This is an presentation on training in LODHA Palava, In this internship, I learned about an overview of the road construction which I mentioned in this presentation.
2. About the Company
Tejas Enterprises provides the best work
efficiency in the world of infrastructure. This
company was founded in 1995
Various Works Are Carried out by the
company
• Cutting
• Filling
• Excavation
3. About the
project
This is a Four lane Carriageway
of 25 m
It is 800 m DP road connecting
the Palava city to both Taloja
bypass road and SH-80
Highway (Badlapur Road
5. Site Clearance
The Area of the road
alignment which is planned is
cleared by JCB Backhoe Loader
Site Clearance is done for
removal of shrubs or any other
organic compound which can
reduce the SBC of the soil
6. Surveying
After Site Clearance, Surveyor surveyed the
land by the interval of 5m width wise and
lengthwise forming a grid of road
Then two levels are taken with help of Dumpy
level of each point of grid of road
Two levels are
OGL – Original Ground Level
EGL – Estimated Ground Level
Area = D/3[FL+LL+(4xsum OL)+(2xsum
EL)]
8. Formation of Bituminous Road
Murum Filling (1m) – Accurate levelling is done and water is used
as binder for next layer
Rubble Soling (0.3m) – Coarse rubble used
Water Bound Macadam (0.22m) – Mix of Agg., Sand and soil used
Tack Coat (4 kg/sq.km) – Binder between Bituminous layer and
WBM
Bituminous Surface course (0.05m) – Mix of Bitumen and Agg.
Sized 10 or 12mm
Seal Coat (0.012m) – Mix of bitumen and sand
11. JCB Backhoe Loader
Backhoe loader a loader having a tractor like unit with bucket and a small backhoe
on the back
Max Load carrying Capacity – 1800 kg
Shovel Capacity – 1.1 cu.m
12. Tippers
Tippers are used to carry loose materials like soil, sand, gravel, etc
Tippers have a open box bed which is hinged and raised by Hydraulic pistons
Max Loading Capacity – 16200 kg
13. Contribution
Estimation of area to be cutted or filled
Supervision on the thickness of each layer
Preparation of bill of the equipment used on the site