SlideShare a Scribd company logo
VAISHALI NEHRA
M.TECH 2nd year
EXECUTIVE SUMMARY
Policy, Legal & Administrative Framework
The proposed Corridor, Central Secretariat – Badarpur was
proposed by DMRC to be part of 2nd Phase on the instance of
Sports Authority of India, and Delhi Police.
The proposed project would be governed by various Acts,
Rules and regulations set by the Ministry of Environment and
Forests (MoEF) at the Central level and other regulatory agencies
at the State and local level.
Project Description
 The Metro corridor line from Central Secretariat to Badarpur
Border is 20.16km with the following stations namely (1) Central
Secretariat (2) Khan Market (3) J.L.N Stadium, (4) Jangpura (5) Lajpat
Nagar, (6) Mool Chand, (7) East of Kailash, (8) Nehru Place (9) Kalkaji
Mandir, (10)Govindpuri, (11) Okhla, (12) Jasola, (13)Sarita Vihar, (14)
Mohan Estate, (15) Tughlakabad and(16)Badarpur.
 Central Secretariat is an interchange station, which is a
connecting Central Secretariat- Vishwavidyalaya (Already
operational) section in the north and Central Secretariat- Qutab Minar-
Arjangarh- Gurgaon in the south with the proposed corridor .
Environmental Baseline Data
The baseline environmental status is established by determining the baseline
levels of significant environmental parameters, which could be affected by the
implementation of the project.
the baseline data include establishing the present status of physico -chemical,
biological and socio - economic aspects of the study area relevant to the
proposed construction of metro corridor between Central Secretariat and
Badarpur. Accordingly, following important parameters were identified for the
detailed baseline data collection through field studies:
 · Air Environment
 · Noise Environment
 · Water Environment
 · Soil Environment
 · Green Cover Survey
 · Socio – Economic component
 · Land – use pattern along the proposed corridors
NEGATIVEENVIRONMENTALIMPACTS
 The primary function of an environmental impact assessment study is
to predict and quantify the magnitude of impacts, evaluate and assess
the importance of the identified changes and formulate plans to
monitor and mitigate the actual changes.
 Environmental impacts could be positive or negative, direct or indirect,
local, regional or global, reversible or irreversible.
Some of the negative impacts associated with the metro
rail project have been summarized below under the following headings:
 · Impacts due to project location,
 · Impacts due to construction works, and
 · Impacts due to project operation.
IMPACTS DUE TO PROJECT
LOCATION
 a) Change of Land use
The alignment is mostly elevated. Both the land requirement and change
of land use is minimum. The development on the study area will not
bring any significant changes in the land use pattern, since the new
proposed depot is planned in mostly vacant area. The development
ofstation buildings will not have any significant impact on the land use
ifuture; however, it will enhance the aesthetics due to development of a
modern building and surrounding horticulture. The change in land use
is estimated to be 54.36 Hect. (includes both government and private
land)
 b) Loss of Trees
Total loss of Trees (Nos.) 4401
Average cost of one tree (Rs.) 700
TOTAL LOSS (RS. LAKHS) 30.80 LAKHS
 c) Loss of Historical and Cultural Monuments
No historical/cultural monuments will be affected as a result of the
proposed development of project.
d) Socio-Economic Impacts
Land required for construction of the project is around 54 Ha. It does
involve acquisition of both government and private land, and also
involves social issues such as resettlement and rehabilitation of 589
families.
e) Utilities / Drainage Problem
The alignment is mostly planned to run through the urban area,
underground and above ground. The alignment will cross drains/nalas
large number of sub-surface, surface and utility services, viz. sewer,
water mains, storm water drains, telephone cables, overhead electrical
transmission lines, electric pipes, traffic signals etc. These utilities/
services are essential and have to be maintained in working order during
different stages of construction by temporary/permanent diversions or
by supporting in position. In addition, cross drainage works such as
bridges, culverts etc. will be required.
f) Risk due to Earthquakes
The project area falls under seismic zone IV as per the Seismic Zoning Map
of India (IS 1893, Part-I, 2002). Necessary seismic factors suggested by
Indian Meteorology Department (IMD) shall be incorporated suitably
while designing the structures to safeguard against earthquake risks.
IMPACTSDUETOPROJECTCONSTRUCTION
 a) Soil Erosion at Construction Site
 The total quantity of earthwork in excavation would be about 9,75,000
