SlideShare a Scribd company logo
Secant Pile Wall
Peer Review
Assumptions, Modeling and Design
Emergency Dump Pond (EDP)
Secant pile walls are formed by drilling secondary piles
between previously installed primary piles to form a
continuous system with mechanical interlocking joints.
What are Secant Pile Walls?
Circular Secant Pile Wall
Emergency Dump Pond (EDP)
40m pond diameter and 13m deep excavation
Project Requirements
• Dumping pond with vertical sides for cleanout. Earth
Ponds are difficult to clean out.
• Close to the primary separation cell (PSC).
• Construction of EDP cannot interfere with PSC erection.
• EDP Pond Required for 1.5 PSC Volume.
• Concern about soil profile (boulders) limited maximum
depth of EDP.
• Pond would be water resistant, not water tight.
Conceptualization
• There are two fundamental considerations that affect the
conceptualization of a secant system;
– Limiting Geometric Considerations:
– Analysis and Design Considerations:
• Some Analysis and Design Considerations are inter-related with the Geometric restraints
• Reinforce each section or reinforce alternate piles?
– Initial concept was not excessively deep and in compressive
hoop stress. Assumes arch develops to reinforced pile.
– Hoop Stress = Pressure X Radius/Thickness
a) Pond diameter and depth are determined as per the
required volume.
b) Estimate the required overlap between primary and
secondary piles. Typical tolerance for CIP piles is +/-75mm
Horizontal and 2% out of Plumb, we decreased the
tolerance to +/- 25mm Horizontal and 0.5% out of Plumb
to ensure contact of the piles at the bottom of excavation.
c) No gap allowed between piles above the pond excavation
level (pond slab on grade). Decided to accept some
discontinuity below the slab depth based on a perception
of a low probability of occurrence.
Out of plumb
0.5% Max.
Pile deviation
+/- 25mm Max.
Limiting Geometrical Criteria.
Reinforce each section or reinforce alternate piles?
Initial concept was not excessively deep and assumed in
compressive hoop stress. Assumed arch develops to transfer
loads to reinforced pile, reinforce every second pile.
Fundamentals of the Design and Analysis: Hoop Stress = Pr/t,
Moment, Shear, Bearing, Active, Passive, At Rest.
Strength yes, but do we care about Serviceability?
Analysis and Design Considerations
Two Design Conditions:
During Excavation to 13.5 meters depth. Ring beam installed prior
to excavation. Lateral earth pressure within excavation is Ka or
(Ko?)? Pile section below the excavation is Ka, Ko or Kp?
During operation. Slab at 12.5 meters supports and defines Ko
section. Pile section below slab resisted by Kp. (or does it??)
Loading and Load Combinations.
a) Piles self weight.
b) Lateral Earth Pressure
a) At Rest pressure coefficient (Ko) used from the top of piles
down to the excavated depth. Ring beam installed prior to
excavation. ( Ko=1 in case of frozen soil or Ko=0.53 unfrozen).
b) Active pressure below the excavation level was resisted by
springs simulating passive earth pressure.
c) Surcharge load of 12KPa acting uniformly for full extent of the pile.
Later refined to Terzaghi and Peck equations for consideration of an
adjacent pump house (initially assumed on piles but now on gravel
pad).
d) Wheel load as per CL-800 truck, axel load = 175KN.
e) No surcharge or wheel load was assumed to transfer lateral loads
when on top of frozen soil.
f) All loading factored for Limit States.
Lateral Earth pressure on piles
What is the structural analysis model?
•Unlinked vertical frame elements represent Piles with ring beam on top and lateral springs along the
embedded length below the excavation to represent the passive earth pressure “pile overlap ignored in
this case”.
•A 600mm wall modeled as a plate element to represent the overlapped piles system with ring beam on
top and soil springs.
•Horizontal struts added to the first model between piles all around to represent pile interlock, struts are
compression only members spaced at 1m vertically.
Unlinked Piles with ring beam and soil springs.
Deflection and bending moment
A 600mm wall modeled as an FEA with ring beam and soil springs
Linked piles
Piles with soil springs
Compression only members added between vertical frame elements.
Disconnected members to represent out of plumb.
Final Structural Model
During Excavation Case :
• Excavation expected to be in the spring so EDP wall will not exposed to
frost action so ko=0.53.
• Piles are unrestrained at the bottom of excavation level as the slab on
grade not constructed yet.
During Operation Case:
•Frost case will govern the lateral earth pressure for design, Ko=1.0.
•The slab on grade constructed at the bottom of excavation level will
provide lateral support to the piles at that level.
Two final structural models was developed with two main differences .
During Excavation
Slab represented as link members to centre
Deflection and bending moment
During Operation(Slab represented as pinned constraint)
Analysis and Design
• Do we trust the model? Is it representing Hoop Stress
contribution correctly?
• All sections must meet the fundamentals. What is
the hoop stress? Stress = Pr/t. Does the hoop
stress exceed the allowable bearing stress (clause
10.8.1- 0.85 Фc fc’ A)
• When we looked at the hoop stress it exceeded our
contact area. What to do?
– Increase pile size?
– Increase overlap by increasing number of piles
• All other considerations must be met, Shear, Moment
and deflection.
Final Design
• Meet the fundamentals – make sure transfer of
theoretical maximum hoop stress is possible. Bearing
governed the initial design, we increased the overlap by
adding piles to ensure the foundation of the design
philosophy, hoop stress, was maintained.
• Design is refined by establishing the extreme boundaries
to guide us toward acceptance of model results. Look at
no hoop stress and full hoop stress.
• There are no templates, the design relies heavily on
engineering judgement. Do not try this at home.

