This document is a request for proposal issued by Rajasthan Renewable Energy Corporation Limited (RREC) on behalf of the Water Resource Department and Discoms of Rajasthan for the selection of developers to set up a 2 MW grid-connected solar PV plant on canal tops in Rajasthan. The key details are:
1) RREC is inviting bids for setting up a 2 MW solar PV project on canal tops managed by IGN Board/Water Resource Department in Hanumangarh, Rajasthan.
2) The project is estimated to cost Rs. 21 crore and is to be commissioned within 15 months of signing the power purchase agreement with the procurers.
3)
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
This presentation highlights on the following :
Need of wind-solar hybrid systems
Indian policy support to hybrid systems - MNRE & Gujarat State
Renewable Energy integration with grid,
Cost savings in hybrid for AC-AC & DC-DC coupling systems,
Case studies
Gensol provides solar advisory and permitting services for utility-scale solar power projects. They assist with obtaining over 32 permits required from various state agencies. These permits are grouped into 5 modules: utility and grid connections; state renewable energy agency approvals; company and tax registrations; land approvals; and local permits. Gensol has experience advising on over 400MW of solar projects and provides owner's representative, lender engineering, design review, and feasibility study services. They also install solar rooftop systems and provide renewable energy certificate and carbon credit advisory services.
Tender Document for 1 MW Solar at DamanHeadway Solar
Tender Document for 1 MW Solar at Daman. Issued by Electricity Department of Daman and Diu.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Solar PV O&M looks easy however maintaining a Solar PV Plant at top performance is a task and based on the experience of Solarig-Gensol in maintaining a 2 GW portfolio of solar plants in India, here are some basics on Solar O&M.
Presentation has the following contents:
a) Balancing Soiling Losses with case study
b) Monitoring & Corrective Maintenance
c) Performance Ratio & Uptime Guarantee
d) Impact of O&M on IRR
A Delay of a single day for a 10 MW plant can lead to a loss of Rs. 6.5 Lacs ($110,000) in addition to Statutory Losses. Here, we explore typical project execution timelines and possible reasons for delay. The presentation talks about Lead Times of Equipment, Key vendors, Permits Required, Construction & Engineering related delays and finally, gives recommendations on how to keep project on track.
Feasibility of nuclear power plant in BangladeshTapasriBarua
The document discusses the feasibility of building a nuclear power plant in Bangladesh called the Rooppur Nuclear Power Plant (RNPP). Key points include:
- Bangladesh needs more power generation to meet growing demand and reduce reliance on fossil fuels. Nuclear could help meet these needs.
- RNPP would have 2 VVER-1200 reactors provided by Russia, with a total capacity of 2400 MW. Construction began in 2013 with a target completion of 2022-2023.
- Safety features include multiple barriers to radiation exposure and both active and passive safety systems. However, high population density near the site and risks of natural disasters or terrorism require further analysis and precautions.
- Nuclear energy could be
Project & Infrastructure Financing- SPV for Solar Park Akhilesh Upadhyay
The document proposes the development of a solar park special purpose vehicle (SPV) in Jharkhand, India. It outlines the power scenario and renewable energy potential in India and Jharkhand. It discusses the feasibility and benefits of developing a solar park, including available wastelands, infrastructure sharing, and reduced costs. The document then covers the legal and regulatory requirements for a solar park, essential infrastructure needs, and financial viability analysis. It proposes an SPV structure with the state government, off-taker, financial institutions, and contractors. Key timelines discussed include the development phase, financial close, commercial operation date, and debt repayment date.
The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.
Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.
This presentation highlights on the following :
Need of wind-solar hybrid systems
Indian policy support to hybrid systems - MNRE & Gujarat State
Renewable Energy integration with grid,
Cost savings in hybrid for AC-AC & DC-DC coupling systems,
Case studies
Gensol provides solar advisory and permitting services for utility-scale solar power projects. They assist with obtaining over 32 permits required from various state agencies. These permits are grouped into 5 modules: utility and grid connections; state renewable energy agency approvals; company and tax registrations; land approvals; and local permits. Gensol has experience advising on over 400MW of solar projects and provides owner's representative, lender engineering, design review, and feasibility study services. They also install solar rooftop systems and provide renewable energy certificate and carbon credit advisory services.
Tender Document for 1 MW Solar at DamanHeadway Solar
Tender Document for 1 MW Solar at Daman. Issued by Electricity Department of Daman and Diu.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Solar PV O&M looks easy however maintaining a Solar PV Plant at top performance is a task and based on the experience of Solarig-Gensol in maintaining a 2 GW portfolio of solar plants in India, here are some basics on Solar O&M.
Presentation has the following contents:
a) Balancing Soiling Losses with case study
b) Monitoring & Corrective Maintenance
c) Performance Ratio & Uptime Guarantee
d) Impact of O&M on IRR
A Delay of a single day for a 10 MW plant can lead to a loss of Rs. 6.5 Lacs ($110,000) in addition to Statutory Losses. Here, we explore typical project execution timelines and possible reasons for delay. The presentation talks about Lead Times of Equipment, Key vendors, Permits Required, Construction & Engineering related delays and finally, gives recommendations on how to keep project on track.
Feasibility of nuclear power plant in BangladeshTapasriBarua
The document discusses the feasibility of building a nuclear power plant in Bangladesh called the Rooppur Nuclear Power Plant (RNPP). Key points include:
- Bangladesh needs more power generation to meet growing demand and reduce reliance on fossil fuels. Nuclear could help meet these needs.
- RNPP would have 2 VVER-1200 reactors provided by Russia, with a total capacity of 2400 MW. Construction began in 2013 with a target completion of 2022-2023.
- Safety features include multiple barriers to radiation exposure and both active and passive safety systems. However, high population density near the site and risks of natural disasters or terrorism require further analysis and precautions.
- Nuclear energy could be
Project & Infrastructure Financing- SPV for Solar Park Akhilesh Upadhyay
The document proposes the development of a solar park special purpose vehicle (SPV) in Jharkhand, India. It outlines the power scenario and renewable energy potential in India and Jharkhand. It discusses the feasibility and benefits of developing a solar park, including available wastelands, infrastructure sharing, and reduced costs. The document then covers the legal and regulatory requirements for a solar park, essential infrastructure needs, and financial viability analysis. It proposes an SPV structure with the state government, off-taker, financial institutions, and contractors. Key timelines discussed include the development phase, financial close, commercial operation date, and debt repayment date.
This document lists permits and licenses required at different stages for setting up a new solar power plant and company. It includes permits related to taxes, land, distribution companies, electrical inspectors, and nodal agencies. Some examples include VAT registration, land purchase permission, pollution control approvals, electrical layout approval, power evacuation clearance, commissioning certification, and REC registration. The permits are grouped into those needed at initial stages, during construction, and at commissioning of the plant.
This document discusses open access power purchase in India. Open access allows for the non-discriminatory use of transmission and distribution systems by licensees, consumers, and generators. It describes bilateral transactions for buying and selling power as well as collective transactions through power exchanges like IEX. Requirements for open access include installation of specialized meters, available transmission capacity, a contract demand over 1 MW, payment security, and no pending legal issues. Cost analyses are provided for purchasing 1 MW of power through IEX daily bidding and a bilateral fixed tariff agreement.
This document discusses national and regional power system planning in India. It begins with an introduction to power system planning, including transmission versus distribution planning and long-term versus short-term planning. It then covers various aspects of planning such as generation planning, capacity resource planning, and transmission planning. The document outlines the five electricity regions in India and discusses the economic benefits of regional coordination in planning. It concludes with mentions of integrated resource planning and least cost utility planning strategies.
IMPACT OF CERC'S SHARING OF TRANSMISSION CHARGES AND LOSSES REGULATIONS Amitava Nag
WBSEDCL may have to bear approximately Rs. 6.48 Cr. + Rs. 1.4 Cr. = Rs. 7.88 Cr. extra charge per month when the enacted sharing regulations 2020 of CERC will be implemented. Since this new regulations have violated Article 14 and Article 303(1) of the Constitution of India, WBSEDCL therefore could file a writ petition at Calcutta High Court as per Article 226 of the Constitution of India for a stay of the notified regulations and justified modification of that statute to stop cross subsidy among States and to reinstate “beneficiary-pays” principle.
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
This document provides a summary of key aspects of solar power projects including technology, costs and project development phases. Some key points from the document include:
- The basic schematic and components of a solar power system are described, including how solar energy is converted to DC and then AC current for transmission to the grid.
- Key solar technologies like polycrystalline and thin film solar modules are discussed as well as manufacturing processes. Historical and projected future increases to solar cell efficiencies are presented.
- The cost structures and trends for solar modules and balance of system components are analyzed, showing modules now account for 65% of project costs on average. Factors driving further cost reductions are also outlined.
-
This document discusses the key cost components and considerations for a 25 MW scale solar power project in India. It outlines that the major cost components are solar modules (60% of costs), inverters (8% of costs), mounting structures (5% of costs), and balance of system equipment (12% of costs). Land costs account for 2% of total costs. The document then provides a breakdown of estimated costs per MW for different project components and scales from 25MW to 100MW, showing economies of scale. It also discusses factors that can impact execution costs and ways to optimize costs through rate contracts, backward integration, and prior land acquisition.
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
This document analyzes the financial feasibility of building a 10MW solar power plant in India. It finds that the project has a low return on investment based on current conditions, but could become more viable if conversion efficiency increases and government incentives continue. A sensitivity analysis shows that returns are highly dependent on power purchase agreement rates, taxes, and conversion efficiency. The project may only be profitable if government policies strongly support the solar energy sector. Foreign investment from countries like Spain could see higher returns. Overall, the solar power sector in India depends heavily on government incentives and support.
Energy Transition - A comprehensive approachSampe Purba
this Paper discuss that a transition energy can be reached by the lining streaming of Supply, Demand, Infrastructure, Commerciality and regulation. However, any transitional energy has to consider the technology, existing power generation and the ability to absorb and competitiveness
Open access financial modelling feasibilityJay Ranvir
This document provides an overview of open access provisions in India and Maharashtra, calculation of open access charges, and financial modeling of a 1 MW bagasse-based co-generation power project. It discusses the key provisions for open access in the Electricity Act 2003, National Electricity Policy, and National Tariff Policy. It also examines open access charges like wheeling charges, transmission charges, cross subsidy surcharge, and analyzes the viability of long-term open access in Maharashtra. Furthermore, it discusses the renewable energy scenario and need for open access in renewables. The document undertakes financial modeling of a bagasse co-generation plant including assumptions, project economics, sensitivity analysis and determines the levelized tariff.
As more & more renewables get integrated into the Indian Grid, Energy Storage will play an important role in helping with Grid Management & smoothing out the peak curve created by Renewable Energy.
It is expected that Energy Storage will be a multi GW market in the years to come.
Primotech Energy Solution provides solar rooftop EPC solutions and is one of the largest independently owned solar companies in Delhi. It offers a full range of services from site surveys and energy audits to installation, commissioning, and long-term maintenance. Primotech can design grid-tied, off-grid, or hybrid solar+battery+generator systems and estimates average payback periods of 3-5 years for its 25 kW commercial rooftop installations. The company targets customers across various industry sectors and provides a full turnkey solar solution through all project phases from promotion to operation and maintenance.
The document discusses open access regulation and grant of connectivity regulation in India. It provides definitions of open access, objectives of open access such as increasing competition and reducing losses. It describes the working process of open access involving generators, utilities, traders and consumers. It also outlines the types of open access transactions and various regulations issued over time in 2004, 2006, 2008, 2013 and 2014 that govern open access.
Electrical and Solar PV Systems (www.solartraining.ca)Irtaza M. Syed
Overview and basics of conventional electric power distribution and solar Photo-voltaic (PV) systems. Generation, Transmission, distribution and utilization. Power flow, anti-islanding and PV systems connection to utility. PV applications and market. (www.solartraining.ca)
The document discusses Bangladesh's first nuclear power plant called the Rooppur Nuclear Power Plant (RNPP) which is under construction. It will be located in Ishwardi, Pabna district and will have 2 units capable of producing 2,400 MW of electricity total. The RNPP is expected to begin operations in 2023 and will provide a safe, reliable and affordable source of clean energy for Bangladesh to meet its growing electricity demands. It discusses the technical features and safety standards that are in place to ensure safe operations.
This document summarizes the electrical characteristics of solar photovoltaic panels and arrays. It explains that panels can be connected in series to increase voltage or parallel to increase current. The maximum power point is always in the upper right corner of the I-V curve. Key parameters discussed include open circuit voltage, short circuit current, maximum power point, fill factor, and efficiency.
1) Hydroelectric power has significant untapped potential in Pakistan to help address the country's energy needs.
2) Pakistan currently generates around 35% of its energy from hydropower but has an estimated potential of over 41,000MW, most of which remains unutilized.
3) Harnessing more of Pakistan's hydro potential through projects like Diamer-Bhasha Dam could help reduce the country's reliance on expensive and imported fossil fuels for energy generation.
A comparative study has been carried by Gensol on Solar-Wind Hybrid Policies issued by Central Government, Gujarat State & Andhra Pradesh (A.P.) in terms of following:
1) Incentives & Pertinent Charges
2) Evacuation & Metering Scheme
3) Energy Accounting & Banking
4) AC-DC Integration & other important clauses.
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
The document outlines the key steps in executing a solar power project from allocation to execution:
1) Land and site finalization includes assessing meteorological resources, connectivity to the grid, soil conditions, and availability of manpower and water.
2) A detailed project report covers site analysis, technology selection, plant design, energy estimates, and project finances.
3) An EPC contractor is selected through a bidding process based on experience, equipment, cost, and guarantees.
4) Drawings and design are vetted for safety, strength, and optimal performance.
5) Onsite monitoring ensures quality, compliance with standards, and documentation during construction.
6) Commissioning validates performance
RFP Document for solar PV Project RajasthanHeadway Solar
RFP Document for solar PV Project Rajasthan. Issued by Rajasthan Renewable Energy Corporation Limited.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
This proposal outlines a 1 MWp solar power plant in Vadodara, Gujarat, India. The key details include:
1) The plant will be grid-connected and use poly-crystalline solar modules covering an area of 5.5-6 acres (1.25 lac sq feet).
2) The main components will be the solar PV array, inverters, monitoring systems, and a substation.
3) A maintenance contract is proposed to include performance monitoring, preventative maintenance, corrective maintenance and other services.
4) An implementation schedule and project management approach is outlined, along with procurement, integration plans and budgets.
This document lists permits and licenses required at different stages for setting up a new solar power plant and company. It includes permits related to taxes, land, distribution companies, electrical inspectors, and nodal agencies. Some examples include VAT registration, land purchase permission, pollution control approvals, electrical layout approval, power evacuation clearance, commissioning certification, and REC registration. The permits are grouped into those needed at initial stages, during construction, and at commissioning of the plant.
This document discusses open access power purchase in India. Open access allows for the non-discriminatory use of transmission and distribution systems by licensees, consumers, and generators. It describes bilateral transactions for buying and selling power as well as collective transactions through power exchanges like IEX. Requirements for open access include installation of specialized meters, available transmission capacity, a contract demand over 1 MW, payment security, and no pending legal issues. Cost analyses are provided for purchasing 1 MW of power through IEX daily bidding and a bilateral fixed tariff agreement.
This document discusses national and regional power system planning in India. It begins with an introduction to power system planning, including transmission versus distribution planning and long-term versus short-term planning. It then covers various aspects of planning such as generation planning, capacity resource planning, and transmission planning. The document outlines the five electricity regions in India and discusses the economic benefits of regional coordination in planning. It concludes with mentions of integrated resource planning and least cost utility planning strategies.
IMPACT OF CERC'S SHARING OF TRANSMISSION CHARGES AND LOSSES REGULATIONS Amitava Nag
WBSEDCL may have to bear approximately Rs. 6.48 Cr. + Rs. 1.4 Cr. = Rs. 7.88 Cr. extra charge per month when the enacted sharing regulations 2020 of CERC will be implemented. Since this new regulations have violated Article 14 and Article 303(1) of the Constitution of India, WBSEDCL therefore could file a writ petition at Calcutta High Court as per Article 226 of the Constitution of India for a stay of the notified regulations and justified modification of that statute to stop cross subsidy among States and to reinstate “beneficiary-pays” principle.
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
This document provides a summary of key aspects of solar power projects including technology, costs and project development phases. Some key points from the document include:
- The basic schematic and components of a solar power system are described, including how solar energy is converted to DC and then AC current for transmission to the grid.
- Key solar technologies like polycrystalline and thin film solar modules are discussed as well as manufacturing processes. Historical and projected future increases to solar cell efficiencies are presented.
- The cost structures and trends for solar modules and balance of system components are analyzed, showing modules now account for 65% of project costs on average. Factors driving further cost reductions are also outlined.
-
This document discusses the key cost components and considerations for a 25 MW scale solar power project in India. It outlines that the major cost components are solar modules (60% of costs), inverters (8% of costs), mounting structures (5% of costs), and balance of system equipment (12% of costs). Land costs account for 2% of total costs. The document then provides a breakdown of estimated costs per MW for different project components and scales from 25MW to 100MW, showing economies of scale. It also discusses factors that can impact execution costs and ways to optimize costs through rate contracts, backward integration, and prior land acquisition.