cum
 Run off from unprotected excavated areas, and underground tunnel
faces can result in excessive soil erosion, especially when the erodability
of soil is high. Exposure of loose soil to rain water will increase turbidity
in the run-off.
 b) Health Risk at Construction Site
 Health risks include disease hazards due to lack of sanitation facilities
(water supply and human waste disposal) and insect vector disease
hazards of local workers and disease hazards to the local
population.Mitigation measures should include proper water supply,
sanitation, drainage, health care and human waste disposal facilities. In
addition to these, efforts need to be made to avoid water spills, adopt
disease control measures and employment of local labour.
.
 c) Traffic Diversions and Risk to Existing Buildings During
construction, traffic diversions on roads will be essentially required. As
most of the construction activities will be confined to centre of the road
and most of the roads are double lane, it will be appropriate that the side
lanes may also be utilised for traffic and also for smooth progress of
construction activities. Advance information on communication systems
will be an advantage to users of any particular road.
 d) Impact due to Solid Waste Disposal
 Problems could arise from dumping of construction spoils (Concrete,
bricks) waste materials (from contractor camps) etc. causing surface
and ground water pollution.
 e) Impact on Water Quality
 Construction activities may have impact on water bodies due to
disposal of waste. The waste could be due to the spillage of construction
materials, dumping of used water from the stone crusher, oils and
greases, and labour camp.
f) Impact on air quality
In such type of projects, air pollution occurs mainly due to fugitive
emissions/dust generation from various construction activities
during construction period and vehicular emission during operation
period. The impacts on air environment, which will be during project
construction phase are briefly discussed below.
 During construction phase, SPM is expected to be the main
pollutant associated with the earthwork activities and material
handling.
g) Like air environment, impact on noise is also anticipated
during construction and operation phase of the project cycle. Noise
at a construction site varies relative to the particular operation in
progress .Operation can be divided into five consecutive phases;
1. Ground Clearing
2. Excavation
3. Foundation
4. Erection
5. Finishing
IMPACTS DUE TO PROJECT
OPERATION
 a) Oil Pollution
Oil spillage during change of lubricants, cleaning and repair processes,
in the maintenance of rolling stock, is very common. The spilled oil
should be trapped in grit chamber for settling of suspended matter.
 b) Noise
The main sources of noise are traction motors, cooling fans, wheel-rail
interaction, electric generator and miscellaneous noise from rolling
stock.
 c) Accidental Hazards
In view of the hazards potential involved due to failure of system and
accident the on-site and off- site emergency measures have been formulated
and will be implemented.
 d) Water Supply
 Public Health facilities such as water supply, sanitation and toilets are very
much needed at the stations; CPHEEO has recommended 45 litres per day,
water supply to persons working at stations.
S.NO
.
ITEM TOTAL(
cubic
m)
DAILY(cub
ic m)
1. Personal use 0.9 0.9
2. Make up water for fire
fighting
108.00 10.80
3. Washing of platform 6.75 6.75
4. For AC/ Ventilation 1.50 1.50
5. Wastage 11.71 1.99
total 128.86 21.94
 e) Railway Station Refuse
The refuse from railway station includes; Garbage, Rubbish, and Floor
Sweepings. The collection and removal of refuse in a sanitary manner
from the Station is of importance for effective vector control, aesthetic
improvement, and nuisance and pollution abatement.
POSITIVE ENVIRONMENTAL IMPACTS
some of the positive benefits expected from the proposed metro
corridors have been given below:
(i) Reduced travel time resulting in increased accessibility
(ii) Safe and comfortable mode of transportation
(iii) Reduced traffic resulting in reduced congestion on roads due to the
probable shifting of significant proportion of private vehicles to the
metro
(iv) Reduced fuel consumption from the transport sector resulting in
precious foreign exchange
(v) Reduction in vehicular emission loads resulting in improved air quality
of the region
(vi) Reduction in road accidents resulting in reduced death and injury
during road accidents
(vii) Increased job/employment opportunities (direct and indirect both)
(viii) Sense of pride to the city and country having a world-class facility
Quantity saved 2011 2013 2015 2019 2021
Total Road Passkm 4086402 4286658 5035603 5148818 6421721
