SlideShare a Scribd company logo
Practical Design of Balanced
Cantilever Bridges
Piyush Santhalia
Project Engineer - AECOM
Image: Wikipedia
Piyush Santhalia
Contents
1. Introduction
2. Longitudinal Span Configuration
3. Construction Sequence
4. Cross Section
5. Support Conditions
6. Sub-Structure and Foundation
7. Prestressing Details
8. Design Check
9. Pre-Camber
10.Modelling & Other Suggestions
Piyush Santhalia
1. Introduction
• Cantilever construction method
– Very ancient technique
– Structure is built component by component above
ground level.
– More recently: Construction of Cable Stayed Bridges,
Extra-dosed Bridges etc.
– Prestressed Concrete Bridges
• Cast in situ Segments or Pre-cast segments
• Integral with Pier or On Bearings
• 60m – 300m span
Piyush Santhalia
1. Introduction
Balanced Cantilever Bridge :
- Cast-in-Situ Segments
- Integral with Pier
Image: Random Site in Delhi
Piyush Santhalia
2. Longitudinal Span Configuration
• Typical 3 Span system
– Mid Span: L
– End Spans: 0.6L to 0.7L (to control uplift in bearing)
L 0.6 L to 0.7L0.6 L to 0.7L
• Typical 4 or more Span (varying) system
0.6 L1 to 0.7L1 L1 (L1 + L2)/2 0.6 L2 to 0.7L2
Piyush Santhalia
2. Longitudinal Span Configuration
• No such luxury in today’s congested urban area
I. 34 + 60 + 34 m
II. 60 + 60 m
III. 37 + 70 + 67 + 55 + 34m
Piyush Santhalia
3. Construction Sequence
• Pier head : On ground supported staging
• Most of Segments:
– Erect/cast using Segment Lifter/Form Traveller
– Cantilevered out from preceding segment.
– Prestressing tendons running one of the cantilever to the other are
stressed.
– Symmetrical construction to minimize unbalanced moment on sub-
structure and foundation: Balanced Cantilever
– Cast portion (beyond 0.5 x L) of both End-spans Ground Supported
staging.
– Cast Stitch segments
• Stitch in the End – span
• Stitch in the Mid-span
• Levels of the Cantilever arms being stitched should be matched
• Segmentation: 2.5m to 4m or even 5m
– Construction Cycle
– Capacity of Form Traveller/Segment Lifter
Piyush Santhalia
3. Construction Sequence
Balanced Cantilever Bridge : Delhi Metro Phase III
60 + 60m span
Piyush Santhalia
3. Construction Sequence
Casting of Stitch at Mid-
span using suspender.
Balanced Cantilever Bridge :
Delhi Metro Phase III
(34 + 60 + 34m)
Piyush Santhalia
4. Cross-Section
L
H1 H2
• Highway Bridges
– Depth at Face of Pier, H1 : L/15 – L/18 (roughly)
– Depth at Mid-Span, H2 : L/30 – L/35 (roughly)
• Highway vs Railway Bridge
– 34+60+34m span CLC
Load Metro Highway
DL 463 463
SIDL 240 85
LL 262 134
Shear Force at Pier Face (ton)
Piyush Santhalia
4. Cross-Section
• Depth may vary
– Parabolic
– Cubically: need to check for insufficient depth around L/4
– Linearly varying depth
• Local thickening of soffit is required.
Piyush Santhalia
5. Support Conditions
• Box Girder – On simple bearing
– Stability check during construction
– Minimal secondary effect of Creep, Shrinkage and Prestressing
• Box Girder Integral with Intermediate Piers
– Check pier for un-balanced moment during construction.
– Pronounced secondary effect.
Piyush Santhalia
6. Sub-Structure and Foundation
• Flexibility
– High time period (lesser seismic force)
– Lower force due to secondary effects of creep, shrinkage
and Prestressing Tendons
– Twin Piers
𝐹 =
3𝐸𝐼
𝐿
δ
Piyush Santhalia
7. Prestressing Details
• Cantilever Tendons
– For holding the segments added during cantilever construction
– To take up the negative moment due to SW of Segments, SIDL and/or
Live Load
– At least 1 pair of tendon is anchored per segment.
• Continuity Tendons:
– To take up the force due to effects after the cantilever have been
stitched.
Piyush Santhalia
7. Prestressing Details
• Top Tendons
– Try to keep the web clear of the Tendons
• Bottom Tendons
– Keep the webs clear of the tendons as much as possible
– Keep tendons nearer to the webs as much as possible
– Enough prestressing for sections at mid-span to hog.
– Blister Blocks for anchoring of tendons