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
This document analyzes the financial feasibility of building a 10MW solar power plant in India. It finds that the project has a low return on investment based on current conditions, but could become more viable if conversion efficiency increases and government incentives continue. A sensitivity analysis shows that returns are highly dependent on power purchase agreement rates, taxes, and conversion efficiency. The project may only be profitable if government policies strongly support the solar energy sector. Foreign investment from countries like Spain could see higher returns. Overall, the solar power sector in India depends heavily on government incentives and support.
Energy Transition - A comprehensive approachSampe Purba
this Paper discuss that a transition energy can be reached by the lining streaming of Supply, Demand, Infrastructure, Commerciality and regulation. However, any transitional energy has to consider the technology, existing power generation and the ability to absorb and competitiveness
Open access financial modelling feasibilityJay Ranvir
This document provides an overview of open access provisions in India and Maharashtra, calculation of open access charges, and financial modeling of a 1 MW bagasse-based co-generation power project. It discusses the key provisions for open access in the Electricity Act 2003, National Electricity Policy, and National Tariff Policy. It also examines open access charges like wheeling charges, transmission charges, cross subsidy surcharge, and analyzes the viability of long-term open access in Maharashtra. Furthermore, it discusses the renewable energy scenario and need for open access in renewables. The document undertakes financial modeling of a bagasse co-generation plant including assumptions, project economics, sensitivity analysis and determines the levelized tariff.
As more & more renewables get integrated into the Indian Grid, Energy Storage will play an important role in helping with Grid Management & smoothing out the peak curve created by Renewable Energy.
It is expected that Energy Storage will be a multi GW market in the years to come.
Primotech Energy Solution provides solar rooftop EPC solutions and is one of the largest independently owned solar companies in Delhi. It offers a full range of services from site surveys and energy audits to installation, commissioning, and long-term maintenance. Primotech can design grid-tied, off-grid, or hybrid solar+battery+generator systems and estimates average payback periods of 3-5 years for its 25 kW commercial rooftop installations. The company targets customers across various industry sectors and provides a full turnkey solar solution through all project phases from promotion to operation and maintenance.
The document discusses open access regulation and grant of connectivity regulation in India. It provides definitions of open access, objectives of open access such as increasing competition and reducing losses. It describes the working process of open access involving generators, utilities, traders and consumers. It also outlines the types of open access transactions and various regulations issued over time in 2004, 2006, 2008, 2013 and 2014 that govern open access.
Electrical and Solar PV Systems (www.solartraining.ca)Irtaza M. Syed
Overview and basics of conventional electric power distribution and solar Photo-voltaic (PV) systems. Generation, Transmission, distribution and utilization. Power flow, anti-islanding and PV systems connection to utility. PV applications and market. (www.solartraining.ca)
The document discusses Bangladesh's first nuclear power plant called the Rooppur Nuclear Power Plant (RNPP) which is under construction. It will be located in Ishwardi, Pabna district and will have 2 units capable of producing 2,400 MW of electricity total. The RNPP is expected to begin operations in 2023 and will provide a safe, reliable and affordable source of clean energy for Bangladesh to meet its growing electricity demands. It discusses the technical features and safety standards that are in place to ensure safe operations.
This document summarizes the electrical characteristics of solar photovoltaic panels and arrays. It explains that panels can be connected in series to increase voltage or parallel to increase current. The maximum power point is always in the upper right corner of the I-V curve. Key parameters discussed include open circuit voltage, short circuit current, maximum power point, fill factor, and efficiency.
1) Hydroelectric power has significant untapped potential in Pakistan to help address the country's energy needs.
2) Pakistan currently generates around 35% of its energy from hydropower but has an estimated potential of over 41,000MW, most of which remains unutilized.
3) Harnessing more of Pakistan's hydro potential through projects like Diamer-Bhasha Dam could help reduce the country's reliance on expensive and imported fossil fuels for energy generation.
A comparative study has been carried by Gensol on Solar-Wind Hybrid Policies issued by Central Government, Gujarat State & Andhra Pradesh (A.P.) in terms of following:
1) Incentives & Pertinent Charges
2) Evacuation & Metering Scheme
3) Energy Accounting & Banking
4) AC-DC Integration & other important clauses.
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
The document outlines the key steps in executing a solar power project from allocation to execution:
1) Land and site finalization includes assessing meteorological resources, connectivity to the grid, soil conditions, and availability of manpower and water.
2) A detailed project report covers site analysis, technology selection, plant design, energy estimates, and project finances.
3) An EPC contractor is selected through a bidding process based on experience, equipment, cost, and guarantees.
4) Drawings and design are vetted for safety, strength, and optimal performance.
5) Onsite monitoring ensures quality, compliance with standards, and documentation during construction.
6) Commissioning validates performance
RFP Document for solar PV Project RajasthanHeadway Solar
RFP Document for solar PV Project Rajasthan. Issued by Rajasthan Renewable Energy Corporation Limited.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
This proposal outlines a 1 MWp solar power plant in Vadodara, Gujarat, India. The key details include:
1) The plant will be grid-connected and use poly-crystalline solar modules covering an area of 5.5-6 acres (1.25 lac sq feet).
2) The main components will be the solar PV array, inverters, monitoring systems, and a substation.
3) A maintenance contract is proposed to include performance monitoring, preventative maintenance, corrective maintenance and other services.
4) An implementation schedule and project management approach is outlined, along with procurement, integration plans and budgets.
The document is a Request for Proposal issued by the Punjab Energy Development Agency to invite bids for new grid connected solar photovoltaic power projects with a total capacity of 300 MW under Phase I. It provides background information on PEDA and the solar power potential in Punjab. Key details include the fiscal incentives available for solar power developers under the state's NRSE policy 2012, the process for project selection through competitive bidding and e-auction, timelines, technical requirements, formats for bid submission and various other terms and conditions.
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...Harish Sharma
Online Bids are invited by Jharkhand Renewable Energy Development Agency (JREDA) from eligible Bidders to participate in the bidding process for Setting up of 1200 MW Grid connected Solar PV projects to be established in the State of Jharkhand by Solar Project Developers and supply of Solar Power at the Delivery Point for a period of 25 years from the Scheduled Commissioning Date in accordance with the terms of the Power Purchase Agreement (PPA) to be entered with JBVNL.
Setting up of Grid Connected Solar PV Projects of Total Capacity 1200 MW as per following Categories:
200 MW for Category - I: 1 - 25 MW size projects
1000 MW for Category – II: 26 - 500 MW size projects
Important Highlights of the Bid Documents are given below
1. Period of downloading of RFP Documents: From 07.12.2015 at 12:00 Noon till 10.01.2016 at 05:00 PM
2. Last date & time for receipt of online bids and submission of hard copies of DD’s & BG: 11.01.2016 upto 05:00 PM (Monday)
3. Technical Bid Opening Date: 12.01.2016 at 03:30 PM (Tuesday)
For more details and bid assistance you can contact us at info@environmentfirst.in
Solar RFP Document for 150mw Solar PV Projects in BiharHeadway Solar
Solar RFP Bid Document for 150mw Solar PV Projects in Bihar.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Rajasthan Net Metering Regulations 2015 released by Rajasthan Regulatory Commission (RERC).
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Power Plants Punjab 2014
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
RFS Document for Solar plant in Telangana for 500 MW. Released by Southern Power Distribution Company of Telangana Limited (TSSPDCL) & Northern Power Distribution Company Limited of Telangana (TSNPDCL)
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
New grid connected solar photo voltaic power projects 500 mw capacity under...ank_
This document is a Request for Proposal issued by the Punjab Energy Development Agency to invite private developers to set up 500 MW of grid-connected solar photovoltaic power projects in Punjab, India. It provides background information on Punjab's solar energy potential and the incentives available for solar power projects. The RfP includes sections on project details, bidder qualifications, the selection process, implementation agreements and power purchase terms. Bidders are invited to submit proposals by the specified deadline to be considered for development of these new solar projects.
RFP Document for Grid Connected Solar Power Project in ChhattisgarhHeadway Solar
RFP Document for Grid Connected Solar Power Project in Chhattisgarh.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
1) Procurement officers play an important leadership role in acquiring goods and services for local governments in an efficient and effective manner. Developing Requests for Proposals (RFPs) for novel acquisitions like solar energy systems can be challenging.
2) The document provides examples of two cities' experiences with developing solar RFPs. Milwaukee initially developed restrictive RFPs that received overly expensive bids, but successful RFPs incorporated feedback and made requirements more flexible and outcome-based. San Jose also found success making its RFP more flexible based on stakeholder input.
3) Developing a successful solar RFP involves starting with a clear goal, involving stakeholders early, and including essential elements like system specifications,
RFP Documents for Solar Plant in Uttar PradeshHeadway Solar
RFP Documents for 200 MW Solar Plant in Uttar Pradesh released by UPNEDA.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Bid Document for Solar PV Project in Assam. Released by AEDA.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Rfp document for Solar PV Project in DelhiHeadway Solar
Bid document for Solar PV Project in Delhi. Released by North Delhi Power Limited.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...Headway Solar
The document is a notice inviting tender for the procurement of 150 MW of solar power through a tariff-based competitive bidding process. It provides key details such as the tender number and date, pre-bid meeting date and time, last date for bid submission, bid opening dates, cost of tender document, earnest money deposit required, and contact information for submitting bids. It also includes disclaimers and definitions of important terms used in the bidding process.
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Headway Solar
This document outlines regulations for grid-connected solar power projects in Goa and Union Territories. It defines key terms related to solar power projects and regulations. The regulations cover the scope, eligibility criteria, technical parameters, metering and billing, tariff structure, and other financial and administrative aspects of setting up and operating grid-connected solar power projects in the region. The overall aim is to promote the development of solar energy generation through these regulations.
Epc service proposal for setting up solar power project standard templateSaurabh Parihar
Global Green Energy provides turnkey services for setting up solar power projects in India, including project development, engineering, procurement, construction, and operations and maintenance. It develops mini solar parks of 25 MW capacity in various Indian states. Its services include assisting clients with project approvals, financing, power evacuation, REC registration and sales. It has expertise developing projects under India's REC mechanism and will handle approvals, design, installation, and providing generation guarantees for solar projects. Fees are charged as a fixed amount plus 1.5% for debt syndication, with milestone-based payments.
This document proposes a solar power system for the PIPS project and provides technical details. It recommends a 45kW solar panel system with polycrystalline solar modules, an MPPT charge controller, deep cycle maintenance-free batteries, and a 60kVA inverter. Installation details are included along with cost estimates totaling approximately 37 million Pakistani rupees. Technical specifications conform to international standards.
Solar Mango provides consulting services to help businesses and developers succeed in India's growing solar energy market. They assist with project development, financing, market entry, manufacturing, and research. Solar Mango's team of experts in engineering, management, and renewable energy can help navigate critical aspects of solar projects to avoid costly mistakes. Their goal is to ensure high-quality solar installations and transactions through guidance based on decades of experience across the solar industry.
Rajasthan Solar Roof Top tender 2014-2015Headway Solar
Solar Roof Top tender 2014-2015 in Rajasthan. Issued by Rajasthan Renewable Energy Corporation Limited.
This document is not a work of Headway Solar (http://headwaysolar.com/) and it has been released here for the benefit of the general public.
This document is a Request for Qualification (RFQ) issued by REC Transmission Projects Company Ltd. (RECTPCL) to shortlist bidders for the establishment of a new transmission system called "System Strengthening Scheme in Northern Region (NRSS-XXXVI)" along with LILO of an existing transmission line. The project involves setting up new transmission lines and bays. RECTPCL seeks to qualify interested bidders through this RFQ based on meeting eligibility criteria. Qualified bidders will then be invited to participate in the Request for Proposal (RFP) stage of procurement. The summary provides details of the transmission system, responsibilities of the Transmission Service Provider, and bidding process
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-VII, SECI has invited setting up of grid connected Solar PV Projects in Uttar Pradesh, on “Build Own Operate” basis for an aggregate capacity of 160 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Bid document for Solar Plant in JharkhandHeadway Solar
The document is a notice inviting bids from eligible participants for a project to design, manufacture, supply, install and maintain rooftop solar power plants with a total capacity of 180kWp at the Civil Court Building in Khunti, Jharkhand. Key details include:
1) The last date for bid submission is March 9, 2015.
2) Eligible bidders must be MNRE approved organizations and have experience installing at least 25% of the project capacity for general bidders or 10% for MSMEs in Jharkhand.
3) The project involves supply and installation of solar modules, electronics and batteries along with 5 years of maintenance.
4) Technical
The document announces a tender notice for the installation of a 60kW solar PV system without batteries at the Junior Naval Academy Ormara in Balochistan, Pakistan. It provides specifications for the solar panels, inverters, distribution boxes, cables, and other components. It also lists the component warranties. Interested bidders must submit sealed technical and commercial bids by July 20, 2018. The bids will be opened on the same day.
The largest tender by Solar Energy Corporation of India for Floating Solar for 150 MW is up for bidding.
The document is a summary of the tender document and covers the commercial & technical guidelines provided in the tender.
This document provides information about a Request for Selection (RfS) issued by Southern Power Distribution Company Limited of Andhra Pradesh (APSPDCL) and Eastern Power Distribution Company Limited of Andhra Pradesh (APEPDCL) for grid connected solar photovoltaic projects in Andhra Pradesh. It outlines the bidding process including key dates, eligibility criteria, technical requirements, and provides disclaimers. Bidders are required to submit bids online through the e-procurement platform by September 17, 2014 along with supporting documents and fees. The techno-commercial bids will be opened on September 18, 2014 and financial bids on September 25, 2014.
Request for selection document for grid connected solar photo voltaic project...Headway Solar
- The document is a Request for Selection (RfS) issued by Southern Power Distribution Company Limited of Andhra Pradesh (APSPDCL) for grid-connected solar photovoltaic projects in Andhra Pradesh.
- It provides information on the bidding process including bid submission deadlines, opening of pre-qualification, techno-commercial and financial bids, and addresses for communication.
- The RfS disclaims any responsibility for inaccuracies in the document and reserves the right to modify any information in the RfS without notice or assigning reason. Bidders are responsible for ensuring the document is complete for their purposes.
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIHarish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-IX, SECI wishes to invite proposals for setting up of grid connected Solar PV Projects in Puducherry, on “Build Own Operate” basis for an aggregate capacity of 35 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Last Date for the Closure of Procurement of Tender Documents is 14-Jun-2016 14:00:00 RTZ.
Gensol has summarised the tender issued by SECI for 2.5GW Wind Solar Hybrid ISTS projects.
The document covers major commercial & technical guidelines provided in the tender.
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...Harish Sharma
As part of JNNSM Phase-II Batch-III, Tranche-VIII, SECI is inviting proposals for setting up of grid connected Solar PV Projects in Himachal Pradesh, on “Build Own Operate” basis for an aggregate capacity of 50 MW. Projects selected based on this RfS shall be given “Viability Gap Funding” in line with terms and conditions of this RfS. SECI shall enter into Power Purchase Agreement (PPA) with the Bidders selected based on this RfS for purchase of solar power selected for a period of 25 years based on the terms, conditions and provisions of the RfS.
Last Date and Time of Closure of Procurement of Tender Documents is 17 June 2016
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Harish Sharma
The document is a Request for Proposal (RfP) issued by Uttarakhand Renewable Energy Development Agency (UREDA) to select developers through competitive bidding for setting up of grid connected solar PV power projects with an aggregate capacity of up to 170 MW. The RfP provides information to bidders regarding the qualification criteria, terms and conditions of tariff based competitive bidding process, timelines, and formats for bid submission to UREDA for procurement of power on long term basis by Uttarakhand Power Corporation Limited.
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...Harish Sharma
EnvironmentFirst Energy Services Private Limited is helping its clients to facilitate the bid invited by Punjab Energy Development Agency, the state nodal agency for promotion and development of New and Renewable Energy Projects in the State of Punjab. PEDA invites offers from the interested project developers to participate in the selection process for setting up of Biogas Power / Bio CNG from Biogas Project near Tajpur Dairy Complex, Ludhiana, on Build Operate & Own (BOO) basis
Gensol has presented quicks highlights of 1200MW Renewable Energy Tender with assured Peak Power Supply in terms of eligibility criteria, bidders obligations, project capacity (MW), generation criteria, various guarantees, project tariff rate (Rs/kWh) and many more. It's interesting to highlight that SECI has issued tender with no cap in tariff at the same assured peak power supply.
Summary of SECI Tranche III - 1200 MW Hybrid Wind SolarPratap Malempati
The document outlines the terms and conditions for setting up 1,200 MW of ISTS-connected wind-solar hybrid power projects in India. Key details include:
- Total capacity of 1,200 MW to be developed in multiple projects of minimum 50 MW each.
- Projects must maintain an annual capacity utilization factor between 80-120% of the declared CUF, which cannot be less than 30%. Compensation will be paid for shortfalls.
- Bidders must meet technical and financial eligibility criteria and obtain necessary clearances from central and state authorities.
- The responsibility of connectivity to the ISTS transmission system and arranging long-term access lies with the bidder. Metering will be done at
This document is a 58-page request for proposal from the Water Resources Department of the Government of Jharkhand to hire a consultant for the preparation of a preliminary project report and bid document for residual work of the Bhairwa reservoir scheme in Ramgarh District.
