VIETNAM - BIOMASS POWER PROJECTS - NEW LAWS AND HOW TO GET HIGHEST LEVELS OF ...Dr. Oliver Massmann
VIETNAM - BIOMASS POWER PROJECTS - NEW LAWS AND HOW TO GET HIGHEST LEVELS OF LEGAL CERTAINTY AND BANKABILITY UNDER EU-VN INVESTMENT PROTECTION AGREEMENT (“EVIPA”) AND COMPREHENSIVE AND PROGRESSIVE TRANS-PACIFIC PARTNERSHIP (“CPTPP”)
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...Dr. Oliver Massmann
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS INTO VIETNAM’S FIRST EVER LAW ON INVESTMENT IN THE FORM OF PUBLIC-PRIVATE PARTNERSHIP (PPP)
VIETNAM - BIOMASS POWER PROJECTS - NEW LAWS AND HOW TO GET HIGHEST LEVELS OF ...Dr. Oliver Massmann
VIETNAM - BIOMASS POWER PROJECTS - NEW LAWS AND HOW TO GET HIGHEST LEVELS OF LEGAL CERTAINTY AND BANKABILITY UNDER EU-VN INVESTMENT PROTECTION AGREEMENT (“EVIPA”) AND COMPREHENSIVE AND PROGRESSIVE TRANS-PACIFIC PARTNERSHIP (“CPTPP”)
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS I...Dr. Oliver Massmann
VIETNAM – THE NATIONAL ASSEMBLY INCORPORATED DUANE MORRIS’S RECOMMENDATIONS INTO VIETNAM’S FIRST EVER LAW ON INVESTMENT IN THE FORM OF PUBLIC-PRIVATE PARTNERSHIP (PPP)
Vietnam – Infrastructure and Waste Treatment Sector – Current Issues and Solu...Dr. Oliver Massmann
Vietnam – Infrastructure and Waste Treatment Sector – Current Issues and Solutions for Investment and Outlook on the Major Trade Deals CPTPP, EUVNFTA and the EU Vietnam Investment Protection Agreement (IPA)
Vietnam – Infrastructure and Waste Treatment Sector – Current Issues and Solu...Dr. Oliver Massmann
Vietnam – Infrastructure and Waste Treatment Sector – Current Issues and Solutions for Investment and Outlook on the Major Trade Deals CPTPP, EUVNFTA and the EU Vietnam Investment Protection Agreement (IPA)
Procurement process in detial to understan the process in real essence of procurement. Besides, it will help the procofessional to learn from it and have idea what the process of procurment is actually.
Presentation of the “SIGMA workshop on tendering of PPP projects and contract signature”, held in Ankara on 11-12 April 2018. Presentation made by Mr. Mario Turkovic, SIGMA.
Understanding Pre Qualification QuestionnairesLloyd Sewell
Tendering for contracts training offers a comprehensive training programme provided by small enterprise support specialists and public sector support specialists for small firms who wish to develop new revenue streams by tendering for public sector contracts.
Melanie Ffrench - Senior Legal Officer, CSME, CARICOM Single Market and Economy Unit - delivered this presentation at the Jamaica Chamber of Commerce 2016 Procurement Seminar during the section dedicated to The CARICOM Market
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due ...Dr. Oliver Massmann
VIETNAM — Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence Directive (CSDDD oder das EU-Lieferkettengesetz): Umfassende Analyse und Ausblick auf die Auswirkungen auf Unternehmen in Vietnam
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chain Law): A Comprehensive Analysis and Review of its Implications on Vietnam-based Companies
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Dr. Oliver Massmann
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to encourage the development of rooftop solar power systems for self-consumption purpose
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chain Law): A Comprehensive Analysis and Review of its Implications on Vietnam-based Companies
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Dr. Oliver Massmann
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence Directive (CSDDD oder das EU-Lieferkettengesetz): Umfassende Analyse und Ausblick auf die Auswirkungen auf Unternehmen in Vietnam
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Dr. Oliver Massmann
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chain Law): A Comprehensive Analysis and Review of its Implications on Vietnam-based Companies
How to Obtain Permanent Residency in the NetherlandsBridgeWest.eu
You can rely on our assistance if you are ready to apply for permanent residency. Find out more at: https://immigration-netherlands.com/obtain-a-permanent-residence-permit-in-the-netherlands/.