Piyush Santhalia
8. Analysis
• Why Construction Stage Analysis
Bending Moment Diagram due to SW: Simultaneous Analysis
Bending Moment Diagram due to SW: Sequential Analysis
Piyush Santhalia
8. Analysis
• Why Construction Stage Analysis
– Time Dependent Effects of Creep and Shrinkage
• No secondary effect of Creep and Shrinkage before stitching
Structure before casting of stitch segment
Deformation
due to
Shrinkage.
Residual Shrinkage Strain:
i) After 3 days – 4.3 x 10-4
ii) After 14 days – 2.5 x 10-4
Piyush Santhalia
8. Analysis
• Why Construction Stage Analysis
– Time Dependent Effects of Creep and Shrinkage
• Different age of concrete at different loading
– Modulus of Elasticity increases with time
Piyush Santhalia
9. Design Check
• Sub-structure & Foundation
– Regular Checks for Foundation & Piers
– Secondary effects of CR, SH & PS should be considered
– Check during construction (stability or adequacy)
i) Imbalance of 1 segment ii) Accidental Fall of Empty Form Traveller
Imbalance of 1 Segment
Fall of empty FT
Piyush Santhalia
9. Design Check
• Super Structure
– Check during construction (ULS & SLS)
• Maximum Compression at each stage
– Maximum compression: 0.48fck (IRC 112-2011)
• Maximum Tension at each stage
– Minimum compression of 0.2fck - Precast segments (temporary Prestressing)
– Maximum tension of 1 MPa – Cast in situ segments.
• Loads
– SW of Segments
– Form Traveller (usually half the weight of heaviest segment) + Shutter
– Weight of Green Concrete
– Construction Live Load
– Wind / EQ (cantilever)
Piyush Santhalia
9. Design Check
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Piyush Santhalia
9. Design Check
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Piyush Santhalia
9. Design Check
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Piyush Santhalia
9. Design Check
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Piyush Santhalia
9. Design Check
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Piyush Santhalia
9. Design Check
Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2)
Stress check during Construction:
37 + 70 + 67 + 55 + 34m
Piyush Santhalia
9. Design Check
• Super Structure
– Check during Service (0 - Design life)
• Loads
– Regular Loads (SW, SIDL, LL)
– Prestressing
» Losses up to design life should be considered
» Secondary effects are usually significant
– CR & SH: Secondary effects are significant.
– Temperature Variation
• SLS Checks
– Maximum Compression
» Maximum compression: 0.48fck (IRC 112-2011)
– Maximum Tension
Piyush Santhalia
9. Design Check
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Moment at the intermediate support
» Hogging for Normal Case
» Reversible in Seismic case
– Shear Check
» Varying depth: Should be checked at regular interval
• Critical at locations with kink
Piyush Santhalia
9. Design Check
• Super Structure
– Check during Service (0 - Design life)
• ULS Checks
– Shear Check
» Vertical component of Prestressing: reduces shear
» Resal Effect: Part of Shear is balanced by the component of Normal force
in the soffit slab.
Piyush Santhalia
10. Pre-Camber
Piyush Santhalia
10. Pre-Camber
• Why pre-camber
– Under permanent loads the deck should have achieved the
desired level.
• Desired Level at what time
– Concrete continues to sag/hog because of creep
– Achieving desired level at the end of design life: not logical
Piyush Santhalia
11. Modelling &other Suggestions
• For very wide or very deep section
– Line Beam modelling: up to 20% error
• Shear Lag effect
• Difference in rates of shrinkage and drying creep because of different thicknesses
of slabs.
• 3D model always yields larger deflections and larger Prestress losses
Ref: Excessive Long-Time Deflections of Prestressed Box Girders. I: Record-Span Bridge
in Palau and Other Paradigms - Zdeněk P. Bažant, Qiang Yu and Guang-Hua Li
• Modelling of Piles
• Give concrete more time to gain strength before prestressing
Piyush Santhalia
THANK YOU
Happy Designing

