SlideShare a Scribd company logo
Some Solved Questions
Q1. Draw the pu impedance diagram for the power system shown in the figure . Neglect
resistance , and use a base of 100 MV A , 230 kV in 50 Ω line. The ratings of the
generator , motor and transformers are : Generator 40 MV A, 25 kV, X” = 20%
                      Motor 50 MV A, 11 kV, X” = 30%
                      Y-Y transformer, 40 MV A, 33 Y-220 Y kV, X = 15%
                      Y-Δ transformer, 30 MV A, 11 Δ-220 Y kV, X = 15%




 Solution: The rectangular blocks are circuit breakers and it is connected at the beginning
and end of each m/c or transformer or transmission line to protect it from high current
due to faults. We don’t have to bother about it. Just neglect it – do not get confused.
Step 1: Identifying the circuits: Let us name it as ckt.1 , ckt(trans line) and ckt 2.
Step 2 : Marking the new bases for each of the 3 ckts.
Ckt(trans line): we should start from this as this is what is given in the question.
And it is 100MVA and 230KV.
Ckt 1: we know the base voltage on the right side of transformer but not left side. The
base on left side (ckt 1) depends on the transformation ratio of Y- Y transformer which is
coming into picture when we are going from transmission line to generator ckt.
Hence VB(ckt 1) / VB(ckt trans line) = 33/220 (since the higher voltage side is always connected
towards the transmission line side)
VB(ckt 1) = 34.5KV
Ckt 2 : Similarly
VB(ckt trans line) / VB(ckt 2) = 220/11
VB(ckt 2) = 11.5KV
Step 3 : Calculating the new reactances
Generator: Xg = 0.2 x (100/40) x (25/34.5)2 = 0.2625pu
Transformer (Y-Y) on the primary side = 0.15 x (100/40) x (33/34.5)2 = 0.343pu
                      on the secondary side = 0.15 x (100/40) x (220/230)2 = 0.343pu
And we notice that whether we do calculations on primary or secondary side, the pu
value does not change for a transformer.
Transformer (Y- Δ) on the primary side = 0.15 x (100/30) x (220/230)2 = 0.457pu
                      on the secondary side = 0.15 x (100/30) x (11/11.5)2 = 0.457pu
Motor: 0.3 x (100/50) x (11/11.5)2 = 0.55pu
Transmission line: Actual/ base impedance(since the actual value is given, we can
directly devide by the base value and get the pu value)
Base impedance in the transmission line circuit = 2302/ 100 = 529 ohms
Hence X (line) = 50/529 = 0.0945pu
Q2.The Figure shows the schematic diagram of a radial transmission system. The ratings
and reactances of the various components are shown therein. A load of 60 MW at 0.9
power factor lagging is tapped from the 66 KV substation which is to be maintained at 60
kV . Calculate the terminal voltage of the synchronous machine . represent the
transmission line and the transformers by series reactances only.




 60 MW and not 60MV
Solution: Let 100 MVA and 11KV be the base in Generator circuit.
Accordingly the base in transmission line will be 100 MVA, 220 KV.
And in the load circuit, it is 100 MVA and 66KV.
Xt1 = j0.1
Xt2 = j0.08
X line = 150/(2202/100) = j0.31
Iload = 60,000/(sqrt 3 x 60x 0.9) = 641.5A
Base current = 100,000/ (sqrt 3 x 66) = 874.77A
Iload (pu) = 641.5/874.77 = 0.733(-25.84 )A
                                        0


V2(pu) = 60/66 = 0.91(0 )
                        0
V1 = V2 + Iload(equivalent Reactance)
   = 0.91(0 ) + 0.733(-25.84 ) x (j0.1 + j0.31 + j0.08)
            0                0


   = 1.11(16.85 )   0


Actual V1 = 1.11 x 11 = 12.2 KV


Q3..A synchronous generator is rated 60 MVA , 11 kV. It has resistance R = 0.1 pu and
                                                                             a

X = 1.65 pu. It is feeding into an infinite bus bar at 11 kV delivering a current 3.15 kA at
 d


0.9 pf lagging.
(a) Determine E and angle δ.
                f


(b) Draw a phasor diagram for this operation.
(c) Bus bar voltage falls to 10 kV while the mechanical power input generator and its
excitation remains unchanged. What is the value and pf of the current delivered to the
bus. In this case assume the generator resistance to be negligible.

