The document discusses the Public Procurement Regularity Authority (PPRA) of Pakistan. It provides background on the need for procurement reforms that led to the establishment of PPRA in 2002. It outlines PPRA's functions of improving governance and transparency in public procurement. It also describes PPRA's legal framework and the public procurement rules and regulations it has established. The document then provides details on the public procurement process and cycle in Pakistan according to PPRA's rules and guidelines.
Pre Qualification Disqualification as per PPRA Rules 2004.pptxFayyaz Khan
Pre qualification , qualification and disqualification as per PPRA Rules 2004 of Pakistan.
Fell free to contact me for guidance in Public Procurement Rules 2004 and its procedures etc
PPRA rules 2004, Rules relating to Procurement by procuring agencies i.e. Institutions coming under the Federal Government. Guidelines for procurement. Topic relating to commercial functions of Government's procurement agencies
Pre Qualification Disqualification as per PPRA Rules 2004.pptxFayyaz Khan
Pre qualification , qualification and disqualification as per PPRA Rules 2004 of Pakistan.
Fell free to contact me for guidance in Public Procurement Rules 2004 and its procedures etc
PPRA rules 2004, Rules relating to Procurement by procuring agencies i.e. Institutions coming under the Federal Government. Guidelines for procurement. Topic relating to commercial functions of Government's procurement agencies
Public procurement is the purchase by governments of goods, services and works and accounts for 13% of GDP in OECD member countries. It is the government activity most vulnerable to waste, fraud and corruption. Integrity in public procurement is essential in maintaining citizens’ trust in government. More information at www.oecd.org/gov/ethics/procurement
Melanie Ffrench - Senior Legal Officer, CSME, CARICOM Single Market and Economy Unit - delivered this presentation at the Jamaica Chamber of Commerce 2016 Procurement Seminar during the section dedicated to The CARICOM Market
Public procurement is the purchase by governments of goods, services and works and accounts for 13% of GDP in OECD member countries. It is the government activity most vulnerable to waste, fraud and corruption. Integrity in public procurement is essential in maintaining citizens’ trust in government. More information at www.oecd.org/gov/ethics/procurement
Melanie Ffrench - Senior Legal Officer, CSME, CARICOM Single Market and Economy Unit - delivered this presentation at the Jamaica Chamber of Commerce 2016 Procurement Seminar during the section dedicated to The CARICOM Market
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Water billing management system project report.pdfKamal Acharya
Our project entitled “Water Billing Management System” aims is to generate Water bill with all the charges and penalty. Manual system that is employed is extremely laborious and quite inadequate. It only makes the process more difficult and hard.
The aim of our project is to develop a system that is meant to partially computerize the work performed in the Water Board like generating monthly Water bill, record of consuming unit of water, store record of the customer and previous unpaid record.
We used HTML/PHP as front end and MYSQL as back end for developing our project. HTML is primarily a visual design environment. We can create a android application by designing the form and that make up the user interface. Adding android application code to the form and the objects such as buttons and text boxes on them and adding any required support code in additional modular.
MySQL is free open source database that facilitates the effective management of the databases by connecting them to the software. It is a stable ,reliable and the powerful solution with the advanced features and advantages which are as follows: Data Security.MySQL is free open source database that facilitates the effective management of the databases by connecting them to the software.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSveerababupersonal22
It consists of cw radar and fmcw radar ,range measurement,if amplifier and fmcw altimeterThe CW radar operates using continuous wave transmission, while the FMCW radar employs frequency-modulated continuous wave technology. Range measurement is a crucial aspect of radar systems, providing information about the distance to a target. The IF amplifier plays a key role in signal processing, amplifying intermediate frequency signals for further analysis. The FMCW altimeter utilizes frequency-modulated continuous wave technology to accurately measure altitude above a reference point.
The Internet of Things (IoT) is a revolutionary concept that connects everyday objects and devices to the internet, enabling them to communicate, collect, and exchange data. Imagine a world where your refrigerator notifies you when you’re running low on groceries, or streetlights adjust their brightness based on traffic patterns – that’s the power of IoT. In essence, IoT transforms ordinary objects into smart, interconnected devices, creating a network of endless possibilities.
Here is a blog on the role of electrical and electronics engineers in IOT. Let's dig in!!!!
For more such content visit: https://nttftrg.com/
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
2. INTRODUCTION
Public Procurement Regularity Authority (PPRA) is an autonomous body
endowed with the responsibility of framing rules, prescribing regulation and
procedures for public procurements by Federal Government owned public
sector organizations.
Need for Procurement Reforms
General Financial Rules (issued 1951/2nd edition 1979).
Purchase Manual of Department of Supplies and Disposals, under MOIP.
Delegation of Powers to Ministers.
Autonomous Bodies had their own rules.
Various Circulars of Ministry of Finance.
3. Functions of PPRA
To improve governance, transparency, accountability and quality of public
procurement.
To supervise the application and implementation of relevant laws, rules,
policies and procedures.
To recommend revision/formulation of laws, rules and policies related to
public procurement.
To formulate regulations on public procurement.
To monitor performance of procuring agencies for improvements in their
institutional set up.
4. Legal frame work
Public Procurement Regularity Authority (PPRA) was established on May
15, 2002.
PPRA ordinance 2002.
Public Procurement Rules 2004.
Six Public Procurement Regulations are notified.
Based on UNCITRAL – a model Procurement Law.
Compliance with World Bank and ADB Procurement Guidelines.
5. Public procurement regime in Pakistan
Punjab PPRA (Established in 2008).