WINDING UP of COMPANY, Modes of DissolutionKHURRAMWALI
Winding up, also known as liquidation, refers to the legal and financial process of dissolving a company. It involves ceasing operations, selling assets, settling debts, and ultimately removing the company from the official business registry.
Here's a breakdown of the key aspects of winding up:
Reasons for Winding Up:
Insolvency: This is the most common reason, where the company cannot pay its debts. Creditors may initiate a compulsory winding up to recover their dues.
Voluntary Closure: The owners may decide to close the company due to reasons like reaching business goals, facing losses, or merging with another company.
Deadlock: If shareholders or directors cannot agree on how to run the company, a court may order a winding up.
Types of Winding Up:
Voluntary Winding Up: This is initiated by the company's shareholders through a resolution passed by a majority vote. There are two main types:
Members' Voluntary Winding Up: The company is solvent (has enough assets to pay off its debts) and shareholders will receive any remaining assets after debts are settled.
Creditors' Voluntary Winding Up: The company is insolvent and creditors will be prioritized in receiving payment from the sale of assets.
Compulsory Winding Up: This is initiated by a court order, typically at the request of creditors, government agencies, or even by the company itself if it's insolvent.
Process of Winding Up:
Appointment of Liquidator: A qualified professional is appointed to oversee the winding-up process. They are responsible for selling assets, paying off debts, and distributing any remaining funds.
Cease Trading: The company stops its regular business operations.
Notification of Creditors: Creditors are informed about the winding up and invited to submit their claims.
Sale of Assets: The company's assets are sold to generate cash to pay off creditors.
Payment of Debts: Creditors are paid according to a set order of priority, with secured creditors receiving payment before unsecured creditors.
Distribution to Shareholders: If there are any remaining funds after all debts are settled, they are distributed to shareholders according to their ownership stake.
Dissolution: Once all claims are settled and distributions made, the company is officially dissolved and removed from the business register.
Impact of Winding Up:
Employees: Employees will likely lose their jobs during the winding-up process.
Creditors: Creditors may not recover their debts in full, especially if the company is insolvent.
Shareholders: Shareholders may not receive any payout if the company's debts exceed its assets.
Winding up is a complex legal and financial process that can have significant consequences for all parties involved. It's important to seek professional legal and financial advice when considering winding up a company.
A "File Trademark" is a legal term referring to the registration of a unique symbol, logo, or name used to identify and distinguish products or services. This process provides legal protection, granting exclusive rights to the trademark owner, and helps prevent unauthorized use by competitors.
Visit Now: https://www.tumblr.com/trademark-quick/751620857551634432/ensure-legal-protection-file-your-trademark-with?source=share
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxshweeta209
transfer of the P.I.L filed by lawyer Ashwini Kumar Upadhyay in Delhi High Court to Supreme Court.
on the issue of UNIFORM MARRIAGE AGE of men and women.
Introducing New Government Regulation on Toll Road.pdfAHRP Law Firm
For nearly two decades, Government Regulation Number 15 of 2005 on Toll Roads ("GR No. 15/2005") has served as the cornerstone of toll road legislation. However, with the emergence of various new developments and legal requirements, the Government has enacted Government Regulation Number 23 of 2024 on Toll Roads to replace GR No. 15/2005. This new regulation introduces several provisions impacting toll business entities and toll road users. Find out more out insights about this topic in our Legal Brief publication.
In 2020, the Ministry of Home Affairs established a committee led by Prof. (Dr.) Ranbir Singh, former Vice Chancellor of National Law University (NLU), Delhi. This committee was tasked with reviewing the three codes of criminal law. The primary objective of the committee was to propose comprehensive reforms to the country’s criminal laws in a manner that is both principled and effective.
The committee’s focus was on ensuring the safety and security of individuals, communities, and the nation as a whole. Throughout its deliberations, the committee aimed to uphold constitutional values such as justice, dignity, and the intrinsic value of each individual. Their goal was to recommend amendments to the criminal laws that align with these values and priorities.