More Related Content

What's hot

Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel examplemamilli
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps design
Nada Zarrak
 
Basics of Foundation Design
Basics of Foundation DesignBasics of Foundation Design
Basics of Foundation Design
duraocorreia
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.
MD.MAHBUB UL ALAM
 
4. Shallow Foundations
4. Shallow Foundations4. Shallow Foundations
4. Shallow Foundations
Godbless I Kedes
 
Chapter 2 design loads(3)
Chapter 2 design loads(3)Chapter 2 design loads(3)
Chapter 2 design loads(3)
FahadYaqoob7
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Muhammad Irfan
 
Design of columns biaxial bending as per IS 456-2000
Design of columns  biaxial bending as per IS 456-2000Design of columns  biaxial bending as per IS 456-2000
Design of columns biaxial bending as per IS 456-2000
PraveenKumar Shanmugam
 
COMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdfCOMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdf
Zeinab Awada
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
AHMED NADIM JILANI
 
Design of isolated footing by ACI code
Design of isolated footing by ACI codeDesign of isolated footing by ACI code
Design of isolated footing by ACI code
Mahmoud Al-Sharawi
 
Footing design(09.02.03.096)
Footing design(09.02.03.096)Footing design(09.02.03.096)
Footing design(09.02.03.096)
Zawad khalil
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
Puspendu Ray
 
Design of mat and combined footing
Design of mat and combined footingDesign of mat and combined footing
Design of mat and combined footing
Md Faiz Ali
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
PraveenKumar Shanmugam
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacity
Abhishek Mangukiya
 
Seminar piled raft_foundation
Seminar piled raft_foundationSeminar piled raft_foundation
Seminar piled raft_foundation
Almotasem Darawish
 
Column design.ppt
Column design.pptColumn design.ppt
Column design.ppt
Samirsinh Parmar
 
Sheet pile and bulkhead (usefulsearch.org) (useful search)
Sheet pile and bulkhead (usefulsearch.org)  (useful search)Sheet pile and bulkhead (usefulsearch.org)  (useful search)
Sheet pile and bulkhead (usefulsearch.org) (useful search)
Make Mannan
 

What's hot (20)

Rc corbel example
Rc corbel exampleRc corbel example
Rc corbel example
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps design
 
Basics of Foundation Design
Basics of Foundation DesignBasics of Foundation Design
Basics of Foundation Design
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.
 