Sindh PPRA (Established in 2010).
Baluchistan PPRA (Established in 2012).
KP PPRA (Established in 2014).
AJK adopted Federal PPRA Rules in 2017, GB follow Federal PPRA and
FATA follows Governor Directives.
6. Public procurement cycle checklist
1) Identifying the need.
2) Writing the specifications.
3) Estimating cost.
4) Securing approvals and funding.
5) Determining the best procurement strategy.
6) Deciding on the tendering procedure that should be followed.
7) Preparing request for tender (RFT).
8) Allowing sufficient time for submission of tenders.
7. Public procurement cycle checklist
9) Issuing tender documents, supporting documents and clarifications
without delay.
10) Receipting and opening tenders.
11) Evaluation of tenders.
12) Awarding the contract.
13) Managing the contract.
8. Public procurement rules 2004
1) Short Title and Commencement
Section 26, Public Procurement Regulatory Authority Ordinance, 2002-
power to make rules.
Public Procurement Rules, 2004.
10. Public procurement rules 2004
3) Scope and Applicability
Save as otherwise provided, these rules shall apply to all procurements
made by all procuring agencies of the Federal Government whether within
or outside Pakistan.
4) Principles of Procurements
Fair and transparent manner.
Procurement bridges value for money to the agency.
Procurement is efficient and economical.
11. Public procurement rules 2004
5) International and inter-government commitments of the Federal
Government
Bilateral-state to state treaties/agreements-provisions of such international
treaty or agreement shall prevail to the extent of such conflict.
6) Language
Federal Government shall either be in Urdu or English or both.
Recently Supreme Court of Pakistan has ordered Urdu to be the official
language.
7) Integrity Impact
Procurements exceeding the prescribed limit shall be subject to an
integrity pact.
12. Public procurement rules 2004
8) Procurement Planning
All procurement agencies – To devise a mechanism, for
- planning in detail for all purposed procurements with all object of
realistically determining the requirements of the procuring agency.
- within its available resources.
- delivery time or completion date and benefits that are likely to accrue to the
procuring agency.
9) Limitation on splitting or regrouping of proposed procurement
Save as otherwise provided and subject to the regulation made by the
Authority, with the prior approval of the Federal Government.
13. Public procurement rules 2004
Proceed accordingly without any splitting or regrouping of the procurements
so planned.
Annual requirements thus determined would be advertised in advanced on
the Authority’s website as well as website of the procuring agency.
10) Specifications
Shall provide the widest possible competition.
Shall not favour any single contractor or supplier.
Shall not put others at a disadvantage.
Shall be generic and shall not include references to brand names, model
numbers, catalogue numbers or similar classifications.
Provided that this rule shall not apply to procurement made by public sector
commercial concerns on the demand or private sector client.
14. Public procurement rules 2004
11) Approval Mechanism
Procuring agencies shall provide clear authorization and delegation of powers
for different categories of procurement and shall only initiate procurements
once approval of the competent authorities.
12) Methods of advertisement
Procurements over one hundred thousand rupees and up to the limit of two
million rupees shall be advertise on the authority’s website.
Maybe also advertise in print media, if deemed necessary.
Over two million rupees should be advertised on the authority’s website as
well as in other print media or newspapers having wide circulation-atleast two
newspapers one Urdu and one English.
Procuring agency utilizing electronic media shall ensure that the information
posted on the website is complete for the purposes for which it has been
posted.
15. Public procurement rules 2004
Such information shall remain available on that website until the closing date
for the submission of bids.
13) Response time
Procuring agency shall provide sufficient time according to complexity of
procurements.
All advertisements or notices shall expressly mention the response time
allowed.
Provided that no time limit shall be applicable in case of emergency.
Response time shall be calculated from the date of first publication of the
advertisement in a newspaper or posting on the website.
In case of advertisement in electronic media and print media-date of
publication in print media.
16. Public procurement rules 2004
14) Expectation
Following circumstances deviation from the requirement is permissible
with the approval of the authority.
Procurement is related to the national security.
Relates to disclosure of information, which is proprietary in nature or falls
within the definition of intellectual property.
15) Pre-qualification of suppliers and contractors.
16) Pre-qualification process.
17) Qualification of suppliers and contractors.
17. Public procurement rules 2004
18) Disqualification of suppliers and contractors.
19) Blacklisting of suppliers and contractors.
20) Principal method of procurement.
21) Open competitive bidding.
22) Submission of bids.
23)Bidding documents.
24) Reservation and preference.
25) Bid security.
18. Public procurement rules 2004
26) Bid validity.
27) Extension of time for submission of bids.
28) Opening of bids.
29) Evaluation of criteria.
30) Evaluation of bids.
31) Clarification of bids.
32) Discriminatory and difficult conditions.
33) Rejection of bids.
19. Public procurement rules 2004
34) Re-bidding.
35) Announcement of evaluation reports.
36) Procedures of open competitive bidding.
37) Conditions for use of single stage two envelope, two stage and two stage
two envelope bidding procedures.
38) Acceptance of bids.
39) Performance of guarantee.
40) Limitation on negotiations.
20. Public procurement rules 2004
41) Confidentiality.
42) Alternative methods of procurements.
43) On account payments.
44) Entry into force of the procurement contract.
45) Closing the contract.
46) Record of procurement proceedings.
47) Public access and transparency.
21. Public procurement rules 2004
48) Redressal of grievances by the procuring agency.
49) Arbitration.
50) Mis-procurement.
51) Overriding effect.