It includes instructions to consultants on eligibility criteria, submission requirements, evaluation procedures, and payment terms. Consultants must have experience preparing water resources project reports and a minimum annual turnover of 100 lakhs. Bids are due by April 18th and will be evaluated based on technical and financial criteria. The selected consultant must establish a local office in Ranchi and complete the work within 6 months.
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...Harish Sharma
This document is a Request for Selection (RfS) for setting up 1000 MW of grid connected solar photovoltaic power projects in Karnataka, India under Jawaharlal Nehru National Solar Mission Phase II Batch III Tranche V. The bidding process is divided into Part A (50 MW) with domestic content requirements and Part B (950 MW) without domestic content requirements. Successful bidders will be given viability gap funding by Solar Energy Corporation of India Limited (SECI) and will enter into a power purchase agreement with SECI to sell solar power for 25 years. The maximum tariff payable is Rs. 4.43/kWh and the upper limit of viability gap funding is Rs.
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Harish Sharma
MNRE launched a pilot scheme for promotion of large scale grid-connected roof top solar PV projects and SECI has been designated as implementing agency for this scheme. The generated solar power may be utilized for captive application and the surplus power may be fed to the grid. The scheme aims to reduce the fossil fuel based electricity and make buildings self-sustainable from the point of electricity, to the extent possible.
The bidding process under this rooftop scheme is for 250 MWp capacity under PART-A (CAPEX Only); 200 MWp capacity under PART-B (RESCO Only) and 50 MWp under Part C (CAPEX Only), in different States of India. Bidder shall submit bids for the minimum aggregate bid capacity of 500 kWp under PART- A, 5 MWp and under PART-B and 100 kWp under Part C.
BID DUE DATE
The Bidder should submit the Bids so as to reach the address indicated below by 1430 hrs (IST) on or before 03/06/2016.
The document outlines the request for proposal for setting up 150 MW of grid-connected solar PV projects coupled with fish farming in Bihar, India. Key details include:
- Projects must be between 2-10 MW in size and set up on land used for fish farming.
- Bidders must meet financial criteria like a minimum net worth and can be a single entity or consortium.
- The 25-year power purchase agreement will be with state distribution companies. Projects must be commissioned within 24 months of signing PPAs.
- A bidding process will be carried out to select developers who will then sign PPAs and meet milestones to commission projects on time.
150 MW Solar RfP by MPPMCL under reverse biddingHarish Sharma
We at EnvironmentFirst Energy Services (P) Limited are helping interested parties in total process of reverse bidding and EPC consulting. The pre bid meeting is proposed on 20th April 2015. Our Indore office is facilitating the bidding process. The brief can be checked at http://www.environmentfirst.in/mp-power-management-company-mppmcl-releases-rfp-for-150-mw-solar-power-plants-through-reverse-bidding-process/
Similar to Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connected Solar PV Plant by RRECL, Rajasthan (20)
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
MNRE Clarification on the eligibility of CFA for rooftop solar plants (with or without net metering/gross metering facility) and for declaring commissioned plant capacity w.r.t installed inverter capacity.
MNRE Guidelines for off-grid and grid connected Solar DC SystemHarish Sharma
Guidelines for off-grid and grid connected Solar DC System installed under programs of Ministry. These guidelines even are advised to be followed by systems which are not being implemented under any ministry scheme.
Future of solar Power Projects in IndiaHarish Sharma
As of 6th April 2017 the country's solar grid had a cumulative capacity of 12.28 gigawatts (GW) compared to 6.76 GW at the end of March 2016. To achieve the targets of year 2022 and 2030 the solar industry would have to grow by leaps and bounds.
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVHarish Sharma
This document is a Request for Selection (RfS) for setting up 250 MW of grid connected solar photovoltaic power projects in the Gujarat Solar Park at Charanka under Phase-II, Batch-IV, Tranche-I of India's National Solar Mission. It provides details about the bidding process for a total capacity of 250 MW divided into Part-A (25MW) and Part-B (225MW). For Part-A, conditions of domestic content requirement will apply. It outlines the scheme for viability gap funding, tariffs, power purchase agreements between SECI and developers, and commissioning timelines. The document aims to facilitate the development of solar projects in India through a transparent bidding process.
RfP for tariff based competitive bidding by KREDL for the installation of 240...Harish Sharma
GoK had intended to undertake development of 1200 MW (Twelve Hundred MWs) (AC) solar
PV ground mount power plants in Karnataka to be implemented in 60 Taluks. Tender was floated
for the same and 48 bids for 48 Taluks have been received. As no bids were received for 12
Taluks, it is intended to undertake development of 240 MW (Two Hundred and Forty MW) (AC)
solar PV ground mount power plants in Karnataka to be implemented in 12 Taluks (hereinafter
referred to individually as the “Project” implemented in one Taluk and collectively referred as the
“Projects” implemented in multiple Taluks). GoK, through KREDL, has decided to carry out the
bidding process for selection of the Bidders to whom the Project(s) may be awarded.
A Bidder may submit Bids for developing the Project(s) under solar PV technology (Solar PV
ground mount Project). It is pertinent to mention that a Bidder can propose any number of Projects,
but the minimum capacity of the individual Project proposed by the Bidder shall be at least 3 MW
(AC) per Taluk, and the maximum capacity of the individual Project proposed by the Bidder shall
be limited to 20 MW (AC) per Taluk. However, the maximum capacity to be allotted to any Bidder
including its Parent, Group Business Entity (ies) either bidding as Single Bidder or as a Consortium
shall not exceed the aggregate maximum capacity of 240 MW (AC).
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKAHarish Sharma
This document is a Request for Proposal (RFP) issued by Karnataka Renewable Energy Development Limited (KREDL) to undertake the development of 1,200 MW of solar power projects across 60 taluks in Karnataka. Bidders can submit bids for one or more projects between 3-20 MW in size and the maximum capacity that can be allotted to a bidder is 1,200 MW. Selected bidders will be responsible for designing, financing, constructing, operating and maintaining the projects as per the terms of the Power Purchase Agreement (PPA) that will be signed with the concerned electricity supply companies. The RFP provides details on the bidding process, timelines, evaluation criteria, terms and conditions
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
Himachal Pradesh State Electricity Board Limited to ensure the sustainable growth of Renewal Power is willing to procure solar power from such power producers who wish to install distributed grid connected Solar Projects in the State of Himachal Pradesh with capacities starting 50 kW up to
5 MW.
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the state of
Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd (PSPCL)
The document discusses Water Benefit Certificates (WBC), a results-based financing mechanism that issues certificates to water supply, purification, and conservation projects. Projects are awarded WBCs based on the volume of water benefits generated. Corporations and other entities can purchase WBCs to fund water projects and meet corporate social responsibility goals. The WBC standard requires projects to demonstrate additionality, measure outcomes, and track sustainable development impacts through external auditing and verification.
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
This document provides guidelines for the implementation of 2000 MW of grid-connected solar PV power projects under Phase II, Batch III of India's Jawaharlal Nehru National Solar Mission (JNNSM). The key points are:
1) SECI will be the implementing agency and will issue Requests for Selection to develop these projects through a competitive bidding process in various states.
2) Projects will be set up either in solar parks being developed by state agencies or on land arranged by developers, and must be a minimum of 10 MW in size.
3) Developers will be provided viability gap funding of up to Rs. 1 crore/MW based on the funding amount they bid for their project.
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...Harish Sharma
Solar Energy Corporation of India (SECI) invited RfS document for Selection of “500 MW Grid Connected Solar PV Power Projects in Maharashtra under JNNSM Phase-II Batch-III, Tranche-I”. EnvironmentFirst Energy Services (P) Ltd. is providing every critical knowledge to make the bidding success for the clients.
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
After inviting EOI from land owning farmers for the set up of solar power projects of the tune from 1MW to 2.5MW, PEDA has now formulated draft scheme for allocation of solar power projects in Punjab.
The document outlines IREDA-NCEF refinance scheme which aims to revive existing biomass and small hydro power projects affected by unforeseen circumstances by providing refinance at 2% interest rates from funds sourced from National Clean Energy Fund. Eligible operational grid connected projects commissioned between 2003-2013 can receive up to 30% refinance of outstanding loans up to Rs. 15 crores at 2% interest for up to 10 years. Scheduled commercial banks and financial institutions can avail this refinance after meeting eligibility criteria to on-lend to project developers.
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS Harish Sharma
IREDA Loan scheme is for all Solar rooftop power projects having minimum aggregate/Individual installed capacity 1000 kWp. Finance is available upto 75% of project cost with very Low interest rates range from 9.9% to 10.75%.
Bid Results for procurement of 215 MW Solar Power by UPNEDAHarish Sharma
As per provision in Solar Policy UPNEDA has declared the Bid Results for procurement of
power from Grid Connect Solar PV Power Projects through Tariff Based Competitive Bidding
Process for total 215 MW capacity on the basis of international competitive bidding in
accordance with the Bidding Guidelines.
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
All the consumers of the State Distribution licensee or PSPCL who intend to encourage solar energy and set up solar PV plants at available places on roof-tops of Individual households, industries, Government or Semi-Government or Local Body offices, commercial establishments, institutions, residential complexes shall be eligible with project capacity ranging from minimum 1 KWp upto 1MWp (AC side) with or without battery back-up support. Consumers may generate solar power for self consumption and may feed excess power into the grid to be adjusted.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART KALYAN CHART
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
L'indice de performance des ports à conteneurs de l'année 2023SPATPortToamasina
Une évaluation comparable de la performance basée sur le temps d'escale des navires
L'objectif de l'ICPP est d'identifier les domaines d'amélioration qui peuvent en fin de compte bénéficier à toutes les parties concernées, des compagnies maritimes aux gouvernements nationaux en passant par les consommateurs. Il est conçu pour servir de point de référence aux principaux acteurs de l'économie mondiale, notamment les autorités et les opérateurs portuaires, les gouvernements nationaux, les organisations supranationales, les agences de développement, les divers intérêts maritimes et d'autres acteurs publics et privés du commerce, de la logistique et des services de la chaîne d'approvisionnement.
Le développement de l'ICPP repose sur le temps total passé par les porte-conteneurs dans les ports, de la manière expliquée dans les sections suivantes du rapport, et comme dans les itérations précédentes de l'ICPP. Cette quatrième itération utilise des données pour l'année civile complète 2023. Elle poursuit le changement introduit l'année dernière en n'incluant que les ports qui ont eu un minimum de 24 escales valides au cours de la période de 12 mois de l'étude. Le nombre de ports inclus dans l'ICPP 2023 est de 405.
Comme dans les éditions précédentes de l'ICPP, la production du classement fait appel à deux approches méthodologiques différentes : une approche administrative, ou technique, une méthodologie pragmatique reflétant les connaissances et le jugement des experts ; et une approche statistique, utilisant l'analyse factorielle (AF), ou plus précisément la factorisation matricielle. L'utilisation de ces deux approches vise à garantir que le classement des performances des ports à conteneurs reflète le plus fidèlement possible les performances réelles des ports, tout en étant statistiquement robuste.
Tired of chasing down expiring contracts and drowning in paperwork? Mastering contract management can significantly enhance your business efficiency and productivity. This guide unveils expert secrets to streamline your contract management process. Learn how to save time, minimize risk, and achieve effortless contract management.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Niswey
50 million companies worldwide leverage WhatsApp as a key marketing channel. You may have considered adding it to your marketing mix, or probably already driving impressive conversions with WhatsApp.
But wait. What happens when you fully integrate your WhatsApp campaigns with HubSpot?
That's exactly what we explored in this session.
We take a look at everything that you need to know in order to deploy effective WhatsApp marketing strategies, and integrate it with your buyer journey in HubSpot. From technical requirements to innovative campaign strategies, to advanced campaign reporting - we discuss all that and more, to leverage WhatsApp for maximum impact. Check out more details about the event here https://events.hubspot.com/events/details/hubspot-new-delhi-presents-unlocking-whatsapp-marketing-with-hubspot-integrating-messaging-into-your-marketing-strategy/
63662490260Kalyan chart, satta matta matka 143, satta matka jodi fix , matka boss OTC 420, Indian Satta, India matka, matka ank, spbossmatka, online satta matka game play, live satta matka results, fix fix fix satta namber, free satta matka games, Kalyan matka jodi chart, Kalyan weekly final anl matka 420
Prescriptive analytics BA4206 Anna University PPTFreelance
Business analysis - Prescriptive analytics Introduction to Prescriptive analytics
Prescriptive Modeling
Non Linear Optimization
Demonstrating Business Performance Improvement
Enhancing Adoption of AI in Agri-food: IntroductionCor Verdouw
Introduction to the Panel on: Pathways and Challenges: AI-Driven Technology in Agri-Food, AI4Food, University of Guelph
“Enhancing Adoption of AI in Agri-food: a Path Forward”, 18 June 2024
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...BBPMedia1
Nathalie zal delen hoe DEI en ESG een fundamentele rol kunnen spelen in je merkstrategie en je de juiste aansluiting kan creëren met je doelgroep. Door middel van voorbeelden en simpele handvatten toont ze hoe dit in jouw organisatie toegepast kan worden.
SATTA MATKA DPBOSS KALYAN MATKA RESULTS KALYAN CHART KALYAN MATKA MATKA RESULT KALYAN MATKA TIPS SATTA MATKA MATKA COM MATKA PANA JODI TODAY BATTA SATKA MATKA PATTI JODI NUMBER MATKA RESULTS MATKA CHART MATKA JODI SATTA COM INDIA SATTA MATKA MATKA TIPS MATKA WAPKA ALL MATKA RESULT LIVE ONLINE MATKA RESULT KALYAN MATKA RESULT DPBOSS MATKA 143 MAIN MATKA KALYAN MATKA RESULTS KALYAN CHART INDIA MATKA KALYAN SATTA MATKA 420 INDIAN MATKA SATTA KING MATKA FIX JODI FIX FIX FIX SATTA NAMBAR MATKA INDIA SATTA BATTA
Cover Story - China's Investment Leader - Dr. Alyce SUmsthrill
In World Expo 2010 Shanghai – the most visited Expo in the World History
https://www.britannica.com/event/Expo-Shanghai-2010
China’s official organizer of the Expo, CCPIT (China Council for the Promotion of International Trade https://en.ccpit.org/) has chosen Dr. Alyce Su as the Cover Person with Cover Story, in the Expo’s official magazine distributed throughout the Expo, showcasing China’s New Generation of Leaders to the World.
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...Herman Kienhuis
Presentation by Herman Kienhuis (Curiosity VC) on developments in AI, the venture capital investment landscape and Curiosity VC's approach to investing, at the alumni event of Amsterdam Business School (University of Amsterdam) on June 13, 2024 in Amsterdam.
3. Canal top Rajasthan Page 2
Request for Proposal (RfP)
For
Installation of 2 MW Grid connected Solar PV
Plant at Menawali minor of NDR (I.G.N.P.) in
Hanumangarh area, Rajasthan by covering
Canal managed by IGN Board / Water
Resource Department,
to be connected at 11kV level to 33/11kV
Discom’s Substation in Rajasthan
(RfP/PV/RREC/Canal Top)
ISSUED BY
RAJASTHAN RENEWABLE ENERGY CORPORATION LIMITED
(A Government of Rajasthan Undertaking)
E-166, Yudhisthir Marg, C-Scheme, Jaipur
CIN No. U40101RJ1995SGC009847
Tel: 0141-2225859, 2229341, 2223966 & 2223965
Fax: 0141-2226028
Email: solar.rrec@gmail.com; Website: www.rrecl.com
Date of Issue of RfP: … 17.09.2015
Cost: Rs. 5000.00
4. Canal top Rajasthan Page 3
RAJASTHAN RENEWABLE ENERGY CORPORATION LIMITED
(A Government of Rajasthan Undertaking)
E-166, Yudhisthir Marg, C-Scheme, Jaipur
CIN No. U40101RJ1995SGC009847
Tel: 0141-2225859, 2229341, 2223966 & 2223965
Fax: 0141-2226028
Email: solar.rrec@gmail.com; Website: www.rrecl.com
Request for Proposal (RfP/PV/RREC/Canal top) invited by RREC on behalf of
Water Resource Department, GoR/ IGN Board and Discoms of Rajasthan for selection
of developers for setting up of 2MW Grid connected Solar PV Plant on canal top to
be connected on 11kV level at Discoms 33/11kV Substation in Rajasthan under
Rajasthan Solar Energy Policy, 2014 for sale of power to Rajasthan Discoms
through tariff based competitive bidding process.
1. Proposal is to be submitted online in electronic format on website
http://eproc.rajasthan.gov.in. The details are as under:
A RfP No. RFP/PV/RREC/Canal top
B Cost of RfP Rs. 5,000.00 (Five Thousand Only)
C Processing Fee of RISL Rs. 1,000.00 (One Thousand Only)
D Processing Fees of RREC Rs. 20,000.00 (Twenty Thousand)
Plus Service tax and cess /levy as applicable.
E Estimated Cost of Project Rs. 21.00 Crore
F Earnest Money Rs. 42 Lac
G Completion period The Project shall be commissioned within 15
months of the date of signing of PPA between
Project Developer and Procurer.
