SlideShare a Scribd company logo
Unit IV Practice Questions

Q1. A 50 MVA, 11KV unloaded generator has the following data:
     Xg0 = 0.04pu, X1 = 0.3pu, X2= 0.25pu, Xn = 0.1pu, Xf = 0.3pu. Find the fault current and the
     voltage of the healthy line if there is a DLG type of fault on the terminals of the generator which is
    maintained at 80% of the rated voltage.                                                  [2.067KA]


Q2. The given figure shows a power network with two generators connected in parallel to a transformer
     feeding a transmission line. The far end of the line is connected to an infinite bus through another
     transformer. Star point of each transformer. Generator 1 and infinite bus are solidly grounded. The
     positive, negative and zero sequence reactance of various components in per unit on a common
     base are :
                             Positive         Negative                  Zero
        Generator 1           0.15              0.15                    0.08
        Generator 2           0.25              0.25                0.06(neutral
                                                                      isolated)
        Each                  0.15              0.15                    0.15
        Transformer
        Infinite Bus          0.15              0.15                   0.05
        Line                  0.20              0.20                   0.40
With both generators and infinite bus operating at 1.0 pu voltage on no load, a line-to-ground fault occurs
at one of the terminals of the star-connected winding of the transformer A.
      Calculate the currents flowing in the fault.




                                                                                    [-j6.74pu]

Q3. For a power system shown in figure below, find the fault current at point F for a SLG type of fault,
    assuming that the pre- fault current in the circuit is zero :




   The rating of the components are:
   machines(generator as well as motor) :       1200KVA, 600V, X1 = X2 = 10% and X0 = 5%
   Transformers : 1200 KVA, 600/3300V and leakage reactance is 5%
Transmission lines : Reactance is 20% on a base of 1200KVA and 3300V

Q4. Determine the fault current, the bus voltages and the line currents during the fault when a 3φ fault

     occurs with a fault impedance of Z f = j0.16 pu. The negative sequence reactance is same as positive

     sequence reactance mentioned in the diagram, the zero sequence reactance is 5% and neutral

     reactance is 4% for both the machines.




Q5. For the power system shown in the figure, there is a DLG fault at the point F. Calculate the fault
     current by taking a base of 100MVA and 11KV in the generator circuit. Rating of generator is
    100MVA, 11KV, X1=20%, X2=15% and X0=10%.the voltage at the load point is 60KV prior to the fault.
    The neutral reactance of the generator is 5% on its rating.




.

                                                                                   [3.255< 97deg pu]

More Related Content

What's hot

Unit4questions
Unit4questionsUnit4questions
Unit4questions
Abha Tripathi
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
Abha Tripathi
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
Abha Tripathi
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
Abha Tripathi
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
Abha Tripathi
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
Abha Tripathi
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
guest67994e4
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
BinodKumarSahu5
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
Abha Tripathi
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questionsguest4ca222
 
electrical objective
electrical objectiveelectrical objective
electrical objective
Kalees Pandiyan
 
EEP303: Exp5
EEP303: Exp5EEP303: Exp5
EEP303: Exp5
Umang Gupta
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objective
maheshwareshwar
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protection
Hakim Futra
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
karikalan123
 
EEP301: Transducer and instrumentation
EEP301: Transducer and instrumentationEEP301: Transducer and instrumentation
EEP301: Transducer and instrumentation
Umang Gupta
 
Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209
Govt. College of Engineering, Kannur
 

What's hot (20)

Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questions
 
EE551_HW6
EE551_HW6EE551_HW6
EE551_HW6
 
electrical objective
electrical objectiveelectrical objective
electrical objective
 
EEP303: Exp5
EEP303: Exp5EEP303: Exp5
EEP303: Exp5
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objective
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protection
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
EEP301: Transducer and instrumentation
EEP301: Transducer and instrumentationEEP301: Transducer and instrumentation
EEP301: Transducer and instrumentation
 
Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209
 
T8 1 ph-tr
T8 1 ph-trT8 1 ph-tr
T8 1 ph-tr
 

Viewers also liked

Unit1 8
Unit1 8Unit1 8
Unit1 8
budashow1
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagramnanonon
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
Mohammed TAMALI
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasico
paulelrapido
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysisdivyanshuprakashrock
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
Hari Kumar
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
kirkusawi
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedure
Mustafa Ismail
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
PRABHAHARAN429
 
Problemas trifasicos
Problemas trifasicos Problemas trifasicos
Problemas trifasicos
Luchetti David Urcia
 

Viewers also liked (12)

Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasico
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedure
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
 
Problemas trifasicos
Problemas trifasicos Problemas trifasicos
Problemas trifasicos
 

Similar to Questions unit4

Fault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdfFault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdf
Saravanan A
 
Single phase transformer
Single phase transformerSingle phase transformer
Single phase transformer
Jayaraju Gaddala
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculations
michaeljmack
 
Mini project submission
Mini project submissionMini project submission
Mini project submissionAkshay Ajay
 
P
PP
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
ssuser99d6551
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power system
Balaram Das
 
06 -synchronous_machine_parameter_measurement
06  -synchronous_machine_parameter_measurement06  -synchronous_machine_parameter_measurement
06 -synchronous_machine_parameter_measurement
Ellixies Fair
 
Per unitcalculations
Per unitcalculationsPer unitcalculations
Per unitcalculations
Anuradha Chathuranga
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
Abinaya Saraswathy T
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
Isham Rashik
 