Solution:
Choose a base of 60MVA, 11kV(as the base MVA to be chosen is not given, we have the
liberty to choose the base same as the rating of the m/c.).
The bus bar voltage is to be maintained at 11KV.
When converted to p.u., it is 11/11(Actual / base) = 1.0(0 )pu
                                                          0


Base current = 60/{sqrt(3)x 11} = 3.15 KA
Actual current = 3.15KA
Hence pu Ia = 1(-cos-1 0.9) = 1(-25.84 )pu
                                       0


    (a) Ef = Vt + Ia(Ra + jIaXa) = 1.81+j1.438 = 2.312(38.47 )    0


        Hence Actual Ef = 11x2.312 = 25.43 and δ = 38.47 leading
                                                              0




     (b)




    (c) Vt = 10/11 = 0.91pu
        Mechanical power input is the input to prime mover(steam) which changes the
active power. Hence P = same as above = Vt x Ia x pf = 1 x 1 x 0.9 = 0.9pu
And P = |Vt| |Ef| sin δ/ Xa (Ef or Excitation is also not changing)
Which gives us δ = 40   0


Hence Ia = (Ef – Vt )/jXa = 1.0436(-30.35)pu
Therefore actual current = 1.0436x3.15 = 3.28 KA and pf = cos30.35 = 0.863 lagging

Q4.Three impedances of 5-j10, 6+j5 and 3+ j15 ohms are connected in star to A, B and C
lines of a 3300 V, 3 phase, 3 wire supply. The phase sequence is ABC. Calculate the line
current Ia.
Solution: this is a case of unbalanced 3 phase star connected load supplied from a
balanced 3 phase supply.
There is 3 wire and hence the phase voltages cannot be taken as balanced(since there is
no neutral connection between supply and load).
Vab = 3300(0 )0


Vbc = 3300(-120 ) 0


Let Va, Vb and Vc be the phase voltages.
Van = (5 – j10)Ia = (5-j10)(Ia1+Ia2+Ia0) = (5-j10)(Ia1+Ia2)                          (1)
Since Ia + Ib +Ic = In = 3Ia0 = 0 , hence Ia0 = 0(there is no neutral wire and hence zero
sequence currents cannot can flow.)
Vbn = (6+j5)Ib = (6+j5)(Ib1+Ib2) = (6+j5)(a2Ia1 + aIa2)                              (2)
                                                           2
Vcn = (3+j15)Ic = (3+j15)(Ic1+Ic2) == (3+j15)(aIa1 + a Ia2)                          (3)
    (1) – (2) gives us
    Van –Vbn = Vab = 3300(0) = (3.67 – j2.3)Ia1 + (12.33 – j12.7)Ia2             (4)
    (2) – (3) gives us
    Vbn – Vcn = Vbc = 3300(-120 ) = (15.8 – j2.8)Ia1 – (18.84 – j12.8)Ia2
                                     0
                                                                                         (5)
Solving (4) and (5) for Ia1 and Ia2,
Ia1 = 134-j65
Ia2 = 95 +j141
Hence Ia = Ia1+ Ia2 = 241(-18.4 ) A
                                 0

More Related Content

What's hot

Unit4questions
Unit4questionsUnit4questions
Unit4questions
Abha Tripathi
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
Forward2025
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
MUET SZAB Campus Khairpur Mir's Sindh Pakistan
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
Nitish NIT
 
Unsymmetrical fault in transmission line
Unsymmetrical fault in transmission lineUnsymmetrical fault in transmission line
Unsymmetrical fault in transmission line
vishalgohel12195
 
Per unit system
Per unit systemPer unit system
Per unit system
Muhammad Kamran Shaikh
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
Revathi Subramaniam
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
firaoltemesgen1
 
Static Relay Presentation
Static Relay PresentationStatic Relay Presentation
Static Relay Presentation
Rohitkmt
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
sneh pratap singh
 
Per unit representation
Per unit representationPer unit representation
Per unit representation
Md. Rimon Mia
 
Buck Boost Converter with simulation model.pdf
Buck Boost Converter with simulation model.pdfBuck Boost Converter with simulation model.pdf
Buck Boost Converter with simulation model.pdf
Indian Institute of Technology Guwahati
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
karikalan123
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
budashow1
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power system
Abrar Ahmed
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
firaoltemesgen1
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
Preet_patel
 
Introduction to reactive power control in electrical power
Introduction to reactive power control in electrical powerIntroduction to reactive power control in electrical power
Introduction to reactive power control in electrical power
Dr.Raja R
 
CONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCYCONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCY
Power System Operation
 

What's hot (20)

Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
Unsymmetrical fault in transmission line
Unsymmetrical fault in transmission lineUnsymmetrical fault in transmission line
Unsymmetrical fault in transmission line
 
Per unit system
Per unit systemPer unit system
Per unit system
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
Static Relay Presentation
Static Relay PresentationStatic Relay Presentation
Static Relay Presentation
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
Per unit representation
Per unit representationPer unit representation
Per unit representation
 
Buck Boost Converter with simulation model.pdf
Buck Boost Converter with simulation model.pdfBuck Boost Converter with simulation model.pdf
Buck Boost Converter with simulation model.pdf
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Unit commitment in power system
Unit commitment in power systemUnit commitment in power system
Unit commitment in power system
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
Power quality ppt
Power quality pptPower quality ppt
Power quality ppt
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
 
Introduction to reactive power control in electrical power
Introduction to reactive power control in electrical powerIntroduction to reactive power control in electrical power
Introduction to reactive power control in electrical power
 
CONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCYCONTROL OF ACTIVE POWER AND FREQUENCY
CONTROL OF ACTIVE POWER AND FREQUENCY
 

Viewers also liked

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
Abha Tripathi
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
Abha Tripathi
 
Practice questions
Practice questionsPractice questions
Practice questions
Abha Tripathi
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Abha Tripathi
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
Abha Tripathi
 
Swing equation
Swing equationSwing equation
Swing equation
Luis Portugal
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
Shikhar Sodhani
 

Viewers also liked (8)

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Solutions -unit4
Solutions  -unit4Solutions  -unit4
Solutions -unit4
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Swing equation
Swing equationSwing equation
Swing equation
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 

Similar to Unit1 And 2 Sample Solutions

Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
Isham Rashik
 
ECE4762011_Lect14.ppt
ECE4762011_Lect14.pptECE4762011_Lect14.ppt
ECE4762011_Lect14.ppt
Godspower Bruno, GMNSE
 
ECE4762011_Lect14.ppt
ECE4762011_Lect14.pptECE4762011_Lect14.ppt
ECE4762011_Lect14.ppt
Godspower Bruno, GMNSE
 
powerflowproblem.ppt
powerflowproblem.pptpowerflowproblem.ppt
powerflowproblem.ppt
Godspower Bruno, GMNSE
 
Electronics and communication engineering_Lect14.ppt
Electronics and communication engineering_Lect14.pptElectronics and communication engineering_Lect14.ppt
Electronics and communication engineering_Lect14.ppt
muhammadzaid733820
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
BinodKumarSahu5
 
ECNG 6503 #4
ECNG 6503 #4ECNG 6503 #4
ECNG 6503 #4
Chandrabhan Sharma
 
Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14
BinodKumarSahu5
 
Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14
BinodKumarSahu5
 
Lecture 12
Lecture 12Lecture 12
Lecture 12
Forward2025
 
Lecture 13
Lecture 13Lecture 13
Lecture 13
Forward2025
 
UNIT-III complex reactive three phase.ppt
UNIT-III complex reactive three phase.pptUNIT-III complex reactive three phase.ppt
UNIT-III complex reactive three phase.ppt
Abinaya Saraswathy T
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questionsguest4ca222
 
Lecture 2
Lecture 2Lecture 2
Lecture 2
Forward2025
 
Stability with analysis and psa and load flow.ppt
Stability with analysis and psa and load flow.pptStability with analysis and psa and load flow.ppt
Stability with analysis and psa and load flow.ppt
Zahid Yousaf
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301Ravi Anand
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
Abha Tripathi
 
Multi phase Star Rectifier
Multi phase Star Rectifier Multi phase Star Rectifier
Multi phase Star Rectifier
ZunAib Ali
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09
Shah Zaib
 

Similar to Unit1 And 2 Sample Solutions (20)

Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
 
ECE4762011_Lect14.ppt
ECE4762011_Lect14.pptECE4762011_Lect14.ppt
ECE4762011_Lect14.ppt
 
ECE4762011_Lect14.ppt
ECE4762011_Lect14.pptECE4762011_Lect14.ppt
ECE4762011_Lect14.ppt
 
powerflowproblem.ppt
powerflowproblem.pptpowerflowproblem.ppt
powerflowproblem.ppt
 
Electronics and communication engineering_Lect14.ppt
Electronics and communication engineering_Lect14.pptElectronics and communication engineering_Lect14.ppt
Electronics and communication engineering_Lect14.ppt
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
 