Time Schedule
S.No. Events Date & Time Location
i Date of issue/ downloading of
RfP
17.09.2015
(11.00AM)
to
19.10.2015
(11.00AM)
http://eproc.
rajasthan.gov.in ;
http://rrecl.com;
http://sppp.raj.nic.in
ii Last date & time of deposit (in
Physical Form) of Cost of RfP,
Processing Fee of RISL & RREC
and Earnest Money Deposit in
sealed Envelope.
Up to
19.10.2015
( 11.00AM)
RREC, E-166,
Yudhisthir Marg, C-
Scheme, Jaipur.
iii Last date & time of
submission of electronic bid
(Cover-1, 2 & 3)
Up to
19.10.2015
(02.00PM)
http://eproc.rajasthan.g
ov.in
iv Opening of sealed Envelope 20.10.2015
(11.00AM)
5. Canal top Rajasthan Page 4
v Opening of Non-financial Bid
(Cover -1 & 2)
20.10.2015
(03.00PM)
http://eproc.rajasthan.g
ov.in
vi Opening of Financial Bid
(Cover -3)
To be
conveyed
subsequentl
y
http://eproc.rajasthan.g
ov.in
2. The selection of Bidders shall be carried out through e-procurement process.
Proposal/Bids are to be submitted online in electronic format on website
http://eproc.rajasthan.gov.in as per RfP document.
3. Please visit regularly our website http://eproc.rajasthan.gov.in., www.rrecl.com
& www.sppp. raj. nic.in for latest up-date after issue of this RfP. All modification
/ amendment /clarification/ information etc. shall be available on the aforesaid
website(s) only.
4. Correspondence at:-
The Managing Director,
Rajasthan Renewable Energy Corporation Ltd.,
E-166, Yudhisthir Marg, C-Scheme,
Jaipur (Raj.), 302001.
Tel: 0141-2225859/ 2229 341/ 2223966/2223965,
Fax: 0141-2226028,
Email: rrec_jai@yahoo.co.in, solar.rrec@gmail.com
6. Canal top Rajasthan Page 5
Introduction
1. Rajasthan Solar Energy Policy, 2014 has been issued by Government of
Rajasthan vide Notification No. F. 20 (6) Energy /2010 dated 08.10.2014
for promoting the Solar energy in Rajasthan. RREC will select solar power
producers for setting up of 2MW Grid connected Solar Photo voltaic (PV)
Plant on canal tops. Selection of bidder shall be through tariff based
competitive bidding process.
2. Rajasthan Discoms hereinafter referred to as “Procurer”, will directly
purchase power generated from aforesaid 2MW Solar PV Plants.
3. RREC invites request for proposal from interested bidder or Bidding
Consortium and/ or any Consortium Member thereof (“Bidders”) on
behalf of Water Resourse Department/IGN Board and Discoms of
Rajasthan for selection of developer(s) for setting up of 2MW Grid
connected Solar Photo voltaic (PV) Plant on canal top for supply of
electricity for 25 years through tariff based competitive bidding process
as per the decision taken in the meeting held on 27.05.2015 under the
chairmanship of Principle Secretary, Energy, Government of Rajasthan.
The responsibility of the Successful Bidder(s) would be to supply power to
the Procurer as per the terms and conditions of the PPA. The PPA will be
signed between Procurer and Successful Bidder(s).
Back-ground
Water Resource Department has planned to install solar power projects of 2 MW
capacity by covering the canal managed by the IGN Board and Water Resource
Department. Planning Commission, GoI, has sanctioned 2 MW solar power plant
on Indira Gandhi Canal, for which central financial assistance of Rs. 7.80 Cr.
has already been approved. In the meeting held on dated 27.05.2015, it was
decided that RREC would carry out tariff based competitive bidding process for
the aforesaid 2 MW Project on behalf of Water Resourse Department/IGN Board
and Discoms. Bidder will be selected through tariff based competitive bidding
process.
Technology:
The Bidder is free to choose any Solar PV power generation technology viz
Crystalline Silicon Solar Cell Modules / Thin Film Modules / Concentrated PV
Modules/any Other Technology either indigenous or Imported. Under this RfP,
it is proposed to promote only established and operational technologies to
minimize the technology risk and to achieve the commissioning of the project in
state.
Tariff:
PPA will be signed between Discoms and Successful Bidder(s).The Discoms shall
pay to the Seller(s) the tariff discovered through the tariff based competitive
bidding process, as per the terms and conditions of the PPA enclosed at
Annexure-9. The tariff shall be payable by the Procurer in Indian Rupees, as per
provisions of the PPA.
7. Canal top Rajasthan Page 6
SECTION 1
INSTRUCTIONS TO BIDDERS
1. The bidders are requested to submit their bid prior to last date of submission to
avoid Non-submission of their bids up to prescribed date & time due to non-
availability/hanging of website, at either ends, at last moment or any reason
whatsoever. The last date of submission of bids will not be extended on such
account.
2. Though adequate care has been taken while preparing the RfP Documents, the
Bidder shall satisfy himself that the document is complete in all respect.
Intimation of any discrepancy shall be given to this office immediately. If no
intimation is received from any Bidder within ten days from the date of issue of
the bid documents, it shall be considered that the bid document is complete in
all respect and has been accepted by the Bidder.
3. The Rajasthan Renewable Energy Corporation Limited (RREC) may modify,
amend or supplement this RfP Document including PPA.
4. This Request for Proposal RfP/PV/RREC/Canal top document is not an
agreement or offer by the RREC to the prospective Bidders or any other party.
The purpose of this RfP is to provide interested parties with information to
assist the formulation of their Bid. This RfP is based on material and
information available in public domain.
5. While this RfP/PV/RREC/Canal top has been prepared in good faith, neither
the RREC nor their employees or advisors make any representation or
warranty, express or implied, or accept any responsibility or liability,
whatsoever, in respect of any statements or omissions herein, or the
accuracy, completeness or reliability of information, and shall incur no liability
under any law, statute, rules or regulations as to the accuracy, reliability or
completeness of this RfP, even if any loss or damage is caused by any act or
omission on their part.
6. The bidder will have to deposit/submit in sealed Envelope :
(i) the prescribed cost of RfP and the processing fees of RREC by way of
DD/Banker’s Cheque in favour of MD, RREC, payable at Jaipur; (ii) the EMD by
way of DD/Banker’s Cheque in favour of MD, RREC, payable at Jaipur OR in
form of BG, as per format 6.3A and (iii) the prescribed Processing Fee of RISL by
way of DD/Banker’s Cheque in favour of MD, RISL, payable at Jaipur.
Please note that in case DD/Pay Order (payable at Jaipur)/BG’s of requisite
amount towards cost of RfP, cost of processing fee of RISL, cost of
processing fee of RREC and Earnest Money is not found as per bid
document, then financial bid in electronic form (Cover-3) may not be
opened of that bidder.
7. Sealed Envelope containing cost of RfP , the processing fees of RREC, the EMD
and the prescribed Processing Fee of RISL will be opened, in the presence of
bidders who wish to be present.
8. Cutting/overwriting, if any in the figures of the tendered documents is
required to be clarified/indicated in words, duly signed, failing which the bid
may be rejected.
9. Deviation of any kind will not be accepted in the Non-financial & financial bid.
Such deviations shall be ignored. Conditional bids are liable to be rejected.
10. All the required information shall be furnished strictly in the prescribed Formats
only. Any information indicated other than the prescribed Formats shall not be
entertained. The bid shall be evaluated on the basis of information furnished in
the prescribed Formats only.
8. Canal top Rajasthan Page 7
11. RREC may advise any bidder to furnish the documents in original or copy
thereof duly attested by Notary for verification, in physical form on short notice
of three days.
12. The bidders should provide complete information at the time of submission of
bid. If the bidders are asked to furnish some more clarification/
confirmation/document, they shall be required to furnish the same within
specified time, failing which the case shall be finalized /decided on the basis
of available information/documents. The responsibility of ignorance of their bid
on account of delay in furnishing of desired information/documents up to the
specified time shall be of the bidder. However, if there are any shortcomings in
the submission of the information which does not materially affect the
qualification criterion, then the Bid Evaluation Committee shall have the
power to consider the facts on the merit of the case and decide the bid
evaluation accordingly.
13. The RfP can be downloaded from web site http://eproc. rajasthan. gov. in. This
Notification is also available at website http://www.rrecl.com &
www.sppp.raj.nic.in.
14. All tender documents should essentially be signed digitally and
submitted/uploaded on http://eproc.rajasthan.gov.in, in time in
accordance with note 17 below.
15. Bidders who wish to participate in this RfP, will have to register on
http://eproc.rajasthan.gov.in (bidders registered earlier on the
www.eproc.rajasthan.gov.in, need not to get registered again). To participate in
online tenders, Bidders will have to procure Digital Signature Certificate (Class
II & Class III) as per requirement under Information Technology Act-2000 using
which they can sign their electronic bids. Bidders can procure the same from
any CCA approved certifying agency or they may contact e-Procurement Cell,
Department of IT & C, Government of Rajasthan on the following
address:-
e-Procurement Cell, RISL, Yojana Bhawan, Tilak Marg, C-Scheme, Jaipur, e-
mail: eproc@rajasthan.gov.in
16. Bidders are also advised to refer “Bidders Manual” available under
“Downloads” section on http://eproc.rajasthan.gov.in for further details about
the e-tendering process.
17. Proposals are to be submitted online in electronic format on website
www.eproc.rajasthan.gov.in as detailed hereunder.
(A) List of required Formats/documents to be submitted online duly signed
digitally by Authorized Signatory:
1) Cover-1:- Up load the scanned copy of DD/Pay Order towards Cost of RfP
document, processing fee of RREC & RISL and scanned copy of DD/Pay
Order OR of Bank Guarantee (in pdf) towards EMD.
2) Cover- 2: - All Non-financial Formats as per Section 6 with digitally signed
Downloaded bid document with all other required documents.
Bidders are advised to download the bid document first and uploaded back with
Scanned copies of all required formats as described in section 6 duly signed by
the authorized person.
3) Cover-3: - Financial bid as per Format 6.12.
NOTE: The financial bid is to be submitted as per format 6.12. This excel (.xls)
file which contains BoQ is to be downloaded from www.eproc.rajasthan.gov.in
9. Canal top Rajasthan Page 8
for this RfP.) and same has to be uploaded on the website of
http://eproc.rajasthan.gov.in for this RfP.
Bid may be rejected if look alike format (.xls) is created/filled and
uploaded on http://eproc.rajasthan.gov.in.
18. Correspondence for enquiries and clarifications:
All correspondence in respect of the RfP and submission of the Bid shall be
addressed to:
The Managing Director,
Rajasthan Renewable Energy Corporation Ltd,.
E-166, Yudhisthir Marg, C-Scheme, Jaipur (Raj.), 302001
Tel: 0141-2225859/ 2229 341/ 2223966/2223965
Fax: 0141-2226028, Email: rrec_jai@yahoo.co.in, solar.rrec@gmail.com
Contact Person:
Mr. R.K.Bhandari
Director (Technical), RREC, Jaipur
E-166, Yudhisthir Marg, C-Scheme, Jaipur (Raj.), 302001
Tel: 0141-2225859/ 2229 341/ 2223966/2223965
Fax: 0141-2226028, Email: rrec_jai@yahoo.co.in, solar.rrec@gmail.com
10. Canal top Rajasthan Page 9
SECTION 2
DEFINITIONS
“Affiliate” shall mean a Company that, directly or indirectly,
i) controls, or
ii) is controlled by, or
iii) is under common control with, a Company developing a Project or a
Member in a Consortium developing the Project and control means
ownership by one Company of at least 26% (twenty six percent) of the
voting rights of the other Company.
“Appropriate Commission” shall mean the CERC or the RERC or the Joint
Commission referred to in Section 83 of the Electricity Act 2003, as the case
may be.
“Bid” Bid shall mean the Non-financial Bid and Financial Bid submitted by the
Bidder, in response to this RfP, in accordance with the terms and conditions
hereof.
“Bidder” shall mean an Individual/Registered Partnership firm/Company or a
Bidding Consortium submitting the Bid. Any reference to the Bidder includes
Bidding Individual/Registered Partnership firm/Company /Bidding
Consortium/ Consortium, Member of a Bidding Consortium including its
successors, executors and permitted assigns and Lead Member of the Bidding
Consortium jointly and severally, as the context may require”.
“Bidding Company” shall refer to such single company that has submitted the
response in accordance with the provisions of this RfP.
“Bidding Consortium” or “Consortium” shall refer to a group of companies that
has collectively submitted the response in accordance with the provisions of this
RfP.
“Chartered Accountant” shall mean a person practicing in India or a firm
whereof all the partners practicing in India as a Chartered Accountant(s) within
the meaning of the Chartered Accountants Act, 1949.
“Company” shall mean a company formed and registered under The Companies
Act, 1956.
“Conflict of Interest” A Bidder may be considered to be in a Conflict of Interest
with one or more Bidders in the same bidding process under this RfP if they
have a relationship with each other, directly or indirectly through a common
company, that puts them in a position to have access to information about or
influence the Bid of another Bidder.
“Consents, Clearances and Permits” shall mean all authorizations, licenses,
approvals, registrations, permits, waivers, privileges, acknowledgements,
agreements, or concessions required to be obtained from or provided by any
concerned authority for the purpose of setting up of the generation facilities.
“Contracted Capacity” shall mean the power (AC) in MW contracted between
the Seller and the Procurer at Solar Power generating end switchyard bus
bar (outgoing feeder).
“Effective Date” shall mean the date of signing of PPA by both the parties.;
11. Canal top Rajasthan Page 10
“Electricity Act 2003” shall mean the Electricity Act, 2003 and any rules,
amendments, regulation, notifications, guidelines or policies issued there under
from time to time.
“Financial Closure or Financial Close” shall mean the execution of all the
Financing Agreements required for the Project and fulfilment of conditions
precedents and waiver, if any, of the conditions precedent for the initial draw
down of funds for the Project. The same is also applicable for Project being
developed based on Balance Sheet financing.
"Financially Evaluated Company" shall mean the company which has been
evaluated for the satisfaction of the financial requirement set forth herein in the
RfP.
"Force Majeure conditions" means any event or circumstance which is beyond
the reasonable direct or indirect control and without the fault or negligence of
the Solar Power Producer or Discom(s) and which results in Solar Power
Producers or Discom(s) inability, notwithstanding its reasonable best efforts, to
perform its obligations in whole or in part and may include rebellion, mutiny,
civil unrest, riot, strike, fire, explosion, flood, cyclone, lightening, earthquake,
act of foreign enemy, war or other forces, theft, burglary, ionizing radiation or
contamination, Government action, inaction or restrictions, accidents or an act
of God or other similar causes.
“Grid Code” / “IEGC” or “State Grid Code” shall mean the Grid Code specified
by the Central Commission under clause (h) of sub-section (1) of Section 79
of the Electricity Act and/or the State Grid Code as specified by the concerned
State Commission referred under clause (h) of sub-section (1)of Section 86 of
the Electricity Act, as applicable.
“Law” shall have the same meaning as ascribed thereto in the PPA.
“Lead Member of the Bidding Consortium” or “Lead Member”: There shall be
only one Lead Member company, having the shareholding of more than 50% in
the Bidding Consortium and cannot be changed till 1 year of the Commercial
Operation Date (COD) of the Project.
“Letter of Intent” or “LOI” shall mean the letter to be issued by Procurer to the
Successful Bidder(s) for Setting up of Solar power plant to supply of solar power
to procurer.
“Limited Liability Partnership” or “LLP” shall mean a partnership formed
and registered under the Limited Liability Partnership Act 2008.
“Member in a Bidding Consortium” or “Member” shall mean each Company
in a Bidding Consortium. In case of a Technology Partner being a member in the
Consortium, it has to be a Company.
“Parent Company” shall mean a company that holds at least twenty six
percent (26%) of the paid - up equity share capital directly or indirectly in the
Bidding Company or in the Member of a Bidding Consortium, as the case may
be.
“PPA” shall mean the agreement to be entered into between the Procurer and the
Seller pursuant to which the Seller shall supply power to the Procurer as per the
terms and conditions specified therein and a draft of which is attached as
Annexure-9 to this RfP, including all its schedules, annexure, and all amendments
12. Canal top Rajasthan Page 11
or modifications.
“Procurer” shall mean Discoms who will directly purchase generated power
from the above 2 MW Solar PV projects.
“Project” shall mean solar PV project with single point of injection in to the
Discom(s) grid substation at 11kV or above voltage level.
"Project Company” shall mean the Company incorporated by the Bidder as per
Indian Laws in accordance with Clause 3.6.
“RERC” shall mean the Rajasthan Electricity Regulatory Commission
constituted under sub – section (1) of Section-82 of the Electricity Act, 2003 or
its successors.
"RERC Approved Tariff" shall mean the tariff notified by RERC for Solar
Projects.
“RfP” shall mean this Request for Proposal along with all formats and RfP
Project Documents attached hereto and shall include any modifications,
amendments alterations or clarifications thereto.