More Related Content

What's hot

CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
Fawad Najam
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
MD.Yeasin Mostafiz
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
ahsanrabbani
 
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
Eur Ing Valentinos Neophytou BEng (Hons), MSc, CEng MICE
 
Bridge loading
Bridge loadingBridge loading
Bridge loading
kapilpant12
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
University of Tikrit
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
David Collings
 
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
GLA University
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
Sachin Kulkarni
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
AKASH SHAH
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
Venkat Ramana Littu
 
Box culverts
Box culvertsBox culverts
Box culverts
sunil choudhary
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
Korutla Harish
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
VVIETCIVIL
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridge
Marian Joyce Macadine
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Pooja Lonare
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
Eddy Ankit Gangani
 
Bridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentalsBridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentals
Madujith Sagara
 

What's hot (20)

CE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie ModelsCE 72.52 - Lecture 7 - Strut and Tie Models
CE 72.52 - Lecture 7 - Strut and Tie Models
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
 
Bridge loading
Bridge loadingBridge loading
Bridge loading
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
 
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE &  NON DESTRUCTIVE TE...
ANALYSIS AND DESIGN OF RAILWAY STEEL AND COCRETE BRIDGE & NON DESTRUCTIVE TE...
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
 
Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
05 chapter 6 mat foundations
05 chapter 6 mat foundations05 chapter 6 mat foundations
05 chapter 6 mat foundations
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridge
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
IRC-6-2016.pdf
IRC-6-2016.pdfIRC-6-2016.pdf
IRC-6-2016.pdf
 
Bridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentalsBridge loading and bridge design fundamentals
Bridge loading and bridge design fundamentals
 

Viewers also liked

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVILGIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
AM Publications
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Cantilever bridge
Cantilever bridgeCantilever bridge
Cantilever bridge
Waiaupa4
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
Ajay Kumar
 
Pt giai doan thi cong su dung fcm wizard
Pt giai doan thi cong su dung fcm wizardPt giai doan thi cong su dung fcm wizard
Pt giai doan thi cong su dung fcm wizard
Ttx Love
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
Palmer Consulting Services, LLC
 
Midas tinh toan_cau_duc_hang
Midas tinh toan_cau_duc_hangMidas tinh toan_cau_duc_hang
Midas tinh toan_cau_duc_hang
Ttx Love
 
L5 Vertical Structure Pt 3
L5 Vertical Structure Pt 3L5 Vertical Structure Pt 3
L5 Vertical Structure Pt 3
chuhonsan
 
Concrete bridge practice by v k raina
Concrete bridge practice by v k rainaConcrete bridge practice by v k raina
Concrete bridge practice by v k raina
Sachin Ramesh
 
PT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSPT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGS
Francois Lepers
 
V.k. raina concrete bridge practice analysis, design and enonomics 1994
V.k. raina concrete bridge practice analysis, design and enonomics    1994V.k. raina concrete bridge practice analysis, design and enonomics    1994
V.k. raina concrete bridge practice analysis, design and enonomics 1994SUJAN GHIMIRE
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
Micotol
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areas
Swapnali Kunjir
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly Areas
Shantanu Patil
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 
different designs of dental bridges
different designs of dental bridgesdifferent designs of dental bridges
different designs of dental bridges
Yasmin Al-taie
 
Bridges
BridgesBridges
Bridges
Deewas Kharka
 

Viewers also liked (20)

segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVILGIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
GIRDER DESIGN OF A BALANCED CANTILEVER BRIDGE WITH ANALYSIS USING MIDAS CIVIL
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Cantilever bridge
Cantilever bridgeCantilever bridge
Cantilever bridge
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
 
Pt giai doan thi cong su dung fcm wizard
Pt giai doan thi cong su dung fcm wizardPt giai doan thi cong su dung fcm wizard
Pt giai doan thi cong su dung fcm wizard
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 
Midas tinh toan_cau_duc_hang
Midas tinh toan_cau_duc_hangMidas tinh toan_cau_duc_hang
Midas tinh toan_cau_duc_hang
 
L5 Vertical Structure Pt 3
L5 Vertical Structure Pt 3L5 Vertical Structure Pt 3
L5 Vertical Structure Pt 3
 
Concrete bridge practice by v k raina
Concrete bridge practice by v k rainaConcrete bridge practice by v k raina
Concrete bridge practice by v k raina
 
