SlideShare a Scribd company logo
1 of 5
Download to read offline
C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND
OWNING FARMERS.docx
DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO
LAND OWNING FARMERS
Hon’ble Prime Minister of Indial has vision of 100 gigawatt (GW) solar energy by 2022,
Which was reflected in the budget speech of the Hon’ble Finance Minister of India,
based on which Ministry of New and Renewable Energy, Govt. Of India has increased
its target to 100GW. Its benefits would stretch beyond energy security and
environmental protection. It could create a million green jobs in India, where large scale
unemployment is one of the top socio-economic issues. As part of the National
programme, Punjab plans to achieve Solar Cap. 5400 MW by 2022.
As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is
introduced for allocation of Solar Power Projects to the land owning farmers of the the
state of Punjab.
The Government of Punjab endeavors to promote solar energy projects by land owning
farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land
owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd.
(PSPCL) at applicable generic tariff determined by Punjab State Electricity Regulatory
Commission (PSERC) on annual basis. With Solar Power Projects located closer to the
agriculture loads in distribution / transmission network, distribution losses will be
reduced considerably and voltage drop at peak day time load will be minimized along
with power supply and power factor improvement . These small solar PV systems shall
act as a micro distributed utility at farm level. The solar power generation shall be
available for enabling the agriculture pump-sets loads to be operated during the
daytime, thereby allowing the utility to dispatch the power so saved from their central
generating station to other area.
Nodal Agency
PEDA shall be the nodal agency for implementation of this special scheme. Project
application processing & allocation shall be with PEDA while administration of Power
Purchase Agreements (PPA) shall be with PSPCL. PEDA will also facilitate the farmers
regarding documentation for the projects.
Capacity Target
The cumulative capacity under this scheme shall be 500MW.
C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND
OWNING FARMERS.docx
Evacuation facilities
Govt. of Punjab (GoP) shall facilitate purchase of energy generated under this scheme
by PSPCL through power purchase agreements of 25 years duration. PSPCL shall be
responsible for providing connectivity of the solar PV power generating station at the
nearest grid sub-station with the grid and provide cable from the last H pole of the 11
KV evacuation line inside the Grid sub/station and 11 KV switchgear along with
metering system in the grid. The farmer shall bear the total cost of the 11 KV line for
evacuation of power from the Out Door Yard of the project to the nearest 66KV sub-
station which can be got constructed by the farmer from PSPCL on deposit job work
basis.
Eligibility, Terms & Conditions
1. Farmer / Group of Farmers, holding agriculture land in their name for the last three
years from date of issue of this scheme. If the land is transferred on succession /
will basis then the time of holding of the land of the person from where land has
been transferred on account of succession / Will shall be counted towards eligibility
of three year time period of the applicant.
2. A group of farmers can also get together for setting up of the SPV Power Project
in the land owned by the members of the group.
3. Farmer / Group of Farmers can also form a company for applying and or
implementation of the project.
4. The minimum capacity is 1MWp and maximum is 2.5 MWp for each farmer/group
of farmers/SPV Company.
5. Only the Farmer / Group of Farmers, owning the land in the State of Punjab,
having valid and duly certified land ownership document (Jamabandi) with entry of
their names are eligible to apply. The existing land use as per revenue records
should be for Agriculture/Horticulture/ Farming including irrigated & non-irrigated
area.
6. The applicant has to furnish the certified copy of the land ownership documents as
proof of land holding of the total required land for the applied capacity. The
minimum land required is 4.5 acres for 1MWp proportionately of higher capacity.
C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND
OWNING FARMERS.docx
7. If the land holding is held jointly each of the joint holder is individually also eligible
to apply for minimum 1MW to maximum 2.5 MW depending upon the extent of
required land. Provided that Husband &Wife will be individually or jointly eligible to
apply for max 2.5 MW only.
8. The following committee will scrutinize the application and verify the original
documents before short listing of eligible applicants and final allottees: -
- Director PEDA, Joint Director PEDA, Senior Manager Finance,
Representatives of Revenue Department (Dy. Secretary), Representatives
of Finance Department (Dy. Secretary), Representatives of PSPCL (Chief
Engineer).
9. The application fee of Rs.50,000/- (Non refundable) shall be submitted through
Draft with the printed application along with the certified copy of the ownership
documents. The farmer has also to furnish a processing fee of Rs. 2,00,000/- per