Daily vehicle saving 546913 557373 590535 689103 736635
Daily vehicle demand 11557 11778 14241 15566 18161
Daily travel time saving
(min)
12964392 13212359 13456506 137226511 18714119
Daily fuel saved(LITRE) 43633 44468 47113 54977 68569
Annual fuel saved
(tonnes)
15926 16707 17196 20067 25028
Annual number of all
accidents saved
104 106 114 117 120
TABLE : QUANTIFICATION OF BENEFITS
S.N
O
PARAMETER NO
IMPACT
NEGATIVE
IMPACT
POSITI
V
IMPAC
T
1. Rehabilitation and Resettlement *
2. Change of land use *
3. Impact on Historical/Cultural
Monuments
*
4. Drainage and utilities problems *
5. Loss of Trees *
6. Risk Due to EarthQuakes *
7. Soil Erosion pollution and health
risk at construction site
*
8. Traffic diversion and risk to existing
buildings
*
9. Soil disposal problem *
CHECKLIST OF IMPACTS
S.NO PARAMETER NO NEGATIVE POSITIVE
10. EMPLOYMENT
OPPORTUNITIES
*
11 OIL POLLUTION *
12 NOISE AND VIBRATION *
13 WATER DEMANDS *
14 BENEFITS TO ECONOMY *
15 QUICK SERVICE AND SAFETY *
16 LESS FUEL CONSUMPTION *
17 LESS AIR POLLUTION *
18 CARBON DIOXIDE
REDUCTION
*
19 REDUCTION IN BUSES
NUMBER
*
20 REDUCTION IN TRAFFIC
CONGESTION
*
ENVIRONMENTALMANAGEMENTPLAN
The proposed Central Secretariat-Badarpur Metro Corridor will provide
quick service and safety, traffic congestion reduction, less fuel
consumption, employment opportunity, and less air pollution on one
hand and problems of Rehabilitation and Resettlement (R&R), soil
disposal, etc. on other hand.
The environmental issues likely to develop during project construction
and operation phases could be minimized by making necessary
provision in the project design and adopting Environmental
Management Plan (EMP).
ImplementationofEnvironmentalManagementPlan A common problem encountered during implementation of
environmental management plans of suchprojects is lack of
environmental awareness among engineers and managers concerned
with day to day construction activities, which can be solved through
regular environmental training.
 The major concern during the construction stage is that the
contractors, due to lack of enforcement, would not practice good
housekeeping, may intend to get unauthorized use of the easily available
natural resources and other available infrastructure like roads and
water resources. This would result in degradation of ambient air quality,
water resources and land environment around the construction sites
and workers camp .
MITIGATION MEASURES
The main aim of mitigation measures is to protect and enhance the
existing environment of the project. These measures should have
positive effects on environment. Some of these have been described in
the following section which includes measures for:
a) Compensation for Loss of Land,
b) Compensation for Loss of Trees,
c) Compensatory Afforestation and Fencing,
d) Compensation for Relocation/Resettlement,
e) Water Supply and Sanitation,
f) Oil Pollution Control,
g) Noise Control,
h) Vibration Control,
i) Soil Disposal,
j) Rain Water Harvesting at Construction Depot Site,
k) Green Belt Development, and
l) Occupational Health Hazards and Control
ENVIRONMENTAL MONITORING PLAN
 Environmental monitoring programme is a vital process of any
management plan of the development project.
 The main objectives of environmental monitoring are:
- to assess the changes in environmental conditions,
- to monitor the effective implementation of mitigation measures,
- to warn significant deteriorations in environmental quality for further
prevention action.
 In order to meet the above objectives the following parameters need to
be
monitored:
- Rehabilitation and Resettlement Programme,
- Afforestation,
- Water Quality and Public Health,
- Air and Noise Quality and
- Soil Conservation Measures.
SUMMARY OF ENVIRONMENTAL MONITORING PROGRAMME
S.NO. ITEM PARAMETERS FREQUENCY LOCATION
DURING PROJECT CONSTRUCTION PHASE
1. SOIL
QUALITY
Heavy Metals:
Arsenic,
Cadmium,Chromiu
m, Lead and
Mercury,
Once before
excavation for
underground
section
One sample at
each u/g
station
location
2 NOISE
QUALITY
Leq, Lmax, L10, L90 As per DMRC
Environmental
Manual
As per DMRC
Environmenta
l
Manual
3 VIBRATI
ON
Ppv/dB 24 hour sample,during
construction
activities that are prone
to cause vibration
Sensitive
receptors(soci
ally important
places like
hospitals,
schools,
NO. ITEM PARAMETER FREQUENCY LOCATION
DURING PROJECT OPERATION PHASE
4 Treated
Effluent from
STP/ETP
pH, BOD, COD,
TSS, Oil and
Grease
Once every three
months
Before and
after
treatment
from STP/ETP
5 Noise Quality Leq, Lmax, L10, L90 24 hour sample,
Once a year
Sensitive
receptors
6 Vibration Ppv/dB 24 hour sample,
twice a year for
next three years
Sensitive
receptors
7 Air Quality SPM, RPM Two samples of 24
hrs each, once in a
month.
Depot Site/
every 5km
(Total
5 locations)
THANK YOU