PT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSPT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGS
 
V.k. raina concrete bridge practice analysis, design and enonomics 1994
V.k. raina concrete bridge practice analysis, design and enonomics    1994V.k. raina concrete bridge practice analysis, design and enonomics    1994
V.k. raina concrete bridge practice analysis, design and enonomics 1994
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Types of Movable bridges
Types of  Movable bridgesTypes of  Movable bridges
Types of Movable bridges
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areas
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly Areas
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
different designs of dental bridges
different designs of dental bridgesdifferent designs of dental bridges
different designs of dental bridges
 
Bridges
BridgesBridges
Bridges
 

Similar to Practical Design of Balanced Cantilever Bridges - Piyush Santhalia

02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
pulakrajpadhai
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
jose bonifacio de souza leite cuadros
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
AIT Solutions
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
Eva Lantsoght
 
Wilshire Grand Redevelopment Project
Wilshire Grand Redevelopment ProjectWilshire Grand Redevelopment Project
Wilshire Grand Redevelopment Project
American Society of Civil Engineers, Orange County Branch
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
SauravShahane
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
ProSIM R & D Pvt. Ltd.
 
Tony
TonyTony
Tony
TONY ROSE
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
Praveendubey82
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
Mani Das
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
Specialized Carriers & Rigging Association
 
200 questions and_answers_on_practical_civil_engineering_works_12.2008
200 questions and_answers_on_practical_civil_engineering_works_12.2008200 questions and_answers_on_practical_civil_engineering_works_12.2008
200 questions and_answers_on_practical_civil_engineering_works_12.2008
ALMASUR
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Cable-stayed Bridge final fig.pptx
Cable-stayed Bridge final     fig.pptxCable-stayed Bridge final     fig.pptx
Cable-stayed Bridge final fig.pptx
ShreeKunjPatel3
 
Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior Project
WSUME_2013_A-TEAM
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridges
Madujith Sagara
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
Shreya Thusoo
 
Secant pile wall for emergency dump pond
Secant pile wall for emergency dump pondSecant pile wall for emergency dump pond
Secant pile wall for emergency dump pond
Islam Mohamed, P.E, P.Eng
 
200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20worksajaipurushothaman
 

Similar to Practical Design of Balanced Cantilever Bridges - Piyush Santhalia (20)

02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
02_Practical_Design_Balanced_Cantilever_Bridges_Piyush_R1.pdf
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
 
Extending service life of existing bridges
Extending service life of existing bridgesExtending service life of existing bridges
Extending service life of existing bridges
 
Wilshire Grand Redevelopment Project
Wilshire Grand Redevelopment ProjectWilshire Grand Redevelopment Project
Wilshire Grand Redevelopment Project
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Seismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear StructuresSeismic Evaluation of Nuclear Structures
Seismic Evaluation of Nuclear Structures
 
Tony
TonyTony
Tony
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
2019 CRW - esign, Fabrication and Testing of Cantilever Beams and Triangle Pl...
 
200 questions and_answers_on_practical_civil_engineering_works_12.2008
200 questions and_answers_on_practical_civil_engineering_works_12.2008200 questions and_answers_on_practical_civil_engineering_works_12.2008
200 questions and_answers_on_practical_civil_engineering_works_12.2008
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Cable-stayed Bridge final fig.pptx
Cable-stayed Bridge final     fig.pptxCable-stayed Bridge final     fig.pptx
Cable-stayed Bridge final fig.pptx
 
Washinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior ProjectWashinton State University/Manchester Fuel Depot Senior Project
Washinton State University/Manchester Fuel Depot Senior Project
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridges
 
Stress ribbon bridge
Stress ribbon bridgeStress ribbon bridge
Stress ribbon bridge
 
Secant pile wall for emergency dump pond
Secant pile wall for emergency dump pondSecant pile wall for emergency dump pond
Secant pile wall for emergency dump pond
 
200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works200%20 questions%20and%20answers%20on%20ce%20works
200%20 questions%20and%20answers%20on%20ce%20works
 