Report_AKbar_PDF
Report_AKbar_PDFReport_AKbar_PDF
Report_AKbar_PDF
 
ECNG 6503 #4
ECNG 6503 #4ECNG 6503 #4
ECNG 6503 #4
 
Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14
 
Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14Eet3082 binod kumar sahu lecturer_14
Eet3082 binod kumar sahu lecturer_14
 
Lecture 12
Lecture 12Lecture 12
Lecture 12
 
Lecture 13
Lecture 13Lecture 13
Lecture 13
 
UNIT-III complex reactive three phase.ppt
UNIT-III complex reactive three phase.pptUNIT-III complex reactive three phase.ppt
UNIT-III complex reactive three phase.ppt
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questions
 
Lecture 2
Lecture 2Lecture 2
Lecture 2
 
Stability with analysis and psa and load flow.ppt
Stability with analysis and psa and load flow.pptStability with analysis and psa and load flow.ppt
Stability with analysis and psa and load flow.ppt
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Multi phase Star Rectifier
Multi phase Star Rectifier Multi phase Star Rectifier
Multi phase Star Rectifier
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09
 

More from Abha Tripathi

Questions unit4
Questions unit4Questions unit4
Questions unit4
Abha Tripathi
 
Questions unit3
Questions unit3Questions unit3
Questions unit3
Abha Tripathi
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutionsAbha Tripathi
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
Abha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
Abha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
Abha Tripathi
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
Abha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
Abha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
Abha Tripathi
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
Abha Tripathi
 
Unit v
Unit vUnit v
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
Abha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
Abha Tripathi
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
Abha Tripathi
 

More from Abha Tripathi (20)

Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Unit1questions
Unit1questionsUnit1questions
Unit1questions
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Unit v
Unit vUnit v
Unit v
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 

Recently uploaded

What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 

Recently uploaded (20)