More Related Content

What's hot

Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveys
Dhwani Shah
 
highway development in india
highway development in indiahighway development in india
highway development in india
Prathi Baa
 
Kochi Metro Rail Project.doc
Kochi Metro Rail Project.docKochi Metro Rail Project.doc
Kochi Metro Rail Project.doc
Suryadev Maity
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
Sai Santosh Yakkali
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
Rashed Alam
 
Smart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiSmart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiJaspal Singh
 
Stormwater management
Stormwater managementStormwater management
Urban water infrastructure
Urban water infrastructureUrban water infrastructure
Urban water infrastructuretanvipatel11
 
Unit 1
Unit 1Unit 1
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination survey
Akash Pandey
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in Railways
Anupama Jha
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
vikasravekar
 
Diiferent types of road
Diiferent types of roadDiiferent types of road
Diiferent types of road
Abhishek Dixit
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
libin paul
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in india
Bhavya Jaiswal
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
mohit kumar panchal
 
Rapid transit system
Rapid transit systemRapid transit system
Rapid transit system
abhishekdayal001
 
Origin and destination survey
Origin and destination surveyOrigin and destination survey
Origin and destination survey
raj balar
 

What's hot (20)

Traffic & Transportation surveys
Traffic & Transportation surveysTraffic & Transportation surveys
Traffic & Transportation surveys
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Kochi Metro Rail Project.doc
Kochi Metro Rail Project.docKochi Metro Rail Project.doc
Kochi Metro Rail Project.doc
 
Spot speed studies and speed delay time survey
Spot speed studies and speed delay time surveySpot speed studies and speed delay time survey
Spot speed studies and speed delay time survey
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
 
Smart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiSmart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of Delhi
 
Stormwater management
Stormwater managementStormwater management
Stormwater management
 
Urban water infrastructure
Urban water infrastructureUrban water infrastructure
Urban water infrastructure
 
Unit 1
Unit 1Unit 1
Unit 1
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination survey
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in Railways
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
Diiferent types of road
Diiferent types of roadDiiferent types of road
Diiferent types of road
 
delhi metro
delhi metrodelhi metro
delhi metro
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Metro and monorail infrastructure development in india
Metro and monorail infrastructure development in indiaMetro and monorail infrastructure development in india
Metro and monorail infrastructure development in india
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Rapid transit system
Rapid transit systemRapid transit system
Rapid transit system
 
Origin and destination survey
Origin and destination surveyOrigin and destination survey
Origin and destination survey
 

Similar to Presentation on DMRC

kochi Metro
kochi Metrokochi Metro
kochi Metro
Anjitha Lekshmi
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET Journal
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
Anchal Garg
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
IRJET Journal
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
Khalid Abdel Naser Abdel Rahim
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
ssuser65cc68
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
Mayur Rahangdale
 
EIA report on thermal power project
EIA report on thermal power projectEIA report on thermal power project
EIA report on thermal power project
Ahsan Nazir
 