MW to PEDA along with application in the shape of separate demand draft. In case
the farmer does not gets the allotment, the processing fee shall be refunded.
10. Allotment shall be made by the project allotment committee notified in the NRSE
policy 2012. The allotment shall be based on discount given in the tariff in the first
instance.
11. In case, two or more applicants are offering the same tariff of more capacity then
the balance left over capacity, then the selection shall be based on technical
capability, understanding or knowledge of the project, resource position,
qualification & experience , performance of the applicant during the interview and
social support if any extended to the village & its residents. This selection shall be
done by the following committee:
- Chief Secretary, Principal Secretary to CM, Principal Secretary Power,
Principal Secretary NRSE, Principal Secretary Finance, CMD PSPCL,
Chief Executive PEDA (Convenor).
12. A List of all eligible applicants will be displayed on PEDA website.
13. In Case the allottee is not given technical feasibility clearance by PSPCL/
Transmission line laying constraints or due to other reasons which are beyond the
control of the allottee, then the project allotment committee under NRSE policy
C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND
OWNING FARMERS.docx
2012 can consider to allow allotted Farmer to implement the project at a new site in
the state through a joint venture with other farmers.
14. The farmer can also form an SPV company after project allocation but before
signing of the IA to implement the project. Farmer will have to continuously hold
51% equity/share/ownership/stake in the project till 7 years from the date of signing
of the PPA.
15. The farmer shall enter into PPA for a period of 25 years (effective from the date of
commissioning of the project) at the net availed tariff arrived after giving discount
on the Generic tariff for solar PV projects as determined by PSERC applicable for
that year of allocation of the project. The signing of IA shall be completed in 45
days and thereafter signing of PPA will be completed in 60 days from the date of
allotment.
16. The farmer has to furnish the financial closure documents, technical feasibility
clearance and final technology selection documents within 120 days of signing of
PPA.
17. PEDA and Punjab Bureau of Investment Promotion shall facilitate the grant of
statutory clearances.
18. PEDA will forward the proposals as and when received to MNRE for extending
Excise & Customs duty benefits.
19. The farmer has to complete the project within the stipulated time as mentioned in
the allotment letter, however extension can be sought for 30 days in the First go on
payment of a fee of Rs. 5000/day/MW. And for another period of maximum 60
days but not later than 31 March on a payment of a fee of Rs.10,000/day/MW.
After which no further extension will be given and the PPA shall stand canceled as
the tariff control period expires as per CERC/ PSERC Regulations. However
incase the PSERC extends the applicability of tariff or derivers a new tariff for the
next control period the PPA will be extended accordingly.
20. The Change of Land use allowed for Agriculture/ Horticulture land for installation of
SPV shall revert back to Agriculture / Horticulture on completion of the Project
period or in the event the Project is removed from the site.
C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND
OWNING FARMERS.docx
21. Canal water connection and supply schedule shall remain as it is in the name of
the farmer.
22. In case two or more applicants setup the project in adjoining lands then the power
can be evacuated through double circuit 11KV Transmission Lines.
23. Farmer who are successful in getting project allotments shall have the option to
join together and setup a SPV company before signing of IA with controlling share
holding of 51% to be held by the allottees in the same proportion as the project
allotment capacity in the SPV company. A single IA shall be signed with PEDA and
a single PPA shall be signed with PSPCL by the SPV company for a maximum
capacity of 2.5MW/ Power can be evacuated from this project through a common
evacuation 66KV transmission line to the nearest technically feasible PSPCL sub-
station. The power evacuation and transmission shall be subject to technical
feasibility clearance by PSPCL.
24. Allottees who have projects in the same village or adjoining villages shall also have
the option to setup a common 66KV pooling sub-station for evacuation of power
from their independent projects through a common 66KV transmission line to the
nearest technically feasible PSPCL sub-station. Energy counting and metering
shall happen on the HT side of the pooling sub-station as per applicable
regulations.
25. Farmers can also operate their agriculture pumps (Both DC or AC pumps) by
taking power from these solar PV Power Plants, Which shall be treated as auxiliary
power.
26. PEDA shall give information about the scheme through print & electronic media
and will also hold interactive meets with farmers to sensitize them about the
scheme.
27. All applicable CERC/PSERC regulations shall have to be adhered to by the
allottee.
28. Other general terms and conditions will be as per NRSE Policy 2012. In case of
any conflict, NRSE Policy 2012 shall prevail.