“RfP Project Documents” shall mean the following documents to be entered
into by the parties to the respective agreements in connection with the supply of
power.
a) PPA to be signed between the successful bidder and Discoms of Rajasthan.
b) MOU to be signed between the successful bidder and Water Resource
Department/IGN Board.
c) any other agreements designated as such, from time to time by the
Procurer/RREC.
“Registered Partnership Firm/Partnership firm” shall mean a Partnership
firm registered with the Income Tax department as well as Registrar of Firms and
having a PAN”.
“Scheduled Commercial Operation Date” or "Scheduled COD" for 2MW allocated
capacity Solar Power Project shall be 15 (Fifteen) months from the date of
signing of PPA.
“Selected Bidder(s) or Successful Bidder(s)”shall mean the Bidder(s) selected
by the Procurer, pursuant to this RfP to set up the project and supply of power
as per the terms of the RfP Project Documents, and to whom a Letter of Intent
has been issued.
“Seller” shall mean the Successful Bidder who submit the Contract
Performance Guarantee and executes the PPA and other Project related
Documents specified in RfP with the Procurer and who shall be responsible for
supplying power to the Procurer at the outgoing point of Solar Power Plant.
“Solar PV Project” or “Project” or “SPV” shall mean the Solar Photo Voltaic
power project that uses sunlight for direct conversion into electricity through
Photo Voltaic technology.
“Statutory Auditor” shall mean the auditor of a Company appointed under the
provisions of the Companies Act, 1956 or under the provisions of any other
applicable governing law.
“STU” or “State Transmission Utility” shall mean the board or the
government company specified as such by the State Government under sub-
13. Canal top Rajasthan Page 12
section (1) of Section 39 of the Act.
“Technology Partner” shall mean an entity from which the Bidder proposes to
take technology support. However if Technology Partner has an equity
participation in Bidding Consortium than it has to be a Company with equity
participation less than 10%.
"Ultimate Parent Company" shall mean a Company which directly or indirectly
owns at least twenty six percent (26%) paid up equity capital in the Bidding
company or member company of a consortium, (as the case may be)
and/or in the financially evaluated Company and such bidding company or
member company of a consortium (as the case may be) and / or the financially
evaluated company shall be under the direct control or indirectly under the
control of such company.
14. Canal top Rajasthan Page 13
SECTION-3
GENERAL TERMS AND CONDITIONS
3.1 The proposed location for Solar Power Project on the canal is as per the
details as under:-
PROPOSED INSTALLATION OF 2 MW CANAL TOP SOLAR PROJECT
S.
No.
Name of the Canal & Location Between RD‘s
Capacity
to be installed
(MW)
1 Menawali minor off taking from RD 62
(Left) of Naurang Desar Disty (I.G.N.P.)
in Hanumangarh area, Rajasthan
0.000 to
38.250
2MW
The bidders are required to visit the project site mentioned in the RfP to
ascertain at their own the space available for solar installations, canal features,
canal banks as well as existing plantation along with banks of the canal and
space availability for installation of canal based Solar Power Project and its
associated works.
3.2 Water Resource Department/IGN Board has given in-principle approval for
installation of Solar Power Project on the canal. All the conditions /
stipulations made by WRD/IGN Board are binding on all the developers.
3.3 The Companies/Developers shall have no right to claim any compensation from
RREC/WRD/IGN Board/Discoms or from any other developer for utilization of
solar potential upstream or downstream of the site allotted to them. WRD /IGN
Board/ RREC/Discoms will be in no way responsible for increased or decreased
generation from the Solar Power Projects installed on the canal top.
3.4 The supplies in the canal shall be run and regulated as per demand/supply of
canal water and strictly as mandated in the Northern India Canal & Drainage Act
1873 (as amended from time to time) which would applicable in this case also.
The Company/Promoter shall satisfy themselves with hydrological data and
pattern of discharges, which vary according to Irrigation requirement in canal
and distributaries. Considering these parameters, Company/Promoter may
structure Solar Power Plant at their own risk. RREC/WRD/IGN Board/Discoms
shall in no way be responsible for decreased/increased generation accruing as a
result of variations in solar radiation / canal flow.
3.5 The Detailed Project Report (DPR) is required to be submitted by the Developer
within two months from Letter of Award.
3.6 Superintending Engineer, Suratgarh Water Resource Circle, Hanumangarh will
be the Nodal officer of WRD/IGN Board who will coordinate with the successful
bidder regarding site visit, providing lay out plan and space availability for
installation of canal based Solar Power Project.
3.7 The Solar power project is to be installed on the canal top as per the proposed
site location. Water Resource Department/IGN Board will allow canal top/ land
to Solar Power producers for development of Solar Power Projects on Build,
Operate and Own basis for 25 years on right to use basis. Ownership of such
canal top/land will remain with Water Resource Department/IGN Board. In case
any extra land along the canal banks is required for installation of equipments or
any other associated works related to Solar Power Plant, the same will be
provided by Water Resource Department/IGN Board to the developer free of cost
on right to use basis for 25 years. MOU for the same will be signed between the
15. Canal top Rajasthan Page 14
successful bidder and Water Resource Department/IGN Board. Draft MoU is
enclosed at Annexure-8.
3.8 Works regarding setting up of solar power plant will be monitored/supervised by
Water Resource Department/IGN Board/RREC.
3.9 General Layout Plan of the Solar Power Project, its required structure to be
implemented /erected / embedded in the canal along with complete design on
which solar panels are to be erected, and Canal Protection Works as per the site
requirement keeping in view the safety of the canal will be approved by Water
Resource Department and shall be binding on the Developers.
3.10 The aforesaid project will be carried out under new Rajasthan Solar Energy
Policy, 2014. Therefore, developer shall comply with all the provisions of the
Policy, 2014.
3.11 All permits and clearances required for setting up of the Project including those
required from State Government and local bodies shall be in the scope of the
developer. However, RREC and Water Resource Department/IGN Board will
facilitate in getting the necessary permits and clearances.
3.12 Developers are free to give their independent own design for solar power
installation on the canal tops/banks. All type of proposed design is required to
be got approved from Water Resource Department/IGN Board, before actual
installations. Bidders are advised to quote their bids keeping in view all these
aspects and are bound to implement the project as per the design approved by
WRD/IGN Board in view of the safety of the canal.
3.13 The selected bidder will sign Power Purchase Agreement (PPA) with Discoms.
Draft of PPA is enclosed at Annexure-9.
3.14 The following terms & conditions of WRD/IGN Board are binding on the Solar
Power Developer and are required to take note of the same before quoting their
bids:-
1) There will be no obstruction i n the flow of water in the canal and
designed FSL will not be disturbed.
2) If any canal protection work is needed for the safety of the canal on
account of setting up of Solar Power Project, the same will be executed
by the selected bidder at his own cost.
3) Due to setting up of solar system, there should be no obstruction
to the maintenance/ strengthening work of canal banks and if any
additional expenditures have to be incurred due to this, the same will be
borne by the developer of the Solar Power Project.
4) If there is a forest strip along the canal where Forest Act is applicable
then, all necessary approvals will be obtained from the Forest
Department by the Solar Power Developer, if necessary.
5) The maintenance works of solar system to be executed time to time will
not be dependent on the canal closure.
6) The site where solar system is proposed to be set up, there should be no
obstruction to the maintenance works and public utilization for traffic on
the banks and roads along the canal.
7) The proposed solar system will be installed at a minimum distance from
the permanent structures as specified by WRD/IGN Board for
maintenance and safety of these structures. The minimum distance will
be fixed depending upon different structures like head works, cross
drainage works and bridge etc.
8) The detailed layout plan and other drawings of these solar systems will
be got vetted by the Solar Developer from the Water Resource
Department /IGN Board before the start of the work.
9) While installing the solar system, the height of solar panels and allied
16. Canal top Rajasthan Page 15
structures should be kept sufficient so that no obstruction is faced
during cleaning & maintenance of the canal.
10) After the installation of solar system and during its operation &
maintenance, if some work is required for the safety of the canal due to
solar system or during the remodeling of the canal, the Developer will be
responsible to bear the whole expenditures on these works.
11) If some building or structure is required in view of the Solar Power
Project, the solar developer will do it at his own cost.
12) The Developer will obtain NOC from any other related department at its
own level and cost.
13) The Developer will be fully responsible for any mishap due to this project
during the construction and afterwards.
14) If there is any obstruction in the working of solar system during the
execution of work by Water Resource Department/ IGN Board keeping in
view the requirement, in that case no compensation will be payable by
Water Resource Department/ IGN Board to the Developer.
15) For safety from floating objects, trash etc. in the canal, the bottom of
the solar panels/its allied structure at the project site, where solar
power project is to be implemented, should be at sufficient height from
the FSL, otherwise it is mandatory to install and maintain the trash
racks so that no obstruction is caused to the flow of water by any
floating object/trash etc. and the whole expenditure on this account will
be borne by the Developer.
3.15 Obtaining RfP Document & Processing Fees:
a) The RfP can be downloaded from website http:www.eproc.rajasthan.gov.in.
This Notification is also available at website http:www.rrecl.com &
www.sppp.raj.nic.in.
b) A bidder/bidding Consortium will be eligible to participate in the bidding
process only on submission of RfP along with the cost of RfP, processing fees
of RREC & RISL and EMD in the form of BG/DD/BC.
3.16 Method of Submission
The response to RfP/PV/RREC/Canal top is to be submitted electronically and
also in physical form in a sealed envelope in the following manner:-
(A) In Physical Form:
Sealed Envelope – Super scribed as:
Envelope of Costs against RfP/PV/RREC/Canal top at the top of the Envelope;
and Name & Address of the Bidder on the left hand side bottom;
This Envelope shall contain
i) Bid cost DD/Pay Order for Rs 5000/- (Rupee five thousand only) in
favour of MD, RREC, Payable at Jaipur.
ii) DD/Pay order of @ Rs. 20,000/- (plus Service Tax and cess/levy as
applicable) towards Processing Fee of RREC in favour of MD, RREC,
Payable at Jaipur.
iii) DD/Pay Order of Rs. 1000/- towards Processing fee of RISL in favour of
MD, RISL, Payable at Jaipur and
iv) DD/Pay order in favour of MD, RREC, Payable at Jaipur towards EMD
of Rs. 42 Lac. / if in the form of BG, then as per format 6.3A
This Envelope should be addressed to:
The Managing Director
Rajasthan Renewable Energy Corporation Ltd.
17. Canal top Rajasthan Page 16
E-166, Yudhisthir Marg, C-Scheme, Jaipur (Raj.)-302001
Tel: 0141-2225859/ 2229 341/ 2223966/2223965.
(B) In Electronic Form:
Cover-1: It shall contain scanned copy(ies) of (i) Bid cost DD/Pay order for Rs
5000/- ; (ii) DD/Pay order towards Processing Fee of RREC; of Rs 20,000/-
(plus service tax and cess/levy as applicable) (iii) DD/Pay Order for
Processing fee of Rs. 1000/- of RISL and (iv) DD/Pay order/Bank Guarantee
towards EMD of Rs. 42 Lac ( as per Format 6.3A)( in pdf).
Cover-2: It shall contain scanned copy(ies) of covering letter & all
other technical documents and Formats as specified in Section 6.0 of this RfP
document as under (except Format 6.3A, 6.3B, 6.3 C, 6.12). In addition to
above, check lists as per Annexure-3 & 4 shall also be submitted in this cover.
All should be submitted digitally signed.
(i) Covering Letter as per Format 6.1;
(ii) In case of a Bidding Consortium, a Power of Attorney in favour of the Lead
Member issued by the other Members of the Consortium shall be provided as
per format attached hereto as Format 6.2.
In the event any Member of the Bidding Consortium (other than Lead Member)
is a foreign entity, it may submit Board Resolutions in place of Power of Attorney
for the purpose of fulfilling the requirements under this Clause. Provided that
such Board Resolutions shall be supported by an unqualified opinion issued
by the legal counsel of such foreign entity stating that the Board
Resolutions are in compliance with the applicable laws of the countries’
respective jurisdictions of the issuing Company and the authorizations granted
therein are true and valid.
(iii) Board Resolutions, as per prescribed formats enclosed as Format 6.4 duly
certified by the Company Secretary or the Director of the relevant Bidder
Company, as applicable to the Bidder Company and mentioned hereunder:
(a) Board resolution from the Bidding Company or the Lead Member of the
Consortium, as the case may be, in favour of the person signing the
response to RfP,
(b) Board Resolution from the Bidding Company committing one hundred
percent (100%) of the equity requirement for the Project / Board
Resolutions from each of the Consortium Members together in
aggregate committingto one hundred percent (100%) of equity requirement
for the Project (in case of Bidding Consortium); and
(c) Board Resolutions from Parent and /or Affiliate (whose credentials were
used in the response to RfP), of the Bidding Company / any Member
Company of the Bidding Consortium, undertaking to invest the entire
amount as committed by Bidding Company / Member Company of the
Bidding Consortium, in event of failure of the same to make such
investment.
(iv) In case of a Consortium, the Consortium Agreement between the Members in
the Consortium as per Format 6.5 along with Board resolution from each
Member of the Consortium for participating in consortium;
(v) Financial Requirements as per Format 6.6 as applicable;
(vi) Technical Criteria wherein Bidder shall certify that the technology to be adopted
18. Canal top Rajasthan Page 17
shall be commercially established technology and is under operation. Final
details of same shall be submitted within Six months of signing of PPA as per
Format 6.7;
(vii) Connectivity of Project with Discom(s) Substation as per Format 6.8;
(viii) A disclosure statement as per Format 6.9 regarding participation of any related
companies in this bidding process;
(ix) Declaration by the Bidder regarding qualification as per Format 6.10.
(x) Declaration by the Bidder /Lead Member of Bidding Consortium for the
Proposed Technology as per Format 6.11.
(xi) Memorandum & Article of Association, Certificate of Incorporation (if applicable)
of Bidding Company/all member companies of Bidding Consortium.
(xii) Certified copies of Income Tax returns
(xiii). In case the bidder is a Partnership firm, a certified/notarized copy of the
Partnership deed.
(xiv) Check lists as per Annexure-3 and 4.
Note: Wherever information has been sought in specified formats, the Bidders shall fill
in the details as per the prescribed formats and shall refrain from referring to
any other document for providing any information required in the prescribed
format.
Cover-3: It shall contain Financial Bid in the specified template (Format-6.12)
3.17 The Bidder should note that:
a. The bidders may be shortlisted based on the declaration made by them in
the relevant schedules of RfP. The documents submitted along with RfP may
be verified before signing of PPA in terms of clause 3.28.
b. If the Bidder/Member in a Bidding Consortium conceals any material
information or makes a wrong statement or misrepresents facts or
makes a misleading statement in its response to RfP, in any manner
whatsoever, the RREC reserves the right to reject such response to RfP
and/or cancel the Letter of Intent, if issued and the EMD provided up to
that stage shall be forfeited.
c. If the event specified at (b) is discovered after the Effective Date,
consequences specified in PPA shall apply.
d. Response to RfP submitted by the Bidder shall become the property of the
RREC and the RREC shall have no obligation to return the same to the
Bidder.
e. All pages of the response to RfP submitted must be digitally signed by the
person authorized by the board as per Format 6.4, on behalf of the Bidder.
f. The response to RfP shall be submitted as mentioned in clause 3.16. No
change or supplementary information to a response to RfP will be
accepted after the scheduled date and time of submission of response to RfP.
RREC reserves the right to seek additional information from the Bidders, if
found necessary, during the course of evaluation of the response to RfP.
g. All the information should be submitted in English language only.
h. Bidders shall mention the name of the contact person and complete address
19. Canal top Rajasthan Page 18
of the Bidder in the covering letter.
i. Response to RfP that are incomplete, which do not substantially meet the
requirements prescribed in this RfP, will be liable for rejection by RREC.
j. Bidders delaying in submission of additional information or clarifications
sought by RREC will be liable for rejection.
k. Response to RfP not submitted in the specified formats will be liable for
rejection by RREC.
l. Non submission and/ or submission of incomplete data / information
required under the provisions of RfP shall not be construed as waiver on the
part of RREC of the obligation of the Bidder to furnish the said
data/information unless the waiver is in writing.
m. Only Jaipur Courts shall have exclusive jurisdiction in all matters pertaining
to RfP & PPA etc.
3.18 Due Date:
The Bidders should submit the response to RfP/PV/RREC/Canal top strictly as
per the manner and timelines specified in Heading of TIME SCHEDULE.
3.19 Validity of the Response to RfP:
i) The Bidder shall submit the response to RfP which shall remain valid up to
the six months from the date of opening of Bids ("Bid Validity"). RREC
reserves the right to reject any response to RfP which does not meet the
aforesaid validity requirement.
ii) RREC may ask to bidder to extend the validity of bid beyond six months
prior to the expiry of the period of validity of bids along with validity of BG of
EMD ( If any) accordingly. A bidder may however refuse the request and
such refusal shall be treated as withdrawal of bid but in such circumstances
EMD shall not be forfeited.
3.20 Preparation cost:
The Bidder shall be responsible for all the costs associated with the
preparation of the response to RfP and participation in discussions and
attending meeting(s) etc. RREC shall not be responsible in any way for such
costs, regardless of the conduct of outcome of the bid process.