IRJET- Ground Water Control Method Simulation in Sphinx Area
IRJET-  	  Ground Water Control Method Simulation in Sphinx AreaIRJET-  	  Ground Water Control Method Simulation in Sphinx Area
IRJET- Ground Water Control Method Simulation in Sphinx Area
IRJET Journal
 
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone AreasGuidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
Phani Mohan K
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVER
vikas rahangdale
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
MNIT,JAIPUR
 
Pathway to Net Zero and EIA
Pathway to Net Zero and EIAPathway to Net Zero and EIA
Pathway to Net Zero and EIA
IES / IAQM
 
Eia procedures
Eia proceduresEia procedures
Eia procedures
Arvind Kumar
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technology
Patricia Faria
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
Palash Mehar
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSepehr Aghamehdi
 
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
MrEddyAsyrafSyed
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionStefan Lammert
 

Similar to Presentation on DMRC (20)

kochi Metro
kochi Metrokochi Metro
kochi Metro
 
IRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil ErosionIRJET - Reaearch on Methods of Controlling Soil Erosion
IRJET - Reaearch on Methods of Controlling Soil Erosion
 
EIA for development projects
EIA for development projectsEIA for development projects
EIA for development projects
 
IRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling MethodsIRJET - Reaearch on Erosion Controlling Methods
IRJET - Reaearch on Erosion Controlling Methods
 
Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...Design appraisal for the construction of a water off-take channel following c...
Design appraisal for the construction of a water off-take channel following c...
 
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptxUnit V - EIA case studies pertaining to Infrastructure Projects.pptx
Unit V - EIA case studies pertaining to Infrastructure Projects.pptx
 
Metro Work
Metro WorkMetro Work
Metro Work
 
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
ENVIRONMENTAL IMPACT ASSESSMENT FOR ANDHERI (E)- DAHISAR (E) CORRIDOR OF MUMB...
 
EIA report on thermal power project
EIA report on thermal power projectEIA report on thermal power project
EIA report on thermal power project
 
IRJET- Ground Water Control Method Simulation in Sphinx Area
IRJET-  	  Ground Water Control Method Simulation in Sphinx AreaIRJET-  	  Ground Water Control Method Simulation in Sphinx Area
IRJET- Ground Water Control Method Simulation in Sphinx Area
 
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone AreasGuidelines for Planning and Construction of Roads in cyclone Prone Areas
Guidelines for Planning and Construction of Roads in cyclone Prone Areas
 
EIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVEREIA PRESENTATION ON NARMDA RIVER
EIA PRESENTATION ON NARMDA RIVER
 
KISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIAKISHANGARH AIRPORT EIA
KISHANGARH AIRPORT EIA
 
Pathway to Net Zero and EIA
Pathway to Net Zero and EIAPathway to Net Zero and EIA
Pathway to Net Zero and EIA
 
Eia procedures
Eia proceduresEia procedures
Eia procedures
 
A new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technologyA new soil tunnelling machine with waterjet technology
A new soil tunnelling machine with waterjet technology
 
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA)
 
Supertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - RotherhamSupertram - Tram Train Pilot - Sheffield - Rotherham
Supertram - Tram Train Pilot - Sheffield - Rotherham
 
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
Evaluating Interface Properties and Predicting Landfill Liner Stability Under...
 
Modern fastening systems in tunnel construction
Modern fastening systems in tunnel constructionModern fastening systems in tunnel construction
Modern fastening systems in tunnel construction
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Presentation on DMRC