More Related Content

What's hot

Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Gensol Engineering Limited
 
Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Headway Solar
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Harish Sharma
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIHarish Sharma
 
RFP Document for Grid Connected Solar Power Project in Chhattisgarh
RFP Document for Grid Connected Solar Power Project in ChhattisgarhRFP Document for Grid Connected Solar Power Project in Chhattisgarh
RFP Document for Grid Connected Solar Power Project in ChhattisgarhHeadway Solar
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...Harish Sharma
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanHeadway Solar
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Gurparvesh kaur
 
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...Josue Tandoum Waffo
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projectsshivraj negi
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Resurgent India
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015Headway Solar
 
20 MW Canal Top Solar RfP by PEDA
20 MW Canal Top Solar RfP by PEDA20 MW Canal Top Solar RfP by PEDA
20 MW Canal Top Solar RfP by PEDAHarish Sharma
 
UP Solar Power Policy 2013
UP Solar Power Policy 2013UP Solar Power Policy 2013
UP Solar Power Policy 2013Headway Solar
 
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...zubeditufail
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 

What's hot (20)

Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Jharkhand solar power policy 2013
Jharkhand solar power policy 2013
 
Presentation by MNRE on Solar Parks
Presentation by MNRE on Solar ParksPresentation by MNRE on Solar Parks
Presentation by MNRE on Solar Parks
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 
RFP Document for Grid Connected Solar Power Project in Chhattisgarh
RFP Document for Grid Connected Solar Power Project in ChhattisgarhRFP Document for Grid Connected Solar Power Project in Chhattisgarh
RFP Document for Grid Connected Solar Power Project in Chhattisgarh
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project Rajasthan
 
REAR_Newsletter_202204.pdf
REAR_Newsletter_202204.pdfREAR_Newsletter_202204.pdf
REAR_Newsletter_202204.pdf
 
Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )Umpp(ultra mega power plant and international bidding )
Umpp(ultra mega power plant and international bidding )
 
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...Eoi – uganda   epc assignments for kikagati hydro power project  uganda – 12 ...
Eoi – uganda epc assignments for kikagati hydro power project uganda – 12 ...
 
Ultra mega power projects
Ultra mega power projectsUltra mega power projects
Ultra mega power projects
 
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
 
Rfp 250 mw fy16 17
Rfp 250 mw fy16 17Rfp 250 mw fy16 17
Rfp 250 mw fy16 17
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015
 
20 MW Canal Top Solar RfP by PEDA
20 MW Canal Top Solar RfP by PEDA20 MW Canal Top Solar RfP by PEDA
20 MW Canal Top Solar RfP by PEDA
 
UP Solar Power Policy 2013
UP Solar Power Policy 2013UP Solar Power Policy 2013
UP Solar Power Policy 2013
 
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
Esia of 132 k v interconnection scheme loop in out from existing boc dhabeji ...
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 

Viewers also liked

RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...Harish Sharma
 
Build a solar panel at home
Build a solar panel at homeBuild a solar panel at home
Build a solar panel at homeKaren Campbell
 
Transforum Sitzung Berlin, Juni 2016 - Translators Without Borders
Transforum Sitzung Berlin, Juni 2016 - Translators Without BordersTransforum Sitzung Berlin, Juni 2016 - Translators Without Borders
Transforum Sitzung Berlin, Juni 2016 - Translators Without BordersChristian Gericke
 