3.21 Right to reject a Bid:
RREC reserves the right to reject all or any of the response to RfP or cancel the
RfP without assigning any reasons whatsoever and without any liability at any
stage.
3.22 Bank Guarantees:
The Bidder may provide the following Bank Guarantees from any of the Banks
listed at Annexure 2 to RREC in a phased manner as detailed hereunder.
Towards Earnest Money Deposit (EMD) of Rs. 42 Lac in the form of Bank
Guarantee as per Format - 6.3 A. (valid for a period of seven (7) months from
last date of submission of the response to RfP).
Towards Security Deposit as per clause 3.26 in form of Bank Guarantee as
per Format - 6.3 B. (valid for a period up to Three (3) months beyond the date
of commissioning of project.)
20. Canal top Rajasthan Page 19
Performance Bank Guarantee as per clause 3.24: The Performance Bank
Guarantee (PBG) shall be submitted by the selected bidder as per terms of
clause 3.24 as per Format – 6.3 C.
The Bank Guarantee issued by foreign Banks is to be endorsed by the Indian
Branch of the same bank or State Bank of India. Bank Guarantees are to be
issued by Banks from bank list given in Annexure-2.
The Bank Guarantees have to be executed on non-judicial stamp paper of
appropriate value as per Stamp Act relevant to place of execution. The Bank
Guarantees have to be in the name of the Bidder /Lead Member Company of
Bidding Consortium.
In order to facilitate the bidders to submit the Bank Guarantee as per the
prescribed format and in line with the requirements, checklist at Annexure- 3
has been attached. Bidders are advised to take note of the above checklist while
submitting the Bank Guarantees.
3.22.1 Number of Response to RfP by a company
Company, including its Parent, Affiliate or Ultimate Parent or any Group Company shall
submit one single application in the prescribed format. Statement for the same is to be
submitted as per Format for Disclosure (Format-6.9).
3.23 Qualification Requirements:
The Bidder can be an individual/partnership firm, Company (Bidding Company)
or a Consortium of Companies (Bidding Consortium) with one of the Companies
acting as the Lead Member of the Bidding Consortium. Short listing of Bidder
will be based on meeting the Qualification Requirements specified below:-
Note: - Who are Eligible for Participation:
i) Individuals
ii) Partnership Firms registered with the Income Tax Department as well as
Registrar of Firms having its PAN.
iii) Companies incorporated under the Companies Act, 1956 are eligible on
standalone basis or as a part of the bidding consortium.
iv) A foreign company can also participate on standalone basis or as a member
of consortium at RfP stage. But before signing of PPA it has to form an
Indian Company registered under the Companies Act,1956 and comply
with necessary formalities of RBI/FEMA as and when required as per those
regulations;
v) Successful Companies can also execute the project through a Special
Purpose Vehicle (SPV). However the SPV has to be formed before signing of
PPA.
A. Financial Criteria:
i) The “Net Worth” of the Bidder should be equal to or greater than Rs 2 crore or
equivalent US$.
However, in case the application is made by two Companies of the same Parent
and using the Net worth of that Parent, the Net Worth required shall be
calculated separately for each Company but not exceeding the percentage equity
shareholding of the Parent in such company. To this extent the Net worth of the
Parent shall be reduced if in case even the Parent is also bidding Company or
any of its affiliate is also a bidding company.
Note: For the Qualification Requirements, if data is provided by the Bidder in
21. Canal top Rajasthan Page 20
foreign currency, equivalent rupees of Net Worth will be calculated using bills
selling exchange rates (card rate) USD/INR of any scheduled Bank as per
Annexure-2 prevailing on the date of closing of the accounts for the respective
financial year as certified by the Bidder’s banker.
For currency other than USD, Bidder shall convert such currency into USD as
per the exchange rates certified by their banker prevailing on the relevant
date and used for such conversion.}
(If the exchange rate for any of the above dates is not available, the rate for the
immediately available previous day shall be taken into account.}
Net Worth calculation for a bidding individual/partnership firms
= Proprietors/Partner’s Capital reflecting in the Audited Balance Sheet
Add: Free Reserves (Including the Credit balance of Reserve and
Surplus appearing in the Balance Sheet)
Subtract: Intangible Assets
Subtract: Miscellaneous Expenditures to the extent not written off and
carry forward losses.
Net Worth calculation for a Bidding Company
= Paid up Share capital which includes
1. Paid up Equity share capital and
2. Fully, compulsorily and mandatorily convertible Preference Shares and
3. Fully, compulsorily and mandatorily convertible Debentures)
Add: Free Reserves
(Including share premium provided it is realized in Cash or Cash
equivalents.)
Subtract: Revaluation Reserves
Subtract: Intangible Assets
Subtract: Miscellaneous Expenditures to the extent not written off and
carry forward losses.
ii) For the purposes of meeting financial requirements, only
unconsolidated audited annual accounts shall be used. However, audited
consolidated annual accounts of the Bidder may be used for the purpose of
financial requirements provided the Bidder is a company and has at least
twenty six percent (26%) equity in each Company whose accounts are merged in
the audited consolidated account and provided further that the financial
capability of such companies (of which accounts are being merged in the
consolidated accounts) shall not be reconsidered again for Net worth.
iii) Existing Entities - The computation of Net Worth shall be based on
unconsolidated audited/unaudited annual accounts of the Bidder. For the
purpose of the computation of Net Worth, the best year in the last four years
including current running year shall be considered. The Bidder would thus be
required to submit annual audited accounts for the last three financial years
2012-13; 2013-14 and 2014-15(or calendar year, 2012, 2013 and 2014 or the
accounting years as adopted by the bidder and acceptable as per the laws of the
respective Country) and part of the current running year (unaudited), along with
a certificate from the Chartered Accountant to demonstrate the fulfillment of the
criteria and CA certified copies of Income Tax return filed, its computation and
other necessary documents/certificates.
In case, the period of existence of the Company/ Registered Partnership
firm/Proprietorship concern is less than three years, then the bidder shall
submit its annual audited accounts starting from the year of
22. Canal top Rajasthan Page 21
incorporation//formation of registered Partnership firm/Proprietorship concern
(alongwith CA certified copies of Income Tax return filed; Computation of Income
and other necessary documents/certificates) while indicating the year which
should be considered for evaluation along with a Net Worth certificate from a
Chartered Accountant to demonstrate the fulfillment of the criteria as at last day
of the concerned Financial Year. Net-worth of Individuals, Directors, in case if
the Bidder is a company, will not be considered for computation of Net Worth
under this RfP.
In case of Bidders whose annual accounts have been prepared for the last
financial year, the Net Worth criteria can also be met as on day more than seven
days prior to the last date of submission of response to RfP) by the Bidder.
To demonstrate fulfillment of the criteria, the Bidder shall submit a certificate
from a Chartered Accountant certifying the availability of Net Worth on the date
more than seven days prior to submission or response to RfP along with a
certified copy of Balance Sheet, Profit & Loss Account, Schedules and Cash Flow
Statement as of that date, CA certified copies of Income Tax return, its
computation and other necessary annexure thereof, as well as the Bank
Statements.
iv) In case of Newly Incorporated Bidder/Consortium, where the Annual accounts
have not been prepared and relying solely on its own credentials, the Net Worth
criteria can be met as on day more than seven days prior to the last date of
submission of response to RfP by the bidding Consortium. To demonstrate
fulfillment of the criteria, the Bidder shall submit a certificate from a
Chartered Accountant certifying the availability of Net Worth on the date
more than seven days prior to submission of response to RfP along with a
certified copy of Balance Sheet, Profit & Loss Account, Schedules and Cash Flow
statement as of that date, supported essentially with the Bank Statements,
and all other related ROC documents to evidence issue of Share capital etc. if
applicable.
v) If the response to RfP is submitted by a Consortium, the financial requirement
shall be met individually and collectively by all the Members in the Bidding
Consortium, in proportion to the equity commitment made by each of them in
the Project Company. For computation of Net-Worth of members methodology as
provided in para (i) above shall be followed. Any Consortium, if selected, shall,
for the purpose of supply of power to procurer, incorporate a Project Company
with equity participation by the Members in line with consortium agreement
before signing the PPA with Procurer i.e. the Project Company incorporated shall
have the same Shareholding Pattern as given at the time of RfP. This shall not
change till the signing of PPA and the percentage of Controlling Shareholding
(held by the Lead Member holding more than 50% of voting rights) shall not
change from the RfP up to One Year after the COD of the Project. However, in
case of any change in the shareholding of the other shareholders (other than the
Controlling Shareholder including Lead Member) after signing of PPA, the
arrangement should not change the status of the Controlling Shareholder and
the lead member in the Project Company at least up to one year after the COD of
the Project. Further, such change in shareholding would be subject to continued
fulfillment of the financial and technical criteria, by the project company.
vi) In case, any Company is selected for developing Solar PV Project, the company
will have to meet the total Net Worth requirement by infusing the same in
the Project Company and submit the required proof like bank statements and
CA certificate for the same before entering into PPA.
vii) In case of Individuals (Proprietorship firm) / Partnership firm, the selected
Bidder shall ensure that the Capital to the extent of required Net Worth is not
23. Canal top Rajasthan Page 22
withdrawn or diluted till the COD of the project.
Note:
(1) In case the Bidder is a Company then only it may seek qualification on the basis
of financial capability of its Parent and/or it’s Affiliate(s) for the purpose of
meeting the Qualification Requirements.
(2) Where the financially evaluated company is not the Bidding Company or a
member of a bidding consortium, as the case may be, the Bidding Company or a
member shall continue to be an affiliate of such financially evaluated company
and shall not change from the RfP up to One Year after the COD of the Project.
(3) It is further clarified that a Parent Company can be a foreign company and it
can hold 100% equity in the bidding company. Once selected, the net worth has
to be brought into the bidding company as per RfP before signing the PPA.
(4) The financial strength of the parent/ultimate parent/ an affiliate can be taken
for calculation of net worth for qualifying at the time of submission of RfP, but
before signing of PPA the required net worth is required to be infused in the
company registered in India and registered with RREC for this RfP, which will
be known as “Project Company”.
(5) In case the strength is drawn from parent/ultimate parent/ affiliate, copy of
Board resolution authorizing to invest the committed equity for the project
company/consortium is to be submitted with RfP along with an unqualified
opinion from a legal counsel of such foreign entity stating that the Board
resolution are in compliance with applicable laws of country(s) respective
jurisdiction of the issuing company and the authorization granted therein are
true and valid.
(6) Only Assets forming part of the balance sheet shall be considered for arriving at
the Net worth of the bidder. No intangible assets will be considered for arriving
at the Net worth.
(7) In case of land/any other asset, only the book value will be considered.
(8) The value of land/any other assets will not be revalued for calculating net
worth. Any reserve created due to this shall not be counted for calculating Net
worth.
(9) No commitment letters from investment companies will be considered as part of
Net worth for qualifying requirement. Similarly any form of loan to bidder or
securitized funding will not be part of the Net worth.
(10) Guarantee/Bond submitted by foreign companies must be submitted through
Banks having branches in India as per list given at Annexure-2 /correspondent
Banks in India and such Bank Guarantee issued by foreign banks should be
endorsed by the Indian Branch of such foreign Bank. In case of claim on Bank
guarantee, same shall be paid by the Indian branches of such foreign Bank.
(11) In a foreign company in case of calendar year instead of financial year is used
for compilation of accounts, then the same shall be used.
(12) In a bidding consortium, each share holding company needs to satisfy the
Net worth requirement on a pro-rata equity commitment basis.
(13) Net worth once used of a Parent Company for Qualification criteria cannot be
used again for / by any Affiliate.
14) Copies of all the Balance Sheets whether of Parent/ Affiliate from where the
financial strength is drawn has to be submitted along with RfP.
24. Canal top Rajasthan Page 23
(15) The company having the maximum number of share (having voting rights) has
to be a Lead member having the shareholding of more than 50% in the Bidding
Consortium.
(16) There is no restriction on the number of companies joining the consortium for
this RfP.
(17) If a company/Technical Partner is having share less than 10% in two bidding
companies then both the bidding companies can be considered provided it does
not have any other relationship such as affiliate/parent/ultimate parent with
each other or with any other bidding company/consortium.
(18) In case of Unlisted companies the infusion of Share premium shall be supported
by ROC certified copy of Form 2.
(19) The bidding companies shall submit an “equity holding tree” duly certified by a
CA/ CS, clearly stating the equity holding and cross holdings between the
Ultimate Parent, Parent and affiliates. Necessary supporting documents such as
ROC forms, Board resolutions should also be annexed.
(20) The Bidders shall also submit CA certified copies of Income Tax Returns filed for
the last three (3) financial years, if applicable, along with the RfP documents.
(21) Failure to comply with the aforesaid provisions shall make the bid liable for
rejection at any stage.
B. Technical Criteria:
The Bidder shall deploy established technology wherein there is at least one
project successfully operational of the proposed technology of at least 1
MW, anywhere in the world. The bidder is required to undertake to furnish
evidence of meeting the above eligibility criteria. in line with provisions of clause
3.29 under the title “Financial Closure”. The undertaking shall be as per
enclosed Format– 6.7 in respect of detailed technical parameters for Solar PV
Projects.
3.24 Payment terms:
In this scheme, bidder will be selected through tariff based competitive bidding
process. A central Financial Assistance of Rs. 7.80 Cr will be released by Water
Resource Department/IGN Board to RREC and RREC will transfer the same to
the selected bidder as under:-
1. 50% CFA on commissioning of the project against Performance bank
guarantee of 10% of such 50% amount valid up to 6 months beyond the
handing over of project (i.e. for 25 and ½ years) to Water Resource
Department/IGN Board.
2. 25% CFA after one year of continuous operation of the plant against
Performance bank guarantee of 10% of such 25% amount valid up to 6
months beyond the handing over of project ( i.e. for 24 and ½ years) to Water
Resource Department/IGN Board.
3. 25% CFA after one year of continuous operation of the plant against
Performance bank guarantee of 10% of such 25% amount valid up to 6
months beyond the handing over of project ( i.e. for 23 and ½ years) to Water
Resource Department/IGN Board
4. Rest of the investment will be made by the bidder himself for which PPA
would be signed between bidder and Discoms on a tariff determined through
the tariff based competitive bidding process.
25. Canal top Rajasthan Page 24
5. After successful commissioning of the project, developer will not be allowed to
dismantle the plant or take machinery and equipments out of the plant
without written permission of Water Resource Department /IGN Board. Water
Resource Department /IGN Board will ensure that the machinery and other
equipment of the plant are in place at all times during the term of PPA for
which proper security arrangement will be put in place by Water Resource
Department /IGN Board.
6. CFA Securitization Agreement will be signed between successful bidder and
Water Resource Department/IGN Board at the time of signing of PPA.
7. In case of nonpayment of import dues of import energy by the generator
RREC will ensure the payment of import dues by invoking PBG of the
generator.
After completion of 25 years, project will be handed over to Water Resource
Department/IGN Board by the selected bidder.
3.24.1 Event of Default and recovery of CFA in the event of default.
1. Event of Default:
a. If the project fails to generate any power continuously for a period of one year during the
term of PPA or
b. If the project is dismantled and/or its major assets are sold by SPD during the term of
PPA or
c. If the SPD defaults any terms and conditions of Loan documents and the Lander takes
any steps of recovery, including for winding up of the SPD.
2. Recovery of CFA:
Upon occurrence of any Event of Default, RREC shall have a right to invoke the
performance bank guarantee submitted by the developer. In addition to this RREC shall
have a right also to refund of CFA on pro-rata basis and if not paid by the developer
then a claim on assets equal to the value of CFA released, on pro-rata basis as specified
hereunder:
Year of default (From COD) RREC’s right to refund of CFA/claim on assets (% of CFA
paid)
Up to 5years 100%
5-6 years 90%
6-7 years 80%
7-8 years 70%
8-9 years 60%
9-10 years 50%
10-11 years 40%
11-12 years 30%
12-13 years 25%
13-14 years 23%
14-15 years 21%
15-16 years 19%
16-17 years 17%
17-18 years 15%
18-19 years 13%
19-20 years 11%
20-21 years 9%
21-22 years 7%
22-23 years 5%
23-24 years 3%
24-25 years 1%
3.25 Short-listing of Project:
26. Canal top Rajasthan Page 25
3.25.1 For the project to be selected through tariff based competitive bidding, the
prospective Solar Power Producers may quote tariff in Rs/kWh. The tariff
quoted by the bidder should be in whole paisa and not in fraction of paisa.
Selection of successful bidder will be done as per following procedure-
a. All the qualified bidders will be arranged in ascending order of their quoted
tariff. The evaluation of bids shall be undertaken by discovering L1 tariff. The
bidder quoting such L1 tariff will be the successful bidder. If two or more
bidders have quoted same tariff, their position in ascending order will be
decided by draw of lot(s).
b. RREC shall have absolute right and discretion to reject the bids if it is found
that the offered tariff is unreasonably higher.
3.25.2 The PPA would be signed between selected bidder and Procurer at the tariff
determined through tariff based competitive bidding process by RREC. The PPA
would be signed on the date intimated by the Procurer/RREC.
3.25.3 It is also to clarify that the project developer to the extent of capacity
contracted by signing PPA with Procurer would not be availing benefit of REC
and such an undertaking would be incorporated in PPA.