  • 2. EXECUTIVE SUMMARY Policy, Legal & Administrative Framework The proposed Corridor, Central Secretariat – Badarpur was proposed by DMRC to be part of 2nd Phase on the instance of Sports Authority of India, and Delhi Police. The proposed project would be governed by various Acts, Rules and regulations set by the Ministry of Environment and Forests (MoEF) at the Central level and other regulatory agencies at the State and local level.
  • 3. Project Description  The Metro corridor line from Central Secretariat to Badarpur Border is 20.16km with the following stations namely (1) Central Secretariat (2) Khan Market (3) J.L.N Stadium, (4) Jangpura (5) Lajpat Nagar, (6) Mool Chand, (7) East of Kailash, (8) Nehru Place (9) Kalkaji Mandir, (10)Govindpuri, (11) Okhla, (12) Jasola, (13)Sarita Vihar, (14) Mohan Estate, (15) Tughlakabad and(16)Badarpur.  Central Secretariat is an interchange station, which is a connecting Central Secretariat- Vishwavidyalaya (Already operational) section in the north and Central Secretariat- Qutab Minar- Arjangarh- Gurgaon in the south with the proposed corridor .
  • 4. Environmental Baseline Data The baseline environmental status is established by determining the baseline levels of significant environmental parameters, which could be affected by the implementation of the project. the baseline data include establishing the present status of physico -chemical, biological and socio - economic aspects of the study area relevant to the proposed construction of metro corridor between Central Secretariat and Badarpur. Accordingly, following important parameters were identified for the detailed baseline data collection through field studies:  · Air Environment  · Noise Environment  · Water Environment  · Soil Environment  · Green Cover Survey  · Socio – Economic component  · Land – use pattern along the proposed corridors
  • 5. NEGATIVEENVIRONMENTALIMPACTS  The primary function of an environmental impact assessment study is to predict and quantify the magnitude of impacts, evaluate and assess the importance of the identified changes and formulate plans to monitor and mitigate the actual changes.  Environmental impacts could be positive or negative, direct or indirect, local, regional or global, reversible or irreversible. Some of the negative impacts associated with the metro rail project have been summarized below under the following headings:  · Impacts due to project location,  · Impacts due to construction works, and  · Impacts due to project operation.
  • 6. IMPACTS DUE TO PROJECT LOCATION  a) Change of Land use The alignment is mostly elevated. Both the land requirement and change of land use is minimum. The development on the study area will not bring any significant changes in the land use pattern, since the new proposed depot is planned in mostly vacant area. The development ofstation buildings will not have any significant impact on the land use ifuture; however, it will enhance the aesthetics due to development of a modern building and surrounding horticulture. The change in land use is estimated to be 54.36 Hect. (includes both government and private land)  b) Loss of Trees Total loss of Trees (Nos.) 4401 Average cost of one tree (Rs.) 700 TOTAL LOSS (RS. LAKHS) 30.80 LAKHS
  • 7.  c) Loss of Historical and Cultural Monuments No historical/cultural monuments will be affected as a result of the proposed development of project. d) Socio-Economic Impacts Land required for construction of the project is around 54 Ha. It does involve acquisition of both government and private land, and also involves social issues such as resettlement and rehabilitation of 589 families. e) Utilities / Drainage Problem The alignment is mostly planned to run through the urban area, underground and above ground. The alignment will cross drains/nalas large number of sub-surface, surface and utility services, viz. sewer, water mains, storm water drains, telephone cables, overhead electrical transmission lines, electric pipes, traffic signals etc. These utilities/ services are essential and have to be maintained in working order during different stages of construction by temporary/permanent diversions or by supporting in position. In addition, cross drainage works such as bridges, culverts etc. will be required.
  • 8. f) Risk due to Earthquakes The project area falls under seismic zone IV as per the Seismic Zoning Map of India (IS 1893, Part-I, 2002). Necessary seismic factors suggested by Indian Meteorology Department (IMD) shall be incorporated suitably while designing the structures to safeguard against earthquake risks.