Port of San Diego Public Parks (2012)
Port of San Diego Public Parks (2012)Port of San Diego Public Parks (2012)
Port of San Diego Public Parks (2012)Port of San Diego
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...Harish Sharma
 
Soltech Corporate presentation
Soltech Corporate presentationSoltech Corporate presentation
Soltech Corporate presentationsoltechindia
 
S4 oman wind energy potential anemometers 2016
S4 oman wind energy potential   anemometers 2016S4 oman wind energy potential   anemometers 2016
S4 oman wind energy potential anemometers 2016CETN
 
Solar energy sources
Solar energy sourcesSolar energy sources
Solar energy sourceskarthhik101
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaHarish Sharma
 

Viewers also liked (20)

2014 PV Performance Modeling Workshop: PV Module Characterization Methods at ...
2014 PV Performance Modeling Workshop: PV Module Characterization Methods at ...2014 PV Performance Modeling Workshop: PV Module Characterization Methods at ...
2014 PV Performance Modeling Workshop: PV Module Characterization Methods at ...
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...
 
Build a solar panel at home
Build a solar panel at homeBuild a solar panel at home
Build a solar panel at home
 
Transforum Sitzung Berlin, Juni 2016 - Translators Without Borders
Transforum Sitzung Berlin, Juni 2016 - Translators Without BordersTransforum Sitzung Berlin, Juni 2016 - Translators Without Borders
Transforum Sitzung Berlin, Juni 2016 - Translators Without Borders
 
Solar Panel
Solar PanelSolar Panel
Solar Panel
 
Port of San Diego Public Parks (2012)
Port of San Diego Public Parks (2012)Port of San Diego Public Parks (2012)
Port of San Diego Public Parks (2012)
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
 
2014 PV Reliability, Operations & Maintenance Workshop: HelioSpec by DreamQii...
2014 PV Reliability, Operations & Maintenance Workshop: HelioSpec by DreamQii...2014 PV Reliability, Operations & Maintenance Workshop: HelioSpec by DreamQii...
2014 PV Reliability, Operations & Maintenance Workshop: HelioSpec by DreamQii...
 
2014 PV Distribution System Modeling Workshop: The IEA PVPS Task 14 High pen...
2014 PV Distribution System Modeling Workshop: The IEA PVPS Task 14  High pen...2014 PV Distribution System Modeling Workshop: The IEA PVPS Task 14  High pen...
2014 PV Distribution System Modeling Workshop: The IEA PVPS Task 14 High pen...
 
2014 PV Performance Modeling Workshop: PVSim Update: Mike Anderson, SunPower ...
2014 PV Performance Modeling Workshop: PVSim Update: Mike Anderson, SunPower ...2014 PV Performance Modeling Workshop: PVSim Update: Mike Anderson, SunPower ...
2014 PV Performance Modeling Workshop: PVSim Update: Mike Anderson, SunPower ...
 
2014 PV Distribution System Modeling Workshop: DOE Solar Energy Grid Integrat...
2014 PV Distribution System Modeling Workshop: DOE Solar Energy Grid Integrat...2014 PV Distribution System Modeling Workshop: DOE Solar Energy Grid Integrat...
2014 PV Distribution System Modeling Workshop: DOE Solar Energy Grid Integrat...
 
Soltech Corporate presentation
Soltech Corporate presentationSoltech Corporate presentation
Soltech Corporate presentation
 
S4 oman wind energy potential anemometers 2016
S4 oman wind energy potential   anemometers 2016S4 oman wind energy potential   anemometers 2016
S4 oman wind energy potential anemometers 2016
 
2014 PV Performance Modeling Workshop: AE's Perspective on PV Inverter Modeli...
2014 PV Performance Modeling Workshop: AE's Perspective on PV Inverter Modeli...2014 PV Performance Modeling Workshop: AE's Perspective on PV Inverter Modeli...
2014 PV Performance Modeling Workshop: AE's Perspective on PV Inverter Modeli...
 