Practical Design of Balanced Cantilever Bridges - Piyush Santhalia

  • 1. Practical Design of Balanced Cantilever Bridges Piyush Santhalia Project Engineer - AECOM Image: Wikipedia
  • 2. Piyush Santhalia Contents 1. Introduction 2. Longitudinal Span Configuration 3. Construction Sequence 4. Cross Section 5. Support Conditions 6. Sub-Structure and Foundation 7. Prestressing Details 8. Design Check 9. Pre-Camber 10.Modelling & Other Suggestions
  • 3. Piyush Santhalia 1. Introduction • Cantilever construction method – Very ancient technique – Structure is built component by component above ground level. – More recently: Construction of Cable Stayed Bridges, Extra-dosed Bridges etc. – Prestressed Concrete Bridges • Cast in situ Segments or Pre-cast segments • Integral with Pier or On Bearings • 60m – 300m span
  • 4. Piyush Santhalia 1. Introduction Balanced Cantilever Bridge : - Cast-in-Situ Segments - Integral with Pier Image: Random Site in Delhi
  • 5. Piyush Santhalia 2. Longitudinal Span Configuration • Typical 3 Span system – Mid Span: L – End Spans: 0.6L to 0.7L (to control uplift in bearing) L 0.6 L to 0.7L0.6 L to 0.7L • Typical 4 or more Span (varying) system 0.6 L1 to 0.7L1 L1 (L1 + L2)/2 0.6 L2 to 0.7L2
  • 6. Piyush Santhalia 2. Longitudinal Span Configuration • No such luxury in today’s congested urban area I. 34 + 60 + 34 m II. 60 + 60 m III. 37 + 70 + 67 + 55 + 34m
  • 7. Piyush Santhalia 3. Construction Sequence • Pier head : On ground supported staging • Most of Segments: – Erect/cast using Segment Lifter/Form Traveller – Cantilevered out from preceding segment. – Prestressing tendons running one of the cantilever to the other are stressed. – Symmetrical construction to minimize unbalanced moment on sub- structure and foundation: Balanced Cantilever – Cast portion (beyond 0.5 x L) of both End-spans Ground Supported staging. – Cast Stitch segments • Stitch in the End – span • Stitch in the Mid-span • Levels of the Cantilever arms being stitched should be matched • Segmentation: 2.5m to 4m or even 5m – Construction Cycle – Capacity of Form Traveller/Segment Lifter
  • 8. Piyush Santhalia 3. Construction Sequence Balanced Cantilever Bridge : Delhi Metro Phase III 60 + 60m span
  • 9. Piyush Santhalia 3. Construction Sequence Casting of Stitch at Mid- span using suspender. Balanced Cantilever Bridge : Delhi Metro Phase III (34 + 60 + 34m)
  • 10. Piyush Santhalia 4. Cross-Section L H1 H2 • Highway Bridges – Depth at Face of Pier, H1 : L/15 – L/18 (roughly) – Depth at Mid-Span, H2 : L/30 – L/35 (roughly) • Highway vs Railway Bridge – 34+60+34m span CLC Load Metro Highway DL 463 463 SIDL 240 85 LL 262 134 Shear Force at Pier Face (ton)
  • 11. Piyush Santhalia 4. Cross-Section • Depth may vary – Parabolic – Cubically: need to check for insufficient depth around L/4 – Linearly varying depth • Local thickening of soffit is required.
  • 12. Piyush Santhalia 5. Support Conditions • Box Girder – On simple bearing – Stability check during construction – Minimal secondary effect of Creep, Shrinkage and Prestressing • Box Girder Integral with Intermediate Piers – Check pier for un-balanced moment during construction. – Pronounced secondary effect.
  • 13. Piyush Santhalia 6. Sub-Structure and Foundation • Flexibility – High time period (lesser seismic force) – Lower force due to secondary effects of creep, shrinkage and Prestressing Tendons – Twin Piers 𝐹 = 3𝐸𝐼 𝐿 δ
  • 14. Piyush Santhalia 7. Prestressing Details • Cantilever Tendons – For holding the segments added during cantilever construction – To take up the negative moment due to SW of Segments, SIDL and/or Live Load – At least 1 pair of tendon is anchored per segment. • Continuity Tendons: – To take up the force due to effects after the cantilever have been stitched.
  • 15. Piyush Santhalia 7. Prestressing Details • Top Tendons – Try to keep the web clear of the Tendons • Bottom Tendons – Keep the webs clear of the tendons as much as possible – Keep tendons nearer to the webs as much as possible – Enough prestressing for sections at mid-span to hog. – Blister Blocks for anchoring of tendons