Subsequently, in February, the committee successfully submitted its recommendations regarding amendments to the criminal law. These recommendations are intended to serve as a foundation for enhancing the current legal framework, promoting safety and security, and upholding the constitutional principles of justice, dignity, and the inherent worth of every individual.
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxanvithaav
These slides helps the student of international law to understand what is the nature of international law? and how international law was originated and developed?.
The slides was well structured along with the highlighted points for better understanding .
Responsibilities of the office bearers while registering multi-state cooperat...Finlaw Consultancy Pvt Ltd
Introduction-
The process of register multi-state cooperative society in India is governed by the Multi-State Co-operative Societies Act, 2002. This process requires the office bearers to undertake several crucial responsibilities to ensure compliance with legal and regulatory frameworks. The key office bearers typically include the President, Secretary, and Treasurer, along with other elected members of the managing committee. Their responsibilities encompass administrative, legal, and financial duties essential for the successful registration and operation of the society.
DNA Testing in Civil and Criminal Matters.pptxpatrons legal
Get insights into DNA testing and its application in civil and criminal matters. Find out how it contributes to fair and accurate legal proceedings. For more information: https://www.patronslegal.com/criminal-litigation.html
Vietnam - The World Bank is asking Duane Morris about Doing Business and Government Contracting - What you must know:
1. Vietnam - The World Bank is asking Duane Morris about Doing Business and
Government Contracting - What you must know:
Case Study Assumptions
BidCo
Is one of the companies participating in the call for tender and meets all solvency,
technical and administrative requirements to compete;
Is a privately and domestically-owned medium-sized Limited Liability Company (or its
most common legal equivalent);
Operates in Ho Chi Minh City;
Is up to date with all regulations and is in good standing with all relevant authorities,
including those related to taxes;
Has all licenses and permits needed to operate in this technical area;
Has already responded to a public call for tender and is already registered with the
procuring entity defined below.
Contract
Entails resurfacing 20 km of a flat two-lane road (not a highway and not under
concession), connecting Ho Chi Minh City to another city within Vietnam (and within the
same state, region or province as Ho Chi Minh City, if applicable), with an asphalt overlay of
40 to 59 mm (or its most common equivalent in Vietnam);
Value: USD 2.5 Million (equivalent to VND 57,641,204,415);
Does not include any other work (such as site clearance, subsoil drainage, bridgework or
further routine maintenance).
Procuring Entity
Is the agency in charge of procuring construction works for the authority that owns the
road described above;
Is the sole funder of the works, has budget for the works and is solvent.
Procurement Process
Is an open, unrestricted, and competitive public call for tender for resurfacing a road like
the one described above;
Is completed without complaints/challenges/protests from interested parties;
Ends with the awarding of the contract to BidCo, whose bid satisfied all technical and
administrative criteria and offered the best value for money.
1. What is the entity that conducts procurement for the authority that owns the majority of roads comparable
to the one described above?
Directorate for Roads of Vietnam within the Transport Ministry (“Procuring Entity”)
2. Please provide a list of the laws, regulations and other binding materials (including guidelines and manuals)
that regulate public procurement in Vietnam. Please include legislation or other binding materials promulgated
at the national/federal level as well as any additional legislation that is applicable to the Procuring Entity.