Dye-Sensitized Solar Cells, Portable Solar Panel, IDM8
Dye-Sensitized Solar Cells, Portable Solar Panel, IDM8Dye-Sensitized Solar Cells, Portable Solar Panel, IDM8
Dye-Sensitized Solar Cells, Portable Solar Panel, IDM8
 
Solar energy sources
Solar energy sourcesSolar energy sources
Solar energy sources
 
2014 PV Performance Modeling Workshop: SolarAnywhere: WebWeb-Accessible Irrad...
2014 PV Performance Modeling Workshop: SolarAnywhere: WebWeb-Accessible Irrad...2014 PV Performance Modeling Workshop: SolarAnywhere: WebWeb-Accessible Irrad...
2014 PV Performance Modeling Workshop: SolarAnywhere: WebWeb-Accessible Irrad...
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of Karnataka
 
FICCI Solar Energy Task Force Report on Financing Solar Energy
FICCI Solar Energy Task Force Report on Financing Solar EnergyFICCI Solar Energy Task Force Report on Financing Solar Energy
FICCI Solar Energy Task Force Report on Financing Solar Energy
 
2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...
2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...
2014 PV Reliability, Operations & Maintenance Workshop: Arizona Public Servic...
 

Similar to Solar Power Scheme for Landowning Farmers

PM_kusum_yojna.pdf
PM_kusum_yojna.pdfPM_kusum_yojna.pdf
PM_kusum_yojna.pdfbhupesh Dave
 
Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Headway Solar
 
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftHeadway Solar
 
Project & Infrastructure Financing- SPV for Solar Park
Project & Infrastructure Financing- SPV for Solar Park Project & Infrastructure Financing- SPV for Solar Park
Project & Infrastructure Financing- SPV for Solar Park Akhilesh Upadhyay
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemesPrivate Consultants
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
 
Ap solar policy 2012.
Ap solar policy 2012.Ap solar policy 2012.
Ap solar policy 2012.antastoya
 
J&K Solar policy 2010
J&K Solar policy 2010J&K Solar policy 2010
J&K Solar policy 2010Headway Solar
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftHeadway Solar
 
Andhra Pradesh solar power policy 2012
Andhra Pradesh solar power policy  2012Andhra Pradesh solar power policy  2012
Andhra Pradesh solar power policy 2012Bakul Haria
 
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...AMLAN SARKAR
 
Review permen 19 th 2016
Review permen 19 th 2016Review permen 19 th 2016
Review permen 19 th 2016Budi Supomo
 
New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012Headway Solar
 
Energy policy of PUNJAB
Energy policy of PUNJABEnergy policy of PUNJAB
Energy policy of PUNJABRahulBhatiya1
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
 

Similar to Solar Power Scheme for Landowning Farmers (20)

PM_kusum_yojna.pdf
PM_kusum_yojna.pdfPM_kusum_yojna.pdf
PM_kusum_yojna.pdf
 
Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
 
PSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptxPSP & Guidelines MOP.pptx
PSP & Guidelines MOP.pptx
 
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
 
Project & Infrastructure Financing- SPV for Solar Park
Project & Infrastructure Financing- SPV for Solar Park Project & Infrastructure Financing- SPV for Solar Park
Project & Infrastructure Financing- SPV for Solar Park
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
 
Ap solar policy 2012.
Ap solar policy 2012.Ap solar policy 2012.
Ap solar policy 2012.
 
J&K Solar policy 2010
J&K Solar policy 2010J&K Solar policy 2010
J&K Solar policy 2010
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
 
Andhra Pradesh solar power policy 2012
Andhra Pradesh solar power policy  2012Andhra Pradesh solar power policy  2012
Andhra Pradesh solar power policy 2012
 
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...
A presentation on the scheme Bangla Krishi Sech Yojona in association with Pe...
 