3.26 Security Deposit and issuance of LOI
LOI will be issued to L1 bidder. The L1 bidder shall submit the security deposit
of Rs. 1.00 Cr. in form of DD/Pay order Or Bank Guarantee as per format 6.3
B within the period specified in the LOI, failing which it will be presumed that
the bidder is not interested in signing the PPA. In such case, EMD submitted
by the bidder will be forfeited by RREC.
EMD (if deposited in form of DD/Pay order) of successful bidder may be
adjusted against Security deposit.
3.27 Returns of Deposits and forfeiture of Deposits:
3.27.1 In case the Bidder is not selected, RREC shall release the EMD or will
return Bank Guarantees towards EMD after Final acceptance of successful
Bid and signing of agreement and submission of Security Deposit by
successful Bidder.
3.27.2 In case, Procurer offers to execute the PPA with the Selected Bidder and if the
Selected Bidder then refuses to execute the PPA with procurer or is unable to
execute the PPA within the stipulated time period or extended time period, the
Bank Guarantees towards security deposit will be forfeited by RREC.
3.28 Power Purchase Agreement:
A copy of Draft Power Purchase Agreement to be executed between Procurer
and the Selected Bidder is enclosed at Annexure 9. The PPA shall be executed
on the date to be intimated by Procurer/RREC.
Before signing of PPA with the selected bidder, RREC may verify the documents
furnished by the bidder at the time of submission of RfP including availability
of net-worth to the extent claimed in RfP with the original documents and
bank statements and the shareholding of the project company along with
a copy of complete documentary evidence supported with originals. Bidder
may be asked to furnish the documentary evidence claimed for meeting the RfP
Eligibility conditions. RREC at this stage may also ask the bidder to furnish the
audited balance sheet of the previous month end along-with complete Bank
statement starting from day one of submission of RfP till date along with a copy
of the documents submitted with ROC which become due during this period. If
27. Canal top Rajasthan Page 26
at any stage it is found that the documents furnished by the bidder are
false/misleading or misrepresented in any way then the RfP bid will be liable to
be rejected and if LOI has been issued and PPA signed, the same will also be
cancelled and all the bank guarantees will be en-cashed Or deposits will be
forfeited.
Minimum equity to be held by the Promoter:
3.29.1 The Bidders developing the project shall provide the information about the
Promoters and their shareholding in the Bidding Company to RREC indicating
the controlling shareholding at the stage of submission of RfP to RREC.
3.29.2 No change in the percentage of controlling shareholding of the Bidding
Company or Lead Member in a Bidding Consortium developing the
Project shall be permitted from the date of response to RfP till the
execution of the PPA. However, in case the Project is being developed by a
listed company, this condition will not be applicable. The controlling
shareholding shall mean the largest shareholding more than 50% of the voting
rights in the Company.
3.29.3 After execution of PPA, the percentage controlling of shareholding of the
Controlling shareholder or Lead Member in the Project Company developing
the Project shall be maintained for a period of (1) one year after
commencement of supply of power. Thereafter, any change can be undertaken
under intimation to RREC.
3.29.4 Bidding Company, forming a project company with no change in Shareholding
shall be permitted from the RfP stage upto PPA, but the controlling
shareholding as informed at the stage of RfP shall not change upto one year
after COD of the Project.
3.29 Financial Closure or Project Financing Arrangements:
The Project Developer shall report tie-up of Financial Arrangements for the
projects within six months from the date of signing Power Purchase Agreement
(PPA). At this stage, the project developer would furnish the following
documents:
(a) A certificate that the technology proposed to be used is commercially
established technology and at least one project based on this technology of
at least 1 MW has been in successful operation for one year anywhere in the
world.
(b) Details of the project with location and the successful operational period of
the project utilizing this technology.
(c) The project developer will submit the final loan sanction letter from the
bank/FI along with copy of the signed loan agreement.
(d) Required canal top/ land for project development is under clear possession
of the project developer. In this regard the Project Developer shall be
required to furnish the following documentary evidences:-
i. Copy of MoU signed with Water Resource Department/IGN Board for right
to use the canal top/ land required for setting up of the solar power plant
and associated works.
ii. Sworn affidavit from the Authorized person of the developer listing the
details of the land and certifying total land required for the project under
clear possession of the Project Developer.
3.30 Commissioning:
3.30.1 The Project shall be commissioned within 15 months of the date of signing of
28. Canal top Rajasthan Page 27
PPA between Project Developer and Procurer. Commissioning period is subject
to Force Majeure Conditions detailed in “Definitions”, section-2.
3.30.2 Should the successful bidder fails to complete the work in the period specified
in the PPA / contract, the RREC may at its discretion to allow an extension in
time of completion, subject to recovery from the developer an agreed liquidated
damages a sum equal to the following percentage from the amount payable by
RREC { i.e. the amount of LD shall be calculated on the total CFA payment
payable by RREC} for the period of delay in commissioning as stated below:-
(a) Delay up to 45 days of the prescribed commissioning period -2.5%.
(b) Delay exceeding 45 days but not exceeding 90 days of the prescribed
commissioning period – 5%
(c) Delay exceeding 90 days but not exceeding 135 days of the prescribed
commissioning period – 7.5%
(d) Delay exceeding 135 days but not exceeding 180 days of the prescribed
commissioning period – 10%
1. The maximum amount of agreed liquidated damages shall be 10% of CFA
amount.
2. If the Developer requires an extension of time in completion of contractual
commissioning on account of occurrence of any hindrance, he shall apply in
writing to the Authority for the same immediately on occurrence of the
hindrance but not after the stipulated date of Commissioning.
3.30.3 Delay beyond 180 days from schedule commissioning, PPA may be terminated.
However, in exceptional cases, RREC may consider to grant extension in the
Scheduled Commissioning of project with a penalty @ 1.0% per week of the
total CFA.
3.31 Technical Parameters:
The Selected Bidder shall be required to adhere to the technical parameters
specified in Annexure-1.
29. Canal top Rajasthan Page 28
SECTION 4
Evaluation Criteria
4.1 The evaluation process comprises of the following two steps:
Step I – Responsiveness check
Step II – Bid evaluation
4.2 Step I - Responsiveness check:
The Bid submitted by the Bidder shall be scrutinized electronically as well as
physically to establish “Responsiveness”. Each Bidder’s Bid shall be checked for
compliance with the submission requirements set forth in this RfP. In case of
any discrepancy found in the document uploaded and physically submitted,
then electronically document will prevail in respect of documents physical
sought. However in case of DD/Pay order/BG sought physically, then physical
shall prevail over electronic document.
The requisite fee in form of DD/Pay Order or Bank Guarantee as submitted
physically in the prescribed envelops will only be considered for evaluation of
Bid(s).
Any of the following conditions shall cause the Bid to be “Non-responsive”:
i) Response to RfP not received by the due date and time.
ii) Response to RfP submitted by a Bidding Consortium not including the
Consortium Agreement.
iii) Response to RfP having Conflict of Interest.
iv) Bidder submitting or participating in more than one Bid either as Bidder or
as a Member company of Bidding Consortium.
v) Technology Partner holding more than 10% in a Consortium and
participating as a Bidding Company/ Member in another Consortium.
vi) Non submission of Cost of Document, Processing fee of RREC and RISL,
EMD or bid-bond in acceptable form along with RfP document.
4.3 Step II - Bid evaluation:
Step II (Bid evaluation) will be carried out considering the information furnished
by Bidders as prescribed under Section 6- Formats. This step would involve
evaluation of the Bid of the Bidder.
30. Canal top Rajasthan Page 29
SECTION 5
SPECIAL TERMS AND CONDITIONS
5.1 Facilitation by Nodal Agency:
State Nodal Agency (RREC) will provide necessary support to facilitate the
development of the project. This shall include facilitation in the following areas:
• Arranging Evacuation approval from Concerned Discom/RVPN.
• Arranging Connectivity to the nearest 33/11kV substation of Discom at the
voltage level of 11kV.
• Timely completion of 11kV Bay at 33/11kV Discoms Substation by
Discoms.
5.2 Land:
The Solar power project is to be installed on the canal top as per the proposed
site location. Water Resource Department/IGN Board will allow canal top/ land
to Solar Power producer for development of Solar Power Project on Build,
Operate and Own basis for 25 years on right to use basis. Ownership of such
canal top/land will remain with Water Resource Department/IGN Board. In
case any extra land along the canal banks is required for installation of
equipments or any other associated works related to Solar Power Plant, the
same will be provided by Water Resource Department/IGN Board to the
developer free of cost on right to use basis for 25 years. MOU for the same will
be signed between the successful bidder and Water Resource Department/IGN
Board. Draft MoU is enclosed at Annexure-8.
5.3 Metering System for Solar power Generation plant
5.3.1 The metering system shall comprise of main, check and standby meters.
5.3.2 For measurement of solar energy supplied by Solar generating station, Main
meter shall be provided at the line isolator on the outgoing feeder on HV side of
the generator transformer at the solar power Plant designated as main meter for
billing purpose. Check meter shall be provided along with main meter on the
outgoing feeder. Meter shall also be provided on the other end of the above
feeder to serve as standby meter. The consumption recorded by main meter
shall be compared with the consumption recorded by standby meter on to
work out transmission losses as well as to monitor the correct functioning of
both meters.
5.3.3 All meters (a) main (b) check (c) standby meters in Solar Power Plant Generating
Substation shall be provided by the solar power producer at his own cost. The
load survey of the meter should have provision of voltage monitoring in addition
to other parameters. Power failure recording is required to be included in ToD
provisions of the meter along with provision of memory requirement as per
RERC Metering Regulations in force.
5.3.4 In the event of main meter or more than one meter becoming defective the order
of precedence for billing shall be (a) main (b) check (c) standby.
5.3.5 The solar power plant requires auxiliary power during generation and non
generation time. Successful bidder should note that separate power
connection for auxiliary power consumption shall not be provided by
Discom. Project developer is required to make either provision of solar lighting
system in their area / plant to meet out the requirement of illumination
otherwise they can draw the power from the STU/Discom through their
metering system. In this case net metering (export – import reading of meters)
will be applicable. The power connection provided by Discoms will be
immediately disconnected after commissioning of the project. The developer will
31. Canal top Rajasthan Page 30
have to produce No-dues certificate from concerned Discom at the time of
commissioning.
5.3.6 Other terms and conditions shall be as per CEA (Installation & Operation of
Meters) Regulations, relevant RERC Regulations, IEGC/REGC and ABT
Regulations as amended & revised from time to time.
5.4 Insulation coordination and Protection system:
The Successful Bidder shall ensure the interfacing of his solar power plant
electrical equipments with RVPN/Discom(s) Grid for evacuation of power as well
as protection of their Solar Power Plant. Discoms Grid is infinite system so
Discom shall not be responsible for any damage of solar power plant under any
fault condition.
5.5 Transmission losses:
The transmission losses beyond solar power plant line terminal point shall be
borne by the Discom(s).
5.6 Evacuation System:
5.6.1 The developer shall lay 11kV line from the Power Plant Generating Substation to
33/11kV Discom GSS. Cost of 11kV line will be borne by developer and the
responsibility of operation/maintenance will also be of the developer. Developer
shall get the specification of the line approved from the Discom.
5.7 Interconnection with Discom Sub Station:
5.7.1 Solar power plant getting connected to the grid for supplying power to Discoms
shall be required to pay connectivity charges @ Rs. 2.0 Lac/MW. Discom shall
provide complete line bay (including civil works) and its interconnection with
existing electrical system in 33/11kV Discom GSS at Discom cost. Line Bay
includes breakers, CTs, CVT/ PTs, isolators, protection equipments, bus bar
material and other allied materials as applicable.
5.7.2 In case at a later date, a new 33/11 kV GSS is constructed nearby solar power
plant, Discom(s) can terminate the 11 kV transmission line to nearby 33/11 kV
GSS by suitable augmentation of line. Discom will provide bay in new
substation. Surplus Line and Bay resulted due to above augmentation shall be
utilized by Discom for system Augmentation.
5.8 Approval of Discom for Connectivity with the Grid:
5.8.1 The Solar PV plant should be designed for interconnection with the nearest
33/11 kV substation of Discom at the voltage level of 11 kV. The project
developer shall be responsible for entering into transmission evacuation
agreement with Discom after allotment of project and signing of PPA.
Generator/developer will submit the schematic diagram of the RVPN/Discoms
network showing the locations of the energy meters( Main meter, Check meter &
Standby meter)with metering equipment installed on the system to measure the
energy injected by RE generator into the system as per prevailing metering code
/policy/regulation. This diagram shall also indicate the metering arrangement
and details of the metering equipments available on generator panel and pooling
station/ receiving station. The SE (M&P) Discom of the area where RE generator
is installed shall approve the metering plan as per prevailing metering
code/regulation/policy before connectivity/commissioning of the plant.
5.8.2 Approval from Discom confirming technical feasibility of the connectivity of the
plant to grid substation at the indicated location shall be required. In case
32. Canal top Rajasthan Page 31
selected bidder forms an SPV before signing of PPA then new technical feasibility
of connectivity in New SPV name will be required to be taken from Discom after
signing of PPA even if same is taken in name of Bidder.
5.9 CDM Benefits:
Project developers are encouraged to identify the potential role of carbon finance
in their investment analysis including: i)The expected revenues from emission
reductions; and ii)The cost of power with and without carbon revenues.
The proceeds of carbon credit from approved CDM project shall be shared
between Solar Power Generating Company and concerned beneficiaries as per
relevant RERC regulations.
5.10 Benefit under Renewable Energy Certificate Mechanism:
The SPP, to the extent of capacity contracted with Procurer by signing PPA for
supply of power under this RfP will not be availing the benefit of REC in respect
of such contracted capacity and such an undertaking would need to be
furnished by the SPP.
5.11 Weather Monitoring Station:
5.11.1 The grid connected solar PV Power Plants will install necessary equipment for
regular monitoring of solar irradiance (GHI and tilted), temperature (ambient
and Module), wind speed and other weather parameters and simultaneously for
monitoring of the electric power generated from the plant. The instruments used
for above measurements should remain calibrated for entire duration of PPA.
5.11.2 Online arrangement would have to be made by the solar power developer for
submission of above data regularly for the entire period of this Power Purchase
Agreement to RREC/Discoms or any other agency authorized by
RREC/Discoms.
5.11.3 Reports on above parameters on monthly basis shall be submitted by the solar
power developer to RREC/Discoms for entire period of PPA.
33. Canal top Rajasthan Page 32
SECTION 6
Formats for Bid Submission
The following formats are required to be submitted as part of the RfP. These
formats are designed to demonstrate the Bidder’s compliance with the
Qualification Requirements set forth in Clause 3.23 of Section 3 and other
submission requirements specified in the RfP.
(i) Format for Earnest Money Deposit (EMD) (Format 6.3 A)
(ii) Format of Covering Letter (Format 6.1)
(iii) Formats for Power of Attorney (Format 6.2)
(iv) Format for Board Resolutions (Format 6.4)
(v) Format for the Consortium Agreement (Format 6.5)
(vi) Format for Financial Requirement (Format 6.6)
(vii) Format for Technical Criteria (Format 6.7)
(viii) Format for connectivity of project with Discom(s) Substation (Format
6.8)
(ix) Format for Disclosure (Format 6.9)
(x) Format for Declaration by Bidder regarding Qualifications (Format
6.10)
(xi) Declaration by the Bidder/ Lead Member of Bidding Consortium for
the Proposed Technology (Format 6.11)
(xii) Format for filling the tariff (Format 6.12- an .xls file which contains
the BoQ which is to be downloaded from www.eproc.rajasthan.gov.in
for this RfP.)
(xiii) Check lists Annexure 3 & 4
(xiv) Memorandum & Article of Association, Certificate of
Incorporation/Registration (if applicable) of Bidding Company / all
member companies of Bidding Consortium.
(xv) CA Certified copy of Income Tax return filed by the Bidder/Lead
member company of Bidding Consortium
(xvi) Certified/notarized copy of Partnership deed (as applicable)
As and when required:
(i) Format for Security Deposit in form of Bank Guarantee (Format 6.3 B)
(ii) Format for Performance Bank Guarantee (Format 6.3 C)
34. Canal top Rajasthan Page 33
Format – 6.1
Format of Covering Letter
(The covering letter should be on the Letter Head of the Bidder / Lead
Member of the Bidding Consortium)
Date:
From: (Insert name and address of Bidder / Lead Member of the Bidding
Consortium)
Tel.#:____________
Fax#:____________
E-mail address#:__________________
To,
Managing Director,
Rajasthan Renewable Energy Corporation Ltd,
E-166, Yudhisthir Marg, C-Scheme
Jaipur-302001 (Rajasthan)
Sub: Response to RfP/PV/RREC/Canal top for setting up of Grid connected
2 MW Solar PV Plant at Menawali minor of NDR (I.G.N.P.) in
Hanumangarh area, Rajasthan by covering Canal managed by IGN
Board/Water Resource Department in Rajasthan.