4. Shallow Foundations
4. Shallow Foundations4. Shallow Foundations
4. Shallow Foundations
 
Chapter 2 design loads(3)
Chapter 2 design loads(3)Chapter 2 design loads(3)
Chapter 2 design loads(3)
 
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
Geotechnical Engineering-II [Lec #21: Lateral Earth Pressure)
 
Design of columns biaxial bending as per IS 456-2000
Design of columns  biaxial bending as per IS 456-2000Design of columns  biaxial bending as per IS 456-2000
Design of columns biaxial bending as per IS 456-2000
 
Wind_Load
Wind_LoadWind_Load
Wind_Load
 
COMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdfCOMPOSITE BEAMS.pdf
COMPOSITE BEAMS.pdf
 
DESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTUREDESIGN OF STEEL STRUCTURE
DESIGN OF STEEL STRUCTURE
 
Design of isolated footing by ACI code
Design of isolated footing by ACI codeDesign of isolated footing by ACI code
Design of isolated footing by ACI code
 
Footing design(09.02.03.096)
Footing design(09.02.03.096)Footing design(09.02.03.096)
Footing design(09.02.03.096)
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
 
Design of mat and combined footing
Design of mat and combined footingDesign of mat and combined footing
Design of mat and combined footing
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacity
 
Seminar piled raft_foundation
Seminar piled raft_foundationSeminar piled raft_foundation
Seminar piled raft_foundation
 
Column design.ppt
Column design.pptColumn design.ppt
Column design.ppt
 
Sheet pile and bulkhead (usefulsearch.org) (useful search)
Sheet pile and bulkhead (usefulsearch.org)  (useful search)Sheet pile and bulkhead (usefulsearch.org)  (useful search)
Sheet pile and bulkhead (usefulsearch.org) (useful search)
 

Similar to Secant pile wall for emergency dump pond

Understanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case StudyUnderstanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case Study
Abhimanyu Singhal
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tank
Aamir Patni
 
dcs ppt .pptx
dcs ppt .pptxdcs ppt .pptx
dcs ppt .pptx
shaik saifulla
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1Keith Daggett
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
Shivananda Roy
 
Well foundation
Well foundationWell foundation
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Hoa Nguyen
 
Pile cap analysis and design.pdf
Pile cap analysis and design.pdfPile cap analysis and design.pdf
Pile cap analysis and design.pdf
sangeetha485835
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .
Udayram Patil
 
4. Types-of Foundations.pdf
4. Types-of Foundations.pdf4. Types-of Foundations.pdf
4. Types-of Foundations.pdf
EmmanuelKiamaMutinda
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptx
kuba9
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
Abhishek Paswan
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
satheeskumarv2
 
Pilework
PileworkPilework
Pilework
Rajiva Gupta
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
MitaliShelke
 
A Critical Review of Flat Slabs under different parameters
A Critical Review of Flat Slabs under different parametersA Critical Review of Flat Slabs under different parameters
A Critical Review of Flat Slabs under different parameters
IRJET Journal
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
DYPCET
 
Design of lifts & escalators
Design of lifts & escalatorsDesign of lifts & escalators
Design of lifts & escalators
Shubham Arora
 
Intze ppt
Intze pptIntze ppt
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
IJMER
 

Similar to Secant pile wall for emergency dump pond (20)

Understanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case StudyUnderstanding Gridshell Structures - Mannheim Multihalle Case Study
Understanding Gridshell Structures - Mannheim Multihalle Case Study
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tank
 
dcs ppt .pptx
dcs ppt .pptxdcs ppt .pptx
dcs ppt .pptx
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Well foundation
Well foundationWell foundation
Well foundation
 
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design NoteAuber_Steel fiber reinforcement concrete_Slab on ground-Design Note
Auber_Steel fiber reinforcement concrete_Slab on ground-Design Note
 
Pile cap analysis and design.pdf
Pile cap analysis and design.pdfPile cap analysis and design.pdf
Pile cap analysis and design.pdf
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .
 