Review permen 19 th 2016
Review permen 19 th 2016Review permen 19 th 2016
Review permen 19 th 2016
 
New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012
 
Energy policy of PUNJAB
Energy policy of PUNJABEnergy policy of PUNJAB
Energy policy of PUNJAB
 
Solar Presentation
Solar PresentationSolar Presentation
Solar Presentation
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
 

More from Harish Sharma

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsHarish Sharma
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemHarish Sharma
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in IndiaHarish Sharma
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVHarish Sharma
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...Harish Sharma
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...Harish Sharma
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKAHarish Sharma
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Harish Sharma
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...Harish Sharma
 
IREDA-NCEF REFINANCE SCHEME
IREDA-NCEF REFINANCE SCHEMEIREDA-NCEF REFINANCE SCHEME
IREDA-NCEF REFINANCE SCHEMEHarish Sharma
 
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...Harish Sharma
 
Bid Results for procurement of 215 MW Solar Power by UPNEDA
Bid Results for procurement of 215 MW Solar Power by UPNEDABid Results for procurement of 215 MW Solar Power by UPNEDA
Bid Results for procurement of 215 MW Solar Power by UPNEDAHarish Sharma
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...Harish Sharma
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantHarish Sharma
 
150 MW Solar bid in Madha Pradesh (India) 2015
150 MW Solar bid in Madha Pradesh (India) 2015150 MW Solar bid in Madha Pradesh (India) 2015
150 MW Solar bid in Madha Pradesh (India) 2015Harish Sharma
 

More from Harish Sharma (17)

MNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting SystemsMNRE recomendations to States for the Solar Street Lighting Systems
MNRE recomendations to States for the Solar Street Lighting Systems
 
MNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC SystemMNRE Guidelines for off-grid and grid connected Solar DC System
MNRE Guidelines for off-grid and grid connected Solar DC System
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS)
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
 
IREDA-NCEF REFINANCE SCHEME
IREDA-NCEF REFINANCE SCHEMEIREDA-NCEF REFINANCE SCHEME
IREDA-NCEF REFINANCE SCHEME
 
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...
Illustration ppt for 2000 mw Tariff based competitive bidding of solar power ...
 
Bid Results for procurement of 215 MW Solar Power by UPNEDA
Bid Results for procurement of 215 MW Solar Power by UPNEDABid Results for procurement of 215 MW Solar Power by UPNEDA
Bid Results for procurement of 215 MW Solar Power by UPNEDA
 
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
RfP for 1MW CAPACITY/12000 CUM BIOGAS PER DAY USING CATTLE DUNG AT TAJPUR DAI...
 
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power PlantNet metering requirements in punjab for grid interactive rooftop SPV Power Plant
Net metering requirements in punjab for grid interactive rooftop SPV Power Plant
 
150 MW Solar bid in Madha Pradesh (India) 2015
150 MW Solar bid in Madha Pradesh (India) 2015150 MW Solar bid in Madha Pradesh (India) 2015
150 MW Solar bid in Madha Pradesh (India) 2015
 

Recently uploaded

GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxgeorgebrinton95
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckHajeJanKamps
 

Recently uploaded (20)

GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptxBanana Powder Manufacturing Plant Project Report 2024 Edition.pptx
Banana Powder Manufacturing Plant Project Report 2024 Edition.pptx
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deckPitch Deck Teardown: NOQX's $200k Pre-seed deck
Pitch Deck Teardown: NOQX's $200k Pre-seed deck
 