  • 16. Piyush Santhalia 8. Analysis • Why Construction Stage Analysis Bending Moment Diagram due to SW: Simultaneous Analysis Bending Moment Diagram due to SW: Sequential Analysis
  • 17. Piyush Santhalia 8. Analysis • Why Construction Stage Analysis – Time Dependent Effects of Creep and Shrinkage • No secondary effect of Creep and Shrinkage before stitching Structure before casting of stitch segment Deformation due to Shrinkage. Residual Shrinkage Strain: i) After 3 days – 4.3 x 10-4 ii) After 14 days – 2.5 x 10-4
  • 18. Piyush Santhalia 8. Analysis • Why Construction Stage Analysis – Time Dependent Effects of Creep and Shrinkage • Different age of concrete at different loading – Modulus of Elasticity increases with time
  • 19. Piyush Santhalia 9. Design Check • Sub-structure & Foundation – Regular Checks for Foundation & Piers – Secondary effects of CR, SH & PS should be considered – Check during construction (stability or adequacy) i) Imbalance of 1 segment ii) Accidental Fall of Empty Form Traveller Imbalance of 1 Segment Fall of empty FT
  • 20. Piyush Santhalia 9. Design Check • Super Structure – Check during construction (ULS & SLS) • Maximum Compression at each stage – Maximum compression: 0.48fck (IRC 112-2011) • Maximum Tension at each stage – Minimum compression of 0.2fck - Precast segments (temporary Prestressing) – Maximum tension of 1 MPa – Cast in situ segments. • Loads – SW of Segments – Form Traveller (usually half the weight of heaviest segment) + Shutter – Weight of Green Concrete – Construction Live Load – Wind / EQ (cantilever)
  • 21. Piyush Santhalia 9. Design Check Stress check during Construction: 37 + 70 + 67 + 55 + 34m Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2)
  • 22. Piyush Santhalia 9. Design Check Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m
  • 23. Piyush Santhalia 9. Design Check Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m
  • 24. Piyush Santhalia 9. Design Check Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m
  • 25. Piyush Santhalia 9. Design Check Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m
  • 26. Piyush Santhalia 9. Design Check Stresses at Top Fibre due to DL + PS + CR + SH (N/mm2) Stresses at Bottom Fibre due to DL + PS + CR + SH (N/mm2) Stress check during Construction: 37 + 70 + 67 + 55 + 34m
  • 27. Piyush Santhalia 9. Design Check • Super Structure – Check during Service (0 - Design life) • Loads – Regular Loads (SW, SIDL, LL) – Prestressing » Losses up to design life should be considered » Secondary effects are usually significant – CR & SH: Secondary effects are significant. – Temperature Variation • SLS Checks – Maximum Compression » Maximum compression: 0.48fck (IRC 112-2011) – Maximum Tension
  • 28. Piyush Santhalia 9. Design Check • Super Structure – Check during Service (0 - Design life) • ULS Checks – Moment at the intermediate support » Hogging for Normal Case » Reversible in Seismic case – Shear Check » Varying depth: Should be checked at regular interval • Critical at locations with kink
  • 29. Piyush Santhalia 9. Design Check • Super Structure – Check during Service (0 - Design life) • ULS Checks – Shear Check » Vertical component of Prestressing: reduces shear » Resal Effect: Part of Shear is balanced by the component of Normal force in the soffit slab.
  • 31. Piyush Santhalia 10. Pre-Camber • Why pre-camber – Under permanent loads the deck should have achieved the desired level. • Desired Level at what time – Concrete continues to sag/hog because of creep – Achieving desired level at the end of design life: not logical
  • 32. Piyush Santhalia 11. Modelling &other Suggestions • For very wide or very deep section – Line Beam modelling: up to 20% error • Shear Lag effect • Difference in rates of shrinkage and drying creep because of different thicknesses of slabs. • 3D model always yields larger deflections and larger Prestress losses Ref: Excessive Long-Time Deflections of Prestressed Box Girders. I: Record-Span Bridge in Palau and Other Paradigms - Zdeněk P. Bažant, Qiang Yu and Guang-Hua Li • Modelling of Piles • Give concrete more time to gain strength before prestressing