Dear Sir,
1. We/I, the undersigned ……. [insert name of the ‘Bidder’] having read,
examined and understood in detail the RfP alongwith PPA for supply of solar
power for 25 years to Procurer(s) and the MoU for right to use the Canal Top
& Land, hereby submit our/my response to RfP for setting up of Grid
Connected 2 MW Solar PV Plant at Menawali minor of NDR (I.G.N.P.) in
Hanumangarh area, Rajasthan by covering Canal managed by IGN
Board/Water Resource Department in Rajasthan.
2. We/I give our/my unconditional acceptance to the RfP/PV/RREC/Canal
top alongwith PPA and MoU attached thereto, issued by RREC. We shall
ensure that the PPA is executed as per the provisions of the RfP and
provisions of PPA & MoU shall be binding on us/me. It is expressly accepted
by us/me that We/I shall abide by the provision of liquidated damages as
stipulated in RfP clause No.-3.30.2 and any decision of RREC/Procurer
regarding encashment of the BGs submitted towards EMD, Security deposit
and Performance Bank Guarantee (PBG) shall be final and binding on
us/me.
3. We/I confirm that our/my Project of capacity 2 MW shall be commissioned
within15 months of the date of signing of PPA.
4. Earnest Money Deposit (EMD).
We/I have enclosed EMD of Rs. ………….. (Insert Amount), in the form of
bank guarantee No………….[Insert bank guarantee number] dated ……….
[Insert date of bank guarantee] as per Format 6.3A from ………… [Insert
name of bank providing bank guarantee] and valid up to………….in terms of
Clause 3.22 of this RfP.
5. We have submitted one bid for development of one Project of 2 MW AC
size using a Solar Photo Voltaic technology.
35. Canal top Rajasthan Page 34
and
Our Parent / Affiliate Company M/s--------------have submitted separate bid
for development of one Project of 2 MW AC size using a Solar PV technology.
6. We/I have submitted our/my response to RfP strictly as per Section – 6
(Formats) of this RfP, without any deviations, conditions and without
mentioning any assumptions or notes in the said Formats.
7. Acceptance
We/I hereby unconditionally and irrevocably agree and accept that the
decision made by RREC in respect of any matter regarding or arising out of
the RfP shall be binding on us/me. We/I hereby expressly waive any and all
claims in respect of this process.
8. Familiarity with Relevant Indian Laws & Regulations
We/I confirm that we/I have studied the provisions of the relevant Indian
laws and regulations as required to enable us/me to submit this response to
RfP and execute the PPA, in the event of our/my selection as Successful
Bidder.
9. We/I are/am submitting herewith our/my response to the RfP with formats
duly signed digitally as desired by you in the RfP for your consideration on
www.eproc.rajasthan.gov.in
10. It is confirmed that our/my response to the RfP is consistent with all the
requirementsof submission as stated in the RfP and subsequent
communications from RREC.
11. The information submitted in our/my response to the RfP is correct to the
best of our/my knowledge and understanding. We/I would be solely
responsible for any errors or omissions in our/my response to the RfP.
12. We/I confirm that all the terms and conditions of our Bid are valid up to a
period of six (6) months from the date of opening of RfP.
Contact Person
Details of the contact person are furnished as under:
Name : …………………………………….
Designation : ………………….………………..
Company/Firm : …………………………………….
Address : …………………………………….
Phone Nos. : ……………………………………….
Fax Nos. : ………………………………………….
E-mail address : …………………………………………..
13. We/I have neither made any statement nor provided any information in this
Bid, which to the best of our/my knowledge is materially inaccurate or
misleading. Further, all the confirmations, declarations and representations
made in our/my Bid are true and accurate. In case this is found to be
incorrect after our/my selection as Successful Bidder, we/I agree that the
same would be treated as a Seller’s event of default under PPA, and
consequent provisions of PPA shall apply.
14. We/I confirm to comply with Grid Code including Load Dispatch and System
Operation Code, Metering Code, Protection Code, Safety Code, relevant
36. Canal top Rajasthan Page 35
regulations/orders of the appropriate authority etc. and provisions of
Rajasthan Solar Energy Policy, 2014, as applicable from time to time in the
State of Rajasthan.
Dated the day of , 20…
Thanking you,
Yours faithfully,
(Name, Designation and Signature of Bidder/Partner/Person Authorized by
the board )
37. Canal top Rajasthan Page 36
Format – 6.2
Format for Power of Attorney to be provided by each of the other members of the
Consortium in favour of the Lead Member
Power of Attorney
(To be on non-judicial stamp paper of appropriate value as per Stamp Act relevant to
place of execution)
Know all men by these presents that M/s. ………………………… having its
registered office at …………………………..…….., and M/s …………………….…. having
its registered office at ………………………………….., (Insert names and registered
offices of all Members of the Consortium) the Members of Consortium have formed a
Bidding Consortium named…………. (insert name of the Consortium if finalized)
(herein after called the ‘Consortium’) vide Consortium Agreement
dated………..……………….. and having agreed to appoint
M/s……………………………..…… as the Lead Member of the said Consortium do
hereby constitute, nominate and appoint M/s…………….………….. a company
incorporated under the laws of ……….……… and having its Registered /Head
Office at …..……….………….. as our duly constituted lawful Attorney
(hereinafter called as Lead Member) to exercise all or any of the powers for and on
behalf of the Consortium in regard to submission of the response to RfP. We also
authorize the said Lead Member to undertake the following acts:
i. To submit on behalf of Consortium Members response to RfP.
ii. To do any other act or submit any information and document related to the above
response to RfP, if required.
It is expressly understood that in the event of the Consortium being selected
as Successful Bidder, this Power of Attorney shall remain valid, binding and
irrevocable until the Bidding Consortium achieves execution of PPA.
We as the Member of the Consortium agree and undertake to ratify and confirm all
whatsoever the said Attorney/Lead Member has done on behalf of the
Consortium Members pursuant to this Power of Attorney and the same shall bind us
and deemed to have been done by us.
IN WITNESS WHEREOF M/s …………………………………………..……., as the
Member of the Consortium have executed these presents on this……….. day of ........
under the Common Seal of our company.
For and on behalf of Consortium Member
M/s………………………….
(Signature of person authorized by the board)
(Name Designation Place:
Date
Accepted-
(Signature, Name, Designation and Address
of the person authorized by the board of the Lead Member)
Attested-
(Signature of the executants)
-
38. Canal top Rajasthan Page 37
(Signature & stamp of Notary of the place of execution)
Place:----------------
Date:------------------
Note: - Lead Member in the Consortium shall have the controlling shareholding in
the company having more than 50% of voting rights in the company.
39. Canal top Rajasthan Page 38
Format 6.3 A
Format for Earnest Money Deposit
(To be on non-judicial stamp paper of appropriate value as per Stamp
Act relevant to place of execution.)
In consideration of the ----- [Insert name of the Bidder] (hereinafter referred
to as 'Bidder') submitting the response to RfP inter-alia for selection of the
project, at …………[Insert Capacity of Plant and name of the place] under
RfP/PV/RREC/Canal top for supply of power there from on long term basis,
in response to the RfP dated issued by Rajasthan Renewable Energy
Corporation Ltd (RREC) and RREC considering such response to the RfP of
………[ insert the name of the Bidder] as per the terms of the RfP, the
[insert name & address of bank] hereby agrees unequivocally, irrevocably
and unconditionally to pay to RREC at Jaipur forthwith on demand in
writing from RREC or any Officer authorized by it in this behalf, any amount
upto and not exceeding Rupees ------[Insert amount not less than that
derived on the basis of Rs. 42 Lacs only (in words Rs. Forty two lacs
only), on behalf of Mr./M/s. [Insert name of the Bidder].
This guarantee shall be valid and binding on this Bank up to and including
[ insert date of validity in accordance with clause 3.22 of this RfP] and
shall not be terminable by notice or any change in the constitution of the
Bank or the term of contract or by any other reasons whatsoever and
our liability hereunder shall not be impaired or discharged by any
extension of time or variations or alternations made, given, or agreed with
or without our knowledge or consent, by or between parties to the respective
agreement.
Our liability under this Guarantee is restricted to Rs.
(Rs only). Our Guarantee shall remain in force until
[insert date of validity in accordance with clause 3.22 of this RfP].
RREC shall be entitled to invoke this Guarantee till [insert date of validity
in accordance with clause 3.22 of this RfP].
The Guarantor Bank hereby agrees and acknowledges that the RREC shall
have a right to invoke this BANK GUARANTEE in part or in full, as it may
deem fit.
The Guarantor Bank hereby expressly agrees that it shall not require any
proof in addition to the written demand by RREC, made in any format, raised
at the above mentioned address of the Guarantor Bank, in order to make the
said payment to RREC.
The Guarantor Bank shall make payment hereunder on first demand
without restriction or conditions and notwithstanding any objection by -------
------ [Insert name of the Bidder] and/or any other person. The Guarantor
Bank shall not require RREC to justify the invocation of this BANK
GUARANTEE, nor shall the Guarantor Bank have any recourse against
RREC in respect of any payment made hereunder:
This BANK GUARANTEE shall be interpreted in accordance with the laws of
India and the courts at Jaipur Rajasthan shall have exclusive jurisdiction.
The Guarantor Bank represents that this BANK GUARANTEE has been
established in such form and with such content that it is fully enforceable in
accordance with its terms as against the Guarantor Bank in the manner
provided herein.
This BANK GUARANTEE shall not be affected in any manner by reason of
merger, amalgamation, restructuring or any other change in the
constitution of the Guarantor Bank.
40. Canal top Rajasthan Page 39
This BANK GUARANTEE shall be a primary obligation of the Guarantor Bank
and accordingly RREC shall not be obliged before enforcing this BANK
GUARANTEE to take any action in any court or arbitral proceedings against
the Bidder, to make any claim against or any demand on the Bidder or to
give any notice to the Bidder or to enforce any security held by RREC or to
exercise, levy or enforce any distress, diligence or other process against the
Bidder.
The Guarantor Bank acknowledges that this BANK GUARANTEE is not
personal to RREC and may be assigned, in whole or in part, (whether
absolutely or by way of security) by RREC to any entity to whom RREC is
entitled to assign its rights and obligations under the PPA.
Not withstanding anything contained herein above, our liability under
this Guarantee is restricted to Rs. (Rs.
only) and it shall remain in force until [Date to be inserted on the basis of
Clause 3.22 of this RfP] . We are liable to pay the guaranteed amount or any
part thereof under this Bank Guarantee only if RREC serves upon us a
written claim or demand.
Signature
Name
Power of Attorney No._
For
[Insert Name of the Bank]
Banker's Stamp and Full Address.
Dated this day of , 20
41. Canal top Rajasthan Page 40
Format 6.3 B
Format for Security Deposit
(To be on non-judicial stamp paper of appropriate value as per Stamp
Act relevant to place of execution.)
In consideration of the ----- [Insert name of the Bidder/ Lead Member (in
case of Consortium)] (hereinafter referred to as ‘Bidder') submitting the
response to RfP inter-alia for selection of the project, at …………[Insert
Capacity of Plant and name of the place] under RfP/PV/RREC/Canal top for
supply of power therefrom on long term basis, in response to the RfP
dated issued by Rajasthan Renewable Energy Corporation
Limited, Jaipur (herein after referred to as RREC) and RREC considering
such response to the RfP of ………[ insert the name of the Bidder] as per the
terms of the RfP, the [insert name & address of bank] hereby agrees
unequivocally, irrevocably and unconditionally to pay to RREC at E-166
Yudhisthir Marg, C-Scheme, Jaipur-302001 forthwith on demand in writing
from RREC or any Officer authorized by it or on its behalf, any amount up to
and not exceeding Rupees ------[Insert amount not less than that derived on
the basis of LOI] only, on behalf of Mr./M/s. [Insert name of the
Bidder] .
This guarantee shall be valid and binding on this Bank up to and including
………………[ insert date of validity in accordance with clause 3.22 of this RfP]
and shall not be terminable by notice or any change in the
constitution of the Bank or the term of contract or by any other
reasons whatsoever and our liability hereunder shall not be impaired or
discharged by any extension of time or variations or alternations made,
given, or agreed with or without our knowledge or consent, by or
between parties to the respective agreement. Our liability under this
Guarantee is restricted to Rs. (Rs. only). Our Guarantee shall
remain in force until [insert date of validity in accordance with clause
3.22 of this RfP] and RREC shall be entitled to invoke this Guarantee till
[insert date of validity in accordance with clause 3.22 of this RfP].
The Guarantor Bank hereby agrees and acknowledges that the RREC shall
have a right to invoke this BANK GUARANTEE in part or in full, as it may
deem fit.
The Guarantor Bank hereby expressly agrees that it shall not require any
proof in addition to the written demand by RREC, made in any format, raised
at the above mentioned address of the Guarantor Bank, in order to make the
said payment to RREC.
The Guarantor Bank shall make payment hereunder on first demand
without restriction or conditions and notwithstanding any objection by -------
------ [Insert name of the Bidder] and/or any other person. The Guarantor
Bank shall not require RREC to justify the invocation of this BANK
GUARANTEE, nor shall the Guarantor Bank have any recourse against
RREC in respect of any payment made hereunder.
This BANK GUARANTEE shall be interpreted in accordance with the laws of
India and the courts at Jaipur shall have exclusive jurisdiction.
The Guarantor Bank represents that this BANK GUARANTEE
42. Canal top Rajasthan Page 41
has been established in such form and with such content that it is fully
enforceable in accordance with its terms as against the Guarantor Bank in
the manner provided herein.
This BANK GUARANTEE shall not be affected in any manner by reason of
merger, amalgamation, restructuring or any other change in the
constitution of the Guarantor Bank.
This BANK GUARANTEE shall be a primary obligation of the Guarantor Bank
and accordingly RREC shall not be obliged before enforcing this BANK
GUARANTEE to take any action in any court or arbitral proceedings against
the Bidder, to make any claim against or any demand on the Bidder or to
give any notice to the Bidder or to enforce any security held by RREC or to
exercise, levy or enforce any distress, diligence or other process against the
Bidder.
The Guarantor Bank acknowledges that this BANK GUARANTEE is not
personal to RREC and may be assigned, in whole or in part, (whether
absolutely or by way of security) by RREC to any entity to whom RREC is
entitled to assign its rights and obligations under the PPA.
Notwithstanding anything contained hereinabove, our
liability under this Guarantee is restricted to Rs.
(Rs. only) and it shall remain
in force until …………………... We are liable to pay the guaranteed amount or
any part thereof under this Bank Guarantee only if RREC serves upon us a
written claim or demand.
Signature
Name
Power of Attorney No._
For
[Insert Name of the Bank]
Banker's Stamp and Full Address.
Dated this day of _, 20
Witness:-
1.
2.
43. Canal top Rajasthan Page 42
Format 6.3 C
Format for Performance Guarantee
(To be on non-judicial stamp paper of appropriate value as per Stamp
Act relevant to place of execution.)
In consideration of the ----- [Insert name of the Bidder] (hereinafter referred
to as selected Solar Power Developer') submitting the response to RfP inter
alia for selection of the project, at …………[Insert name of the place] under
RfP/PV/RREC/Canal top for supply of power therefrom on long term basis,
in response to the RfP dated… issued by RREC and RREC[Insert Name of
the Place from the address ]considering such response to the RfP of
………[insert the name of the selected Solar Power Developer] (which
expression shall unless repugnant to the context or meaning thereof include
its executers, administrators, successors and assignees) and selecting the
Solar Power Project of the developer and issuing Letter of Intent No ------- to
(Insert Name of selected Solar Power Developer) as per terms of RfP and the
same having been accepted by the selected SPD resulting in a Power
Purchase Agreement (PPA) to be entered into, for purchase of Power [from
selected Solar Power Developer or a Project Company, M/s ------------- {a
Special Purpose Vehicle (SPV) formed for this purpose}, if applicable]. As per
the terms of the RfP, the [insert name & address of bank] hereby agrees
unequivocally, irrevocably and unconditionally to pay to RREC at [Insert
Name of the Place from the address] forthwith on demand in writing from
RREC or any Officer authorized by it in this behalf, any amount up to and
not exceeding Rupees------ [Total Value] only, on behalf of M/s [Insert
name of the selected Solar Power Developer/ Project Company]
This guarantee shall be valid and binding on this Bank up to and including
………………[ insert date of validity in accordance with clause 3.24 of this RfP]
and shall not be terminable by notice or any change in the constitution of
the Bank or the term of contract or by any other reasons whatsoever and our
liability hereunder shall not be impaired or discharged by any extension of
time or variations or alternations made, given, or agreed with or without our
knowledge or consent, by or between parties to the respective agreement.
Our liability under this Guarantee is restricted to Rs.___________ (Rs.
__________ only). Our Guarantee shall remain in force until RREC or their
authorized representatives shall be entitled to invoke this Guarantee
till___________.
The Guarantor Bank hereby agrees and acknowledges that the procurer(s) or
their authorized representatives shall have a right to invoke this BANK
GUARANTEE in part or in full, as it may deem fit.
The Guarantor Bank hereby expressly agrees that it shall not require any
proof in addition to the written demand by RREC or their authorized
representatives, made in any format, raised at the above mentioned address
of the Guarantor Bank, in order to make the said payment to RREC or their
authorized representatives.
The Guarantor Bank shall make payment hereunder on first demand
without restriction or conditions and notwithstanding any objection by -------