Civil Code of Vietnam no. 91/2015/QH13 by the National Assembly of Vietnam dated 24 November 2015 18
June 2014
2. Construction Law no. 50/2014/QH13 by the National Assembly dated 18 June 2014
Law on Bidding no. 43/2013/QH13 dated 26 November 2013
Commercial Law no. 36/2005/QH11 dated 14 June 2005
Decree no. 63/2014/ND-CP dated 26 June 2014
Decree no. 37/2015/ND-CP dated 22 April 2015
Decree no. 46/2015/ND-CP dated 17 March 2015
Decree no. 30/2015/ND-CP dated 17 March 2015
Decree no. 63/2018/ND-CP dated 4 May 2018
Circular no. 04/2017/TT-BKHDT dated 15 November 2017
Circular no. 26/2016/TT-BXD dated 26 October 2016
Circular no. 10/2016/TT-BKHDT dated 22 July 2016
Circular no. 23/2015/TT-BKHDT dated 21 December 2015
Circular no. 10/2015/TT-BKHDT dated 31 October 2015
Circular no. 01/2015/TT-BKHDT dated 15 April 2015
Circular no. 07/2015/TTLT-BKHDT-BTC dated 8 September 2015
3. Please list any mandatory standard tender documents and/or standard contract terms that the Procuring
Entity must use for a contract like the one described above
Contract terms must specify:
Applied legal bases;
Language used in the contract;
Content and volume of work;
Quality, technical requirements of work; pre-acceptance test and handover;
Contract performance duration and schedule;
Contract price, advance payment, currency used in payment, and payment for the contract;
Contract performance security, contract advance guarantee;
Adjustment of the construction contract;
Rights and obligations of the parties to the construction contract;
Liability for violations of the contract, rewards and fines for violations of the contract;
3. Suspension and termination of the contract;
Settlement of disputes over the contract;
Risks and force majeure events; o/ Settlement and liquidation of the contract;
Other contents.
4. If such documents are in use, can the Procuring Entity modify any of their clauses without justification?
No
5. Are you aware of any change in laws/regulations/procedures) related to public procurement between May 2,
2018 and May 1, 2019? For example: amendments to applicable public procurement laws, enactment and/or
implementation of new regulations, implementation or improvement of e-procurement platforms, changes to
the bid security and performance guarantee framework, etc.
Yes. Issuance of Decree 63/2018/ND-CP dated 04 May 2018 to replace Decree 15/2015/ND-CP on public private
partnership.
6. If one or several electronic procurement portal(s) (i.e., an official website(s) specifically and exclusively
dedicated to public procurement) are in operation please mark which platform would most commonly be used
bv the Procuring Entity.
http://muasamcong. mpi.gov.vn/
7. Which information about road works contracts procured by the Procuring Entity is made publicly available?
Estimated cost/length/completion time - as calculated by the Procuring Entity at the time of advertising the procurement
opportunity.
8. According to the legal framework, when the Procuring Entity prepares to advertise a new procurement
opportunity for a contract like the one described in Section 1, what are used to estimate the contract value and
projected length of works?
Market analysis, Standardized unit cost, Project-specific technical drawings, Similar projects from previous years, and price
evaluation result by authorized state agency or price evaluation enterprise for assets, goods and services subject to price
evaluation under the Law on Price.
9. In practice, is the estimated contract value / budget published in the tender notice/tender documents?
Yes, contract value.
10. Is the Procuring Entity required to have already allocated budget to a specific project before tendering?
Yes, there is a specific budget allocation.
11. In an open tendering procedure, how often does the Procuring Entity award a contract without having already
set aside all the necessary funds?
Rarely (between 10-25%).
12. According to the legal framework, would open tendering (i.e. the process in which any business can submit a
bid) be the default method of procurement in Vietnam for a contract like the one described in Section 1?
4. Open tendering is not the default but remains the most common in practice.
13. In practice, how many days would be necessary for BidCo to receive a decision on its prequalification from the
moment it submitted all the necessary documents?
30 days
14. According to the legal framework, after the advertisement of an open tendering procedure can the Procuring
Entity require bidders to participate in a prequalification process specific to that contract before being able to
submit their economic offer?
Yes. This happens occasionally for a contract like the one described in Section 1.
15. In practice, what is the most common method of procurement for a contract like the one described in Section
1?
Open tendering is not the default but remains the most common in practice.
16. Does the legal framework define the situations in which each procurement method should be used?
Yes, Section 2 of the Bidding Law.
17. Does the legal framework prohibit dividing contracts to circumvent thresholds for open tendering?
Yes, Article 89.6.k of Law on Bidding No. 43/2013/QH13.
18. What are the commonly used strategies to circumvent the rules and thresholds on open procurement?
The procuring entity sets out very high technical specifications.
19. According to the legal framework, is there a minimum time limit between the advertisement of the tender
notice and the submission deadline for an open tendering procedure like the one described in Section 1?