4. Types-of Foundations.pdf
4. Types-of Foundations.pdf4. Types-of Foundations.pdf
4. Types-of Foundations.pdf
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptx
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
 
reinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.pptreinforced-cement-concrete_prof-aquib.ppt
reinforced-cement-concrete_prof-aquib.ppt
 
Pilework
PileworkPilework
Pilework
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
A Critical Review of Flat Slabs under different parameters
A Critical Review of Flat Slabs under different parametersA Critical Review of Flat Slabs under different parameters
A Critical Review of Flat Slabs under different parameters
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Design of lifts & escalators
Design of lifts & escalatorsDesign of lifts & escalators
Design of lifts & escalators
 
Intze ppt
Intze pptIntze ppt
Intze ppt
 
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
Economic Design of Water Tank of Different Shapes With Reference To IS: 3370 ...
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 

Secant pile wall for emergency dump pond

  • 1. Secant Pile Wall Peer Review Assumptions, Modeling and Design Emergency Dump Pond (EDP)
  • 2. Secant pile walls are formed by drilling secondary piles between previously installed primary piles to form a continuous system with mechanical interlocking joints. What are Secant Pile Walls?
  • 3.
  • 4. Circular Secant Pile Wall Emergency Dump Pond (EDP) 40m pond diameter and 13m deep excavation
  • 5. Project Requirements • Dumping pond with vertical sides for cleanout. Earth Ponds are difficult to clean out. • Close to the primary separation cell (PSC). • Construction of EDP cannot interfere with PSC erection. • EDP Pond Required for 1.5 PSC Volume. • Concern about soil profile (boulders) limited maximum depth of EDP. • Pond would be water resistant, not water tight.
  • 6. Conceptualization • There are two fundamental considerations that affect the conceptualization of a secant system; – Limiting Geometric Considerations: – Analysis and Design Considerations: • Some Analysis and Design Considerations are inter-related with the Geometric restraints • Reinforce each section or reinforce alternate piles? – Initial concept was not excessively deep and in compressive hoop stress. Assumes arch develops to reinforced pile. – Hoop Stress = Pressure X Radius/Thickness
  • 7. a) Pond diameter and depth are determined as per the required volume. b) Estimate the required overlap between primary and secondary piles. Typical tolerance for CIP piles is +/-75mm Horizontal and 2% out of Plumb, we decreased the tolerance to +/- 25mm Horizontal and 0.5% out of Plumb to ensure contact of the piles at the bottom of excavation. c) No gap allowed between piles above the pond excavation level (pond slab on grade). Decided to accept some discontinuity below the slab depth based on a perception of a low probability of occurrence. Out of plumb 0.5% Max. Pile deviation +/- 25mm Max. Limiting Geometrical Criteria.
  • 8. Reinforce each section or reinforce alternate piles? Initial concept was not excessively deep and assumed in compressive hoop stress. Assumed arch develops to transfer loads to reinforced pile, reinforce every second pile. Fundamentals of the Design and Analysis: Hoop Stress = Pr/t, Moment, Shear, Bearing, Active, Passive, At Rest. Strength yes, but do we care about Serviceability? Analysis and Design Considerations
  • 9. Two Design Conditions: During Excavation to 13.5 meters depth. Ring beam installed prior to excavation. Lateral earth pressure within excavation is Ka or (Ko?)? Pile section below the excavation is Ka, Ko or Kp? During operation. Slab at 12.5 meters supports and defines Ko section. Pile section below slab resisted by Kp. (or does it??)
  • 10.
  • 11.
  • 12.
  • 13.
  • 14. Loading and Load Combinations. a) Piles self weight. b) Lateral Earth Pressure a) At Rest pressure coefficient (Ko) used from the top of piles down to the excavated depth. Ring beam installed prior to excavation. ( Ko=1 in case of frozen soil or Ko=0.53 unfrozen). b) Active pressure below the excavation level was resisted by springs simulating passive earth pressure. c) Surcharge load of 12KPa acting uniformly for full extent of the pile. Later refined to Terzaghi and Peck equations for consideration of an adjacent pump house (initially assumed on piles but now on gravel pad). d) Wheel load as per CL-800 truck, axel load = 175KN. e) No surcharge or wheel load was assumed to transfer lateral loads when on top of frozen soil. f) All loading factored for Limit States.
  • 16.
  • 17.
  • 18.
  • 19. What is the structural analysis model? •Unlinked vertical frame elements represent Piles with ring beam on top and lateral springs along the embedded length below the excavation to represent the passive earth pressure “pile overlap ignored in this case”. •A 600mm wall modeled as a plate element to represent the overlapped piles system with ring beam on top and soil springs. •Horizontal struts added to the first model between piles all around to represent pile interlock, struts are compression only members spaced at 1m vertically.
  • 20. Unlinked Piles with ring beam and soil springs. Deflection and bending moment
  • 21. A 600mm wall modeled as an FEA with ring beam and soil springs
  • 23. Piles with soil springs
  • 24. Compression only members added between vertical frame elements. Disconnected members to represent out of plumb.
  • 25. Final Structural Model During Excavation Case : • Excavation expected to be in the spring so EDP wall will not exposed to frost action so ko=0.53. • Piles are unrestrained at the bottom of excavation level as the slab on grade not constructed yet. During Operation Case: •Frost case will govern the lateral earth pressure for design, Ko=1.0. •The slab on grade constructed at the bottom of excavation level will provide lateral support to the piles at that level. Two final structural models was developed with two main differences .
  • 27. Slab represented as link members to centre Deflection and bending moment
  • 28. During Operation(Slab represented as pinned constraint)
  • 29. Analysis and Design • Do we trust the model? Is it representing Hoop Stress contribution correctly? • All sections must meet the fundamentals. What is the hoop stress? Stress = Pr/t. Does the hoop stress exceed the allowable bearing stress (clause 10.8.1- 0.85 Фc fc’ A) • When we looked at the hoop stress it exceeded our contact area. What to do? – Increase pile size? – Increase overlap by increasing number of piles • All other considerations must be met, Shear, Moment and deflection.
  • 30. Final Design • Meet the fundamentals – make sure transfer of theoretical maximum hoop stress is possible. Bearing governed the initial design, we increased the overlap by adding piles to ensure the foundation of the design philosophy, hoop stress, was maintained. • Design is refined by establishing the extreme boundaries to guide us toward acceptance of model results. Look at no hoop stress and full hoop stress. • There are no templates, the design relies heavily on engineering judgement. Do not try this at home.