Solar Power Scheme for Landowning Farmers

  • 1. C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS.docx DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS Hon’ble Prime Minister of Indial has vision of 100 gigawatt (GW) solar energy by 2022, Which was reflected in the budget speech of the Hon’ble Finance Minister of India, based on which Ministry of New and Renewable Energy, Govt. Of India has increased its target to 100GW. Its benefits would stretch beyond energy security and environmental protection. It could create a million green jobs in India, where large scale unemployment is one of the top socio-economic issues. As part of the National programme, Punjab plans to achieve Solar Cap. 5400 MW by 2022. As provided in the NRSE Policy-2012 and subsequent amendment, this scheme is introduced for allocation of Solar Power Projects to the land owning farmers of the the state of Punjab. The Government of Punjab endeavors to promote solar energy projects by land owning farmers with a minimum capacity of 1MWp to a maximum capacity of 2.5 MWp (per land owning farmer) in the state for sale of power to Punjab State Power Corporation Ltd. (PSPCL) at applicable generic tariff determined by Punjab State Electricity Regulatory Commission (PSERC) on annual basis. With Solar Power Projects located closer to the agriculture loads in distribution / transmission network, distribution losses will be reduced considerably and voltage drop at peak day time load will be minimized along with power supply and power factor improvement . These small solar PV systems shall act as a micro distributed utility at farm level. The solar power generation shall be available for enabling the agriculture pump-sets loads to be operated during the daytime, thereby allowing the utility to dispatch the power so saved from their central generating station to other area. Nodal Agency PEDA shall be the nodal agency for implementation of this special scheme. Project application processing & allocation shall be with PEDA while administration of Power Purchase Agreements (PPA) shall be with PSPCL. PEDA will also facilitate the farmers regarding documentation for the projects. Capacity Target The cumulative capacity under this scheme shall be 500MW.
  • 2. C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS.docx Evacuation facilities Govt. of Punjab (GoP) shall facilitate purchase of energy generated under this scheme by PSPCL through power purchase agreements of 25 years duration. PSPCL shall be responsible for providing connectivity of the solar PV power generating station at the nearest grid sub-station with the grid and provide cable from the last H pole of the 11 KV evacuation line inside the Grid sub/station and 11 KV switchgear along with metering system in the grid. The farmer shall bear the total cost of the 11 KV line for evacuation of power from the Out Door Yard of the project to the nearest 66KV sub- station which can be got constructed by the farmer from PSPCL on deposit job work basis. Eligibility, Terms & Conditions 1. Farmer / Group of Farmers, holding agriculture land in their name for the last three years from date of issue of this scheme. If the land is transferred on succession / will basis then the time of holding of the land of the person from where land has been transferred on account of succession / Will shall be counted towards eligibility of three year time period of the applicant. 2. A group of farmers can also get together for setting up of the SPV Power Project in the land owned by the members of the group. 3. Farmer / Group of Farmers can also form a company for applying and or implementation of the project. 4. The minimum capacity is 1MWp and maximum is 2.5 MWp for each farmer/group of farmers/SPV Company. 5. Only the Farmer / Group of Farmers, owning the land in the State of Punjab, having valid and duly certified land ownership document (Jamabandi) with entry of their names are eligible to apply. The existing land use as per revenue records should be for Agriculture/Horticulture/ Farming including irrigated & non-irrigated area. 6. The applicant has to furnish the certified copy of the land ownership documents as proof of land holding of the total required land for the applied capacity. The minimum land required is 4.5 acres for 1MWp proportionately of higher capacity.
  • 3. C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS.docx 7. If the land holding is held jointly each of the joint holder is individually also eligible to apply for minimum 1MW to maximum 2.5 MW depending upon the extent of required land. Provided that Husband &Wife will be individually or jointly eligible to apply for max 2.5 MW only. 8. The following committee will scrutinize the application and verify the original documents before short listing of eligible applicants and final allottees: - - Director PEDA, Joint Director PEDA, Senior Manager Finance, Representatives of Revenue Department (Dy. Secretary), Representatives of Finance Department (Dy. Secretary), Representatives of PSPCL (Chief Engineer). 9. The application fee of Rs.50,000/- (Non refundable) shall be submitted through Draft with the printed application along with the certified copy of the ownership documents. The farmer has also to furnish a processing fee of Rs. 2,00,000/- per MW to PEDA along with application in the shape of separate demand draft. In case the farmer does not gets the allotment, the processing fee shall be refunded. 