UNIT-3-PPT (2).pptx
UNIT-3-PPT (2).pptxUNIT-3-PPT (2).pptx
UNIT-3-PPT (2).pptx
Karthik Kathan
 
E&e lab manual
E&e lab manualE&e lab manual
E&e lab manual
Sugunakar Mamidala
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdf
ShanmukhSaiR
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)efrataderebe
 
Transformer Course Lab.pdf
Transformer Course Lab.pdfTransformer Course Lab.pdf
Transformer Course Lab.pdf
smuftah
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
michaeljmack
 
Micro-controller based Automatic Power Factor Correction System Report
Micro-controller based Automatic Power Factor Correction System ReportMicro-controller based Automatic Power Factor Correction System Report
Micro-controller based Automatic Power Factor Correction System Report
Theory to Practical
 
Unit7-DC_Motors.ppt
Unit7-DC_Motors.pptUnit7-DC_Motors.ppt
Unit7-DC_Motors.ppt
NAVNEETGUPTA251
 

Similar to Questions unit4 (20)

Fault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdfFault Analysis using Z Bus..pdf
Fault Analysis using Z Bus..pdf
 
Single phase transformer
Single phase transformerSingle phase transformer
Single phase transformer
 
EE101 Lab4 Guillemaud
EE101 Lab4 GuillemaudEE101 Lab4 Guillemaud
EE101 Lab4 Guillemaud
 
Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculations
 
Mini project submission
Mini project submissionMini project submission
Mini project submission
 
P
PP
P
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power system
 
06 -synchronous_machine_parameter_measurement
06  -synchronous_machine_parameter_measurement06  -synchronous_machine_parameter_measurement
06 -synchronous_machine_parameter_measurement
 
Per unitcalculations
Per unitcalculationsPer unitcalculations
Per unitcalculations
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
 
UNIT-3-PPT (2).pptx
UNIT-3-PPT (2).pptxUNIT-3-PPT (2).pptx
UNIT-3-PPT (2).pptx
 
E&e lab manual
E&e lab manualE&e lab manual
E&e lab manual
 
symmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdfsymmetrical_fault_analysis.pdf
symmetrical_fault_analysis.pdf
 
Assignment & solution (selected)
Assignment & solution (selected)Assignment & solution (selected)
Assignment & solution (selected)
 
Transformer Course Lab.pdf
Transformer Course Lab.pdfTransformer Course Lab.pdf
Transformer Course Lab.pdf
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Micro-controller based Automatic Power Factor Correction System Report
Micro-controller based Automatic Power Factor Correction System ReportMicro-controller based Automatic Power Factor Correction System Report
Micro-controller based Automatic Power Factor Correction System Report
 
Unit7-DC_Motors.ppt
Unit7-DC_Motors.pptUnit7-DC_Motors.ppt
Unit7-DC_Motors.ppt
 

More from Abha Tripathi

Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
Abha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
Abha Tripathi
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
Abha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
Abha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
Abha Tripathi
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Abha Tripathi
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
Abha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
Abha Tripathi
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
Abha Tripathi
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
Abha Tripathi
 

More from Abha Tripathi (14)

Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Recently uploaded

Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 

Recently uploaded (20)

Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 

Questions unit4

  • 1. Unit IV Practice Questions Q1. A 50 MVA, 11KV unloaded generator has the following data: Xg0 = 0.04pu, X1 = 0.3pu, X2= 0.25pu, Xn = 0.1pu, Xf = 0.3pu. Find the fault current and the voltage of the healthy line if there is a DLG type of fault on the terminals of the generator which is maintained at 80% of the rated voltage. [2.067KA] Q2. The given figure shows a power network with two generators connected in parallel to a transformer feeding a transmission line. The far end of the line is connected to an infinite bus through another transformer. Star point of each transformer. Generator 1 and infinite bus are solidly grounded. The positive, negative and zero sequence reactance of various components in per unit on a common base are : Positive Negative Zero Generator 1 0.15 0.15 0.08 Generator 2 0.25 0.25 0.06(neutral isolated) Each 0.15 0.15 0.15 Transformer Infinite Bus 0.15 0.15 0.05 Line 0.20 0.20 0.40 With both generators and infinite bus operating at 1.0 pu voltage on no load, a line-to-ground fault occurs at one of the terminals of the star-connected winding of the transformer A. Calculate the currents flowing in the fault. [-j6.74pu] Q3. For a power system shown in figure below, find the fault current at point F for a SLG type of fault, assuming that the pre- fault current in the circuit is zero : The rating of the components are: machines(generator as well as motor) : 1200KVA, 600V, X1 = X2 = 10% and X0 = 5% Transformers : 1200 KVA, 600/3300V and leakage reactance is 5%
  • 2. Transmission lines : Reactance is 20% on a base of 1200KVA and 3300V Q4. Determine the fault current, the bus voltages and the line currents during the fault when a 3φ fault occurs with a fault impedance of Z f = j0.16 pu. The negative sequence reactance is same as positive sequence reactance mentioned in the diagram, the zero sequence reactance is 5% and neutral reactance is 4% for both the machines. Q5. For the power system shown in the figure, there is a DLG fault at the point F. Calculate the fault current by taking a base of 100MVA and 11KV in the generator circuit. Rating of generator is 100MVA, 11KV, X1=20%, X2=15% and X0=10%.the voltage at the load point is 60KV prior to the fault. The neutral reactance of the generator is 5% on its rating. . [3.255< 97deg pu]