Di Ciccio
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
DianaGray10
 
Building Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and MilvusBuilding Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and Milvus
Zilliz
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
Zilliz
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
Adtran
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
kumardaparthi1024
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 

Recently uploaded (20)

How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
Infrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI modelsInfrastructure Challenges in Scaling RAG with Custom AI models
Infrastructure Challenges in Scaling RAG with Custom AI models
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
Mariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceXMariano G Tinti - Decoding SpaceX
Mariano G Tinti - Decoding SpaceX
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”“I’m still / I’m still / Chaining from the Block”
“I’m still / I’m still / Chaining from the Block”
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
 
Building Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and MilvusBuilding Production Ready Search Pipelines with Spark and Milvus
Building Production Ready Search Pipelines with Spark and Milvus
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
Programming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup SlidesProgramming Foundation Models with DSPy - Meetup Slides
Programming Foundation Models with DSPy - Meetup Slides
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
Pushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 daysPushing the limits of ePRTC: 100ns holdover for 100 days
Pushing the limits of ePRTC: 100ns holdover for 100 days
 
GenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizationsGenAI Pilot Implementation in the organizations
GenAI Pilot Implementation in the organizations
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 

Ch16 mrp

  • 2. 2 OBJECTIVES  Materials requirement Planning (MRP)  MRP Logic and Product Structure Trees  Time Fences  MRP Example  MRP II and Lot Sizing
  • 3. 3 MATERIALS REQUIREMENT PLANNING (MRP)  Fundamental Questions in Manufacturing are – • What are we going to make? • What does it take to make it? • What do we have? • What do we have to get?
  • 4. Materials Requirement Planning • Materials requirement planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product • MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced • • Dependent demand drives MRP MRP is a software system 4
  • 5. 5 Product Hierarchy End Product Assembly 2 Assembly 1 Subassembly 1 Component A Subassembly 2 Component E Component B Component C Raw Material X Component D Raw material Y Component F
  • 6. 6 MRP Example of BOM Top Leg Short Rail Long Rail 16-6
  • 7. 7 BOM (Product Structure) Table (End Item) 1 week Leg Assembly (1) 1 week Short Rails (2) Long Rails (2) 1 week 1 week Top (1) 2 weeks Legs (4) 1 week 16-7
  • 8. Example of MRP Logic and Product Structure Tree Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed Product Structure Tree for Assembly A A B(4) D(2) C(2) E(1) D(3) F(2) Lead Times A 1 day B 2 days C 1 day D 3 days E 4 days F 1 day Total Unit Demand Day 10 50 A Day 8 20 B (Spares) Day 6 15 D (Spares) 8
  • 9. 9 First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10. Day: A Required Order Placement 1 2 3 4 5 6 7 8 9 50 LT = 1 day 10 50
  • 10. 10 Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time. Day: 1 2 3 4 5 20 LT = 2 A B(4) D(2) D(3) 9 50 200 200 Spares 4x50=200 C(2) E(1) 7 8 20 A Required Order Placement B Required Order Placement 6 F(2) 10 50
  • 11. Finally, repeating the process for all components, we have the final materials requirements plan: Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 1 2 4 5 6 20 7 8 9 20 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 3 11 10 50 50 200 200 100 55 20 55 20 400 400 100 300 200 300 200 200 200 A B(4) D(2) Part D: Day 6 C(2) E(1) D(3) 40 + 15 spares F(2) ©The McGraw-Hill Companies, Inc., 2001
  • 12. Master Production Schedule (MPS)  12 Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan Aggregate Plan (Product Groups) (Product Groups) MPS (Specific End Items)
  • 13. 13 Types of Time Fences  Frozen – No schedule changes allowed within this window  Moderately Firm – Specific changes allowed within product groups as long as parts are available  Flexible – Significant variation allowed as long as overall capacity requirements remain at the same levels
  • 14. 14 Example of Time Fences Moderately Firm Frozen Flexible Capacity Forecast and available capacity Firm Customer Orders 8 15 Weeks 26
  • 15. Materials Requirement Planning System Based on a Master Production Schedule, a Materials Requirement Planning system: • Creates schedules identifying the specific parts and materials required to produce End Items • Determines exact unit numbers needed • Determines the dates when orders for those materials should be released – based on Leadtimes 15
  • 16. 16 Aggregate product plan Firm orders from known customers Engineering design changes Master production Schedule (MPS) Bill of material file Primary reports Planned order schedule for inventory and production control Materials Planning (MRP computer program) Forecasts of demand from random customers Inventory transactions Inventory record file Secondary reports Exception reports Planning reports Reports for performance control ©The McGraw-Hill Companies, Inc., 2004
  • 17. 17 Bill of Materials (BOM) File A Complete Product Description • Materials • Parts • Components • Production sequence • Modular BOM • Subassemblies • Super BOM • Fractional options
  • 18. 18 Inventory Records File • Each inventory item carried as a separate file • Status according to “time buckets” • Pegging each parent item that created Identify • demand
  • 19. 19 Primary MRP Reports • Planned orders to be released at a future time • Order release notices to execute the planned • • orders Changes in due dates of open orders due to rescheduling Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule • Inventory status data