  • 9. IMPACTSDUETOPROJECTCONSTRUCTION  a) Soil Erosion at Construction Site  The total quantity of earthwork in excavation would be about 9,75,000 cum  Run off from unprotected excavated areas, and underground tunnel faces can result in excessive soil erosion, especially when the erodability of soil is high. Exposure of loose soil to rain water will increase turbidity in the run-off.  b) Health Risk at Construction Site  Health risks include disease hazards due to lack of sanitation facilities (water supply and human waste disposal) and insect vector disease hazards of local workers and disease hazards to the local population.Mitigation measures should include proper water supply, sanitation, drainage, health care and human waste disposal facilities. In addition to these, efforts need to be made to avoid water spills, adopt disease control measures and employment of local labour.
  • 10. .  c) Traffic Diversions and Risk to Existing Buildings During construction, traffic diversions on roads will be essentially required. As most of the construction activities will be confined to centre of the road and most of the roads are double lane, it will be appropriate that the side lanes may also be utilised for traffic and also for smooth progress of construction activities. Advance information on communication systems will be an advantage to users of any particular road.  d) Impact due to Solid Waste Disposal  Problems could arise from dumping of construction spoils (Concrete, bricks) waste materials (from contractor camps) etc. causing surface and ground water pollution.  e) Impact on Water Quality  Construction activities may have impact on water bodies due to disposal of waste. The waste could be due to the spillage of construction materials, dumping of used water from the stone crusher, oils and greases, and labour camp.
  • 11. f) Impact on air quality In such type of projects, air pollution occurs mainly due to fugitive emissions/dust generation from various construction activities during construction period and vehicular emission during operation period. The impacts on air environment, which will be during project construction phase are briefly discussed below.  During construction phase, SPM is expected to be the main pollutant associated with the earthwork activities and material handling. g) Like air environment, impact on noise is also anticipated during construction and operation phase of the project cycle. Noise at a construction site varies relative to the particular operation in progress .Operation can be divided into five consecutive phases; 1. Ground Clearing 2. Excavation 3. Foundation 4. Erection 5. Finishing
  • 12. IMPACTS DUE TO PROJECT OPERATION  a) Oil Pollution Oil spillage during change of lubricants, cleaning and repair processes, in the maintenance of rolling stock, is very common. The spilled oil should be trapped in grit chamber for settling of suspended matter.  b) Noise The main sources of noise are traction motors, cooling fans, wheel-rail interaction, electric generator and miscellaneous noise from rolling stock.
  • 13.  c) Accidental Hazards In view of the hazards potential involved due to failure of system and accident the on-site and off- site emergency measures have been formulated and will be implemented.  d) Water Supply  Public Health facilities such as water supply, sanitation and toilets are very much needed at the stations; CPHEEO has recommended 45 litres per day, water supply to persons working at stations. S.NO . ITEM TOTAL( cubic m) DAILY(cub ic m) 1. Personal use 0.9 0.9 2. Make up water for fire fighting 108.00 10.80 3. Washing of platform 6.75 6.75 4. For AC/ Ventilation 1.50 1.50 5. Wastage 11.71 1.99 total 128.86 21.94
  • 14.  e) Railway Station Refuse The refuse from railway station includes; Garbage, Rubbish, and Floor Sweepings. The collection and removal of refuse in a sanitary manner from the Station is of importance for effective vector control, aesthetic improvement, and nuisance and pollution abatement.
  • 15. POSITIVE ENVIRONMENTAL IMPACTS some of the positive benefits expected from the proposed metro corridors have been given below: (i) Reduced travel time resulting in increased accessibility (ii) Safe and comfortable mode of transportation (iii) Reduced traffic resulting in reduced congestion on roads due to the probable shifting of significant proportion of private vehicles to the metro (iv) Reduced fuel consumption from the transport sector resulting in precious foreign exchange (v) Reduction in vehicular emission loads resulting in improved air quality of the region (vi) Reduction in road accidents resulting in reduced death and injury during road accidents (vii) Increased job/employment opportunities (direct and indirect both) (viii) Sense of pride to the city and country having a world-class facility