Editor's Notes

  1. Add what a Tangent Wall is.
  2. 40 meters diameter, slab 12.5 meters from grade and 19 meter long piles. Ring beam cast at top tieing in all piles.
  3. Initial suggestion is to dump directly into EDP by placing under PSC. Rejected because of uncertainty in construction time, critical equipment risk. Boulders at 11 to 15 meters, suggested piles do not enter boulder zone.
  4. During Excavation: We used Ko within the excavation, Ka below the excavation and springs simulating Kp. Operation: We used Ko frozen to slab depth, Ka below and resisted by Kp. Hoop stress question: When is diameter so large that wall acts linear?? Getting close at 40m diameter.
  5. Diameter 40 meters, depth to base 10 meters plus trench allowance 2.5 meters. Initial pile length estimated at 16 meters, later revised to account for 2.5 meters of trench that enters the wall at grade. Initially the client did not allow the trench to be flooded (later revised to allow 1.0 meters of trench to be flooded..
  6. Based on the at rest and active earth pressure Versus Passive earth pressure, 2D staad model for a single pile used to indicate the resultant of these forces at the bottom of the pile.
  7. Explain discontinuity
  8. Explain why the discontinuity?????
  9. This is equivalent to the Tangent Pile system. Gives us a sensitivity to the extremes and guides us toward a refined solution.
  10. This is the Ideal case at which piles will behave as retaining wall. This is the other extreme. We lie somewhere in between.
  11. Next Two Slides are illustrating this slide.
  12. Tangent wall.
  13. The disconnected members were later deemed redundant.
  14. We have two modeling cases first is during excavation which means no floor slab to constraint the piles at the bottom of excavation level, second is during operation which means piles are restraint at the slab level.
  15. No floor slab to constraint the piles at the bottom of excavation level
  16. During Operation Model, piles are restraint at slab level at max. Moment.