  • 20. 20 Secondary MRP Reports • Planning reports, for example, forecasting • • inventory requirements over a period of time Performance reports used to determine agreement between actual and programmed usage and costs Exception reports used to point out serious discrepancies, such as late or overdue orders
  • 21. 21 Additional MRP Scheduling Terminology • Gross Requirements • Scheduled receipts • Projected available balance • Net requirements • Planned order receipt • Planned order release
  • 22. 22 MRP Example Item X A B C D X A(2) C(3) B(1) C(2) On-Hand Lead Time (Weeks) 50 2 75 3 25 1 10 2 20 2 D(5) Requirements include 95 units (80 firm orders and 15 forecast) of X Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10 in week 10
  • 23. 23 Day: X A(2) It takes It takes 2 A’s for 2 A’s for each X each X X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20 Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 50 50 50 50 50 50 50 50 50 45 45 45 90 75 75 75 75 75 75 75 75 15 15 15 45 25 25 25 25 25 25 20 40 45 10 10 10 10 35 25 10 35 35 40 40 40 100 20 20 20 20 20 80 20 20 80 80 25 20 20
  • 24. 24 Day: X LT=2 X A(2) B(1) It takes It takes 1 B for 1 B for each X each X Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20 Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 50 50 50 50 50 50 50 50 50 45 45 45 90 75 75 75 75 75 75 75 75 15 15 15 45 25 25 25 25 25 25 20 40 45 10 10 10 10 35 25 10 35 35 40 40 40 100 20 20 20 20 20 80 20 20 80 80 25 20 20
  • 25. 25 Day: X LT=2 X A(2) C(3) It takes 3 It takes 3 C’s for C’s for each A each A B(1) Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20 Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 50 50 50 50 50 50 50 50 50 45 45 45 90 75 75 75 75 75 75 75 75 15 15 15 45 25 25 25 25 25 25 20 40 45 10 10 10 10 35 25 10 35 35 40 40 40 100 20 20 20 20 20 80 20 20 80 80 25 20 20
  • 26. 26 Day: X LT=2 X A(2) C(3) B(1) C(2) It takes 2 It takes 2 C’s for C’s for each B each B Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20 Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 50 50 50 50 50 50 50 50 50 45 45 45 90 75 75 75 75 75 75 75 75 15 15 15 45 25 25 25 25 25 25 20 40 45 10 10 10 10 35 25 10 35 35 40 40 40 100 20 20 20 20 20 80 20 20 80 80 25 20 20
  • 27. 27 Day: X LT=2 X A(2) C(3) B(1) C(2) It takes 5 It takes 5 D’s for D’s for each B each B D(5) Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand 20 Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Scheduled receipts Proj. avail. balance Net requirements Planned order receipt Planner order release 1 2 3 4 5 6 7 8 9 10 95 50 50 50 50 50 50 50 50 50 50 45 45 45 90 75 75 75 75 75 75 75 75 15 15 15 45 25 25 25 25 25 25 20 40 45 10 10 10 10 35 25 10 35 35 40 40 40 100 20 20 20 20 20 80 20 20 80 80 25 20 20
  • 28. 28 Closed Loop MRP Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning No Feedback Realistic? Yes Execute: Capacity Plans Material Plans Feedback
  • 29. 29 EVOLUTION OF MRP - II MRP MPS PPC IC ENG CC - Materials Requirement Planning Master Production Schedule Production Planning and Control Inventory Control Engineering Data Cost Control
  • 30. 30 Manufacturing Resource Planning (MRP II)  Goal: Plan and monitor all resources of a manufacturing firm (closed loop): – – marketing – finance –  manufacturing engineering Simulate the manufacturing system
  • 31. 31 Question Bowl Which type of industry has only “medium” expected benefits from the use of MRP? a. Assemble-to-stock b. Fabricate-to-stock c. Assemble-to-order d. Fabricate-to-order e. Process Answer: e. Process
  • 32. 32 Question Bowl a. b. c. d. e. To ensure good master scheduling, a master scheduler must do which of the following? Never lose sight of the aggregate plan Identify and communicate all problems Be involved with customer order promising Be visible to all levels of management All of the above Answer: e. All of the above (Correct answer can also include objectively trade off manufacturing, marketing, and engineering conflicts and include all demands from product sales, warehouse replenishment, spares, and interplant requirements.)
  • 33. 33 Question Bowl The purpose of a “time fence” is which of the following? a. Make sure the cows don’t get out of the barn b. Control flow through the production system c. Maximize sales to retailers d. All of the above e. None of the above Answer: b. Control flow through the production system
  • 34. 34 Question Bowl Which of the following is an objective under an MRP system? a. To improve customer service b. Minimize inventory investment c. Maximize production operating efficiency d. All of the above e. None of the above Answer: d. All of the above
  • 35. 35 Question Bowl a. b. c. d. e. Which of the following is one of the three main inputs into an MRP system? BOM file Exception report Planning report All of the above None of the above Answer: a. BOM file (Correct answer can also include Master Schedule and Inventory Records File.)
  • 36. 36 Question Bowl An MRP program accesses the status of a job according to specific time periods called which of the following? a. Peg record b. Time fence c. Time bucket d. Time clock e. None of the above Answer: c. Time bucket
  • 37. 37 Question Bowl In MRP, workload per work center can be determined. When the work capacity is exceeded, which of the following options can be implemented to correct the imbalance of workload? a. Work overtime b. Renegotiate the due date and reschedule c. Subcontract to an outside shop d. All of the above e. None of the above Answer: d. All of the above (Correct answer can also include selecting an alternative work center and rescheduling the work at a different time.)
  • 38. 38 Question Bowl Which of the following are reasons why a Lot-ForLot (L4L) method of lot sizing can be used in an MRP application? a. Minimizes carrying costs b. Sets planned orders to exactly match the net requirements c. Produces exactly what is needed d. Does not carry any units over into future periods e. All of the above Answer: e. All of the above