Yes. Article 12.1.e of Law on Bidding No. 43/2013/QH13.
20. In practice, how many days would pass between the advertisement of the tender notice and the submission
deadline for a contract like the one described in Section 1?
30-40 days
21. How often does the Procuring Entity modify the tender documents for any reason after advertisement, but
before the submission deadline?
Occasionally (between 25-50%).
22. Does the legal framework establish the minimum content of the tender notice and tender documents?
Yes. Articles 218-219 of Commercial Law No. 36/2005/QH 11; and Circular No. 03/2015/TT-BKHDT
Tender notice must include:
Name and address of procuring entity
brief description of bidding contents
5. time limit, place and procedures for receipt of bid documents
time limt, place and procedures for submission of bid documents
guidance on seeking clarification of the tender documents
Tender documents must include:
tender notice
requirements on procuring goods or services
methods of evaluation, comparison, ranking and selection of bidders
other instructions related to bidding
23. In practice, which of the following are usually NOT included in the tender notice and/or tender documents?
Grounds for exclusion of bidders; Main terms and conditions of the contract; Payment schedule under the procurement
contract.
24. Which aspects of subcontracting are regulated by the applicable legal framework?
Features - the legal framework regulates the administrative process to subcontract, the limits of
subcontracting, the authorizations required, etc.
Disclosure - the legal framework regulates when and how companies should inform the Procuring Entity of
their intent to subcontract
Liability - the legal framework regulates liability of the contractor and subcontractor in case of poor
performance
25. In practice, how are clarification requests from potential bidders usually addressed?
The procuring entity addresses all clarifications in a public meeting;
The procuring entity will answer, and it is always required to communicate the answer to all other bidders too.
26. According to the legal framework, is BidCo required to provide a form of bid guarantee?
Yes. Article 11.1 of Law on Bidding No. 43/2013/QH13
27. In practice, which instrument would BidCo most commonly use as a bid guarantee?
Cash/Certified check; Bank guarantee/Letter of credit; Bid bond
28. Does the legal framework establish a timeframe for the Procuring Entity to proceed to bid opening once the
deadline for bid submission has been reached?
Yes, Article 14.3(b) Decree no. 63/2014/ND-CP.
29. Selection committee - Which of the following characteristics are regulated by the applicable legal framework?
The education requirements of members of the committee;
6. The professional requirements of members of the committee.
30. Are employees of the Procuring Entity required to follow a mandatory code of conduct or ethics that includes
topics like screening procedures, conflict of interest, training requirements, etc.?
No
31. According to the legal framework, which award criterion would be used for a contract like the one described
in Section 1?
Price
Price and other qualitative elements (i.e. best value for money or the most advantageous combination of
cost, time to completion, quality and sustainability, or the most economically advantageous tender)
The choice is left at the discretion of the Procuring Entity
32. Does the legal framework require all non-price evaluation criteria to be objective and quantifiable?
This is not mentioned in laws.
33. Does the legal framework establish a criteria to identify abnormally low bids?
No
34. Does the legal framework define what constitutes a non-substantial error?
Yes, Article 17, Decree 63/2014/ND-CP
35. When a bidder is excluded before the contract is awarded, is it provided with an explanation of the reasons for
the exclusion in writing?
No, the excluded bidder will be notified directly in the contract award.
36. According to the legal framework, is BidCo required to provide a performance guarantee deposit that ensures
a source of compensation in case of failure to perform its contractual obligations?
Yes, Articles 66 and 72 of Bidding Law.
37. In practice, which instrument would BidCo most commonly use as a performance guarantee?
Certificate of deposit; Bank Guarantee / Letter of Credit; Payment retention until satisfactory completion of the contract.
38. Which aspects of contract management are regulated by the applicable legal framework?
Renegotiation (Article 67 Bidding Law, Article 93 Decree no. 63/2014/ND-CP).
39. According to the legal framework, is there a percentage of price increase below which the procuring entity is
not required to provide a reason for the renegotiation?
No
40. According to the legal framework, is there a percentage of price increase above which the procuring entity is
not allowed to renegotiate and is always required to re-tender?
7. No
41. In practice, are the results of contract renegotiations made publicly available?
No.