What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 

Unit1 And 2 Sample Solutions

  • 1. Some Solved Questions Q1. Draw the pu impedance diagram for the power system shown in the figure . Neglect resistance , and use a base of 100 MV A , 230 kV in 50 Ω line. The ratings of the generator , motor and transformers are : Generator 40 MV A, 25 kV, X” = 20% Motor 50 MV A, 11 kV, X” = 30% Y-Y transformer, 40 MV A, 33 Y-220 Y kV, X = 15% Y-Δ transformer, 30 MV A, 11 Δ-220 Y kV, X = 15% Solution: The rectangular blocks are circuit breakers and it is connected at the beginning and end of each m/c or transformer or transmission line to protect it from high current due to faults. We don’t have to bother about it. Just neglect it – do not get confused. Step 1: Identifying the circuits: Let us name it as ckt.1 , ckt(trans line) and ckt 2. Step 2 : Marking the new bases for each of the 3 ckts. Ckt(trans line): we should start from this as this is what is given in the question. And it is 100MVA and 230KV. Ckt 1: we know the base voltage on the right side of transformer but not left side. The base on left side (ckt 1) depends on the transformation ratio of Y- Y transformer which is coming into picture when we are going from transmission line to generator ckt. Hence VB(ckt 1) / VB(ckt trans line) = 33/220 (since the higher voltage side is always connected towards the transmission line side) VB(ckt 1) = 34.5KV Ckt 2 : Similarly VB(ckt trans line) / VB(ckt 2) = 220/11 VB(ckt 2) = 11.5KV Step 3 : Calculating the new reactances Generator: Xg = 0.2 x (100/40) x (25/34.5)2 = 0.2625pu Transformer (Y-Y) on the primary side = 0.15 x (100/40) x (33/34.5)2 = 0.343pu on the secondary side = 0.15 x (100/40) x (220/230)2 = 0.343pu And we notice that whether we do calculations on primary or secondary side, the pu value does not change for a transformer. Transformer (Y- Δ) on the primary side = 0.15 x (100/30) x (220/230)2 = 0.457pu on the secondary side = 0.15 x (100/30) x (11/11.5)2 = 0.457pu Motor: 0.3 x (100/50) x (11/11.5)2 = 0.55pu Transmission line: Actual/ base impedance(since the actual value is given, we can directly devide by the base value and get the pu value) Base impedance in the transmission line circuit = 2302/ 100 = 529 ohms Hence X (line) = 50/529 = 0.0945pu
  • 2. Q2.The Figure shows the schematic diagram of a radial transmission system. The ratings and reactances of the various components are shown therein. A load of 60 MW at 0.9 power factor lagging is tapped from the 66 KV substation which is to be maintained at 60 kV . Calculate the terminal voltage of the synchronous machine . represent the transmission line and the transformers by series reactances only. 60 MW and not 60MV Solution: Let 100 MVA and 11KV be the base in Generator circuit. Accordingly the base in transmission line will be 100 MVA, 220 KV. And in the load circuit, it is 100 MVA and 66KV. Xt1 = j0.1 Xt2 = j0.08 X line = 150/(2202/100) = j0.31 Iload = 60,000/(sqrt 3 x 60x 0.9) = 641.5A Base current = 100,000/ (sqrt 3 x 66) = 874.77A Iload (pu) = 641.5/874.77 = 0.733(-25.84 )A 0 V2(pu) = 60/66 = 0.91(0 ) 0
  • 3. V1 = V2 + Iload(equivalent Reactance) = 0.91(0 ) + 0.733(-25.84 ) x (j0.1 + j0.31 + j0.08) 0 0 = 1.11(16.85 ) 0 Actual V1 = 1.11 x 11 = 12.2 KV Q3..A synchronous generator is rated 60 MVA , 11 kV. It has resistance R = 0.1 pu and a X = 1.65 pu. It is feeding into an infinite bus bar at 11 kV delivering a current 3.15 kA at d 0.9 pf lagging. (a) Determine E and angle δ. f (b) Draw a phasor diagram for this operation. (c) Bus bar voltage falls to 10 kV while the mechanical power input generator and its excitation remains unchanged. What is the value and pf of the current delivered to the bus. In this case assume the generator resistance to be negligible. Solution: Choose a base of 60MVA, 11kV(as the base MVA to be chosen is not given, we have the liberty to choose the base same as the rating of the m/c.). The bus bar voltage is to be maintained at 11KV. When converted to p.u., it is 11/11(Actual / base) = 1.0(0 )pu 0 Base current = 60/{sqrt(3)x 11} = 3.15 KA Actual current = 3.15KA Hence pu Ia = 1(-cos-1 0.9) = 1(-25.84 )pu 0 (a) Ef = Vt + Ia(Ra + jIaXa) = 1.81+j1.438 = 2.312(38.47 ) 0 Hence Actual Ef = 11x2.312 = 25.43 and δ = 38.47 leading 0 (b) (c) Vt = 10/11 = 0.91pu Mechanical power input is the input to prime mover(steam) which changes the active power. Hence P = same as above = Vt x Ia x pf = 1 x 1 x 0.9 = 0.9pu And P = |Vt| |Ef| sin δ/ Xa (Ef or Excitation is also not changing) Which gives us δ = 40 0 Hence Ia = (Ef – Vt )/jXa = 1.0436(-30.35)pu
  • 4. Therefore actual current = 1.0436x3.15 = 3.28 KA and pf = cos30.35 = 0.863 lagging Q4.Three impedances of 5-j10, 6+j5 and 3+ j15 ohms are connected in star to A, B and C lines of a 3300 V, 3 phase, 3 wire supply. The phase sequence is ABC. Calculate the line current Ia. Solution: this is a case of unbalanced 3 phase star connected load supplied from a balanced 3 phase supply. There is 3 wire and hence the phase voltages cannot be taken as balanced(since there is no neutral connection between supply and load). Vab = 3300(0 )0 Vbc = 3300(-120 ) 0 Let Va, Vb and Vc be the phase voltages. Van = (5 – j10)Ia = (5-j10)(Ia1+Ia2+Ia0) = (5-j10)(Ia1+Ia2) (1) Since Ia + Ib +Ic = In = 3Ia0 = 0 , hence Ia0 = 0(there is no neutral wire and hence zero sequence currents cannot can flow.) Vbn = (6+j5)Ib = (6+j5)(Ib1+Ib2) = (6+j5)(a2Ia1 + aIa2) (2) 2 Vcn = (3+j15)Ic = (3+j15)(Ic1+Ic2) == (3+j15)(aIa1 + a Ia2) (3) (1) – (2) gives us Van –Vbn = Vab = 3300(0) = (3.67 – j2.3)Ia1 + (12.33 – j12.7)Ia2 (4) (2) – (3) gives us Vbn – Vcn = Vbc = 3300(-120 ) = (15.8 – j2.8)Ia1 – (18.84 – j12.8)Ia2 0 (5) Solving (4) and (5) for Ia1 and Ia2, Ia1 = 134-j65 Ia2 = 95 +j141 Hence Ia = Ia1+ Ia2 = 241(-18.4 ) A 0