  • 16. Quantity saved 2011 2013 2015 2019 2021 Total Road Passkm 4086402 4286658 5035603 5148818 6421721 Daily vehicle saving 546913 557373 590535 689103 736635 Daily vehicle demand 11557 11778 14241 15566 18161 Daily travel time saving (min) 12964392 13212359 13456506 137226511 18714119 Daily fuel saved(LITRE) 43633 44468 47113 54977 68569 Annual fuel saved (tonnes) 15926 16707 17196 20067 25028 Annual number of all accidents saved 104 106 114 117 120 TABLE : QUANTIFICATION OF BENEFITS
  • 17. S.N O PARAMETER NO IMPACT NEGATIVE IMPACT POSITI V IMPAC T 1. Rehabilitation and Resettlement * 2. Change of land use * 3. Impact on Historical/Cultural Monuments * 4. Drainage and utilities problems * 5. Loss of Trees * 6. Risk Due to EarthQuakes * 7. Soil Erosion pollution and health risk at construction site * 8. Traffic diversion and risk to existing buildings * 9. Soil disposal problem * CHECKLIST OF IMPACTS
  • 18. S.NO PARAMETER NO NEGATIVE POSITIVE 10. EMPLOYMENT OPPORTUNITIES * 11 OIL POLLUTION * 12 NOISE AND VIBRATION * 13 WATER DEMANDS * 14 BENEFITS TO ECONOMY * 15 QUICK SERVICE AND SAFETY * 16 LESS FUEL CONSUMPTION * 17 LESS AIR POLLUTION * 18 CARBON DIOXIDE REDUCTION * 19 REDUCTION IN BUSES NUMBER * 20 REDUCTION IN TRAFFIC CONGESTION *
  • 19. ENVIRONMENTALMANAGEMENTPLAN The proposed Central Secretariat-Badarpur Metro Corridor will provide quick service and safety, traffic congestion reduction, less fuel consumption, employment opportunity, and less air pollution on one hand and problems of Rehabilitation and Resettlement (R&R), soil disposal, etc. on other hand. The environmental issues likely to develop during project construction and operation phases could be minimized by making necessary provision in the project design and adopting Environmental Management Plan (EMP).
  • 20. ImplementationofEnvironmentalManagementPlan A common problem encountered during implementation of environmental management plans of suchprojects is lack of environmental awareness among engineers and managers concerned with day to day construction activities, which can be solved through regular environmental training.  The major concern during the construction stage is that the contractors, due to lack of enforcement, would not practice good housekeeping, may intend to get unauthorized use of the easily available natural resources and other available infrastructure like roads and water resources. This would result in degradation of ambient air quality, water resources and land environment around the construction sites and workers camp .
  • 21. MITIGATION MEASURES The main aim of mitigation measures is to protect and enhance the existing environment of the project. These measures should have positive effects on environment. Some of these have been described in the following section which includes measures for: a) Compensation for Loss of Land, b) Compensation for Loss of Trees, c) Compensatory Afforestation and Fencing, d) Compensation for Relocation/Resettlement, e) Water Supply and Sanitation, f) Oil Pollution Control, g) Noise Control, h) Vibration Control, i) Soil Disposal, j) Rain Water Harvesting at Construction Depot Site, k) Green Belt Development, and l) Occupational Health Hazards and Control
  • 22. ENVIRONMENTAL MONITORING PLAN  Environmental monitoring programme is a vital process of any management plan of the development project.  The main objectives of environmental monitoring are: - to assess the changes in environmental conditions, - to monitor the effective implementation of mitigation measures, - to warn significant deteriorations in environmental quality for further prevention action.  In order to meet the above objectives the following parameters need to be monitored: - Rehabilitation and Resettlement Programme, - Afforestation, - Water Quality and Public Health, - Air and Noise Quality and - Soil Conservation Measures.
  • 23. SUMMARY OF ENVIRONMENTAL MONITORING PROGRAMME S.NO. ITEM PARAMETERS FREQUENCY LOCATION DURING PROJECT CONSTRUCTION PHASE 1. SOIL QUALITY Heavy Metals: Arsenic, Cadmium,Chromiu m, Lead and Mercury, Once before excavation for underground section One sample at each u/g station location 2 NOISE QUALITY Leq, Lmax, L10, L90 As per DMRC Environmental Manual As per DMRC Environmenta l Manual 3 VIBRATI ON Ppv/dB 24 hour sample,during construction activities that are prone to cause vibration Sensitive receptors(soci ally important places like hospitals, schools,
  • 24. NO. ITEM PARAMETER FREQUENCY LOCATION DURING PROJECT OPERATION PHASE 4 Treated Effluent from STP/ETP pH, BOD, COD, TSS, Oil and Grease Once every three months Before and after treatment from STP/ETP 5 Noise Quality Leq, Lmax, L10, L90 24 hour sample, Once a year Sensitive receptors 6 Vibration Ppv/dB 24 hour sample, twice a year for next three years Sensitive receptors 7 Air Quality SPM, RPM Two samples of 24 hrs each, once in a month. Depot Site/ every 5km (Total 5 locations)