42. In practice, how many days would pass on average from the moment one of the parties requests/initiates a
renegotiation of the contract until a new contract amendment is signed?
It depends on the extent of renegotiation.
43. According to the legal framework, is there a limit to how much the Procuring Entity can pay upfront for the
contractor to hire workers, buy materials, and start operations in a contract like the one described in Section 1?
No.
44. During the execution of the contract, does the legal framework establish a timeframe within which the
Procuring Entity must process the payment once an invoice is received?
Yes. Article 19 of Decree No. 37/2015/ND-CP.
45. According to the legal framework, is the company entitled to claim interest on late payments if the Procuring
Entity does not pay within the legally-established timeframe?
Yes. Article 94 of Decree No. 63/2014/ND-CP
46. Assuming that BidCo delivers works complying with the quality standards agreed-upon in the contract, within
budget and on time, what strategies, if any, does the Procuring Entity use to delay or avoid payment?
Bureaucracy/paperwork Inspections/ financial difficulties
47. Does the procuring entity have guidelines or protocols regulating inspections on the quality of the works?
Yes
48. According to the legal framework, is BidCo required to provide a guarantee upon completion of the works?
Yes. Bank guarantee / Letter of credit; Payment retention.
49. If a post-completion guarantee is not required bv law would it usually be requested by the Procuring Entity
for a contract like the one described in Section 1?
No.
50. In practice, which instrument of post-completion guarantee would the Procuring Entity most commonly
request?
Bank guarantee / Letter of credit; Payment retention.
51. In practice, what are the main reasons for works delivered over the original budget?
Market conditions (changes in input prices, fluctuations in exchange rate, etc.); burdensome administrative processes within
the procuring entity; Capacity of the contractor (technical/financial/managerial/human capital constraints); Poor planning
on the procuring entity's side (poorly designed project specifications, etc.); Poor planning on the contractor's side.
8. Formal Challenges throughout the Procurement Process
Assume that:
The Procuring Entity publishes tender documents for a road works contract.
Before the deadline to submit the bids, 3 companies challenge the tender documents on the following grounds:
Company 1 argues that the tender documents favor one specific bidder.
Company 2 argues that one of the evaluation criteria establishing that the Project Manager assigned to the project
has at least 20 years of experience is arbitrary and should not be used.
Company 3 argues that requiring a 10% performance guarantee hinders access to SMEs.
Assume all challengers submit their claims within the legal deadlines, free of mistakes, pay the fees associated with their
challenges, and pursue their claims until no further legal remedy is available.
52. According to the legal framework, can tender documents be challenged prior to the deadline to submit bids?
Yes.
53. According to the legal framework, who has legal standing to challenge tender documents?
Potential bidders.
First instance
Which authority would hear the challenge?
Investor of the project
Would the challenge suspend the procurement process?
No, the procurement process would continue
Second instance
To which authority would the first instance decision be appealed?
Procuring entity, investor of the project
Would the appeal suspend the procurement process?
No, the procurement process would continue
Assume that:
The Procuring Entity has awarded a works contract to BidCo.
Three companies challenge the award on the following grounds:
Company 1 argues that BidCo submitted a recklessly low bid that should have been excluded.
9. Company 2 argues that one of the evaluation criteria was used arbitrarily by the Procuring Entity to reduce the
Company's final score.
Company 3 argues that the technical project they submitted met the minimum standards established by the tender
documents and should not have been excluded.
Assume all challengers submit their claims within the legal deadlines, free of mistakes, pay the fees associated with their
challenges, and pursue their claims until no further legal remedy is available.
54. According to the legal framework, who has legal standing to challenge the contract award?
Bidders.
First instance
Which authority would hear the challenge?
Procuring entity
Would the challenge suspend the procurement process?
No, the procurement process would continue
Second instance
To which authority would the first instance decision be appealed?
Responsible persons in the bidder/ investor selection process, Advisory Committee
Would the challenge suspend the procurement process?
No, suspension is discretionary but not common in practice for similar cases.
***
Please do not hesitate to contact Dr. Oliver Massmann under omassmann@duanemorris.com if you have any questions or
want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.