10. Allotment shall be made by the project allotment committee notified in the NRSE policy 2012. The allotment shall be based on discount given in the tariff in the first instance. 11. In case, two or more applicants are offering the same tariff of more capacity then the balance left over capacity, then the selection shall be based on technical capability, understanding or knowledge of the project, resource position, qualification & experience , performance of the applicant during the interview and social support if any extended to the village & its residents. This selection shall be done by the following committee: - Chief Secretary, Principal Secretary to CM, Principal Secretary Power, Principal Secretary NRSE, Principal Secretary Finance, CMD PSPCL, Chief Executive PEDA (Convenor). 12. A List of all eligible applicants will be displayed on PEDA website. 13. In Case the allottee is not given technical feasibility clearance by PSPCL/ Transmission line laying constraints or due to other reasons which are beyond the control of the allottee, then the project allotment committee under NRSE policy
  • 4. C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS.docx 2012 can consider to allow allotted Farmer to implement the project at a new site in the state through a joint venture with other farmers. 14. The farmer can also form an SPV company after project allocation but before signing of the IA to implement the project. Farmer will have to continuously hold 51% equity/share/ownership/stake in the project till 7 years from the date of signing of the PPA. 15. The farmer shall enter into PPA for a period of 25 years (effective from the date of commissioning of the project) at the net availed tariff arrived after giving discount on the Generic tariff for solar PV projects as determined by PSERC applicable for that year of allocation of the project. The signing of IA shall be completed in 45 days and thereafter signing of PPA will be completed in 60 days from the date of allotment. 16. The farmer has to furnish the financial closure documents, technical feasibility clearance and final technology selection documents within 120 days of signing of PPA. 17. PEDA and Punjab Bureau of Investment Promotion shall facilitate the grant of statutory clearances. 18. PEDA will forward the proposals as and when received to MNRE for extending Excise & Customs duty benefits. 19. The farmer has to complete the project within the stipulated time as mentioned in the allotment letter, however extension can be sought for 30 days in the First go on payment of a fee of Rs. 5000/day/MW. And for another period of maximum 60 days but not later than 31 March on a payment of a fee of Rs.10,000/day/MW. After which no further extension will be given and the PPA shall stand canceled as the tariff control period expires as per CERC/ PSERC Regulations. However incase the PSERC extends the applicability of tariff or derivers a new tariff for the next control period the PPA will be extended accordingly. 20. The Change of Land use allowed for Agriculture/ Horticulture land for installation of SPV shall revert back to Agriculture / Horticulture on completion of the Project period or in the event the Project is removed from the site.
  • 5. C:UsersasminDesktopupload (7)DRAFT SCHEME FOR ALLOCATION OF SOLAR POWER PROJECTS TO LAND OWNING FARMERS.docx 21. Canal water connection and supply schedule shall remain as it is in the name of the farmer. 22. In case two or more applicants setup the project in adjoining lands then the power can be evacuated through double circuit 11KV Transmission Lines. 23. Farmer who are successful in getting project allotments shall have the option to join together and setup a SPV company before signing of IA with controlling share holding of 51% to be held by the allottees in the same proportion as the project allotment capacity in the SPV company. A single IA shall be signed with PEDA and a single PPA shall be signed with PSPCL by the SPV company for a maximum capacity of 2.5MW/ Power can be evacuated from this project through a common evacuation 66KV transmission line to the nearest technically feasible PSPCL sub- station. The power evacuation and transmission shall be subject to technical feasibility clearance by PSPCL. 24. Allottees who have projects in the same village or adjoining villages shall also have the option to setup a common 66KV pooling sub-station for evacuation of power from their independent projects through a common 66KV transmission line to the nearest technically feasible PSPCL sub-station. Energy counting and metering shall happen on the HT side of the pooling sub-station as per applicable regulations. 25. Farmers can also operate their agriculture pumps (Both DC or AC pumps) by taking power from these solar PV Power Plants, Which shall be treated as auxiliary power. 26. PEDA shall give information about the scheme through print & electronic media and will also hold interactive meets with farmers to sensitize them about the scheme. 27. All applicable CERC/PSERC regulations shall have to be adhered to by the allottee. 28. Other general terms and conditions will be as per NRSE Policy 2012. In case of any conflict, NRSE Policy 2012 shall prevail.